The document describes 4 cases with different relationship types (FS, FF, SS) and statuses (In Progress, Completed, Not Started) and provides solutions for each case. Case 1 is FS and In Progress for both predecessor and successor, requiring no change. Case 2 is either FS or FF and has different statuses, suggesting changing to SS or SS and FF. Case 3 and 4 are not started for predecessor and have different successor statuses, recommending manual checking and considering various options like removing or adding relationships.
The document describes 4 cases with different relationship types (FS, FF, SS) and statuses (In Progress, Completed, Not Started) and provides solutions for each case. Case 1 is FS and In Progress for both predecessor and successor, requiring no change. Case 2 is either FS or FF and has different statuses, suggesting changing to SS or SS and FF. Case 3 and 4 are not started for predecessor and have different successor statuses, recommending manual checking and considering various options like removing or adding relationships.
The document describes 4 cases with different relationship types (FS, FF, SS) and statuses (In Progress, Completed, Not Started) and provides solutions for each case. Case 1 is FS and In Progress for both predecessor and successor, requiring no change. Case 2 is either FS or FF and has different statuses, suggesting changing to SS or SS and FF. Case 3 and 4 are not started for predecessor and have different successor statuses, recommending manual checking and considering various options like removing or adding relationships.