ID Name Total length Duration Start Finish U.

Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
1 Structuri Ploiesti-Buzau LOT2 398 days 4/4/22 11/21/23 1 Structuri Ploiesti-Buzau LOT2
2 Access 45 edays 4/4/22 5/19/22 1425FS+5 days,818FS+5 days 2 Access
3 Pod pe DJ 100C peste autostrada km 20+809 120 190 days 6/1/22 3/17/23 3 Pod pe DJ 100C peste autostrada km 20+809
4 Fundatii pile si culei 41 days 6/1/22 7/28/22 4 Fundatii pile si culei
5 Culeea 1 32 days 6/1/22 7/15/22 5 Culeea 1
6 Piloti forati 5 days 6/1/22 6/7/22 buc 10 2.0 1431 10FS+10 days,13,7FS+5 days 6 Piloti forati
7 Sapatura 2 days 6/16/22 6/17/22 mc 310.50 155.3 6FS+5 days 8 7 Sapatura
8 Demolare capete piloti 2 days 6/20/22 6/21/22 mc 13.75 6.9 7 9 8 Demolare capete piloti
9 Beton de egalizare 1 day 6/22/22 6/22/22 mc 12.5 12.5 8 10 9 Beton de egalizare
10 Teste coloane forate 2 days 6/23/22 6/24/22 buc 11 5.5 6FS+10 days,9 11,72 10 Teste coloane forate
11 Realizare Radier 5 days 7/11/22 7/15/22 mc 205 41.0 10,1438SS+10 days 34,18SS+3 days 11 Realizare Radier
12 Pila 1 30 days 6/8/22 7/20/22 12 Pila 1
13 Piloti forati 5 days 6/8/22 6/15/22 buc 10 2.0 6 17FS+10 days,20,14FS+5 days 13 Piloti forati
14 Sapatura 2 days 6/23/22 6/24/22 mc 310.5 155.3 13FS+5 days 15 14 Sapatura
15 Demolare capete piloti 2 days 6/27/22 6/28/22 mc 13.75 6.9 14 16 15 Demolare capete piloti
16 Beton de egalizare 1 day 6/29/22 6/29/22 mc 12.5 12.5 15 17 16 Beton de egalizare
17 Teste coloane forate 2 days 6/30/22 7/1/22 buc 10 5.0 13FS+10 days,16 18 17 Teste coloane forate
18 Realizare Radier 5 days 7/14/22 7/20/22 mc 205 41.0 11SS+3 days,17 35,25SS+3 days 18 Realizare Radier
19 Pila 2 28 days 6/16/22 7/25/22 19 Pila 2
20 Piloti forati 5 days 6/16/22 6/22/22 buc 10 2.0 13 27,25,21FS+5 days,24FS+10 days 20 Piloti forati
21 Sapatura 2 days 6/30/22 7/1/22 mc 310.5 155.3 20FS+5 days 22 21 Sapatura
22 Demolare capete piloti 2 days 7/4/22 7/5/22 mc 13.75 6.9 21 23 22 Demolare capete piloti
23 Beton de egalizare 1 day 7/6/22 7/6/22 mc 12.5 12.5 22 24 23 Beton de egalizare
24 Teste coloane forate 2 days 7/7/22 7/8/22 buc 10 5.0 23,20FS+10 days 25 24 Teste coloane forate
25 Realizare Radier 5 days 7/19/22 7/25/22 mc 205 41.0 18SS+3 days,20,24 36,32SS+3 days 25 Realizare Radier
26 Culeea 2 26 days 6/23/22 7/28/22 26 Culeea 2
27 Piloti forati 5 days 6/23/22 6/29/22 buc 10 2.0 20 32FS+10 days,81,28FS+5 days,31FS+10 days 27 Piloti forati
28 Sapatura 2 days 7/7/22 7/8/22 mc 310.50 155.3 27FS+5 days 29 28 Sapatura
29 Demolare capete piloti 2 days 7/11/22 7/12/22 mc 13.75 6.9 28 30 29 Demolare capete piloti
30 Beton de egalizare 1 day 7/13/22 7/13/22 mc 12.5 12.5 29 31 30 Beton de egalizare
31 Teste coloane forate 2 days 7/14/22 7/15/22 buc 10 5.0 30,27FS+10 days 32 31 Teste coloane forate
32 Realizare Radier 5 days 7/22/22 7/28/22 mc 25 5.0 27FS+10 days,25SS+3 days,31 37,34SS+2 days 32 Realizare Radier
33 Elevatii pile si culei 46 days 7/26/22 9/28/22 33 Elevatii pile si culei
34 Elevatie si banchete C1 20 days 7/26/22 8/23/22 mc 157.5 7.9 11,32SS+2 days 35SS+7 days,41 34 Elevatie si banchete C1
35 Elevatie si Rigla P1 15 days 8/4/22 8/25/22 mc 157.5 10.5 34SS+7 days,18 36SS+7 days 35 Elevatie si Rigla P1
36 Elevatie si Rigla P2 15 days 8/16/22 9/5/22 mc 157.5 10.5 35SS+7 days,25 37SS+7 days 36 Elevatie si Rigla P2
37 Elevatie si banchete C2 20 days 8/25/22 9/21/22 mc 157.5 7.9 32,36SS+7 days 86SS+10 days,38,51 37 Elevatie si banchete C2
38 Montare dispozitive antiseismice si aparate reazem 5 days 9/22/22 9/28/22 buc 24 4.8 37 61 38 Montare dispozitive antiseismice si aparate reazem
39 Racordari cu terasamente 96 days 8/24/22 1/26/23 39 Racordari cu terasamente
40 C1 96 days 8/24/22 1/26/23 40 C1
41 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 8/24/22 8/25/22 mc 130 65.0 34 42 41 Sapatura pentru fundatie protectie taluz/sfert de con
42 Fundatie protectie taluz/sfert de con 5 days 8/26/22 9/1/22 mc 105 21.0 41 44,43 42 Fundatie protectie taluz/sfert de con
43 Tevi ape pluviale 2 days 9/2/22 9/5/22 m 225 112.5 42 45 43 Tevi ape pluviale
44 Umpluturi sfert de con material granular 5 days 9/2/22 9/8/22 mc 1700 340.0 42 45 44 Umpluturi sfert de con material granular
45 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 9/9/22 9/15/22 mp 1025 205.0 43,44 46 45 Protectie taluz / sfert con cu pereu de beton C35/45
46 Scari pe taluz 3 days 9/16/22 9/20/22 m 46 15.3 45 47 46 Scari pe taluz
47 Casiuri pe taluz 3 days 9/21/22 9/23/22 m 56 18.7 46 48 47 Casiuri pe taluz
48 Placi racordare C1 3 days 1/23/23 1/25/23 mc 34 11.3 47,65 49 48 Placi racordare C1
49 Hidroizolatie Placa racordare 1 day 1/26/23 1/26/23 mp 85 85.0 48 49 Hidroizolatie Placa racordare
50 C2 75 days 9/22/22 1/26/23 50 C2
51 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 9/22/22 9/23/22 mc 130 65.0 37 52 51 Sapatura pentru fundatie protectie taluz/sfert de con
52 Fundatie protectie taluz/sfert de con 5 days 9/26/22 9/30/22 mc 105 21.0 51 54,53 52 Fundatie protectie taluz/sfert de con
53 Tevi ape pluviale 2 days 10/3/22 10/4/22 m 225 112.5 52 55 53 Tevi ape pluviale
54 Umpluturi sfert de con material granular 5 days 10/3/22 10/7/22 mc 1700 340.0 52 55 54 Umpluturi sfert de con material granular
55 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 10/10/22 10/14/22 mp 1025 205.0 53,54 56 55 Protectie taluz / sfert con cu pereu de beton C35/45
56 Scari pe taluz 3 days 10/17/22 10/19/22 m 46 15.3 55 57 56 Scari pe taluz
57 Casiuri pe taluz 3 days 10/20/22 10/24/22 m 56 18.7 56 58 57 Casiuri pe taluz
58 Placi racordare C2 3 days 1/23/23 1/25/23 mc 34 11.3 57,65 59 58 Placi racordare C2
59 Hidroizolatie Placa racordare 1 day 1/26/23 1/26/23 mp 85 85.0 58 59 Hidroizolatie Placa racordare
60 Suprastructura 66 days 9/29/22 1/20/23 60 Suprastructura
61 Montaj tronsoane tablier 21 days 9/29/22 10/27/22 t 547 26.0 38 62 61 Montaj tronsoane tablier
62 Montaj predale 10 days 10/28/22 11/10/22 mc 175 17.5 61 63SS+5 days 62 Montaj predale
63 Montaj armatura in placa de suprabetonare 20 days 11/4/22 12/2/22 t 95 4.8 62SS+5 days 64SS+10 days,67SS+5 days 63 Montaj armatura in placa de suprabetonare
64 Montaj cofraj la placa de suprabetonare 20 days 11/18/22 12/16/22 mp 410 20.5 63SS+10 days 65SS+10 days 64 Montaj cofraj la placa de suprabetonare
65 Turnare beton in placa de suprabetonare 20 days 12/5/22 1/20/23 mc 600 30.0 64SS+10 days,67 69FS+5 days,68,48,58 65 Turnare beton in placa de suprabetonare
66 Cale, trotuar, parapet 75 days 11/11/22 3/17/23 66 Cale, trotuar, parapet
67 Montaj guri de scurgere 5 days 11/11/22 11/17/22 buc 12 2.4 63SS+5 days 65 67 Montaj guri de scurgere
68 Prefabricat din beton pentru lisa parapet 5 days 1/23/23 1/27/23 m 264 52.8 65 70 68 Prefabricat din beton pentru lisa parapet
69 Hidroizolatie cale 10 days 1/30/23 2/10/23 mp 1900 190.0 65FS+5 days 70 69 Hidroizolatie cale
70 Borduri pe Pod 5 days 2/13/23 2/17/23 m 260 52.0 69,68 71,74 70 Borduri pe Pod
71 Trotuare pe pod 10 days 2/20/23 3/3/23 mc 36 3.6 70 72,75 71 Trotuare pe pod
72 Sistem rutier 5 days 3/6/23 3/10/23 mp 1560 312.0 10,71 73 72 Sistem rutier
73 Dispozitive de acoperire a rosturilor 5 days 3/13/23 3/17/23 m 34 6.8 72 73 Dispozitive de acoperire a rosturilor
74 Parapeti pietonali si plase de protectie 10 days 2/20/23 3/3/23 m 260 26.0 70 74 Parapeti pietonali si plase de protectie
75 Parapeti metalici 10 days 3/6/23 3/17/23 m 180 18.0 71 76SS 75 Parapeti metalici
76 Parapeti New Jersey 5 days 3/6/23 3/10/23 m 180 36.0 75SS 77 76 Parapeti New Jersey
77 Marcaje rutiere 5 days 3/13/23 3/17/23 0.0 76 77 Marcaje rutiere
78 Pod peste paraul Valea Ceptura II si drum agricol km 22+13430.00 156 days 6/30/22 2/27/23 78 Pod peste paraul Valea Ceptura II si drum agricol km 22+134
79 Fundatii pile si culei 63 days 6/30/22 9/27/22 79 Fundatii pile si culei
80 Culeea 1s 54 days 6/30/22 9/14/22 80 Culeea 1s
81 Piloti forati 4 days 6/30/22 7/5/22 buc 8 2.0 27 85FS+10 days,88,82FS+5 days 81 Piloti forati
82 Sapatura 2 days 7/13/22 7/14/22 mc 450 225.0 81FS+5 days 83 82 Sapatura
83 Demolare capete piloti 2 days 7/15/22 7/18/22 mc 11.25 5.6 82 84 83 Demolare capete piloti
84 Beton de egalizare 1 day 7/19/22 7/19/22 mc 16.25 16.3 83 85 84 Beton de egalizare
85 Teste coloane forate 2 days 7/20/22 7/21/22 buc 9 4.5 81FS+10 days,84 86 85 Teste coloane forate
86 Realizare Radier 5 days 9/8/22 9/14/22 mc 210 42.0 85,37SS+10 days 109,93SS+3 days 86 Realizare Radier
87 Culeea 1d 53 days 7/6/22 9/19/22 87 Culeea 1d
88 Piloti forati 4 days 7/6/22 7/11/22 buc 8 2.0 81 95,92FS+10 days,89FS+5 days 88 Piloti forati
89 Sapatura 2 days 7/19/22 7/20/22 mc 450 225.0 88FS+5 days 90 89 Sapatura
90 Demolare capete piloti 2 days 7/21/22 7/22/22 mc 11.25 5.6 89 91 90 Demolare capete piloti
91 Beton de egalizare 1 day 7/25/22 7/25/22 mc 16.25 16.3 90 92 91 Beton de egalizare
92 Teste coloane forate 2 days 7/26/22 7/27/22 buc 9 4.5 88FS+10 days,91 93 92 Teste coloane forate
93 Realizare Radier 5 days 9/13/22 9/19/22 mc 210 42.0 86SS+3 days,92 110,100SS+3 days 93 Realizare Radier
94 Culeea 2s 52 days 7/12/22 9/22/22 94 Culeea 2s
95 Piloti forati 4 days 7/12/22 7/15/22 buc 8 2.0 88 102,100,99FS+10 days,96FS+5 days 95 Piloti forati
96 Sapatura 2 days 7/25/22 7/26/22 mc 450 225.0 95FS+5 days 97 96 Sapatura
97 Demolare capete piloti 2 days 7/27/22 7/28/22 mc 11.25 5.6 96 98 97 Demolare capete piloti
98 Beton de egalizare 1 day 7/29/22 7/29/22 mc 16.25 16.3 97 99 98 Beton de egalizare
99 Teste coloane forate 2 days 8/1/22 8/2/22 buc 8 4.0 98,95FS+10 days 100 99 Teste coloane forate
100 Realizare Radier 5 days 9/16/22 9/22/22 mc 210 42.0 93SS+3 days,95,99 111,107SS+3 days 100 Realizare Radier
101 Culeea 2d 51 days 7/18/22 9/27/22 101 Culeea 2d
102 Piloti forati 4 days 7/18/22 7/21/22 buc 8 2.0 95 107FS+10 days,155,103FS+5 days,106FS+10 days 102 Piloti forati
103 Sapatura 2 days 7/29/22 8/1/22 mc 450 225.0 102FS+5 days 104 103 Sapatura
104 Demolare capete piloti 2 days 8/2/22 8/3/22 mc 11.25 5.6 103 105 104 Demolare capete piloti
105 Beton de egalizare 1 day 8/4/22 8/4/22 mc 16.25 16.3 104 106 105 Beton de egalizare
106 Teste coloane forate 2 days 8/5/22 8/8/22 buc 8 4.0 105,102FS+10 days 107 106 Teste coloane forate
107 Realizare Radier 5 days 9/21/22 9/27/22 mc 210 42.0 100SS+3 days,102FS+10 days,106 112,109SS+2 days 107 Realizare Radier

Seite 1
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
108 Elevatii pile si culei 34 days 9/23/22 11/9/22 108 Elevatii pile si culei
109 Elevatie si banchete C1s 10 days 9/23/22 10/6/22 mc 363 36.3 86,107SS+2 days 110SS+7 days 109 Elevatie si banchete C1s
110 Elevatie si banchete C1d 10 days 10/4/22 10/17/22 mc 363 36.3 109SS+7 days,93 111SS+7 days,116 110 Elevatie si banchete C1d
111 Elevatie si banchete C2s 10 days 10/13/22 10/26/22 mc 363 36.3 110SS+7 days,100 112SS+5 days 111 Elevatie si banchete C2s
112 Elevatie si banchete C2d 10 days 10/20/22 11/2/22 mc 363 36.3 111SS+5 days,107 113,179SS+10 days,127 112 Elevatie si banchete C2d
113 Montare dispozitive antiseismice si aparate reazem 5 days 11/3/22 11/9/22 buc 16 3.2 112 138 113 Montare dispozitive antiseismice si aparate reazem
114 Racordari cu terasamente 48 days 10/18/22 1/13/23 114 Racordari cu terasamente
115 C1 48 days 10/18/22 1/13/23 115 C1
116 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 10/18/22 10/19/22 mc 123 61.5 110 117 116 Sapatura pentru fundatie protectie taluz/sfert de con
117 Fundatie protectie taluz/sfert de con 5 days 10/20/22 10/26/22 mc 100 20.0 116 120,118,119 117 Fundatie protectie taluz/sfert de con
118 Dren din geotextil 2 days 10/27/22 10/28/22 mp 300 150.0 117 121 118 Dren din geotextil
119 Tevi ape pluviale 2 days 10/27/22 10/28/22 m 40 20.0 117 121 119 Tevi ape pluviale
120 Umpluturi sfert de con material granular 5 days 10/27/22 11/2/22 mc 1200 240.0 117 121 120 Umpluturi sfert de con material granular
121 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 11/3/22 11/9/22 mp 430 86.0 118,119,120 122 121 Protectie taluz / sfert con cu pereu de beton C35/45
122 Scari pe taluz 3 days 11/10/22 11/14/22 m 36 12.0 121 123 122 Scari pe taluz
123 Casiuri pe taluz 3 days 11/15/22 11/17/22 m 42 14.0 122 123 Casiuri pe taluz
124 Placi racordare C1 3 days 1/10/23 1/12/23 mc 62 20.7 142 125 124 Placi racordare C1
125 Hidroizolatie Placa racordare 1 day 1/13/23 1/13/23 mp 175 175.0 124 125 Hidroizolatie Placa racordare
126 C2 36 days 11/3/22 1/13/23 126 C2
127 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 11/3/22 11/4/22 mc 123 61.5 112 128 127 Sapatura pentru fundatie protectie taluz/sfert de con
128 Fundatie protectie taluz/sfert de con 5 days 11/7/22 11/11/22 mc 100 20.0 127 131,129,130 128 Fundatie protectie taluz/sfert de con
129 Dren din geotextil 2 days 11/14/22 11/15/22 mp 300 150.0 128 132 129 Dren din geotextil
130 Tevi ape pluviale 2 days 11/14/22 11/15/22 m 40 20.0 128 132 130 Tevi ape pluviale
131 Umpluturi sfert de con material granular 5 days 11/14/22 11/18/22 mc 1200 240.0 128 132 131 Umpluturi sfert de con material granular
132 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 11/21/22 11/25/22 mp 430 86.0 129,130,131 133 132 Protectie taluz / sfert con cu pereu de beton C35/45
133 Scari pe taluz 3 days 11/28/22 12/1/22 m 36 12.0 132 134 133 Scari pe taluz
134 Casiuri pe taluz 3 days 12/2/22 12/6/22 m 42 14.0 133 134 Casiuri pe taluz
135 Placi racordare C2 3 days 1/10/23 1/12/23 mc 62 20.7 142 136 135 Placi racordare C2
136 Hidroizolatie Placa racordare 1 day 1/13/23 1/13/23 mp 175 175.0 135 136 Hidroizolatie Placa racordare
137 Suprastructura 27 days 11/10/22 1/9/23 137 Suprastructura
138 Montaj grinzi 10 days 11/10/22 11/23/22 buc 12 1.2 113 139 138 Montaj grinzi
139 Montaj predale 5 days 11/24/22 12/1/22 mc 83 16.6 138 140 139 Montaj predale
140 Montaj armatura in placa de suprabetonare 5 days 12/2/22 12/8/22 t 49.5 9.9 139 141SS+2 days,144SS+2 days 140 Montaj armatura in placa de suprabetonare
141 Montaj cofraj la placa de suprabetonare 5 days 12/6/22 12/12/22 mp 200 40.0 140SS+2 days 142SS+2 days 141 Montaj cofraj la placa de suprabetonare
142 Turnare beton in placa de suprabetonare 5 days 12/13/22 1/9/23 mc 330 66.0 144,141SS+2 days 146FS+5 days,145,124,135 142 Turnare beton in placa de suprabetonare
143 Cale, trotuar, parapet 45 days 12/6/22 2/27/23 143 Cale, trotuar, parapet
144 Montaj guri de scurgere 5 days 12/6/22 12/12/22 buc 4 0.8 140SS+2 days 142 144 Montaj guri de scurgere
145 Prefabricat din beton pentru lisa parapet 5 days 1/10/23 1/16/23 m 168 33.6 142 147 145 Prefabricat din beton pentru lisa parapet
146 Hidroizolatie cale 10 days 1/17/23 1/30/23 mp 780 78.0 142FS+5 days 147 146 Hidroizolatie cale
147 Borduri pe Pod 5 days 1/31/23 2/6/23 m 168 33.6 145,146 148 147 Borduri pe Pod
148 Sistem rutier 5 days 2/7/23 2/13/23 mp 720 144.0 147 149,150 148 Sistem rutier
