You are on page 1of 4

Proforma of PTR trippings from April 2020- March 2021

Name of the Name of the Sub Duration


SI No Division station PTR Capacity Date From
28.04.2020 12:55
20.05.2020 10:18
25.10.2020 10:29
220/132/33KV
1 DINDI 100 MVA PTR 1
NAGARKURNOOL SS
04.05.2021 14:12
11.05.2021 10:44
14.09.2020 11:29
28.10.2020 11:29
28.04.2020 13:40

19.05.2020 10:12
220/132/33KV
2 DINDI 100 MVA PTR 2 25.10.2020 12:20
NAGARKURNOOL SS
14.09.2020 11:29
07.12.2020 11:29
04.05.2021 15:12
08.05.2020 13:04
19.05.2020 11:20
02.06.2020 7:30

03.06.2020 7:05
11.06.2020 16:20
12.06.2020 5:38
220/132/33KV 12.06.2020 15:15
3 DINDI 31.5 MVA PTR 1
NAGARKURNOOL SS
25.09.2020 11:40

12.11.2020 13:45
29.01.2021 14:35

30.01.2021 11:10
31.03.2021 10:37
28.04.2021 14:25
08.05.2020 13:34
20.05.2020 10:08

03.06.2020 7:06
220/132/33KV
4 DINDI 50 MVA PTR 2 11.06.2020 10:00
NAGARKURNOOL SS
31.07.2020 7:45
25.09.2020 15:20
23.10.2020 10:20
28.04.2021 10:20
28.04.2020 9:00
08.05.2020
19.05.2020

27.05.2020
28.05.2020
31.5 MVA PTR III 03.06.2020
220/132/33KV
5 DINDI (Failed Emco 03.06.2020
NAGARKURNOOL SS Make PTR)
11.06.2020

11.06.2020
12.06.2020

25.09.2020
01.10.2020
08.05.2020 13:34
20.05.2020 10:08

03.06.2020 7:06
220/132/33KV
4 DINDI NAGARKURNOOL SS 50 MVA PTR 2 11.06.2020 10:00
31.07.2020 7:45
25.09.2020 15:20
23.10.2020 10:20
28.04.2021 10:20
om April 2020- March 2021

Duration
To Remarks
13:35 Relay Testing
13:32 Tan Delta Testing
12:13 Maintenance work

14:52 Tan Delta and IR value Testing


14:36 Maintenance work
12:13 AS per Load Dispatch Hyd
12:13 AS per Load Dispatch Hyd
14:10 Relay Testing

14:57 Tan Delta and IR value Testing


13:30 Maintenance work

12:54 AS per Load Dispatch Hyd


12:54 AS per Load Dispatch Hyd
15:46 Tan Delta and IR value Testing
13:34 Relay Testing
15:06 Tan Delta Testing
9:00 Releasing gas from Bucholz Relay

8:58 Replacement of Jumpers for 132KV Midjil Feeder


16:40 Releasing gas from Bucholz Relay
15:15 Tripped on Bucholz Relay
16:45 Rectifying Bucholz problem
12:40 General maintenance

18:35 OLTC Oil Change


15:17 Rectification of Thermal Fault

18:12 Rectification of Thermal Fault


12:00 General maintenance
16:40 General maintenance
14:14 Relay Testing
12:38 Tan Delta Test

8:51 Replacement of Jumpers for 132KV Midjil Feeder

16:10 LV 2 Circuit Breaker Tripped due to low loads


9:05 Replacement of LV Y Phase Bushing Clamp
15:57 Maintenance work
11:16 Hot Lines Points Rectification
14:25 OLTC Oil Change
14:14 Relay Testing
12:38 Tan Delta Test

8:51 Replacement of Jumpers for 132KV Midjil Feeder

16:10 LV 2 Circuit Breaker Tripped due to low loads


9:05 Replacement of LV Y Phase Bushing Clamp
15:57 Maintenance work
11:16 Hot Lines Points Rectification
14:25 OLTC Oil Change

You might also like