149 Dispozitive de acoperire a rosturilor 5 days 2/14/23 2/20/23 m 56 11.2 148 149 Dispozitive de acoperire a rosturilor
150 Parapeti metalici 5 days 2/14/23 2/20/23 m 368 73.6 148 151 150 Parapeti metalici
151 Marcaje rutiere 5 days 2/21/23 2/27/23 0.0 150 151 Marcaje rutiere
152 Pod peste paraul Ghighiu km 22+606 40.00 171 days 7/22/22 4/11/23 152 Pod peste paraul Ghighiu km 22+606
153 Fundatii pile si culei 20 days 7/22/22 8/19/22 153 Fundatii pile si culei
154 Culeea 1s 14 days 7/22/22 8/10/22 154 Culeea 1s
155 Piloti forati 2 days 7/22/22 7/25/22 buc 4 2.0 102 159FS+10 days,161,156FS+5 days 155 Piloti forati
156 Sapatura 2 days 8/2/22 8/3/22 mc 220 110.0 155FS+5 days 157 156 Sapatura
157 Demolare capete piloti 2 days 8/4/22 8/5/22 mc 5.5 2.8 156 158 157 Demolare capete piloti
158 Beton de egalizare 1 day 8/8/22 8/8/22 mc 8.75 8.8 157 159 158 Beton de egalizare
159 Teste coloane forate 2 days 8/9/22 8/10/22 buc 5 2.5 155FS+10 days,158 179 159 Teste coloane forate
160 Culeea 1d 14 days 7/26/22 8/12/22 160 Culeea 1d
161 Piloti forati 2 days 7/26/22 7/27/22 buc 4 2.0 155 167,165FS+10 days,162FS+5 days 161 Piloti forati
162 Sapatura 2 days 8/4/22 8/5/22 mc 220 110.0 161FS+5 days 163 162 Sapatura
163 Demolare capete piloti 2 days 8/8/22 8/9/22 mc 5.5 2.8 162 164 163 Demolare capete piloti
164 Beton de egalizare 1 day 8/10/22 8/10/22 mc 8.75 8.8 163 165 164 Beton de egalizare
165 Teste coloane forate 2 days 8/11/22 8/12/22 buc 5 2.5 161FS+10 days,164 180 165 Teste coloane forate
166 Culeea 2s 14 days 7/28/22 8/17/22 166 Culeea 2s
167 Piloti forati 2 days 7/28/22 7/29/22 buc 4 2.0 161 173,168FS+5 days,171FS+10 days 167 Piloti forati
168 Sapatura 2 days 8/8/22 8/9/22 mc 220 110.0 167FS+5 days 169 168 Sapatura
169 Demolare capete piloti 2 days 8/10/22 8/11/22 mc 5.5 2.8 168 170 169 Demolare capete piloti
170 Beton de egalizare 1 day 8/12/22 8/12/22 mc 8.75 8.8 169 171 170 Beton de egalizare
171 Teste coloane forate 2 days 8/16/22 8/17/22 buc 4 2.0 170,167FS+10 days 181 171 Teste coloane forate
172 Culeea 2d 14 days 8/1/22 8/19/22 172 Culeea 2d
173 Piloti forati 2 days 8/1/22 8/2/22 buc 4 2.0 167 224,174FS+5 days,177FS+10 days 173 Piloti forati
174 Sapatura 2 days 8/10/22 8/11/22 mc 220 110.0 173FS+5 days 175 174 Sapatura
175 Demolare capete piloti 2 days 8/12/22 8/16/22 mc 5.5 2.8 174 176 175 Demolare capete piloti
176 Beton de egalizare 1 day 8/17/22 8/17/22 mc 8.75 8.8 175 177 176 Beton de egalizare
177 Teste coloane forate 2 days 8/18/22 8/19/22 buc 4 2.0 176,173FS+10 days 182 177 Teste coloane forate
178 Elevatii pile si culei 36 days 11/3/22 1/13/23 178 Elevatii pile si culei
179 Elevatie si banchete C1s 10 days 11/3/22 11/16/22 mc 206.25 20.6 159,112SS+10 days 180SS+7 days 179 Elevatie si banchete C1s
180 Elevatie si banchete C1d 10 days 11/14/22 11/25/22 mc 206.25 20.6 179SS+7 days,165 181SS+7 days,186 180 Elevatie si banchete C1d
181 Elevatie si banchete C2s 10 days 11/23/22 12/7/22 mc 206.25 20.6 180SS+7 days,171 182SS+7 days 181 Elevatie si banchete C2s
182 Elevatie si banchete C2d 10 days 12/5/22 12/16/22 mc 206.25 20.6 181SS+7 days,177 183,197 182 Elevatie si banchete C2d
183 Montare dispozitive antiseismice si aparate reazem 5 days 1/9/23 1/13/23 buc 20 4.0 182 208 183 Montare dispozitive antiseismice si aparate reazem
184 Racordari cu terasamente 50 days 11/28/22 2/27/23 184 Racordari cu terasamente
185 C1 50 days 11/28/22 2/27/23 185 C1
186 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 11/28/22 11/29/22 mc 70 35.0 180 187 186 Sapatura pentru fundatie protectie taluz/sfert de con
187 Fundatie protectie taluz/sfert de con 5 days 12/1/22 12/7/22 mc 55 11.0 186 190,188,189 187 Fundatie protectie taluz/sfert de con
188 Dren din geotextil 2 days 12/8/22 12/9/22 mp 300 150.0 187 191 188 Dren din geotextil
189 Tevi ape pluviale 2 days 12/8/22 12/9/22 m 45 22.5 187 191 189 Tevi ape pluviale
190 Umpluturi sfert de con material granular 5 days 12/8/22 12/14/22 mc 742.5 148.5 187 191 190 Umpluturi sfert de con material granular
191 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 12/15/22 1/11/23 mp 362.5 72.5 188,189,190 192 191 Protectie taluz / sfert con cu pereu de beton C35/45
192 Scari pe taluz 3 days 1/12/23 1/16/23 m 27 9.0 191 193 192 Scari pe taluz
193 Casiuri pe taluz 3 days 1/17/23 1/19/23 m 35 11.7 192 193 Casiuri pe taluz
194 Placi racordare C1 3 days 2/22/23 2/24/23 mc 62 20.7 211 195 194 Placi racordare C1
195 Hidroizolatie Placa racordare 1 day 2/27/23 2/27/23 mp 175 175.0 194 195 Hidroizolatie Placa racordare
196 C2 36 days 1/9/23 2/27/23 196 C2
197 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 1/9/23 1/10/23 mc 70 35.0 182 198 197 Sapatura pentru fundatie protectie taluz/sfert de con
198 Fundatie protectie taluz/sfert de con 5 days 1/11/23 1/17/23 mc 55 11.0 197 201,199,200 198 Fundatie protectie taluz/sfert de con
199 Dren din geotextil 2 days 1/18/23 1/19/23 mp 300 150.0 198 202 199 Dren din geotextil
200 Tevi ape pluviale 2 days 1/18/23 1/19/23 m 45 22.5 198 202 200 Tevi ape pluviale
201 Umpluturi sfert de con material granular 5 days 1/18/23 1/24/23 mc 742.5 148.5 198 202 201 Umpluturi sfert de con material granular
202 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 1/25/23 1/31/23 mp 362.5 72.5 199,200,201 203 202 Protectie taluz / sfert con cu pereu de beton C35/45
203 Scari pe taluz 3 days 2/1/23 2/3/23 m 27 9.0 202 204 203 Scari pe taluz
204 Casiuri pe taluz 3 days 2/6/23 2/8/23 m 35 11.7 203 204 Casiuri pe taluz
205 Placi racordare C2 3 days 2/22/23 2/24/23 mc 62 20.7 211 206 205 Placi racordare C2
206 Hidroizolatie Placa racordare 1 day 2/27/23 2/27/23 mp 175 175.0 205 206 Hidroizolatie Placa racordare
207 Suprastructura 27 days 1/16/23 2/21/23 207 Suprastructura
208 Montaj grinzi 10 days 1/16/23 1/27/23 buc 12 1.2 183 209 208 Montaj grinzi
209 Montaj armatura in placa de suprabetonare si antretoaze 15 days 1/30/23 2/17/23 t 71.5 4.8 208 210SS+2 days,213SS+2 days 209 Montaj armatura in placa de suprabetonare si antretoaze
210 Montaj cofraj la placa de suprabetonare 10 days 2/1/23 2/14/23 mp 635 63.5 209SS+2 days 211SS+2 days 210 Montaj cofraj la placa de suprabetonare
211 Turnare beton in placa de suprabetonare si antretoaze 10 days 2/8/23 2/21/23 mc 471 47.1 213,210SS+2 days 215FS+5 days,214,194,205 211 Turnare beton in placa de suprabetonare si antretoaze
212 Cale, trotuar, parapet 50 days 2/1/23 4/11/23 212 Cale, trotuar, parapet
213 Montaj guri de scurgere 5 days 2/1/23 2/7/23 buc 4 0.8 209SS+2 days 211 213 Montaj guri de scurgere
214 Prefabricat din beton pentru lisa parapet 5 days 2/22/23 2/28/23 m 200 40.0 211 216 214 Prefabricat din beton pentru lisa parapet

Seite 2
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
215 Hidroizolatie cale 10 days 3/1/23 3/14/23 mp 1040 104.0 211FS+5 days 216 215 Hidroizolatie cale
216 Borduri pe Pod 5 days 3/15/23 3/21/23 m 200 40.0 214,215 217 216 Borduri pe Pod
217 Sistem rutier 5 days 3/22/23 3/28/23 mp 1040 208.0 216 218,219 217 Sistem rutier
218 Dispozitive de acoperire a rosturilor 5 days 3/29/23 4/4/23 m 56 11.2 217 218 Dispozitive de acoperire a rosturilor
219 Parapeti metalici 5 days 3/29/23 4/4/23 m 400 80.0 217 220 219 Parapeti metalici
220 Marcaje rutiere 5 days 4/5/23 4/11/23 0.0 219 220 Marcaje rutiere
221 Pod pe DJ 102Dpeste autostrada km 23+732 88.00 151 days 8/3/22 3/24/23 221 Pod pe DJ 102Dpeste autostrada km 23+732
222 Fundatii pile si culei 33 days 8/3/22 9/19/22 222 Fundatii pile si culei
223 Culeea 1 21 days 8/3/22 9/1/22 223 Culeea 1
224 Piloti forati 4 days 8/3/22 8/8/22 buc 8 2.0 173 228FS+10 days,231,225FS+5 days 224 Piloti forati
225 Sapatura 2 days 8/17/22 8/18/22 mc 288 144.0 224FS+5 days 226 225 Sapatura
226 Demolare capete piloti 2 days 8/19/22 8/22/22 mc 9 4.5 225 227 226 Demolare capete piloti
227 Beton de egalizare 1 day 8/23/22 8/23/22 mc 12 12.0 226 228 227 Beton de egalizare
228 Teste coloane forate 2 days 8/24/22 8/25/22 buc 9 4.5 224FS+10 days,227 229,290 228 Teste coloane forate
229 Realizare Radier 5 days 8/26/22 9/1/22 117 23.4 228 252,236SS+3 days 229 Realizare Radier
230 Pila 1 21 days 8/9/22 9/7/22 230 Pila 1
231 Piloti forati 4 days 8/9/22 8/12/22 buc 8 2.0 224 235FS+10 days,238,232FS+5 days 231 Piloti forati
232 Sapatura 2 days 8/23/22 8/24/22 mc 288 144.0 231FS+5 days 233 232 Sapatura
233 Demolare capete piloti 2 days 8/25/22 8/26/22 mc 9 4.5 232 234 233 Demolare capete piloti
234 Beton de egalizare 1 day 8/29/22 8/29/22 mc 12 12.0 233 235 234 Beton de egalizare
235 Teste coloane forate 2 days 8/30/22 8/31/22 buc 9 4.5 231FS+10 days,234 236 235 Teste coloane forate
236 Realizare Radier 5 days 9/1/22 9/7/22 117 23.4 229SS+3 days,235 253,243SS+3 days 236 Realizare Radier
237 Pila 2 21 days 8/16/22 9/13/22 237 Pila 2
238 Piloti forati 4 days 8/16/22 8/19/22 buc 8 2.0 231 245,243,239FS+5 days,242FS+10 days 238 Piloti forati
239 Sapatura 2 days 8/29/22 8/30/22 mc 288 144.0 238FS+5 days 240 239 Sapatura
240 Demolare capete piloti 2 days 8/31/22 9/1/22 mc 9 4.5 239 241 240 Demolare capete piloti
241 Beton de egalizare 1 day 9/2/22 9/2/22 mc 12 12.0 240 242 241 Beton de egalizare
242 Teste coloane forate 2 days 9/5/22 9/6/22 buc 8 4.0 241,238FS+10 days 243 242 Teste coloane forate
243 Realizare Radier 5 days 9/7/22 9/13/22 mc 117 23.4 236SS+3 days,238,242 254,250SS+3 days 243 Realizare Radier
244 Culeea 2 21 days 8/22/22 9/19/22 244 Culeea 2
245 Piloti forati 4 days 8/22/22 8/25/22 buc 8 2.0 238 250FS+10 days,447,246FS+5 days,249FS+10 days 245 Piloti forati
246 Sapatura 2 days 9/2/22 9/5/22 mc 288 144.0 245FS+5 days 247 246 Sapatura
247 Demolare capete piloti 2 days 9/6/22 9/7/22 mc 9 4.5 246 248 247 Demolare capete piloti
248 Beton de egalizare 1 day 9/8/22 9/8/22 mc 12 12.0 247 249 248 Beton de egalizare
249 Teste coloane forate 2 days 9/9/22 9/12/22 buc 8 4.0 248,245FS+10 days 250 249 Teste coloane forate
250 Realizare Radier 5 days 9/13/22 9/19/22 mc 117 23.4 243SS+3 days,245FS+10 days,249 255,252SS+2 days 250 Realizare Radier
251 Elevatii pile si culei 41 days 9/15/22 11/10/22 251 Elevatii pile si culei
252 Elevatie si banchete C1 15 days 9/15/22 10/5/22 mc 140 9.3 229,250SS+2 days 253SS+7 days,259 252 Elevatie si banchete C1
253 Elevatie si Rigla P1 10 days 9/26/22 10/7/22 mc 140 14.0 252SS+7 days,236 254SS+7 days 253 Elevatie si Rigla P1
254 Elevatie si Rigla P2 10 days 10/5/22 10/18/22 mc 140 14.0 253SS+7 days,243 255SS+7 days 254 Elevatie si Rigla P2
255 Elevatie si banchete C2 15 days 10/14/22 11/3/22 mc 140 9.3 254SS+7 days,250 256,452SS+10 days,269 255 Elevatie si banchete C2
256 Montare dispozitive antiseismice si aparate reazem 5 days 11/4/22 11/10/22 buc 20 4.0 255 279 256 Montare dispozitive antiseismice si aparate reazem
257 Racordari cu terasamente 75 days 10/6/22 2/9/23 257 Racordari cu terasamente
258 C1 75 days 10/6/22 2/9/23 258 C1
259 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 10/6/22 10/7/22 mc 200 100.0 252 260 259 Sapatura pentru fundatie protectie taluz/sfert de con
260 Fundatie protectie taluz/sfert de con 5 days 10/10/22 10/14/22 mc 160 32.0 259 262,261 260 Fundatie protectie taluz/sfert de con
261 Tevi ape pluviale 2 days 10/17/22 10/18/22 m 95 47.5 260 263 261 Tevi ape pluviale
262 Umpluturi sfert de con material granular 5 days 10/17/22 10/21/22 mc 3000 600.0 260 263 262 Umpluturi sfert de con material granular
263 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 10/24/22 10/28/22 mp 1150 230.0 261,262 264 263 Protectie taluz / sfert con cu pereu de beton C35/45
264 Scari pe taluz 3 days 10/31/22 11/2/22 m 45 15.0 263 265 264 Scari pe taluz
265 Casiuri pe taluz 3 days 11/3/22 11/7/22 m 55 18.3 264 265 Casiuri pe taluz
266 Placi racordare C1 3 days 2/6/23 2/8/23 mc 21 7.0 283 267 266 Placi racordare C1
267 Hidroizolatie Placa racordare 1 day 2/9/23 2/9/23 mp 62.5 62.5 266 267 Hidroizolatie Placa racordare
268 C2 54 days 11/4/22 2/9/23 268 C2
269 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 11/4/22 11/7/22 mc 200 100.0 255 270 269 Sapatura pentru fundatie protectie taluz/sfert de con
270 Fundatie protectie taluz/sfert de con 5 days 11/8/22 11/14/22 mc 160 32.0 269 272,271 270 Fundatie protectie taluz/sfert de con
271 Tevi ape pluviale 2 days 11/15/22 11/16/22 m 95 47.5 270 273 271 Tevi ape pluviale
272 Umpluturi sfert de con material granular 5 days 11/15/22 11/21/22 mc 3000 600.0 270 273 272 Umpluturi sfert de con material granular
273 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 11/22/22 11/28/22 mp 1150 230.0 271,272 274 273 Protectie taluz / sfert con cu pereu de beton C35/45
274 Scari pe taluz 3 days 11/29/22 12/2/22 m 45 15.0 273 275 274 Scari pe taluz
275 Casiuri pe taluz 3 days 12/5/22 12/7/22 m 55 18.3 274 275 Casiuri pe taluz
276 Placi racordare C2 3 days 2/6/23 2/8/23 mc 21 7.0 283 277 276 Placi racordare C2
277 Hidroizolatie Placa racordare 1 day 2/9/23 2/9/23 mp 62.5 62.5 276 277 Hidroizolatie Placa racordare
278 Suprastructura 45 days 11/11/22 2/3/23 278 Suprastructura
279 Montaj grinzi 10 days 11/11/22 11/24/22 buc 18 1.8 256 280 279 Montaj grinzi
280 Montaj predale 10 days 11/25/22 12/9/22 mc 106 10.6 279 281SS+5 days 280 Montaj predale
281 Montaj armatura in placa de suprabetonare si antretoaze 15 days 12/5/22 1/13/23 t 116.5 7.8 280SS+5 days 282SS+10 days,285SS+5 days 281 Montaj armatura in placa de suprabetonare si antretoaze
282 Montaj cofraj la placa de suprabetonare 15 days 1/9/23 1/27/23 mp 215 14.3 281SS+10 days 283SS+10 days 282 Montaj cofraj la placa de suprabetonare
283 Turnare beton in placa de suprabetonare si antretoaze 10 days 1/23/23 2/3/23 mc 365 36.5 285,282SS+10 days 287FS+5 days,286,266,276 283 Turnare beton in placa de suprabetonare si antretoaze
284 Cale, trotuar, parapet 60 days 12/12/22 3/24/23 284 Cale, trotuar, parapet
285 Montaj guri de scurgere 5 days 12/12/22 12/16/22 buc 12 2.4 281SS+5 days 283 285 Montaj guri de scurgere
286 Prefabricat din beton pentru lisa parapet 5 days 2/6/23 2/10/23 m 196 39.2 283 288 286 Prefabricat din beton pentru lisa parapet
287 Hidroizolatie cale 10 days 2/13/23 2/24/23 mp 1144 114.4 283FS+5 days 288 287 Hidroizolatie cale
288 Borduri pe Pod 5 days 2/27/23 3/3/23 m 196 39.2 286,287 289,292 288 Borduri pe Pod
289 Trotuare pe pod 5 days 3/6/23 3/10/23 mc 71 14.2 288 290,293 289 Trotuare pe pod
290 Sistem rutier 5 days 3/13/23 3/17/23 mp 690 138.0 228,289 291 290 Sistem rutier
291 Dispozitive de acoperire a rosturilor 5 days 3/20/23 3/24/23 m 25 5.0 290 291 Dispozitive de acoperire a rosturilor
292 Parapeti pietonali si plase de protectie 10 days 3/6/23 3/17/23 m 196 19.6 288 292 Parapeti pietonali si plase de protectie
293 Parapeti metalici 5 days 3/13/23 3/17/23 m 296 59.2 289 294 293 Parapeti metalici
294 Marcaje rutiere 5 days 3/20/23 3/24/23 0.0 293 294 Marcaje rutiere
295 Pod pe DJ 102H peste autostrada km 26+274 140.00 180 days 10/11/22 7/20/23 295 Pod pe DJ 102H peste autostrada km 26+274
296 Fundatii pile si culei 36 days 10/11/22 11/29/22 296 Fundatii pile si culei
297 Culeea 1 22 days 10/11/22 11/9/22 297 Culeea 1
298 Piloti forati 5 days 10/11/22 10/17/22 buc 9 1.8 542 302FS+10 days,305,299FS+5 days 298 Piloti forati
299 Sapatura 2 days 10/25/22 10/26/22 mc 277.5 138.8 298FS+5 days 300 299 Sapatura
300 Demolare capete piloti 2 days 10/27/22 10/28/22 mc 12.5 6.3 299 301 300 Demolare capete piloti
301 Beton de egalizare 1 day 10/31/22 10/31/22 mc 11.25 11.3 300 302 301 Beton de egalizare
302 Teste coloane forate 2 days 11/1/22 11/2/22 buc 10 5.0 298FS+10 days,301 303,365 302 Teste coloane forate
303 Realizare Radier 5 days 11/3/22 11/9/22 mc 180 36.0 302 326,310SS+3 days 303 Realizare Radier
304 Pila 1 22 days 10/18/22 11/16/22 304 Pila 1
305 Piloti forati 5 days 10/18/22 10/24/22 buc 9 1.8 298 309FS+10 days,312,306FS+5 days 305 Piloti forati
306 Sapatura 2 days 11/1/22 11/2/22 mc 277.5 138.8 305FS+5 days 307 306 Sapatura
307 Demolare capete piloti 2 days 11/3/22 11/4/22 mc 12.5 6.3 306 308 307 Demolare capete piloti
308 Beton de egalizare 1 day 11/7/22 11/7/22 mc 11.25 11.3 307 309 308 Beton de egalizare
309 Teste coloane forate 2 days 11/8/22 11/9/22 buc 10 5.0 305FS+10 days,308 310 309 Teste coloane forate
310 Realizare Radier 5 days 11/10/22 11/16/22 mc 180 36.0 303SS+3 days,309 327,317SS+3 days 310 Realizare Radier
311 Pila 2 21 days 10/25/22 11/22/22 311 Pila 2
312 Piloti forati 5 days 10/25/22 10/31/22 buc 9 1.8 305 319,317,316FS+10 days,313FS+5 days 312 Piloti forati
313 Sapatura 2 days 11/8/22 11/9/22 mc 277.5 138.8 312FS+5 days 314 313 Sapatura
314 Demolare capete piloti 2 days 11/10/22 11/11/22 mc 12.5 6.3 313 315 314 Demolare capete piloti
315 Beton de egalizare 1 day 11/14/22 11/14/22 mc 11.25 11.3 314 316 315 Beton de egalizare
316 Teste coloane forate 1 day 11/15/22 11/15/22 buc 9 9.0 315,312FS+10 days 317 316 Teste coloane forate
317 Realizare Radier 5 days 11/16/22 11/22/22 mc 180 36.0 310SS+3 days,312,316 328,324SS+3 days 317 Realizare Radier
318 Culeea 2 21 days 11/1/22 11/29/22 318 Culeea 2
319 Piloti forati 5 days 11/1/22 11/7/22 buc 9 1.8 312 324FS+10 days,373,320FS+5 days,323FS+10 days 319 Piloti forati
320 Sapatura 2 days 11/15/22 11/16/22 mc 277.5 138.8 319FS+5 days 321 320 Sapatura
321 Demolare capete piloti 2 days 11/17/22 11/18/22 mc 12.5 6.3 320 322 321 Demolare capete piloti

Seite 3
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
322 Beton de egalizare 1 day 11/21/22 11/21/22 mc 11.25 11.3 321 323 322 Beton de egalizare
323 Teste coloane forate 1 day 11/22/22 11/22/22 buc 9 9.0 322,319FS+10 days 324 323 Teste coloane forate
324 Realizare Radier 5 days 11/23/22 11/29/22 mc 180 36.0 317SS+3 days,319FS+10 days,323 329,326SS+2 days 324 Realizare Radier
325 Elevatii pile si culei 46 days 11/25/22 2/20/23 325 Elevatii pile si culei
326 Elevatie si banchete C1 20 days 11/25/22 1/13/23 mc 95.00 4.8 303,324SS+2 days 327SS+7 days,333 326 Elevatie si banchete C1
327 Elevatie si Rigla P1 15 days 12/7/22 1/17/23 mc 95.00 6.3 326SS+7 days,310 328SS+7 days 327 Elevatie si Rigla P1
328 Elevatie si Rigla P2 15 days 12/16/22 1/26/23 mc 95.00 6.3 327SS+7 days,317 329SS+7 days 328 Elevatie si Rigla P2
329 Elevatie si banchete C2 20 days 1/17/23 2/13/23 mc 95.00 4.8 328SS+7 days,324 330,378SS+10 days,343 329 Elevatie si banchete C2
330 Montare dispozitive antiseismice si aparate reazem 5 days 2/14/23 2/20/23 buc 20 4.0 329 353 330 Montare dispozitive antiseismice si aparate reazem
331 Racordari cu terasamente 48 days 1/16/23 3/22/23 331 Racordari cu terasamente
332 C1 27 days 1/16/23 2/21/23 332 C1
333 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 1/16/23 1/17/23 mc 125 62.5 326 334 333 Sapatura pentru fundatie protectie taluz/sfert de con
334 Fundatie protectie taluz/sfert de con 5 days 1/18/23 1/24/23 mc 100 20.0 333 336,335 334 Fundatie protectie taluz/sfert de con
335 Tevi ape pluviale 2 days 1/25/23 1/26/23 m 160 80.0 334 337 335 Tevi ape pluviale
336 Umpluturi sfert de con material granular 5 days 1/25/23 1/31/23 mc 1600 320.0 334 337 336 Umpluturi sfert de con material granular
337 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 2/1/23 2/7/23 mp 950 190.0 335,336 338 337 Protectie taluz / sfert con cu pereu de beton C35/45
338 Scari pe taluz 3 days 2/8/23 2/10/23 m 45 15.0 337 339 338 Scari pe taluz
339 Casiuri pe taluz 3 days 2/13/23 2/15/23 m 55 18.3 338 340 339 Casiuri pe taluz
340 Placi racordare C1 3 days 2/16/23 2/20/23 mc 19.25 6.4 339 341 340 Placi racordare C1
341 Hidroizolatie Placa racordare 1 day 2/21/23 2/21/23 mp 47.5 47.5 340 341 Hidroizolatie Placa racordare
342 C2 27 days 2/14/23 3/22/23 342 C2
343 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 2/14/23 2/15/23 mc 125 62.5 329 344 343 Sapatura pentru fundatie protectie taluz/sfert de con
344 Fundatie protectie taluz/sfert de con 5 days 2/16/23 2/22/23 mc 100 20.0 343 346,345 344 Fundatie protectie taluz/sfert de con
345 Tevi ape pluviale 2 days 2/23/23 2/24/23 m 160 80.0 344 347 345 Tevi ape pluviale
346 Umpluturi sfert de con material granular 5 days 2/23/23 3/1/23 mc 1600 320.0 344 347 346 Umpluturi sfert de con material granular
347 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 3/2/23 3/8/23 mp 950 190.0 345,346 348 347 Protectie taluz / sfert con cu pereu de beton C35/45
348 Scari pe taluz 3 days 3/9/23 3/13/23 m 45 15.0 347 349 348 Scari pe taluz
349 Casiuri pe taluz 3 days 3/14/23 3/16/23 m 55 18.3 348 350 349 Casiuri pe taluz
350 Placi racordare C2 3 days 3/17/23 3/21/23 mc 19.25 6.4 349 351 350 Placi racordare C2
351 Hidroizolatie Placa racordare 1 day 3/22/23 3/22/23 mp 47.5 47.5 350 351 Hidroizolatie Placa racordare
352 Suprastructura 66 days 2/21/23 5/29/23 352 Suprastructura
353 Montaj tronsoane tablier 21 days 2/21/23 3/21/23 t 468 22.3 330 354 353 Montaj tronsoane tablier
354 Montaj predale 15 days 3/22/23 4/11/23 mc 150 10.0 353 355SS+5 days 354 Montaj predale
355 Montaj armatura in placa de suprabetonare 20 days 3/29/23 4/28/23 t 80 4.0 354SS+5 days 356SS+10 days,360SS+5 days 355 Montaj armatura in placa de suprabetonare
356 Montaj cofraj la placa de suprabetonare 15 days 4/12/23 5/8/23 mp 480 32.0 355SS+10 days 357SS+10 days 356 Montaj cofraj la placa de suprabetonare
357 Turnare beton in placa de suprabetonare 15 days 5/2/23 5/22/23 mc 520 34.7 360,356SS+10 days 362FS+5 days,361,358FS+4 days 357 Turnare beton in placa de suprabetonare
358 Incercare statica si dinamica cu actiuni de proba pe structura 1 day 5/29/23 5/29/23 buc 1 1.0 357FS+4 days 362 358 Incercare statica si dinamica cu actiuni de proba pe structura
359 Cale, trotuar, parapet 70 days 4/5/23 7/20/23 359 Cale, trotuar, parapet
360 Montaj guri de scurgere 5 days 4/5/23 4/11/23 buc 12 2.4 355SS+5 days 357 360 Montaj guri de scurgere
361 Prefabricat din beton pentru lisa parapet 5 days 5/23/23 5/29/23 m 304 60.8 357 363 361 Prefabricat din beton pentru lisa parapet
362 Hidroizolatie cale 10 days 5/30/23 6/15/23 mp 1600 160.0 357FS+5 days,358 363 362 Hidroizolatie cale
363 Borduri pe Pod 5 days 6/16/23 6/22/23 m 315 63.0 361,362 364,367 363 Borduri pe Pod
364 Trotuare pe pod 10 days 6/23/23 7/6/23 mc 85 8.5 363 365,368 364 Trotuare pe pod
365 Sistem rutier 5 days 7/7/23 7/13/23 mp 1100 220.0 302,364 366 365 Sistem rutier
366 Dispozitive de acoperire a rosturilor 5 days 7/14/23 7/20/23 m 25 5.0 365 366 Dispozitive de acoperire a rosturilor
367 Parapeti pietonali si plase de protectie 10 days 6/23/23 7/6/23 m 304 30.4 363 367 Parapeti pietonali si plase de protectie
368 Parapeti metalici si confectie metalica pentru stalpi 5 days 7/7/23 7/13/23 m 404 80.8 364 369 368 Parapeti metalici si confectie metalica pentru stalpi
369 Marcaje rutiere 5 days 7/14/23 7/20/23 0.0 368 369 Marcaje rutiere
370 Pod peste paraul Raiosu km 27+294 24.00 148 days 11/8/22 7/4/23 370 Pod peste paraul Raiosu km 27+294
371 Fundatii pile si culei 58 days 11/8/22 2/17/23 371 Fundatii pile si culei
372 Culeea 1s 49 days 11/8/22 2/6/23 372 Culeea 1s
373 Piloti forati 4 days 11/8/22 11/11/22 buc 8 2.0 319 377FS+10 days,380,374FS+5 days 373 Piloti forati
374 Sapatura 2 days 11/21/22 11/22/22 mc 324 162.0 373FS+5 days 375 374 Sapatura
375 Demolare capete piloti 2 days 11/23/22 11/24/22 mc 11.25 5.6 374 376 375 Demolare capete piloti
376 Beton de egalizare 1 day 11/25/22 11/25/22 mc 13.75 13.8 375 377 376 Beton de egalizare
377 Teste coloane forate 2 days 11/28/22 11/29/22 buc 9 4.5 373FS+10 days,376 378 377 Teste coloane forate
378 Realizare Radier 5 days 1/31/23 2/6/23 mc 135 27.0 377,329SS+10 days 401,385SS+3 days 378 Realizare Radier
379 Culeea 1d 48 days 11/14/22 2/9/23 379 Culeea 1d
380 Piloti forati 4 days 11/14/22 11/17/22 buc 8 2.0 373 384FS+10 days,387,381FS+5 days 380 Piloti forati
381 Sapatura 2 days 11/25/22 11/28/22 mc 324 162.0 380FS+5 days 382 381 Sapatura
382 Demolare capete piloti 2 days 11/29/22 12/1/22 mc 11.25 5.6 381 383 382 Demolare capete piloti
383 Beton de egalizare 1 day 12/2/22 12/2/22 mc 13.75 13.8 382 384 383 Beton de egalizare
384 Teste coloane forate 2 days 12/5/22 12/6/22 buc 9 4.5 380FS+10 days,383 385 384 Teste coloane forate
385 Realizare Radier 5 days 2/3/23 2/9/23 mc 135 27.0 378SS+3 days,384 402,392SS+3 days 385 Realizare Radier
386 Culeea 2s 47 days 11/18/22 2/14/23 386 Culeea 2s
387 Piloti forati 4 days 11/18/22 11/23/22 buc 8 2.0 380 394,392,388FS+5 days,391FS+10 days 387 Piloti forati
388 Sapatura 2 days 12/2/22 12/5/22 mc 324 162.0 387FS+5 days 389 388 Sapatura
389 Demolare capete piloti 2 days 12/6/22 12/7/22 mc 11.25 5.6 388 390 389 Demolare capete piloti
390 Beton de egalizare 1 day 12/8/22 12/8/22 mc 13.75 13.8 389 391 390 Beton de egalizare
391 Teste coloane forate 2 days 12/9/22 12/12/22 buc 8 4.0 390,387FS+10 days 392 391 Teste coloane forate
392 Realizare Radier 5 days 2/8/23 2/14/23 mc 135 27.0 385SS+3 days,387,391 403,399SS+3 days 392 Realizare Radier
393 Culeea 2d 46 days 11/24/22 2/17/23 393 Culeea 2d
394 Piloti forati 4 days 11/24/22 11/29/22 buc 8 2.0 387 399FS+10 days,595,395FS+5 days,398FS+10 days 394 Piloti forati
395 Sapatura 2 days 12/8/22 12/9/22 mc 324 162.0 394FS+5 days 396 395 Sapatura
396 Demolare capete piloti 2 days 12/12/22 12/13/22 mc 11.25 5.6 395 397 396 Demolare capete piloti
397 Beton de egalizare 1 day 12/14/22 12/14/22 mc 13.75 13.8 396 398 397 Beton de egalizare
398 Teste coloane forate 2 days 12/15/22 12/16/22 buc 8 4.0 397,394FS+10 days 399 398 Teste coloane forate
399 Realizare Radier 5 days 2/13/23 2/17/23 mc 135 27.0 392SS+3 days,394FS+10 days,398 404,401SS+2 days 399 Realizare Radier
400 Elevatii pile si culei 36 days 2/15/23 4/5/23 400 Elevatii pile si culei
401 Elevatie si banchete C1s 10 days 2/15/23 2/28/23 mc 215 21.5 378,399SS+2 days 402SS+7 days 401 Elevatie si banchete C1s
402 Elevatie si banchete C1d 10 days 2/24/23 3/9/23 mc 215 21.5 401SS+7 days,385 403SS+7 days,408 402 Elevatie si banchete C1d
403 Elevatie si banchete C2s 10 days 3/7/23 3/20/23 mc 215 21.5 402SS+7 days,392 404SS+7 days 403 Elevatie si banchete C2s
404 Elevatie si banchete C2d 10 days 3/16/23 3/29/23 mc 215 21.5 403SS+7 days,399 405,600SS+10 days,419 404 Elevatie si banchete C2d
405 Montare dispozitive antiseismice si aparate reazem 5 days 3/30/23 4/5/23 buc 20 4.0 404 430 405 Montare dispozitive antiseismice si aparate reazem
406 Racordari cu terasamente 45 days 3/10/23 5/17/23 406 Racordari cu terasamente
407 C1 45 days 3/10/23 5/17/23 407 C1
408 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 3/10/23 3/13/23 mc 70 35.0 402 409 408 Sapatura pentru fundatie protectie taluz/sfert de con
409 Fundatie protectie taluz/sfert de con 5 days 3/14/23 3/20/23 mc 55 11.0 408 412,410,411 409 Fundatie protectie taluz/sfert de con
410 Dren din geotextil 2 days 3/21/23 3/22/23 mp 300 150.0 409 413 410 Dren din geotextil
411 Tevi ape pluviale 2 days 3/21/23 3/22/23 m 30 15.0 409 413 411 Tevi ape pluviale
412 Umpluturi sfert de con material granular 5 days 3/21/23 3/27/23 mc 742.5 148.5 409 413 412 Umpluturi sfert de con material granular
413 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 3/28/23 4/3/23 mp 362.5 72.5 410,411,412 414 413 Protectie taluz / sfert con cu pereu de beton C35/45
414 Scari pe taluz 3 days 4/4/23 4/6/23 m 27 9.0 413 415 414 Scari pe taluz
415 Casiuri pe taluz 3 days 4/7/23 4/11/23 m 35 11.7 414 415 Casiuri pe taluz
416 Placi racordare C1 3 days 5/12/23 5/16/23 mc 62 20.7 434 417 416 Placi racordare C1
417 Hidroizolatie Placa racordare 1 day 5/17/23 5/17/23 mp 175 175.0 416 417 Hidroizolatie Placa racordare
418 C2 31 days 3/30/23 5/17/23 418 C2
419 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 3/30/23 3/31/23 mc 70 35.0 404 420 419 Sapatura pentru fundatie protectie taluz/sfert de con
420 Fundatie protectie taluz/sfert de con 5 days 4/3/23 4/7/23 mc 55 11.0 419 423,421,422 420 Fundatie protectie taluz/sfert de con
421 Dren din geotextil 2 days 4/10/23 4/11/23 mp 300 150.0 420 424 421 Dren din geotextil
422 Tevi ape pluviale 2 days 4/10/23 4/11/23 m 30 15.0 420 424 422 Tevi ape pluviale
423 Umpluturi sfert de con material granular 5 days 4/10/23 4/19/23 mc 742.5 148.5 420 424 423 Umpluturi sfert de con material granular
424 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 4/20/23 4/26/23 mp 362.5 72.5 421,422,423 425 424 Protectie taluz / sfert con cu pereu de beton C35/45
425 Scari pe taluz 3 days 4/27/23 5/2/23 m 27 9.0 424 426 425 Scari pe taluz
426 Casiuri pe taluz 3 days 5/3/23 5/5/23 m 35 11.7 425 426 Casiuri pe taluz
427 Placi racordare C2 3 days 5/12/23 5/16/23 mc 62 20.7 434 428 427 Placi racordare C2
428 Hidroizolatie Placa racordare 1 day 5/17/23 5/17/23 mp 175 175.0 427 428 Hidroizolatie Placa racordare

Seite 4
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
429 Suprastructura 22 days 4/6/23 5/11/23 429 Suprastructura
430 Montaj grinzi 10 days 4/6/23 4/24/23 buc 12 1.2 405 431 430 Montaj grinzi
431 Montaj predale 3 days 4/25/23 4/27/23 mc 66 22.0 430 432 431 Montaj predale
432 Montaj armatura in placa de suprabetonare si antretoaze 5 days 4/28/23 5/5/23 t 43.5 8.7 431 433SS+2 days,436SS+2 days 432 Montaj armatura in placa de suprabetonare si antretoaze
433 Montaj cofraj la placa de suprabetonare 5 days 5/3/23 5/9/23 mp 200 40.0 432SS+2 days 434SS+2 days 433 Montaj cofraj la placa de suprabetonare
434 Turnare beton in placa de suprabetonare si antretoaze 5 days 5/5/23 5/11/23 mc 276 55.2 436,433SS+2 days 438FS+5 days,437,416,427 434 Turnare beton in placa de suprabetonare si antretoaze
435 Cale, trotuar, parapet 42 days 5/3/23 7/4/23 435 Cale, trotuar, parapet
436 Montaj guri de scurgere 2 days 5/3/23 5/4/23 buc 4 2.0 432SS+2 days 434 436 Montaj guri de scurgere
437 Prefabricat din beton pentru lisa parapet 5 days 5/12/23 5/18/23 m 128 25.6 434 439 437 Prefabricat din beton pentru lisa parapet
438 Hidroizolatie cale 10 days 5/19/23 6/6/23 mp 650 65.0 434FS+5 days 439 438 Hidroizolatie cale
439 Borduri pe Pod 5 days 6/7/23 6/13/23 m 128 25.6 437,438 440 439 Borduri pe Pod
440 Sistem rutier 5 days 6/14/23 6/20/23 mp 576 115.2 439 441,442 440 Sistem rutier
441 Dispozitive de acoperire a rosturilor 5 days 6/21/23 6/27/23 m 56 11.2 440 441 Dispozitive de acoperire a rosturilor
442 Parapeti metalici 5 days 6/21/23 6/27/23 m 328 65.6 440 443 442 Parapeti metalici
443 Marcaje rutiere 5 days 6/28/23 7/4/23 0.0 442 443 Marcaje rutiere
444 Pod pe drum agricol peste autostrada km 29+623 88.00 177 days 8/26/22 5/29/23 444 Pod pe drum agricol peste autostrada km 29+623
445 Fundatii pile si culei 59 days 8/26/22 11/16/22 445 Fundatii pile si culei
446 Culeea 1 50 days 8/26/22 11/3/22 446 Culeea 1
447 Piloti forati 4 days 8/26/22 8/31/22 buc 8 2.0 245 451FS+10 days,454,448FS+5 days 447 Piloti forati
448 Sapatura 2 days 9/8/22 9/9/22 mc 288 144.0 447FS+5 days 449 448 Sapatura
449 Demolare capete piloti 2 days 9/12/22 9/13/22 mc 9 4.5 448 450 449 Demolare capete piloti
450 Beton de egalizare 1 day 9/14/22 9/14/22 mc 12 12.0 449 451 450 Beton de egalizare
451 Teste coloane forate 2 days 9/15/22 9/16/22 buc 9 4.5 447FS+10 days,450 452,513 451 Teste coloane forate
452 Realizare Radier 5 days 10/28/22 11/3/22 mc 117 23.4 451,255SS+10 days 475,459SS+3 days 452 Realizare Radier
453 Pila 1 49 days 9/1/22 11/8/22 453 Pila 1
454 Piloti forati 4 days 9/1/22 9/6/22 buc 8 2.0 447 458FS+10 days,461,455FS+5 days 454 Piloti forati
455 Sapatura 2 days 9/14/22 9/15/22 mc 288 144.0 454FS+5 days 456 455 Sapatura
456 Demolare capete piloti 2 days 9/16/22 9/19/22 mc 9 4.5 455 457 456 Demolare capete piloti
457 Beton de egalizare 1 day 9/20/22 9/20/22 mc 12 12.0 456 458 457 Beton de egalizare
458 Teste coloane forate 2 days 9/21/22 9/22/22 buc 9 4.5 454FS+10 days,457 459 458 Teste coloane forate
459 Realizare Radier 5 days 11/2/22 11/8/22 mc 117 23.4 452SS+3 days,458 476,466SS+3 days 459 Realizare Radier
460 Pila 2 48 days 9/7/22 11/11/22 460 Pila 2
461 Piloti forati 4 days 9/7/22 9/12/22 buc 8 2.0 454 468,466,462FS+5 days,465FS+10 days 461 Piloti forati
462 Sapatura 2 days 9/20/22 9/21/22 mc 288 144.0 461FS+5 days 463 462 Sapatura
463 Demolare capete piloti 2 days 9/22/22 9/23/22 mc 9 4.5 462 464 463 Demolare capete piloti
464 Beton de egalizare 1 day 9/26/22 9/26/22 mc 12 12.0 463 465 464 Beton de egalizare
465 Teste coloane forate 2 days 9/27/22 9/28/22 buc 8 4.0 464,461FS+10 days 466 465 Teste coloane forate
466 Realizare Radier 5 days 11/7/22 11/11/22 mc 117 23.4 459SS+3 days,461,465 477,473SS+3 days 466 Realizare Radier
467 Culeea 2 47 days 9/13/22 11/16/22 467 Culeea 2
468 Piloti forati 4 days 9/13/22 9/16/22 buc 8 2.0 461 473FS+10 days,521,469FS+5 days,472FS+10 days 468 Piloti forati
469 Sapatura 2 days 9/26/22 9/27/22 mc 288 144.0 468FS+5 days 470 469 Sapatura
470 Demolare capete piloti 2 days 9/28/22 9/29/22 mc 9 4.5 469 471 470 Demolare capete piloti
471 Beton de egalizare 1 day 9/30/22 9/30/22 mc 12 12.0 470 472 471 Beton de egalizare
472 Teste coloane forate 2 days 10/3/22 10/4/22 buc 8 4.0 471,468FS+10 days 473 472 Teste coloane forate
473 Realizare Radier 5 days 11/10/22 11/16/22 mc 117 23.4 466SS+3 days,468FS+10 days,472 478,475SS+2 days 473 Realizare Radier
474 Elevatii pile si culei 41 days 11/14/22 1/31/23 474 Elevatii pile si culei
475 Elevatie si banchete C1 15 days 11/14/22 12/5/22 mc 140 9.3 452,473SS+2 days 476SS+7 days,482 475 Elevatie si banchete C1
476 Elevatie si Rigla P1 10 days 11/23/22 12/7/22 mc 140 14.0 475SS+7 days,459 477SS+7 days 476 Elevatie si Rigla P1
477 Elevatie si Rigla P2 10 days 12/5/22 12/16/22 mc 140 14.0 476SS+7 days,466 478SS+7 days 477 Elevatie si Rigla P2
478 Elevatie si banchete C2 15 days 12/14/22 1/24/23 mc 140 9.3 477SS+7 days,473 479,526SS+10 days,492 478 Elevatie si banchete C2
479 Montare dispozitive antiseismice si aparate reazem 5 days 1/25/23 1/31/23 buc 20 4.0 478 502 479 Montare dispozitive antiseismice si aparate reazem
480 Racordari cu terasamente 75 days 12/6/22 4/10/23 480 Racordari cu terasamente
481 C1 75 days 12/6/22 4/10/23 481 C1
482 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 12/6/22 12/7/22 mc 200 100.0 475 483 482 Sapatura pentru fundatie protectie taluz/sfert de con
483 Fundatie protectie taluz/sfert de con 5 days 12/8/22 12/14/22 mc 160 32.0 482 485,484 483 Fundatie protectie taluz/sfert de con
484 Tevi ape pluviale 2 days 12/15/22 12/16/22 m 95 47.5 483 486 484 Tevi ape pluviale
485 Umpluturi sfert de con material granular 5 days 12/15/22 1/11/23 mc 3000 600.0 483 486 485 Umpluturi sfert de con material granular
486 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 1/12/23 1/18/23 mp 1150 230.0 484,485 487 486 Protectie taluz / sfert con cu pereu de beton C35/45
487 Scari pe taluz 3 days 1/19/23 1/23/23 m 45 15.0 486 488 487 Scari pe taluz
488 Casiuri pe taluz 3 days 1/24/23 1/26/23 m 55 18.3 487 488 Casiuri pe taluz
489 Placi racordare C1 3 days 4/5/23 4/7/23 mc 18.5 6.2 506 490 489 Placi racordare C1
490 Hidroizolatie Placa racordare 1 day 4/10/23 4/10/23 mp 62.5 62.5 489 490 Hidroizolatie Placa racordare
491 C2 54 days 1/25/23 4/10/23 491 C2
492 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 1/25/23 1/26/23 mc 200 100.0 478 493 492 Sapatura pentru fundatie protectie taluz/sfert de con
493 Fundatie protectie taluz/sfert de con 5 days 1/27/23 2/2/23 mc 160 32.0 492 495,494 493 Fundatie protectie taluz/sfert de con
494 Tevi ape pluviale 2 days 2/3/23 2/6/23 m 95 47.5 493 496 494 Tevi ape pluviale
495 Umpluturi sfert de con material granular 5 days 2/3/23 2/9/23 mc 3000 600.0 493 496 495 Umpluturi sfert de con material granular
496 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 2/10/23 2/16/23 mp 1150 230.0 494,495 497 496 Protectie taluz / sfert con cu pereu de beton C35/45
497 Scari pe taluz 3 days 2/17/23 2/21/23 m 45 15.0 496 498 497 Scari pe taluz
498 Casiuri pe taluz 3 days 2/22/23 2/24/23 m 55 18.3 497 498 Casiuri pe taluz
499 Placi racordare C2 3 days 4/5/23 4/7/23 mc 18.5 6.2 506 500 499 Placi racordare C2
500 Hidroizolatie Placa racordare 1 day 4/10/23 4/10/23 mp 62.5 62.5 499 500 Hidroizolatie Placa racordare
501 Suprastructura 45 days 2/1/23 4/4/23 501 Suprastructura
502 Montaj grinzi 10 days 2/1/23 2/14/23 buc 18 1.8 479 503 502 Montaj grinzi
503 Montaj predale 10 days 2/15/23 2/28/23 mc 99 9.9 502 504SS+5 days 503 Montaj predale
504 Montaj armatura in placa de suprabetonare si antretoaze 15 days 2/22/23 3/14/23 t 56.5 3.8 503SS+5 days 505SS+10 days,508SS+5 days 504 Montaj armatura in placa de suprabetonare si antretoaze
505 Montaj cofraj la placa de suprabetonare 15 days 3/8/23 3/28/23 mp 200 13.3 504SS+10 days 506SS+10 days 505 Montaj cofraj la placa de suprabetonare
506 Turnare beton in placa de suprabetonare si antretoaze 10 days 3/22/23 4/4/23 mc 360 36.0 508,505SS+10 days 510FS+5 days,509,489,499 506 Turnare beton in placa de suprabetonare si antretoaze
507 Cale, trotuar, parapet 60 days 3/1/23 5/29/23 507 Cale, trotuar, parapet
508 Montaj guri de scurgere 5 days 3/1/23 3/7/23 buc 12 2.4 504SS+5 days 506 508 Montaj guri de scurgere
509 Prefabricat din beton pentru lisa parapet 5 days 4/5/23 4/11/23 m 196 39.2 506 511 509 Prefabricat din beton pentru lisa parapet
510 Hidroizolatie cale 10 days 4/12/23 4/28/23 mp 1075 107.5 506FS+5 days 511 510 Hidroizolatie cale
511 Borduri pe Pod 5 days 5/2/23 5/8/23 m 196 39.2 509,510 512,515 511 Borduri pe Pod
512 Trotuare pe pod 5 days 5/9/23 5/15/23 mc 71 14.2 511 513,516 512 Trotuare pe pod
513 Sistem rutier 5 days 5/16/23 5/22/23 mp 620 124.0 451,512 514 513 Sistem rutier
514 Dispozitive de acoperire a rosturilor 5 days 5/23/23 5/29/23 m 25 5.0 513 514 Dispozitive de acoperire a rosturilor
515 Parapeti pietonali si plase de protectie 10 days 5/9/23 5/22/23 m 196 19.6 511 515 Parapeti pietonali si plase de protectie
516 Parapeti metalici 5 days 5/16/23 5/22/23 m 296 59.2 512 517 516 Parapeti metalici
517 Marcaje rutiere 5 days 5/23/23 5/29/23 0.0 516 517 Marcaje rutiere
518 Pod pe DC 54 peste autostrada km 32+165 88.00 203 days 9/19/22 7/31/23 518 Pod pe DC 54 peste autostrada km 32+165
519 Fundatii pile si culei 85 days 9/19/22 2/6/23 519 Fundatii pile si culei
520 Culeea 1 76 days 9/19/22 1/24/23 520 Culeea 1
521 Piloti forati 4 days 9/19/22 9/22/22 buc 8 2.0 468 525FS+10 days,528,522FS+5 days 521 Piloti forati
522 Sapatura 2 days 9/30/22 10/3/22 mc 288 144.0 521FS+5 days 523 522 Sapatura
523 Demolare capete piloti 2 days 10/4/22 10/5/22 mc 9 4.5 522 524 523 Demolare capete piloti
524 Beton de egalizare 1 day 10/6/22 10/6/22 mc 12 12.0 523 525 524 Beton de egalizare
525 Teste coloane forate 2 days 10/7/22 10/10/22 buc 9 4.5 521FS+10 days,524 526 525 Teste coloane forate
526 Realizare Radier 5 days 1/18/23 1/24/23 mc 117 23.4 525,478SS+10 days 549,533SS+3 days 526 Realizare Radier
527 Pila 1 75 days 9/23/22 1/27/23 527 Pila 1
528 Piloti forati 4 days 9/23/22 9/28/22 buc 8 2.0 521 532FS+10 days,535,529FS+5 days 528 Piloti forati
529 Sapatura 2 days 10/6/22 10/7/22 mc 288 144.0 528FS+5 days 530 529 Sapatura
530 Demolare capete piloti 2 days 10/10/22 10/11/22 mc 9 4.5 529 531 530 Demolare capete piloti
531 Beton de egalizare 1 day 10/12/22 10/12/22 mc 12 12.0 530 532 531 Beton de egalizare
532 Teste coloane forate 2 days 10/13/22 10/14/22 buc 9 4.5 528FS+10 days,531 533 532 Teste coloane forate
533 Realizare Radier 5 days 1/23/23 1/27/23 mc 117 23.4 526SS+3 days,532 550,540SS+3 days 533 Realizare Radier
534 Pila 2 74 days 9/29/22 2/1/23 534 Pila 2
535 Piloti forati 4 days 9/29/22 10/4/22 buc 8 2.0 528 542,540,536FS+5 days,539FS+10 days 535 Piloti forati

Seite 5
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
536 Sapatura 2 days 10/12/22 10/13/22 mc 288 144.0 535FS+5 days 537 536 Sapatura
537 Demolare capete piloti 2 days 10/14/22 10/17/22 mc 9 4.5 536 538 537 Demolare capete piloti
538 Beton de egalizare 1 day 10/18/22 10/18/22 mc 12 12.0 537 539 538 Beton de egalizare
539 Teste coloane forate 2 days 10/19/22 10/20/22 buc 8 4.0 538,535FS+10 days 540 539 Teste coloane forate
540 Realizare Radier 5 days 1/26/23 2/1/23 mc 117 23.4 533SS+3 days,535,539 551,547SS+3 days 540 Realizare Radier
541 Culeea 2 73 days 10/5/22 2/6/23 541 Culeea 2
542 Piloti forati 4 days 10/5/22 10/10/22 buc 8 2.0 535 547FS+10 days,298,543FS+5 days,546FS+10 days 542 Piloti forati
543 Sapatura 2 days 10/18/22 10/19/22 mc 288 144.0 542FS+5 days 544 543 Sapatura
544 Demolare capete piloti 2 days 10/20/22 10/21/22 mc 9 4.5 543 545 544 Demolare capete piloti
545 Beton de egalizare 1 day 10/24/22 10/24/22 mc 12 12.0 544 546 545 Beton de egalizare
546 Teste coloane forate 2 days 10/25/22 10/26/22 buc 8 4.0 545,542FS+10 days 547 546 Teste coloane forate
547 Realizare Radier 5 days 1/31/23 2/6/23 mc 117 23.4 540SS+3 days,542FS+10 days,546 552,549SS+2 days 547 Realizare Radier
548 Elevatii pile si culei 41 days 2/2/23 3/30/23 548 Elevatii pile si culei
549 Elevatie si banchete C1 15 days 2/2/23 2/22/23 mc 140 9.3 526,547SS+2 days 550SS+7 days,556 549 Elevatie si banchete C1
550 Elevatie si Rigla P1 10 days 2/13/23 2/24/23 mc 140 14.0 549SS+7 days,533 551SS+7 days 550 Elevatie si Rigla P1
551 Elevatie si Rigla P2 10 days 2/22/23 3/7/23 mc 140 14.0 550SS+7 days,540 552SS+7 days 551 Elevatie si Rigla P2
552 Elevatie si banchete C2 15 days 3/3/23 3/23/23 mc 140 9.3 551SS+7 days,547 553,566 552 Elevatie si banchete C2
553 Montare dispozitive antiseismice si aparate reazem 5 days 3/24/23 3/30/23 buc 20 4.0 552 576 553 Montare dispozitive antiseismice si aparate reazem
554 Racordari cu terasamente 75 days 2/23/23 6/16/23 554 Racordari cu terasamente
555 C1 75 days 2/23/23 6/16/23 555 C1
556 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 2/23/23 2/24/23 mc 200 100.0 549 557 556 Sapatura pentru fundatie protectie taluz/sfert de con
557 Fundatie protectie taluz/sfert de con 5 days 2/27/23 3/3/23 mc 160 32.0 556 559,558 557 Fundatie protectie taluz/sfert de con
558 Tevi ape pluviale 2 days 3/6/23 3/7/23 m 95 47.5 557 560 558 Tevi ape pluviale
559 Umpluturi sfert de con material granular 5 days 3/6/23 3/10/23 mc 3000 600.0 557 560 559 Umpluturi sfert de con material granular
560 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 3/13/23 3/17/23 mp 1150 230.0 558,559 561 560 Protectie taluz / sfert con cu pereu de beton C35/45
561 Scari pe taluz 3 days 3/20/23 3/22/23 m 45 15.0 560 562 561 Scari pe taluz
562 Casiuri pe taluz 3 days 3/23/23 3/27/23 m 55 18.3 561 562 Casiuri pe taluz
563 Placi racordare C1 3 days 6/13/23 6/15/23 mc 21 7.0 580 564 563 Placi racordare C1
564 Hidroizolatie Placa racordare 1 day 6/16/23 6/16/23 mp 62.5 62.5 563 564 Hidroizolatie Placa racordare
565 C2 54 days 3/24/23 6/16/23 565 C2
566 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 3/24/23 3/27/23 mc 200 100.0 552 567 566 Sapatura pentru fundatie protectie taluz/sfert de con
567 Fundatie protectie taluz/sfert de con 5 days 3/28/23 4/3/23 mc 160 32.0 566 569,568 567 Fundatie protectie taluz/sfert de con
568 Tevi ape pluviale 2 days 4/4/23 4/5/23 m 95 47.5 567 570 568 Tevi ape pluviale
569 Umpluturi sfert de con material granular 5 days 4/4/23 4/10/23 mc 3000 600.0 567 570 569 Umpluturi sfert de con material granular
570 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 4/11/23 4/20/23 mp 1150 230.0 568,569 571 570 Protectie taluz / sfert con cu pereu de beton C35/45
571 Scari pe taluz 3 days 4/21/23 4/25/23 m 45 15.0 570 572 571 Scari pe taluz
572 Casiuri pe taluz 3 days 4/26/23 4/28/23 m 55 18.3 571 572 Casiuri pe taluz
573 Placi racordare C2 3 days 6/13/23 6/15/23 mc 21 7.0 580 574 573 Placi racordare C2
574 Hidroizolatie Placa racordare 1 day 6/16/23 6/16/23 mp 62.5 62.5 573 574 Hidroizolatie Placa racordare
575 Suprastructura 45 days 3/31/23 6/12/23 575 Suprastructura
576 Montaj grinzi 10 days 3/31/23 4/13/23 buc 18 1.8 553 577 576 Montaj grinzi
577 Montaj predale 10 days 4/19/23 5/3/23 mc 106 10.6 576 578SS+5 days 577 Montaj predale
578 Montaj armatura in placa de suprabetonare si antretoaze 15 days 4/26/23 5/17/23 t 56.5 3.8 577SS+5 days 579SS+10 days,582SS+5 days 578 Montaj armatura in placa de suprabetonare si antretoaze
579 Montaj cofraj la placa de suprabetonare 15 days 5/11/23 5/31/23 mp 215 14.3 578SS+10 days 580SS+10 days 579 Montaj cofraj la placa de suprabetonare
580 Turnare beton in placa de suprabetonare si antretoaze 10 days 5/25/23 6/12/23 mc 365 36.5 582,579SS+10 days 584FS+5 days,583,563,573 580 Turnare beton in placa de suprabetonare si antretoaze
581 Cale, trotuar, parapet 60 days 5/4/23 7/31/23 581 Cale, trotuar, parapet
582 Montaj guri de scurgere 5 days 5/4/23 5/10/23 buc 12 2.4 578SS+5 days 580 582 Montaj guri de scurgere
583 Prefabricat din beton pentru lisa parapet 5 days 6/13/23 6/19/23 m 196 39.2 580 585 583 Prefabricat din beton pentru lisa parapet
584 Hidroizolatie cale 10 days 6/20/23 7/3/23 mp 1144 114.4 580FS+5 days 585 584 Hidroizolatie cale
585 Borduri pe Pod 5 days 7/4/23 7/10/23 m 196 39.2 583,584 586,589 585 Borduri pe Pod
586 Trotuare pe pod 5 days 7/11/23 7/17/23 mc 71 14.2 585 587,590 586 Trotuare pe pod
587 Sistem rutier 5 days 7/18/23 7/24/23 mp 690 138.0 586 588 587 Sistem rutier
588 Dispozitive de acoperire a rosturilor 5 days 7/25/23 7/31/23 m 25 5.0 587 588 Dispozitive de acoperire a rosturilor
589 Parapeti pietonali si plase de protectie 10 days 7/11/23 7/24/23 m 196 19.6 585 589 Parapeti pietonali si plase de protectie
590 Parapeti metalici 5 days 7/18/23 7/24/23 m 296 59.2 586 591 590 Parapeti metalici
591 Marcaje rutiere 5 days 7/25/23 7/31/23 0.0 590 591 Marcaje rutiere
592 Pod pe DJ 103R peste autostrada km 33+755 140.00 230 days 12/1/22 11/21/23 592 Pod pe DJ 103R peste autostrada km 33+755
593 Fundatii pile si culei 84 days 12/1/22 4/21/23 593 Fundatii pile si culei
594 Culeea 1 75 days 12/1/22 4/5/23 594 Culeea 1
595 Piloti forati 5 days 12/1/22 12/7/22 buc 9 1.8 394 599FS+10 days,602,596FS+5 days 595 Piloti forati
596 Sapatura 2 days 12/15/22 12/16/22 mc 277.5 138.8 595FS+5 days 597 596 Sapatura
597 Demolare capete piloti 2 days 1/9/23 1/10/23 mc 12.5 6.3 596 598 597 Demolare capete piloti
598 Beton de egalizare 1 day 1/11/23 1/11/23 mc 11.25 11.3 597 599 598 Beton de egalizare
599 Teste coloane forate 2 days 1/12/23 1/13/23 buc 10 5.0 595FS+10 days,598 600,661 599 Teste coloane forate
600 Realizare Radier 5 days 3/30/23 4/5/23 mc 180 36.0 599,404SS+10 days 623,607SS+3 days 600 Realizare Radier
601 Pila 1 73 days 12/8/22 4/10/23 601 Pila 1
602 Piloti forati 5 days 12/8/22 12/14/22 buc 9 1.8 595 606FS+10 days,609,603FS+5 days 602 Piloti forati
603 Sapatura 2 days 1/12/23 1/13/23 mc 277.5 138.8 602FS+5 days 604 603 Sapatura
604 Demolare capete piloti 2 days 1/16/23 1/17/23 mc 12.5 6.3 603 605 604 Demolare capete piloti
605 Beton de egalizare 1 day 1/18/23 1/18/23 mc 11.25 11.3 604 606 605 Beton de egalizare
606 Teste coloane forate 2 days 1/19/23 1/20/23 buc 10 5.0 602FS+10 days,605 607 606 Teste coloane forate
607 Realizare Radier 5 days 4/4/23 4/10/23 mc 180 36.0 600SS+3 days,606 624,614SS+3 days 607 Realizare Radier
608 Pila 2 71 days 12/15/22 4/13/23 608 Pila 2
609 Piloti forati 5 days 12/15/22 1/11/23 buc 9 1.8 602 616,614,610FS+5 days,613FS+10 days 609 Piloti forati
610 Sapatura 2 days 1/19/23 1/20/23 mc 277.5 138.8 609FS+5 days 611 610 Sapatura
611 Demolare capete piloti 2 days 1/23/23 1/24/23 mc 12.5 6.3 610 612 611 Demolare capete piloti
612 Beton de egalizare 1 day 1/25/23 1/25/23 mc 11.25 11.3 611 613 612 Beton de egalizare
613 Teste coloane forate 2 days 1/26/23 1/27/23 buc 10 5.0 612,609FS+10 days 614 613 Teste coloane forate
614 Realizare Radier 5 days 4/7/23 4/13/23 mc 180 36.0 607SS+3 days,609,613 625,621SS+3 days 614 Realizare Radier
615 Culeea 2 69 days 1/12/23 4/21/23 615 Culeea 2
616 Piloti forati 5 days 1/12/23 1/18/23 buc 9 1.8 609 621FS+10 days,617FS+5 days,620FS+10 days 616 Piloti forati
617 Sapatura 2 days 1/26/23 1/27/23 mc 277.5 138.8 616FS+5 days 618 617 Sapatura
618 Demolare capete piloti 2 days 1/30/23 1/31/23 mc 12.5 6.3 617 619 618 Demolare capete piloti
619 Beton de egalizare 1 day 2/1/23 2/1/23 mc 11.25 11.3 618 620 619 Beton de egalizare
620 Teste coloane forate 2 days 2/2/23 2/3/23 buc 10 5.0 619,616FS+10 days 621 620 Teste coloane forate
621 Realizare Radier 5 days 4/12/23 4/21/23 mc 180 36.0 614SS+3 days,616FS+10 days,620 626,623SS+2 days 621 Realizare Radier
622 Elevatii pile si culei 46 days 4/19/23 6/27/23 622 Elevatii pile si culei
623 Elevatie si banchete C1 20 days 4/19/23 5/17/23 mc 97.5 4.9 600,621SS+2 days 624SS+7 days,630 623 Elevatie si banchete C1
624 Elevatie si Rigla P1 15 days 4/28/23 5/19/23 mc 97.5 6.5 623SS+7 days,607 625SS+7 days 624 Elevatie si Rigla P1
625 Elevatie si Rigla P2 15 days 5/10/23 5/30/23 mc 97.5 6.5 624SS+7 days,614 626SS+7 days 625 Elevatie si Rigla P2
626 Elevatie si banchete C2 20 days 5/19/23 6/20/23 mc 97.5 4.9 625SS+7 days,621 627,640 626 Elevatie si banchete C2
627 Montare dispozitive antiseismice si aparate reazem 5 days 6/21/23 6/27/23 buc 20 4.0 626 650 627 Montare dispozitive antiseismice si aparate reazem
628 Racordari cu terasamente 93 days 5/18/23 10/2/23 628 Racordari cu terasamente
629 C1 93 days 5/18/23 10/2/23 629 C1
630 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 5/18/23 5/19/23 mc 125 62.5 623 631 630 Sapatura pentru fundatie protectie taluz/sfert de con
631 Fundatie protectie taluz/sfert de con 5 days 5/22/23 5/26/23 mc 100 20.0 630 633,632 631 Fundatie protectie taluz/sfert de con
632 Tevi ape pluviale 2 days 5/29/23 5/30/23 m 160 80.0 631 634 632 Tevi ape pluviale
633 Umpluturi sfert de con material granular 5 days 5/29/23 6/7/23 mc 1600 320.0 631 634 633 Umpluturi sfert de con material granular
634 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 6/8/23 6/14/23 mp 950 190.0 632,633 635 634 Protectie taluz / sfert con cu pereu de beton C35/45
635 Scari pe taluz 3 days 6/15/23 6/19/23 m 45 15.0 634 636 635 Scari pe taluz
636 Casiuri pe taluz 3 days 6/20/23 6/22/23 m 55 18.3 635 636 Casiuri pe taluz
637 Placi racordare C1 3 days 9/27/23 9/29/23 mc 19.25 6.4 654 638 637 Placi racordare C1
638 Hidroizolatie Placa racordare 1 day 10/2/23 10/2/23 mp 47.5 47.5 637 638 Hidroizolatie Placa racordare
639 C2 72 days 6/21/23 10/2/23 639 C2
640 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 6/21/23 6/22/23 mc 125 62.5 626 641 640 Sapatura pentru fundatie protectie taluz/sfert de con
641 Fundatie protectie taluz/sfert de con 5 days 6/23/23 6/29/23 mc 100 20.0 640 643,642 641 Fundatie protectie taluz/sfert de con
642 Tevi ape pluviale 2 days 6/30/23 7/3/23 m 160 80.0 641 644 642 Tevi ape pluviale

Seite 6
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
643 Umpluturi sfert de con material granular 5 days 6/30/23 7/6/23 mc 1600 320.0 641 644 643 Umpluturi sfert de con material granular
644 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 7/7/23 7/13/23 mp 950 190.0 642,643 645 644 Protectie taluz / sfert con cu pereu de beton C35/45
645 Scari pe taluz 3 days 7/14/23 7/18/23 m 45 15.0 644 646 645 Scari pe taluz
646 Casiuri pe taluz 3 days 7/19/23 7/21/23 m 55 18.3 645 646 Casiuri pe taluz
647 Placi racordare C2 3 days 9/27/23 9/29/23 mc 19.25 6.4 654 648 647 Placi racordare C2
648 Hidroizolatie Placa racordare 1 day 10/2/23 10/2/23 mp 47.5 47.5 647 648 Hidroizolatie Placa racordare
649 Suprastructura 63 days 6/28/23 9/26/23 649 Suprastructura
650 Montaj tronsoane tablier 23 days 6/28/23 7/28/23 t 468 20.3 627 651 650 Montaj tronsoane tablier
651 Montaj predale 15 days 7/31/23 8/22/23 mc 150 10.0 650 652SS+5 days 651 Montaj predale
652 Montaj armatura in placa de suprabetonare 20 days 8/7/23 9/5/23 t 80 4.0 651SS+5 days 653SS+10 days,656SS+5 days 652 Montaj armatura in placa de suprabetonare
653 Montaj cofraj la placa de suprabetonare 15 days 8/23/23 9/12/23 mp 480 32.0 652SS+10 days 654SS+10 days 653 Montaj cofraj la placa de suprabetonare
654 Turnare beton in placa de suprabetonare 15 days 9/6/23 9/26/23 mc 520 34.7 656,653SS+10 days 658FS+5 days,657,637,647 654 Turnare beton in placa de suprabetonare
655 Cale, trotuar, parapet 70 days 8/16/23 11/21/23 655 Cale, trotuar, parapet
656 Montaj guri de scurgere 5 days 8/16/23 8/22/23 buc 12 2.4 652SS+5 days 654 656 Montaj guri de scurgere
657 Prefabricat din beton pentru lisa parapet 5 days 9/27/23 10/3/23 m 304 60.8 654 659 657 Prefabricat din beton pentru lisa parapet
658 Hidroizolatie cale 10 days 10/4/23 10/17/23 mp 1600 160.0 654FS+5 days 659 658 Hidroizolatie cale
659 Borduri pe Pod 5 days 10/18/23 10/24/23 m 315 63.0 657,658 660,663 659 Borduri pe Pod
660 Trotuare pe pod 10 days 10/25/23 11/7/23 mc 85 8.5 659 661,664 660 Trotuare pe pod
661 Sistem rutier 5 days 11/8/23 11/14/23 mp 1100 220.0 599,660 662 661 Sistem rutier
662 Dispozitive de acoperire a rosturilor 5 days 11/15/23 11/21/23 m 25 5.0 661 662 Dispozitive de acoperire a rosturilor
663 Parapeti pietonali si plase de protectie 10 days 10/25/23 11/7/23 m 304 30.4 659 663 Parapeti pietonali si plase de protectie
664 Parapeti metalici si confectie metalica pentru stalpi 5 days 11/8/23 11/14/23 m 404 80.8 660 665 664 Parapeti metalici si confectie metalica pentru stalpi
665 Marcaje rutiere 5 days 11/15/23 11/21/23 0.0 664 665 Marcaje rutiere
666 Pod peste paraul Naianca km 34+369 30.00 136 days 11/8/22 6/16/23 666 Pod peste paraul Naianca km 34+369
667 Fundatii pile si culei 41 days 11/8/22 1/25/23 667 Fundatii pile si culei
668 Culeea 1s 32 days 11/8/22 1/12/23 668 Culeea 1s
669 Piloti forati 5 days 11/8/22 11/14/22 buc 8 1.6 1376 673FS+10 days,676,670FS+5 days 669 Piloti forati
670 Sapatura 2 days 11/22/22 11/23/22 mc 324 162.0 669FS+5 days 671 670 Sapatura
671 Demolare capete piloti 2 days 11/24/22 11/25/22 mc 13.75 6.9 670 672 671 Demolare capete piloti
672 Beton de egalizare 1 day 11/28/22 11/28/22 mc 16.25 16.3 671 673 672 Beton de egalizare
673 Teste coloane forate 2 days 11/29/22 12/1/22 buc 9 4.5 669FS+10 days,672 674 673 Teste coloane forate
674 Realizare Radier 5 days 12/16/22 1/12/23 mc 135 27.0 673,1383SS+10 days 697,681SS+3 days 674 Realizare Radier
675 Culeea 1d 30 days 11/15/22 1/17/23 675 Culeea 1d
676 Piloti forati 5 days 11/15/22 11/21/22 buc 8 1.6 669 683,680FS+10 days,677FS+5 days 676 Piloti forati
677 Sapatura 2 days 11/29/22 12/1/22 mc 324 162.0 676FS+5 days 678 677 Sapatura
678 Demolare capete piloti 2 days 12/2/22 12/5/22 mc 13.75 6.9 677 679 678 Demolare capete piloti
679 Beton de egalizare 1 day 12/6/22 12/6/22 mc 16.25 16.3 678 680 679 Beton de egalizare
680 Teste coloane forate 2 days 12/7/22 12/8/22 buc 9 4.5 676FS+10 days,679 681 680 Teste coloane forate
681 Realizare Radier 5 days 1/11/23 1/17/23 mc 135 27.0 674SS+3 days,680 698,688SS+3 days 681 Realizare Radier
682 Culeea 2s 28 days 11/22/22 1/20/23 682 Culeea 2s
683 Piloti forati 5 days 11/22/22 11/28/22 buc 8 1.6 676 690,684FS+5 days,687FS+10 days 683 Piloti forati
684 Sapatura 2 days 12/7/22 12/8/22 mc 324 162.0 683FS+5 days 685 684 Sapatura
685 Demolare capete piloti 2 days 12/9/22 12/12/22 mc 13.75 6.9 684 686 685 Demolare capete piloti
686 Beton de egalizare 1 day 12/13/22 12/13/22 mc 16.25 16.3 685 687 686 Beton de egalizare
687 Teste coloane forate 2 days 12/14/22 12/15/22 buc 8 4.0 686,683FS+10 days 688 687 Teste coloane forate
688 Realizare Radier 5 days 1/16/23 1/20/23 mc 135 27.0 681SS+3 days,687 699,695SS+3 days 688 Realizare Radier
689 Culeea 2d 26 days 11/29/22 1/25/23 689 Culeea 2d
690 Piloti forati 5 days 11/29/22 12/6/22 buc 8 1.6 683 744,691FS+5 days,694FS+10 days 690 Piloti forati
691 Sapatura 2 days 12/14/22 12/15/22 mc 324 162.0 690FS+5 days 692 691 Sapatura
692 Demolare capete piloti 2 days 12/16/22 1/9/23 mc 13.75 6.9 691 693 692 Demolare capete piloti
693 Beton de egalizare 1 day 1/10/23 1/10/23 mc 16.25 16.3 692 694 693 Beton de egalizare
694 Teste coloane forate 2 days 1/11/23 1/12/23 buc 8 4.0 693,690FS+10 days 695 694 Teste coloane forate
695 Realizare Radier 5 days 1/19/23 1/25/23 mc 135 27.0 688SS+3 days,694 700,697SS+2 days 695 Realizare Radier
696 Elevatii pile si culei 36 days 1/23/23 3/13/23 696 Elevatii pile si culei
697 Elevatie si banchete C1s 10 days 1/23/23 2/3/23 mc 215 21.5 674,695SS+2 days 698SS+7 days 697 Elevatie si banchete C1s
698 Elevatie si banchete C1d 10 days 2/1/23 2/14/23 mc 215 21.5 697SS+7 days,681 699SS+7 days,704 698 Elevatie si banchete C1d
699 Elevatie si banchete C2s 10 days 2/10/23 2/23/23 mc 215 21.5 698SS+7 days,688 700SS+7 days 699 Elevatie si banchete C2s
700 Elevatie si banchete C2d 10 days 2/21/23 3/6/23 mc 215 21.5 699SS+7 days,695 701,749SS+10 days,715 700 Elevatie si banchete C2d
701 Montare dispozitive antiseismice si aparate reazem 5 days 3/7/23 3/13/23 buc 20 4.0 700 726 701 Montare dispozitive antiseismice si aparate reazem
702 Racordari cu terasamente 50 days 2/15/23 4/28/23 702 Racordari cu terasamente
703 C1 50 days 2/15/23 4/28/23 703 C1
704 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 2/15/23 2/16/23 mc 70 35.0 698 705 704 Sapatura pentru fundatie protectie taluz/sfert de con
705 Fundatie protectie taluz/sfert de con 5 days 2/17/23 2/23/23 mc 55 11.0 704 708,706,707 705 Fundatie protectie taluz/sfert de con
706 Dren din geotextil 2 days 2/24/23 2/27/23 mp 300 150.0 705 709 706 Dren din geotextil
707 Tevi ape pluviale 2 days 2/24/23 2/27/23 m 40 20.0 705 709 707 Tevi ape pluviale
708 Umpluturi sfert de con material granular 5 days 2/24/23 3/2/23 mc 742.5 148.5 705 709 708 Umpluturi sfert de con material granular
709 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 3/3/23 3/9/23 mp 362.5 72.5 706,707,708 710 709 Protectie taluz / sfert con cu pereu de beton C35/45
710 Scari pe taluz 3 days 3/10/23 3/14/23 m 27 9.0 709 711 710 Scari pe taluz
711 Casiuri pe taluz 3 days 3/15/23 3/17/23 m 35 11.7 710 711 Casiuri pe taluz
712 Placi racordare C1 3 days 4/25/23 4/27/23 mc 62 20.7 730 713 712 Placi racordare C1
713 Hidroizolatie Placa racordare 1 day 4/28/23 4/28/23 mp 175 175.0 712 713 Hidroizolatie Placa racordare
714 C2 36 days 3/7/23 4/28/23 714 C2
715 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 3/7/23 3/8/23 mc 70 35.0 700 716 715 Sapatura pentru fundatie protectie taluz/sfert de con
716 Fundatie protectie taluz/sfert de con 5 days 3/9/23 3/15/23 mc 55 11.0 715 719,717,718 716 Fundatie protectie taluz/sfert de con
717 Dren din geotextil 2 days 3/16/23 3/17/23 mp 300 150.0 716 720 717 Dren din geotextil
718 Tevi ape pluviale 2 days 3/16/23 3/17/23 m 40 20.0 716 720 718 Tevi ape pluviale
719 Umpluturi sfert de con material granular 5 days 3/16/23 3/22/23 mc 742.5 148.5 716 720 719 Umpluturi sfert de con material granular
720 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 3/23/23 3/29/23 mp 362.5 72.5 717,718,719 721 720 Protectie taluz / sfert con cu pereu de beton C35/45
721 Scari pe taluz 3 days 3/30/23 4/3/23 m 27 9.0 720 722 721 Scari pe taluz
722 Casiuri pe taluz 3 days 4/4/23 4/6/23 m 35 11.7 721 722 Casiuri pe taluz
723 Placi racordare C2 3 days 4/25/23 4/27/23 mc 62 20.7 730 724 723 Placi racordare C2
724 Hidroizolatie Placa racordare 1 day 4/28/23 4/28/23 mp 175 175.0 723 724 Hidroizolatie Placa racordare
725 Suprastructura 27 days 3/14/23 4/24/23 725 Suprastructura
726 Montaj grinzi 10 days 3/14/23 3/27/23 buc 12 1.2 701 727 726 Montaj grinzi
727 Montaj predale 5 days 3/28/23 4/3/23 mc 83 16.6 726 728 727 Montaj predale
728 Montaj armatura in placa de suprabetonare si antretoaze 5 days 4/4/23 4/10/23 t 49.5 9.9 727 729SS+2 days,732SS+2 days 728 Montaj armatura in placa de suprabetonare si antretoaze
729 Montaj cofraj la placa de suprabetonare 5 days 4/6/23 4/12/23 mp 200 40.0 728SS+2 days 730SS+2 days 729 Montaj cofraj la placa de suprabetonare
730 Turnare beton in placa de suprabetonare si antretoaze 5 days 4/13/23 4/24/23 mc 330 66.0 732,729SS+2 days 734FS+5 days,733,712,723 730 Turnare beton in placa de suprabetonare si antretoaze
731 Cale, trotuar, parapet 45 days 4/6/23 6/16/23 731 Cale, trotuar, parapet
732 Montaj guri de scurgere 5 days 4/6/23 4/12/23 buc 4 0.8 728SS+2 days 730 732 Montaj guri de scurgere
733 Prefabricat din beton pentru lisa parapet 5 days 4/25/23 5/2/23 m 152 30.4 730 735 733 Prefabricat din beton pentru lisa parapet
734 Hidroizolatie cale 10 days 5/3/23 5/16/23 mp 780 78.0 730FS+5 days 735 734 Hidroizolatie cale
735 Borduri pe Pod 5 days 5/17/23 5/23/23 m 152 30.4 733,734 736 735 Borduri pe Pod
736 Sistem rutier 5 days 5/24/23 5/30/23 mp 720 144.0 735 737,738 736 Sistem rutier
737 Dispozitive de acoperire a rosturilor 5 days 5/31/23 6/9/23 m 56 11.2 736 737 Dispozitive de acoperire a rosturilor
738 Parapeti metalici 5 days 5/31/23 6/9/23 m 352 70.4 736 740,739 738 Parapeti metalici
739 Panou protectie pajiste 5 days 6/12/23 6/16/23 mp 1112 222.4 738 739 Panou protectie pajiste
740 Marcaje rutiere 5 days 6/12/23 6/16/23 0.0 738 740 Marcaje rutiere
741 Pod pe drum agricol peste autostrada km 35+700 88.00 181 days 12/7/22 9/19/23 741 Pod pe drum agricol peste autostrada km 35+700
742 Fundatii pile si culei 63 days 12/7/22 3/24/23 742 Fundatii pile si culei
743 Culeea 1 54 days 12/7/22 3/13/23 743 Culeea 1
744 Piloti forati 4 days 12/7/22 12/12/22 buc 8 2.0 690 748FS+10 days,751,745FS+5 days 744 Piloti forati
745 Sapatura 2 days 1/10/23 1/11/23 mc 288 144.0 744FS+5 days 746 745 Sapatura
746 Demolare capete piloti 2 days 1/12/23 1/13/23 mc 9 4.5 745 747 746 Demolare capete piloti
747 Beton de egalizare 1 day 1/16/23 1/16/23 mc 12 12.0 746 748 747 Beton de egalizare
748 Teste coloane forate 2 days 1/17/23 1/18/23 buc 9 4.5 744FS+10 days,747 749 748 Teste coloane forate
749 Realizare Radier 5 days 3/7/23 3/13/23 mc 117 23.4 748,700SS+10 days,762 772,756SS+3 days 749 Realizare Radier

Seite 7
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
750 Pila 1 53 days 12/13/22 3/16/23 750 Pila 1
751 Piloti forati 4 days 12/13/22 12/16/22 buc 8 2.0 744 755FS+10 days,758,752FS+5 days 751 Piloti forati
752 Sapatura 2 days 1/16/23 1/17/23 mc 288 144.0 751FS+5 days 753 752 Sapatura
753 Demolare capete piloti 2 days 1/18/23 1/19/23 mc 9 4.5 752 754 753 Demolare capete piloti
754 Beton de egalizare 1 day 1/20/23 1/20/23 mc 12 12.0 753 755 754 Beton de egalizare
755 Teste coloane forate 2 days 1/23/23 1/24/23 buc 9 4.5 751FS+10 days,754 756 755 Teste coloane forate
756 Realizare Radier 5 days 3/10/23 3/16/23 mc 117 23.4 749SS+3 days,755 773,763SS+3 days 756 Realizare Radier
757 Pila 2 52 days 1/9/23 3/21/23 757 Pila 2
758 Piloti forati 4 days 1/9/23 1/12/23 buc 8 2.0 751 765,763,759FS+5 days,762FS+10 days 758 Piloti forati
759 Sapatura 2 days 1/20/23 1/23/23 mc 288 144.0 758FS+5 days 760 759 Sapatura
760 Demolare capete piloti 2 days 1/24/23 1/25/23 mc 9 4.5 759 761 760 Demolare capete piloti
761 Beton de egalizare 1 day 1/26/23 1/26/23 mc 12 12.0 760 762 761 Beton de egalizare
762 Teste coloane forate 2 days 1/27/23 1/30/23 buc 8 4.0 761,758FS+10 days 749 762 Teste coloane forate
763 Realizare Radier 5 days 3/15/23 3/21/23 mc 117 23.4 756SS+3 days,758 774,770SS+3 days 763 Realizare Radier
764 Culeea 2 51 days 1/13/23 3/24/23 764 Culeea 2
765 Piloti forati 4 days 1/13/23 1/18/23 buc 8 2.0 758 1296,766FS+5 days,769FS+10 days 765 Piloti forati
766 Sapatura 2 days 1/26/23 1/27/23 mc 288 144.0 765FS+5 days 767 766 Sapatura
767 Demolare capete piloti 2 days 1/30/23 1/31/23 mc 9 4.5 766 768 767 Demolare capete piloti
768 Beton de egalizare 1 day 2/1/23 2/1/23 mc 12 12.0 767 769 768 Beton de egalizare
769 Teste coloane forate 2 days 2/2/23 2/3/23 buc 8 4.0 768,765FS+10 days 770 769 Teste coloane forate
770 Realizare Radier 5 days 3/20/23 3/24/23 mc 117 23.4 763SS+3 days,769 775,772SS+2 days 770 Realizare Radier
771 Elevatii pile si culei 41 days 3/22/23 5/23/23 771 Elevatii pile si culei
772 Elevatie si banchete C1 15 days 3/22/23 4/11/23 mc 147 9.8 749,770SS+2 days 773SS+7 days,779 772 Elevatie si banchete C1
773 Elevatie si Rigla P1 10 days 3/31/23 4/13/23 mc 147 14.7 772SS+7 days,756 774SS+7 days 773 Elevatie si Rigla P1
774 Elevatie si Rigla P2 10 days 4/11/23 4/27/23 mc 147 14.7 773SS+7 days,763 775SS+7 days 774 Elevatie si Rigla P2
775 Elevatie si banchete C2 15 days 4/25/23 5/16/23 mc 147 9.8 774SS+7 days,770 776,1301SS+10 days,789 775 Elevatie si banchete C2
776 Montare dispozitive antiseismice si aparate reazem 5 days 5/17/23 5/23/23 buc 20 4.0 775 799 776 Montare dispozitive antiseismice si aparate reazem
777 Racordari cu terasamente 75 days 4/12/23 8/3/23 777 Racordari cu terasamente
778 C1 75 days 4/12/23 8/3/23 778 C1
779 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 4/12/23 4/13/23 mc 200 100.0 772 780 779 Sapatura pentru fundatie protectie taluz/sfert de con
780 Fundatie protectie taluz/sfert de con 5 days 4/19/23 4/25/23 mc 160 32.0 779 782,781 780 Fundatie protectie taluz/sfert de con
781 Tevi ape pluviale 2 days 4/26/23 4/27/23 m 95 47.5 780 783 781 Tevi ape pluviale
782 Umpluturi sfert de con material granular 5 days 4/26/23 5/3/23 mc 3000 600.0 780 783 782 Umpluturi sfert de con material granular
783 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 5/4/23 5/10/23 mp 1150 230.0 781,782 784 783 Protectie taluz / sfert con cu pereu de beton C35/45
784 Scari pe taluz 3 days 5/11/23 5/15/23 m 45 15.0 783 785 784 Scari pe taluz
785 Casiuri pe taluz 3 days 5/16/23 5/18/23 m 55 18.3 784 785 Casiuri pe taluz
786 Placi racordare C1 3 days 7/31/23 8/2/23 mc 21 7.0 803 787 786 Placi racordare C1
787 Hidroizolatie Placa racordare 1 day 8/3/23 8/3/23 mp 62.5 62.5 786 787 Hidroizolatie Placa racordare
788 C2 54 days 5/17/23 8/3/23 788 C2
789 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 5/17/23 5/18/23 mc 200 100.0 775 790 789 Sapatura pentru fundatie protectie taluz/sfert de con
790 Fundatie protectie taluz/sfert de con 5 days 5/19/23 5/25/23 mc 160 32.0 789 792,791 790 Fundatie protectie taluz/sfert de con
791 Tevi ape pluviale 2 days 5/26/23 5/29/23 m 95 47.5 790 793 791 Tevi ape pluviale
792 Umpluturi sfert de con material granular 5 days 5/26/23 6/6/23 mc 3000 600.0 790 793 792 Umpluturi sfert de con material granular
793 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 6/7/23 6/13/23 mp 1150 230.0 791,792 794 793 Protectie taluz / sfert con cu pereu de beton C35/45
794 Scari pe taluz 3 days 6/14/23 6/16/23 m 45 15.0 793 795 794 Scari pe taluz
795 Casiuri pe taluz 3 days 6/19/23 6/21/23 m 55 18.3 794 795 Casiuri pe taluz
796 Placi racordare C2 3 days 7/31/23 8/2/23 mc 21 7.0 803 797 796 Placi racordare C2
797 Hidroizolatie Placa racordare 1 day 8/3/23 8/3/23 mp 62.5 62.5 796 797 Hidroizolatie Placa racordare
798 Suprastructura 45 days 5/24/23 7/28/23 798 Suprastructura
799 Montaj grinzi 10 days 5/24/23 6/9/23 buc 18 1.8 776 800 799 Montaj grinzi
800 Montaj predale 10 days 6/12/23 6/23/23 mc 99 9.9 799 801SS+5 days 800 Montaj predale
801 Montaj armatura in placa de suprabetonare si antretoaze 15 days 6/19/23 7/7/23 t 56.5 3.8 800SS+5 days 802SS+10 days,805SS+5 days 801 Montaj armatura in placa de suprabetonare si antretoaze
802 Montaj cofraj la placa de suprabetonare 15 days 7/3/23 7/21/23 mp 200 13.3 801SS+10 days 803SS+10 days 802 Montaj cofraj la placa de suprabetonare
803 Turnare beton in placa de suprabetonare si antretoaze 10 days 7/17/23 7/28/23 mc 360 36.0 805,802SS+10 days 807FS+5 days,806,786,796 803 Turnare beton in placa de suprabetonare si antretoaze
804 Cale, trotuar, parapet 60 days 6/26/23 9/19/23 804 Cale, trotuar, parapet
805 Montaj guri de scurgere 5 days 6/26/23 6/30/23 buc 12 2.4 801SS+5 days 803 805 Montaj guri de scurgere
806 Prefabricat din beton pentru lisa parapet 5 days 7/31/23 8/4/23 m 196 39.2 803 808 806 Prefabricat din beton pentru lisa parapet
807 Hidroizolatie cale 10 days 8/7/23 8/22/23 mp 1075 107.5 803FS+5 days 808 807 Hidroizolatie cale
808 Borduri pe Pod 5 days 8/23/23 8/29/23 m 196 39.2 806,807 809,812 808 Borduri pe Pod
809 Trotuare pe pod 5 days 8/30/23 9/5/23 mc 71 14.2 808 810,813 809 Trotuare pe pod
810 Sistem rutier 5 days 9/6/23 9/12/23 mp 620 124.0 809 811 810 Sistem rutier
811 Dispozitive de acoperire a rosturilor 5 days 9/13/23 9/19/23 m 25 5.0 810 811 Dispozitive de acoperire a rosturilor
812 Parapeti pietonali si plase de protectie 10 days 8/30/23 9/12/23 m 196 19.6 808 812 Parapeti pietonali si plase de protectie
813 Parapeti metalici 5 days 9/6/23 9/12/23 m 296 59.2 809 814 813 Parapeti metalici
814 Marcaje rutiere 5 days 9/13/23 9/19/23 0.0 813 814 Marcaje rutiere
815 Pod peste paraul Pietroasa(Greceanca) km 37+185 40.00 112 days 5/26/22 11/1/22 815 Pod peste paraul Pietroasa(Greceanca) km 37+185
816 Fundatii pile si culei 20 days 5/26/22 6/23/22 816 Fundatii pile si culei
817 Culeea 1s 14 days 5/26/22 6/15/22 817 Culeea 1s
818 Piloti forati 2 days 5/26/22 5/27/22 buc 4 2.0 2FS+5 days 822FS+10 days,824,819FS+5 days 818 Piloti forati
819 Sapatura 2 days 6/6/22 6/7/22 mc 220 110.0 818FS+5 days 820 819 Sapatura
820 Demolare capete piloti 2 days 6/8/22 6/9/22 mc 5.5 2.8 819 821 820 Demolare capete piloti
821 Beton de egalizare 1 day 6/10/22 6/10/22 mc 8.75 8.8 820 822 821 Beton de egalizare
822 Teste coloane forate 2 days 6/14/22 6/15/22 buc 5 2.5 818FS+10 days,821 842 822 Teste coloane forate
823 Culeea 1d 14 days 5/30/22 6/17/22 823 Culeea 1d
824 Piloti forati 2 days 5/30/22 5/31/22 buc 4 2.0 818 830,828FS+10 days,825FS+5 days 824 Piloti forati
825 Sapatura 2 days 6/8/22 6/9/22 mc 220 110.0 824FS+5 days 826 825 Sapatura
826 Demolare capete piloti 2 days 6/10/22 6/14/22 mc 5.5 2.8 825 827 826 Demolare capete piloti
827 Beton de egalizare 1 day 6/15/22 6/15/22 mc 8.75 8.8 826 828 827 Beton de egalizare
828 Teste coloane forate 2 days 6/16/22 6/17/22 buc 5 2.5 824FS+10 days,827 843 828 Teste coloane forate
829 Culeea 2s 14 days 6/1/22 6/21/22 829 Culeea 2s
830 Piloti forati 2 days 6/1/22 6/2/22 buc 4 2.0 824 836,831FS+5 days,834FS+10 days 830 Piloti forati
831 Sapatura 2 days 6/10/22 6/14/22 mc 220 110.0 830FS+5 days 832 831 Sapatura
832 Demolare capete piloti 2 days 6/15/22 6/16/22 mc 5.5 2.8 831 833 832 Demolare capete piloti
833 Beton de egalizare 1 day 6/17/22 6/17/22 mc 8.75 8.8 832 834 833 Beton de egalizare
834 Teste coloane forate 2 days 6/20/22 6/21/22 buc 4 2.0 833,830FS+10 days 844 834 Teste coloane forate
835 Culeea 2d 14 days 6/3/22 6/23/22 835 Culeea 2d
836 Piloti forati 2 days 6/3/22 6/6/22 buc 4 2.0 830 887,837FS+5 days,840FS+10 days 836 Piloti forati
837 Sapatura 2 days 6/15/22 6/16/22 mc 220 110.0 836FS+5 days 838 837 Sapatura
838 Demolare capete piloti 2 days 6/17/22 6/20/22 mc 5.5 2.8 837 839 838 Demolare capete piloti
839 Beton de egalizare 1 day 6/21/22 6/21/22 mc 8.75 8.8 838 840 839 Beton de egalizare
840 Teste coloane forate 2 days 6/22/22 6/23/22 buc 4 2.0 839,836FS+10 days 845 840 Teste coloane forate
841 Elevatii pile si culei 36 days 6/16/22 8/4/22 841 Elevatii pile si culei
842 Elevatie si banchete C1s 10 days 6/16/22 6/29/22 mc 206.25 20.6 822 843SS+7 days 842 Elevatie si banchete C1s
843 Elevatie si banchete C1d 10 days 6/27/22 7/8/22 mc 206.25 20.6 842SS+7 days,828 844SS+7 days,849 843 Elevatie si banchete C1d
844 Elevatie si banchete C2s 10 days 7/6/22 7/19/22 mc 206.25 20.6 843SS+7 days,834 845SS+7 days 844 Elevatie si banchete C2s
845 Elevatie si banchete C2d 10 days 7/15/22 7/28/22 mc 206.25 20.6 844SS+7 days,840 846,892SS+10 days,860 845 Elevatie si banchete C2d
846 Montare dispozitive antiseismice si aparate reazem 5 days 7/29/22 8/4/22 buc 20 4.0 845 871 846 Montare dispozitive antiseismice si aparate reazem
847 Racordari cu terasamente 50 days 7/11/22 9/19/22 847 Racordari cu terasamente
848 C1 50 days 7/11/22 9/19/22 848 C1
849 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 7/11/22 7/12/22 mc 70 35.0 843 850 849 Sapatura pentru fundatie protectie taluz/sfert de con
850 Fundatie protectie taluz/sfert de con 5 days 7/13/22 7/19/22 mc 55 11.0 849 853,851,852 850 Fundatie protectie taluz/sfert de con
851 Dren din geotextil 2 days 7/20/22 7/21/22 mp 300 150.0 850 854 851 Dren din geotextil
852 Tevi ape pluviale 2 days 7/20/22 7/21/22 m 45 22.5 850 854 852 Tevi ape pluviale
853 Umpluturi sfert de con material granular 5 days 7/20/22 7/26/22 mc 742.5 148.5 850 854 853 Umpluturi sfert de con material granular
854 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 7/27/22 8/2/22 mp 362.5 72.5 851,852,853 855 854 Protectie taluz / sfert con cu pereu de beton C35/45
855 Scari pe taluz 3 days 8/3/22 8/5/22 m 27 9.0 854 856 855 Scari pe taluz
856 Casiuri pe taluz 3 days 8/8/22 8/10/22 m 35 11.7 855 856 Casiuri pe taluz

Seite 8
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
857 Placi racordare C1 3 days 9/14/22 9/16/22 mc 62 20.7 874 858 857 Placi racordare C1
858 Hidroizolatie Placa racordare 1 day 9/19/22 9/19/22 mp 175 175.0 857 858 Hidroizolatie Placa racordare
859 C2 36 days 7/29/22 9/19/22 859 C2
860 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 7/29/22 8/1/22 mc 70 35.0 845 861 860 Sapatura pentru fundatie protectie taluz/sfert de con
861 Fundatie protectie taluz/sfert de con 5 days 8/2/22 8/8/22 mc 55 11.0 860 864,862,863 861 Fundatie protectie taluz/sfert de con
862 Dren din geotextil 2 days 8/9/22 8/10/22 mp 300 150.0 861 865 862 Dren din geotextil
863 Tevi ape pluviale 2 days 8/9/22 8/10/22 m 45 22.5 861 865 863 Tevi ape pluviale
864 Umpluturi sfert de con material granular 5 days 8/9/22 8/16/22 mc 742.5 148.5 861 865 864 Umpluturi sfert de con material granular
865 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 8/17/22 8/23/22 mp 362.5 72.5 862,863,864 866 865 Protectie taluz / sfert con cu pereu de beton C35/45
866 Scari pe taluz 3 days 8/24/22 8/26/22 m 27 9.0 865 867 866 Scari pe taluz
867 Casiuri pe taluz 3 days 8/29/22 8/31/22 m 35 11.7 866 867 Casiuri pe taluz
868 Placi racordare C2 3 days 9/14/22 9/16/22 mc 62 20.7 874 869 868 Placi racordare C2
869 Hidroizolatie Placa racordare 1 day 9/19/22 9/19/22 mp 175 175.0 868 869 Hidroizolatie Placa racordare
870 Suprastructura 27 days 8/5/22 9/13/22 870 Suprastructura
871 Montaj grinzi 10 days 8/5/22 8/19/22 buc 12 1.2 846 872 871 Montaj grinzi
872 Montaj armatura in placa de suprabetonare si antretoaze 10 days 8/22/22 9/2/22 t 71.5 7.2 871 873SS+2 days,876SS+2 days 872 Montaj armatura in placa de suprabetonare si antretoaze
873 Montaj cofraj la placa de suprabetonare 10 days 8/24/22 9/6/22 mp 635 63.5 872SS+2 days 874SS+2 days 873 Montaj cofraj la placa de suprabetonare
874 Turnare beton in placa de suprabetonare si antretoaze 10 days 8/31/22 9/13/22 mc 471 47.1 876,873SS+2 days 878FS+5 days,877,868,857 874 Turnare beton in placa de suprabetonare si antretoaze
875 Cale, trotuar, parapet 50 days 8/24/22 11/1/22 875 Cale, trotuar, parapet
876 Montaj guri de scurgere 5 days 8/24/22 8/30/22 buc 4 0.8 872SS+2 days 874 876 Montaj guri de scurgere
877 Prefabricat din beton pentru lisa parapet 5 days 9/14/22 9/20/22 m 200 40.0 874 879 877 Prefabricat din beton pentru lisa parapet
878 Hidroizolatie cale 10 days 9/21/22 10/4/22 mp 1040 104.0 874FS+5 days 879 878 Hidroizolatie cale
879 Borduri pe Pod 5 days 10/5/22 10/11/22 m 200 40.0 877,878 880 879 Borduri pe Pod
880 Sistem rutier 5 days 10/12/22 10/18/22 mp 1040 208.0 879 881,882 880 Sistem rutier
881 Dispozitive de acoperire a rosturilor 5 days 10/19/22 10/25/22 m 56 11.2 880 881 Dispozitive de acoperire a rosturilor
882 Parapeti metalici 5 days 10/19/22 10/25/22 m 400 80.0 880 883 882 Parapeti metalici
883 Marcaje rutiere 5 days 10/26/22 11/1/22 0.0 882 883 Marcaje rutiere
884 Pod peste paraul Sarata km 38+309 140.00 272 days 6/7/22 7/26/23 884 Pod peste paraul Sarata km 38+309
885 Fundatii pile si culei 63 days 6/7/22 9/5/22 885 Fundatii pile si culei
886 Culeea 1s 42 days 6/7/22 8/4/22 886 Culeea 1s
887 Piloti forati 6 days 6/7/22 6/15/22 buc 12 2.0 836 891FS+10 days,894,888FS+5 days 887 Piloti forati
888 Sapatura 2 days 6/23/22 6/24/22 mc 528.75 264.4 887FS+5 days 889 888 Sapatura
889 Demolare capete piloti 2 days 6/27/22 6/28/22 mc 16.50 8.3 888 890 889 Demolare capete piloti
890 Beton de egalizare 1 day 6/29/22 6/29/22 mc 18.15 18.2 889 891 890 Beton de egalizare
891 Teste coloane forate 2 days 6/30/22 7/1/22 buc 13 6.5 887FS+10 days,890 892 891 Teste coloane forate
892 Realizare Radier 5 days 7/29/22 8/4/22 mc 252 50.4 891,845SS+10 days 943,899SS+3 days 892 Realizare Radier
893 Pila 1s 39 days 6/16/22 8/9/22 893 Pila 1s
894 Piloti forati 4 days 6/16/22 6/21/22 buc 8 2.0 887 898FS+10 days,901,895FS+5 days 894 Piloti forati
895 Sapatura 2 days 6/29/22 6/30/22 mc 352.50 176.3 894FS+5 days 896 895 Sapatura
896 Demolare capete piloti 2 days 7/1/22 7/4/22 mc 11.00 5.5 895 897 896 Demolare capete piloti
897 Beton de egalizare 1 day 7/5/22 7/5/22 mc 12.10 12.1 896 898 897 Beton de egalizare
898 Teste coloane forate 2 days 7/6/22 7/7/22 buc 9 4.5 894FS+10 days,897 899 898 Teste coloane forate
899 Realizare Radier 5 days 8/3/22 8/9/22 mc 168 33.6 892SS+3 days,898 944,906SS+3 days 899 Realizare Radier
900 Pila 2s 38 days 6/22/22 8/12/22 900 Pila 2s
901 Piloti forati 4 days 6/22/22 6/27/22 buc 8 2.0 894 908,906,905FS+10 days,902FS+5 days 901 Piloti forati
902 Sapatura 2 days 7/5/22 7/6/22 mc 352.50 176.3 901FS+5 days 903 902 Sapatura
903 Demolare capete piloti 2 days 7/7/22 7/8/22 mc 11.00 5.5 902 904 903 Demolare capete piloti
904 Beton de egalizare 1 day 7/11/22 7/11/22 mc 12.10 12.1 903 905 904 Beton de egalizare
905 Teste coloane forate 2 days 7/12/22 7/13/22 buc 8 4.0 904,901FS+10 days 906 905 Teste coloane forate
906 Realizare Radier 5 days 8/8/22 8/12/22 mc 168 33.6 899SS+3 days,901,905,912 945,913SS+3 days 906 Realizare Radier
907 Culeea 2s 37 days 6/28/22 8/18/22 907 Culeea 2s
908 Piloti forati 6 days 6/28/22 7/5/22 buc 12 2.0 901 915,909FS+5 days,912FS+10 days 908 Piloti forati
909 Sapatura 2 days 7/13/22 7/14/22 mc 528.75 264.4 908FS+5 days 910 909 Sapatura
910 Demolare capete piloti 2 days 7/15/22 7/18/22 mc 16.50 8.3 909 911 910 Demolare capete piloti
911 Beton de egalizare 1 day 7/19/22 7/19/22 mc 18.15 18.2 910 912 911 Beton de egalizare
912 Teste coloane forate 2 days 7/20/22 7/21/22 buc 12 6.0 911,908FS+10 days 906 912 Teste coloane forate
913 Realizare Radier 5 days 8/11/22 8/18/22 mc 252 50.4 906SS+3 days 946,920SS+3 days 913 Realizare Radier
914 Culeea 1d 34 days 7/6/22 8/23/22 914 Culeea 1d
915 Piloti forati 6 days 7/6/22 7/13/22 buc 12 2.0 908 919FS+10 days,922,916FS+5 days 915 Piloti forati
916 Sapatura 2 days 7/21/22 7/22/22 mc 528.75 264.4 915FS+5 days 917 916 Sapatura
917 Demolare capete piloti 2 days 7/25/22 7/26/22 mc 16.50 8.3 916 918 917 Demolare capete piloti
918 Beton de egalizare 1 day 7/27/22 7/27/22 mc 18.15 18.2 917 919 918 Beton de egalizare
919 Teste coloane forate 2 days 7/28/22 7/29/22 buc 12 6.0 915FS+10 days,918 920 919 Teste coloane forate
920 Realizare Radier 5 days 8/17/22 8/23/22 mc 252 50.4 919,913SS+3 days 947,927SS+3 days 920 Realizare Radier
921 Pila 1d 31 days 7/14/22 8/26/22 921 Pila 1d
922 Piloti forati 4 days 7/14/22 7/19/22 buc 8 2.0 915 926FS+10 days,929,923FS+5 days 922 Piloti forati
923 Sapatura 2 days 7/27/22 7/28/22 mc 352.50 176.3 922FS+5 days 924 923 Sapatura
924 Demolare capete piloti 2 days 7/29/22 8/1/22 mc 11.00 5.5 923 925 924 Demolare capete piloti
925 Beton de egalizare 1 day 8/2/22 8/2/22 mc 12.10 12.1 924 926 925 Beton de egalizare
926 Teste coloane forate 2 days 8/3/22 8/4/22 buc 8 4.0 922FS+10 days,925 927 926 Teste coloane forate
927 Realizare Radier 5 days 8/22/22 8/26/22 mc 168 33.6 920SS+3 days,926 948,934SS+3 days 927 Realizare Radier
928 Pila 2d 30 days 7/20/22 8/31/22 928 Pila 2d
929 Piloti forati 4 days 7/20/22 7/25/22 buc 8 2.0 922 936,934,930FS+5 days,933FS+10 days 929 Piloti forati
930 Sapatura 2 days 8/2/22 8/3/22 mc 352.50 176.3 929FS+5 days 931 930 Sapatura
931 Demolare capete piloti 2 days 8/4/22 8/5/22 mc 11.00 5.5 930 932 931 Demolare capete piloti
932 Beton de egalizare 1 day 8/8/22 8/8/22 mc 12.10 12.1 931 933 932 Beton de egalizare
933 Teste coloane forate 2 days 8/9/22 8/10/22 buc 8 4.0 932,929FS+10 days 934 933 Teste coloane forate
934 Realizare Radier 5 days 8/25/22 8/31/22 mc 168 33.6 927SS+3 days,929,933 949,941SS+3 days 934 Realizare Radier
935 Culeea 2d 29 days 7/26/22 9/5/22 935 Culeea 2d
936 Piloti forati 6 days 7/26/22 8/2/22 buc 12 2.0 929 941FS+10 days,1001,937FS+5 days,940FS+10 days 936 Piloti forati
937 Sapatura 2 days 8/10/22 8/11/22 mc 528.75 264.4 936FS+5 days 938 937 Sapatura
938 Demolare capete piloti 2 days 8/12/22 8/16/22 mc 16.50 8.3 937 939 938 Demolare capete piloti
939 Beton de egalizare 1 day 8/17/22 8/17/22 mc 18.15 18.2 938 940 939 Beton de egalizare
940 Teste coloane forate 2 days 8/18/22 8/19/22 buc 12 6.0 939,936FS+10 days 941 940 Teste coloane forate
941 Realizare Radier 5 days 8/30/22 9/5/22 mc 252 50.4 934SS+3 days,936FS+10 days,940 950,943SS+2 days 941 Realizare Radier
942 Elevatii pile si culei 79 days 9/1/22 1/11/23 942 Elevatii pile si culei
943 Elevatie si banchete C1s 20 days 9/1/22 9/28/22 mc 292.50 14.6 892,941SS+2 days 944SS+7 days 943 Elevatie si banchete C1s
944 Elevatie si Rigla P1s 15 days 9/12/22 9/30/22 mc 195.00 13.0 943SS+7 days,899 945SS+7 days 944 Elevatie si Rigla P1s
945 Elevatie si Rigla P2s 15 days 9/21/22 10/11/22 mc 195.00 13.0 944SS+7 days,906 946SS+7 days 945 Elevatie si Rigla P2s
946 Elevatie si banchete C2s 20 days 9/30/22 10/27/22 mc 292.50 14.6 945SS+7 days,913 947SS+7 days,954 946 Elevatie si banchete C2s
947 Elevatie si banchete C1d 20 days 10/11/22 11/7/22 mc 292.50 14.6 920,946SS+7 days 948SS+7 days 947 Elevatie si banchete C1d
948 Elevatie si Rigla P1d 15 days 10/20/22 11/9/22 mc 195.00 13.0 947SS+7 days,927 949SS+7 days 948 Elevatie si Rigla P1d
949 Elevatie si Rigla P2d 15 days 10/31/22 11/18/22 mc 195.00 13.0 948SS+7 days,934 950SS+7 days 949 Elevatie si Rigla P2d
950 Elevatie si banchete C2d 20 days 11/9/22 12/7/22 mc 292.50 14.6 949SS+7 days,941 951,965 950 Elevatie si banchete C2d
951 Montare dispozitive antiseismice si aparate reazem 10 days 12/8/22 1/11/23 buc 32 3.2 950 977 951 Montare dispozitive antiseismice si aparate reazem
952 Racordari cu terasamente 125 days 10/28/22 5/18/23 952 Racordari cu terasamente
953 C1 125 days 10/28/22 5/18/23 953 C1
954 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 10/28/22 10/31/22 mc 200 946 955 954 Sapatura pentru fundatie protectie taluz/sfert de con
955 Fundatie protectie taluz/sfert de con 5 days 11/1/22 11/7/22 mc 160 954 958,956,957 955 Fundatie protectie taluz/sfert de con
956 Dren din geotextil 2 days 11/8/22 11/9/22 mp 300 955 959 956 Dren din geotextil
957 Tevi ape pluviale 2 days 11/8/22 11/9/22 m 150 955 959 957 Tevi ape pluviale
958 Umpluturi sfert de con material granular 5 days 11/8/22 11/14/22 mc 3000 955 959 958 Umpluturi sfert de con material granular
959 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 11/15/22 11/21/22 mp 1150 956,957,958 960 959 Protectie taluz / sfert con cu pereu de beton C35/45
960 Scari pe taluz 3 days 11/22/22 11/24/22 m 45 959 961 960 Scari pe taluz
961 Casiuri pe taluz 3 days 11/25/22 11/29/22 m 55 960 961 Casiuri pe taluz
962 Placi racordare C1 3 days 5/15/23 5/17/23 mc 62 987 963 962 Placi racordare C1
963 Hidroizolatie Placa racordare 1 day 5/18/23 5/18/23 mp 175 962 963 Hidroizolatie Placa racordare

Seite 9
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
964 C2 97 days 12/8/22 5/18/23 964 C2
965 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 12/8/22 12/9/22 mc 200 950 966 965 Sapatura pentru fundatie protectie taluz/sfert de con
966 Fundatie protectie taluz/sfert de con 5 days 12/12/22 12/16/22 mc 160 965 969,967,968 966 Fundatie protectie taluz/sfert de con
967 Dren din geotextil 2 days 1/9/23 1/10/23 mp 300 966 970 967 Dren din geotextil
968 Tevi ape pluviale 2 days 1/9/23 1/10/23 m 150 966 970 968 Tevi ape pluviale
969 Umpluturi sfert de con material granular 5 days 1/9/23 1/13/23 mc 3000 966 970 969 Umpluturi sfert de con material granular
970 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 1/16/23 1/20/23 mp 1150 967,968,969 971 970 Protectie taluz / sfert con cu pereu de beton C35/45
971 Scari pe taluz 3 days 1/23/23 1/25/23 m 45 970 972 971 Scari pe taluz
972 Casiuri pe taluz 3 days 1/26/23 1/30/23 m 55 971 972 Casiuri pe taluz
973 Placi racordare C2 3 days 5/15/23 5/17/23 mc 62 987 974 973 Placi racordare C2
974 Hidroizolatie Placa racordare 1 day 5/18/23 5/18/23 mp 175 973 974 Hidroizolatie Placa racordare
975 Suprastructura 83 days 1/12/23 5/12/23 975 Suprastructura
976 Stanga 62 days 1/12/23 4/7/23 976 Stanga
977 Montaj tronsoane tablier 22 days 1/12/23 2/10/23 t 555.5 25.3 951 978,983 977 Montaj tronsoane tablier
978 Montaj predale 15 days 2/13/23 3/3/23 mc 192.5 12.8 977 979SS+5 days 978 Montaj predale
979 Montaj armatura in placa de suprabetonare 20 days 2/20/23 3/17/23 t 79 4.0 978SS+5 days 980SS+10 days 979 Montaj armatura in placa de suprabetonare
980 Montaj cofraj la placa de suprabetonare 15 days 3/6/23 3/24/23 mp 480 32.0 979SS+10 days 981SS+10 days 980 Montaj cofraj la placa de suprabetonare
981 Turnare beton in placa de suprabetonare 15 days 3/20/23 4/7/23 mc 525 35.0 980SS+10 days 991FS+5 days,990 981 Turnare beton in placa de suprabetonare
982 Dreapta 61 days 2/13/23 5/12/23 982 Dreapta
983 Montaj tronsoane tablier 21 days 2/13/23 3/13/23 t 555.5 977 984 983 Montaj tronsoane tablier
984 Montaj predale 15 days 3/14/23 4/3/23 mc 192.5 983 985SS+5 days 984 Montaj predale
985 Montaj armatura in placa de suprabetonare 20 days 3/21/23 4/20/23 t 79 984SS+5 days 986SS+10 days,989SS+5 days 985 Montaj armatura in placa de suprabetonare
986 Montaj cofraj la placa de suprabetonare 15 days 4/4/23 4/27/23 mp 480 985SS+10 days 987SS+10 days 986 Montaj cofraj la placa de suprabetonare
987 Turnare beton in placa de suprabetonare 15 days 4/21/23 5/12/23 mc 525 989,986SS+10 days 991FS+5 days,990,962,973 987 Turnare beton in placa de suprabetonare
988 Cale, trotuar, parapet 80 days 3/28/23 7/26/23 988 Cale, trotuar, parapet
989 Montaj guri de scurgere 5 days 3/28/23 4/3/23 buc 16 3.2 985SS+5 days 987 989 Montaj guri de scurgere
990 Prefabricat din beton pentru lisa parapet 10 days 5/15/23 5/26/23 m 624 62.4 981,987 993 990 Prefabricat din beton pentru lisa parapet
991 Hidroizolatie cale 10 days 5/22/23 6/7/23 mp 3640 364.0 981FS+5 days,987FS+5 days 993,992 991 Hidroizolatie cale
992 Geocompozit antifisura 1 day 6/8/23 6/8/23 mp 288 288.0 991 994 992 Geocompozit antifisura
993 Borduri pe Pod 10 days 6/8/23 6/21/23 m 624 62.4 990,991 994 993 Borduri pe Pod
994 Sistem rutier 10 days 6/22/23 7/5/23 mp 3360 336.0 993,992 995,996 994 Sistem rutier
995 Dispozitive de acoperire a rosturilor 5 days 7/6/23 7/12/23 m 56 11.2 994 995 Dispozitive de acoperire a rosturilor
996 Parapeti metalici si confectie metalica pentru stalpi 10 days 7/6/23 7/19/23 m 824 82.4 994 997 996 Parapeti metalici si confectie metalica pentru stalpi
997 Marcaje rutiere 5 days 7/20/23 7/26/23 0.0 996 997 Marcaje rutiere
998 Pod pe DJ203C peste autostrada km 38+945 88.00 157 days 8/3/22 4/3/23 998 Pod pe DJ203C peste autostrada km 38+945
999 Fundatii pile si culei 39 days 8/3/22 9/27/22 999 Fundatii pile si culei
1000 Culeea 1 21 days 8/3/22 9/1/22 1000 Culeea 1
1001 Piloti forati 4 days 8/3/22 8/8/22 buc 8 2.0 936 1005FS+10 days,1008,1002FS+5 days 1001 Piloti forati
1002 Sapatura 2 days 8/17/22 8/18/22 mc 288 144.0 1001FS+5 days 1003 1002 Sapatura
1003 Demolare capete piloti 2 days 8/19/22 8/22/22 mc 9 4.5 1002 1004 1003 Demolare capete piloti
1004 Beton de egalizare 1 day 8/23/22 8/23/22 mc 12 12.0 1003 1005 1004 Beton de egalizare
1005 Teste coloane forate 2 days 8/24/22 8/25/22 buc 9 4.5 1001FS+10 days,1004 1006,1067 1005 Teste coloane forate
1006 Realizare Radier 5 days 8/26/22 9/1/22 mc 117 23.4 1005 1029,1013SS+3 days 1006 Realizare Radier
1007 Pila 1 29 days 8/9/22 9/19/22 1007 Pila 1
1008 Piloti forati 4 days 8/9/22 8/12/22 buc 8 2.0 1001 1012FS+10 days,1015,1009FS+5 days 1008 Piloti forati
1009 Sapatura 2 days 8/23/22 8/24/22 mc 288 144.0 1008FS+5 days 1010 1009 Sapatura
1010 Demolare capete piloti 2 days 8/25/22 8/26/22 mc 9 4.5 1009 1011 1010 Demolare capete piloti
1011 Beton de egalizare 1 day 8/29/22 8/29/22 mc 12 12.0 1010 1012 1011 Beton de egalizare
1012 Teste coloane forate 2 days 8/30/22 8/31/22 buc 9 4.5 1008FS+10 days,1011 1013 1012 Teste coloane forate
1013 Realizare Radier 5 days 9/13/22 9/19/22 mc 117 23.4 1006SS+3 days,1012,1019,1026 1030,1020SS+3 days 1013 Realizare Radier
1014 Pila 2 28 days 8/16/22 9/22/22 1014 Pila 2
1015 Piloti forati 4 days 8/16/22 8/19/22 buc 8 2.0 1008 1022,1020,1016FS+5 days,1019FS+10 days 1015 Piloti forati
1016 Sapatura 2 days 8/29/22 8/30/22 mc 288 144.0 1015FS+5 days 1017 1016 Sapatura
1017 Demolare capete piloti 2 days 8/31/22 9/1/22 mc 9 4.5 1016 1018 1017 Demolare capete piloti
1018 Beton de egalizare 1 day 9/2/22 9/2/22 mc 12 12.0 1017 1019 1018 Beton de egalizare
1019 Teste coloane forate 2 days 9/5/22 9/6/22 buc 8 4.0 1015FS+10 days,1018 1013 1019 Teste coloane forate
1020 Realizare Radier 5 days 9/16/22 9/22/22 mc 117 23.4 1013SS+3 days,1015 1031,1027SS+3 days 1020 Realizare Radier
1021 Culeea 2 27 days 8/22/22 9/27/22 1021 Culeea 2
1022 Piloti forati 4 days 8/22/22 8/25/22 buc 8 2.0 1015 1027FS+10 days,1075,1023FS+5 days,1026FS+10 days 1022 Piloti forati
1023 Sapatura 2 days 9/2/22 9/5/22 mc 288 144.0 1022FS+5 days 1024 1023 Sapatura
1024 Demolare capete piloti 2 days 9/6/22 9/7/22 mc 9 4.5 1023 1025 1024 Demolare capete piloti
1025 Beton de egalizare 1 day 9/8/22 9/8/22 mc 12 12.0 1024 1026 1025 Beton de egalizare
1026 Teste coloane forate 2 days 9/9/22 9/12/22 buc 8 4.0 1025,1022FS+10 days 1013 1026 Teste coloane forate
1027 Realizare Radier 5 days 9/21/22 9/27/22 mc 117 23.4 1020SS+3 days,1022FS+10 days 1032,1029SS+2 days 1027 Realizare Radier
1028 Elevatii pile si culei 41 days 9/23/22 11/18/22 1028 Elevatii pile si culei
1029 Elevatie si banchete C1 15 days 9/23/22 10/13/22 mc 147 9.8 1006,1027SS+2 days 1030SS+7 days,1036 1029 Elevatie si banchete C1
1030 Elevatie si Rigla P1 10 days 10/4/22 10/17/22 mc 147 14.7 1029SS+7 days,1013 1031SS+7 days 1030 Elevatie si Rigla P1
1031 Elevatie si Rigla P2 10 days 10/13/22 10/26/22 mc 147 14.7 1030SS+7 days,1020 1032SS+7 days 1031 Elevatie si Rigla P2
1032 Elevatie si banchete C2 15 days 10/24/22 11/11/22 mc 147 9.8 1031SS+7 days,1027 1033,1080SS+10 days,1046 1032 Elevatie si banchete C2
1033 Montare dispozitive antiseismice si aparate reazem 5 days 11/14/22 11/18/22 buc 20 4.0 1032 1056 1033 Montare dispozitive antiseismice si aparate reazem
1034 Racordari cu terasamente 75 days 10/14/22 2/17/23 1034 Racordari cu terasamente
1035 C1 75 days 10/14/22 2/17/23 1035 C1
1036 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 10/14/22 10/17/22 mc 200 100.0 1029 1037 1036 Sapatura pentru fundatie protectie taluz/sfert de con
1037 Fundatie protectie taluz/sfert de con 5 days 10/18/22 10/24/22 mc 160 32.0 1036 1039,1038 1037 Fundatie protectie taluz/sfert de con
1038 Tevi ape pluviale 2 days 10/25/22 10/26/22 m 95 47.5 1037 1040 1038 Tevi ape pluviale
1039 Umpluturi sfert de con material granular 5 days 10/25/22 10/31/22 mc 3000 600.0 1037 1040 1039 Umpluturi sfert de con material granular
1040 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 11/1/22 11/7/22 mp 1150 230.0 1038,1039 1041 1040 Protectie taluz / sfert con cu pereu de beton C35/45
1041 Scari pe taluz 3 days 11/8/22 11/10/22 m 45 15.0 1040 1042 1041 Scari pe taluz
1042 Casiuri pe taluz 3 days 11/11/22 11/15/22 m 55 18.3 1041 1042 Casiuri pe taluz
1043 Placi racordare C1 3 days 2/14/23 2/16/23 mc 21 7.0 1060 1044 1043 Placi racordare C1
1044 Hidroizolatie Placa racordare 1 day 2/17/23 2/17/23 mp 62.5 62.5 1043 1044 Hidroizolatie Placa racordare
1045 C2 54 days 11/14/22 2/17/23 1045 C2
1046 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 11/14/22 11/15/22 mc 200 100.0 1032 1047 1046 Sapatura pentru fundatie protectie taluz/sfert de con
1047 Fundatie protectie taluz/sfert de con 5 days 11/16/22 11/22/22 mc 160 32.0 1046 1049,1048 1047 Fundatie protectie taluz/sfert de con
1048 Tevi ape pluviale 2 days 11/23/22 11/24/22 m 95 47.5 1047 1050 1048 Tevi ape pluviale
1049 Umpluturi sfert de con material granular 5 days 11/23/22 11/29/22 mc 3000 600.0 1047 1050 1049 Umpluturi sfert de con material granular
1050 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 12/1/22 12/7/22 mp 1150 230.0 1048,1049 1051 1050 Protectie taluz / sfert con cu pereu de beton C35/45
1051 Scari pe taluz 3 days 12/8/22 12/12/22 m 45 15.0 1050 1052 1051 Scari pe taluz
1052 Casiuri pe taluz 3 days 12/13/22 12/15/22 m 55 18.3 1051 1052 Casiuri pe taluz
1053 Placi racordare C2 3 days 2/14/23 2/16/23 mc 21 7.0 1060 1054 1053 Placi racordare C2
1054 Hidroizolatie Placa racordare 1 day 2/17/23 2/17/23 mp 62.5 62.5 1053 1054 Hidroizolatie Placa racordare
1055 Suprastructura 45 days 11/21/22 2/13/23 1055 Suprastructura
1056 Montaj grinzi 10 days 11/21/22 12/5/22 buc 18 1.8 1033 1057 1056 Montaj grinzi
1057 Montaj predale 10 days 12/6/22 1/9/23 mc 106 10.6 1056 1058SS+5 days 1057 Montaj predale
1058 Montaj armatura in placa de suprabetonare si antretoaze 15 days 12/13/22 1/23/23 t 56.5 3.8 1057SS+5 days 1059SS+10 days,1062SS+5 days 1058 Montaj armatura in placa de suprabetonare si antretoaze
1059 Montaj cofraj la placa de suprabetonare 15 days 1/17/23 2/6/23 mp 215 14.3 1058SS+10 days 1060SS+10 days 1059 Montaj cofraj la placa de suprabetonare
1060 Turnare beton in placa de suprabetonare si antretoaze 10 days 1/31/23 2/13/23 mc 365 36.5 1062,1059SS+10 days 1064FS+5 days,1063,1043,1053 1060 Turnare beton in placa de suprabetonare si antretoaze
1061 Cale, trotuar, parapet 60 days 1/10/23 4/3/23 1061 Cale, trotuar, parapet
1062 Montaj guri de scurgere 5 days 1/10/23 1/16/23 buc 12 2.4 1058SS+5 days 1060 1062 Montaj guri de scurgere
1063 Prefabricat din beton pentru lisa parapet 5 days 2/14/23 2/20/23 m 196 39.2 1060 1065 1063 Prefabricat din beton pentru lisa parapet
1064 Hidroizolatie cale 10 days 2/21/23 3/6/23 mp 1144 114.4 1060FS+5 days 1065 1064 Hidroizolatie cale
1065 Borduri pe Pod 5 days 3/7/23 3/13/23 m 196 39.2 1063,1064 1066,1069 1065 Borduri pe Pod
1066 Trotuare pe pod 5 days 3/14/23 3/20/23 mc 71 14.2 1065 1067,1070 1066 Trotuare pe pod
1067 Sistem rutier 5 days 3/21/23 3/27/23 mp 690 138.0 1005,1066 1068 1067 Sistem rutier
1068 Dispozitive de acoperire a rosturilor 5 days 3/28/23 4/3/23 m 25 5.0 1067 1068 Dispozitive de acoperire a rosturilor
1069 Parapeti pietonali si plase de protectie 10 days 3/14/23 3/27/23 m 196 19.6 1065 1069 Parapeti pietonali si plase de protectie
1070 Parapeti metalici 5 days 3/21/23 3/27/23 m 296 59.2 1066 1071 1070 Parapeti metalici

Seite 10
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
1071 Marcaje rutiere 5 days 3/28/23 4/3/23 0.0 1070 1071 Marcaje rutiere
1072 Pod pe drum agricol peste autostrada km 41+676 88.00 183 days 8/26/22 6/9/23 1072 Pod pe drum agricol peste autostrada km 41+676
1073 Fundatii pile si culei 65 days 8/26/22 11/24/22 1073 Fundatii pile si culei
1074 Culeea 1 56 days 8/26/22 11/11/22 1074 Culeea 1
1075 Piloti forati 4 days 8/26/22 8/31/22 buc 8 2.0 1022 1079FS+10 days,1082,1076FS+5 days 1075 Piloti forati
1076 Sapatura 2 days 9/8/22 9/9/22 mc 288 144.0 1075FS+5 days 1077 1076 Sapatura
1077 Demolare capete piloti 2 days 9/12/22 9/13/22 mc 9 4.5 1076 1078 1077 Demolare capete piloti
1078 Beton de egalizare 1 day 9/14/22 9/14/22 mc 12 12.0 1077 1079 1078 Beton de egalizare
1079 Teste coloane forate 2 days 9/15/22 9/16/22 buc 9 4.5 1075FS+10 days,1078 1080 1079 Teste coloane forate
1080 Realizare Radier 5 days 11/7/22 11/11/22 mc 117 23.4 1079,1032SS+10 days 1103,1087SS+3 days 1080 Realizare Radier
1081 Pila 1 55 days 9/1/22 11/16/22 1081 Pila 1
1082 Piloti forati 4 days 9/1/22 9/6/22 buc 8 2.0 1075 1086FS+10 days,1089,1083FS+5 days,1090FS+5 days,1093FS+10 days 1082 Piloti forati
1083 Sapatura 2 days 9/14/22 9/15/22 mc 288 144.0 1082FS+5 days 1084 1083 Sapatura
1084 Demolare capete piloti 2 days 9/16/22 9/19/22 mc 9 4.5 1083 1085 1084 Demolare capete piloti
1085 Beton de egalizare 1 day 9/20/22 9/20/22 mc 12 12.0 1084 1086 1085 Beton de egalizare
1086 Teste coloane forate 2 days 9/21/22 9/22/22 buc 9 4.5 1082FS+10 days,1085 1087 1086 Teste coloane forate
1087 Realizare Radier 5 days 11/10/22 11/16/22 mc 117 23.4 1080SS+3 days,1086 1104,1094SS+3 days 1087 Realizare Radier
1088 Pila 2 54 days 9/7/22 11/21/22 1088 Pila 2
1089 Piloti forati 4 days 9/7/22 9/12/22 buc 8 2.0 1082 1096 1089 Piloti forati
1090 Sapatura 2 days 9/14/22 9/15/22 mc 288 144.0 1082FS+5 days 1091 1090 Sapatura
1091 Demolare capete piloti 2 days 9/16/22 9/19/22 mc 9 4.5 1090 1092 1091 Demolare capete piloti
1092 Beton de egalizare 1 day 9/20/22 9/20/22 mc 12 12.0 1091 1093 1092 Beton de egalizare
1093 Teste coloane forate 2 days 9/21/22 9/22/22 buc 8 4.0 1092,1082FS+10 days 1094 1093 Teste coloane forate
1094 Realizare Radier 5 days 11/15/22 11/21/22 mc 117 23.4 1087SS+3 days,1093 1105,1101SS+3 days 1094 Realizare Radier
1095 Culeea 2 53 days 9/13/22 11/24/22 1095 Culeea 2
1096 Piloti forati 4 days 9/13/22 9/16/22 buc 8 2.0 1089 1149,1097FS+5 days,1100FS+10 days 1096 Piloti forati
1097 Sapatura 2 days 9/26/22 9/27/22 mc 288 144.0 1096FS+5 days 1098 1097 Sapatura
1098 Demolare capete piloti 2 days 9/28/22 9/29/22 mc 9 4.5 1097 1099 1098 Demolare capete piloti
1099 Beton de egalizare 1 day 9/30/22 9/30/22 mc 12 12.0 1098 1100 1099 Beton de egalizare
1100 Teste coloane forate 2 days 10/3/22 10/4/22 buc 8 4.0 1099,1096FS+10 days 1101 1100 Teste coloane forate
1101 Realizare Radier 5 days 11/18/22 11/24/22 mc 117 23.4 1094SS+3 days,1100 1106,1103SS+2 days 1101 Realizare Radier
1102 Elevatii pile si culei 41 days 11/22/22 2/8/23 1102 Elevatii pile si culei
1103 Elevatie si banchete C1 15 days 11/22/22 12/13/22 mc 141 9.4 1080,1101SS+2 days 1104SS+7 days,1110 1103 Elevatie si banchete C1
1104 Elevatie si Rigla P1 10 days 12/2/22 12/15/22 mc 141 14.1 1103SS+7 days,1087 1105SS+7 days 1104 Elevatie si Rigla P1
1105 Elevatie si Rigla P2 10 days 12/13/22 1/16/23 mc 141 14.1 1104SS+7 days,1094 1106SS+7 days 1105 Elevatie si Rigla P2
1106 Elevatie si banchete C2 15 days 1/12/23 2/1/23 mc 141 9.4 1105SS+7 days,1101 1107,1154SS+5 days,1120 1106 Elevatie si banchete C2
1107 Montare dispozitive antiseismice si aparate reazem 5 days 2/2/23 2/8/23 buc 20 4.0 1106 1130 1107 Montare dispozitive antiseismice si aparate reazem
1108 Racordari cu terasamente 75 days 12/14/22 4/21/23 1108 Racordari cu terasamente
1109 C1 75 days 12/14/22 4/21/23 1109 C1
1110 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 12/14/22 12/15/22 mc 200 100.0 1103 1111 1110 Sapatura pentru fundatie protectie taluz/sfert de con
1111 Fundatie protectie taluz/sfert de con 5 days 12/16/22 1/12/23 mc 160 32.0 1110 1113,1112 1111 Fundatie protectie taluz/sfert de con
1112 Tevi ape pluviale 2 days 1/13/23 1/16/23 m 95 47.5 1111 1114 1112 Tevi ape pluviale
1113 Umpluturi sfert de con material granular 5 days 1/13/23 1/19/23 mc 3000 600.0 1111 1114 1113 Umpluturi sfert de con material granular
1114 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 1/20/23 1/26/23 mp 1150 230.0 1112,1113 1115 1114 Protectie taluz / sfert con cu pereu de beton C35/45
1115 Scari pe taluz 3 days 1/27/23 1/31/23 m 45 15.0 1114 1116 1115 Scari pe taluz
1116 Casiuri pe taluz 3 days 2/1/23 2/3/23 m 55 18.3 1115 1116 Casiuri pe taluz
1117 Placi racordare C1 3 days 4/13/23 4/20/23 mc 19.5 6.5 1134 1118 1117 Placi racordare C1
1118 Hidroizolatie Placa racordare 1 day 4/21/23 4/21/23 mp 62.5 62.5 1117 1118 Hidroizolatie Placa racordare
1119 C2 54 days 2/2/23 4/21/23 1119 C2
1120 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 2/2/23 2/3/23 mc 200 100.0 1106 1121 1120 Sapatura pentru fundatie protectie taluz/sfert de con
1121 Fundatie protectie taluz/sfert de con 5 days 2/6/23 2/10/23 mc 160 32.0 1120 1123,1122 1121 Fundatie protectie taluz/sfert de con
1122 Tevi ape pluviale 2 days 2/13/23 2/14/23 m 95 47.5 1121 1124 1122 Tevi ape pluviale
1123 Umpluturi sfert de con material granular 5 days 2/13/23 2/17/23 mc 3000 600.0 1121 1124 1123 Umpluturi sfert de con material granular
1124 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 2/20/23 2/24/23 mp 1150 230.0 1122,1123 1125 1124 Protectie taluz / sfert con cu pereu de beton C35/45
1125 Scari pe taluz 3 days 2/27/23 3/1/23 m 45 15.0 1124 1126 1125 Scari pe taluz
1126 Casiuri pe taluz 3 days 3/2/23 3/6/23 m 55 18.3 1125 1126 Casiuri pe taluz
1127 Placi racordare C2 3 days 4/13/23 4/20/23 mc 19.5 6.5 1134 1128 1127 Placi racordare C2
1128 Hidroizolatie Placa racordare 1 day 4/21/23 4/21/23 mp 62.5 62.5 1127 1128 Hidroizolatie Placa racordare
1129 Suprastructura 45 days 2/9/23 4/12/23 1129 Suprastructura
1130 Montaj grinzi 10 days 2/9/23 2/22/23 buc 18 1.8 1107 1131 1130 Montaj grinzi
1131 Montaj predale 10 days 2/23/23 3/8/23 mc 99 9.9 1130 1132SS+5 days 1131 Montaj predale
1132 Montaj armatura in placa de suprabetonare si antretoaze 15 days 3/2/23 3/22/23 t 56.5 3.8 1131SS+5 days 1133SS+10 days,1136SS+5 days 1132 Montaj armatura in placa de suprabetonare si antretoaze
1133 Montaj cofraj la placa de suprabetonare 15 days 3/16/23 4/5/23 mp 200 13.3 1132SS+10 days 1134SS+10 days 1133 Montaj cofraj la placa de suprabetonare
1134 Turnare beton in placa de suprabetonare si antretoaze 10 days 3/30/23 4/12/23 mc 360 36.0 1136,1133SS+10 days 1138FS+5 days,1137,1117,1127 1134 Turnare beton in placa de suprabetonare si antretoaze
1135 Cale, trotuar, parapet 60 days 3/9/23 6/9/23 1135 Cale, trotuar, parapet
1136 Montaj guri de scurgere 5 days 3/9/23 3/15/23 buc 12 2.4 1132SS+5 days 1134 1136 Montaj guri de scurgere
1137 Prefabricat din beton pentru lisa parapet 5 days 4/13/23 4/24/23 m 196 39.2 1134 1139 1137 Prefabricat din beton pentru lisa parapet
1138 Hidroizolatie cale 10 days 4/25/23 5/9/23 mp 1075 107.5 1134FS+5 days 1139 1138 Hidroizolatie cale
1139 Borduri pe Pod 5 days 5/10/23 5/16/23 m 196 39.2 1137,1138 1140,1143 1139 Borduri pe Pod
1140 Trotuare pe pod 5 days 5/17/23 5/23/23 mc 71 14.2 1139 1141,1144 1140 Trotuare pe pod
1141 Sistem rutier 5 days 5/24/23 5/30/23 mp 620 124.0 1140 1142 1141 Sistem rutier
1142 Dispozitive de acoperire a rosturilor 5 days 5/31/23 6/9/23 m 25 5.0 1141 1142 Dispozitive de acoperire a rosturilor
1143 Parapeti pietonali si plase de protectie 10 days 5/17/23 5/30/23 m 196 19.6 1139 1143 Parapeti pietonali si plase de protectie
1144 Parapeti metalici 5 days 5/24/23 5/30/23 m 296 59.2 1140 1145 1144 Parapeti metalici
1145 Marcaje rutiere 5 days 5/31/23 6/9/23 0.0 1144 1145 Marcaje rutiere
1146 Pod pe drum agricol peste autostrada km 44+493 88.00 204 days 9/19/22 8/1/23 1146 Pod pe drum agricol peste autostrada km 44+493
1147 Fundatii pile si culei 86 days 9/19/22 2/7/23 1147 Fundatii pile si culei
1148 Culeea 1 77 days 9/19/22 1/25/23 1148 Culeea 1
1149 Piloti forati 4 days 9/19/22 9/22/22 buc 8 2.0 1096 1153FS+10 days,1156,1150FS+5 days 1149 Piloti forati
1150 Sapatura 2 days 9/30/22 10/3/22 mc 288 144.0 1149FS+5 days 1151 1150 Sapatura
1151 Demolare capete piloti 2 days 10/4/22 10/5/22 mc 9.25 4.6 1150 1152 1151 Demolare capete piloti
1152 Beton de egalizare 1 day 10/6/22 10/6/22 mc 12 12.0 1151 1153 1152 Beton de egalizare
1153 Teste coloane forate 2 days 10/7/22 10/10/22 buc 9 4.5 1149FS+10 days,1152 1154,1215 1153 Teste coloane forate
1154 Realizare Radier 5 days 1/19/23 1/25/23 mc 117 23.4 1153,1106SS+5 days 1177,1161SS+3 days 1154 Realizare Radier
1155 Pila 1 76 days 9/23/22 1/30/23 1155 Pila 1
1156 Piloti forati 4 days 9/23/22 9/28/22 buc 8 2.0 1149 1160FS+10 days,1163,1157FS+5 days 1156 Piloti forati
1157 Sapatura 2 days 10/6/22 10/7/22 mc 288 144.0 1156FS+5 days 1158 1157 Sapatura
1158 Demolare capete piloti 2 days 10/10/22 10/11/22 mc 9.25 4.6 1157 1159 1158 Demolare capete piloti
1159 Beton de egalizare 1 day 10/12/22 10/12/22 mc 12 12.0 1158 1160 1159 Beton de egalizare
1160 Teste coloane forate 2 days 10/13/22 10/14/22 buc 9 4.5 1156FS+10 days,1159 1161 1160 Teste coloane forate
1161 Realizare Radier 5 days 1/24/23 1/30/23 mc 117 23.4 1154SS+3 days,1160 1178,1168SS+3 days 1161 Realizare Radier
1162 Pila 2 75 days 9/29/22 2/2/23 1162 Pila 2
1163 Piloti forati 4 days 9/29/22 10/4/22 buc 8 2.0 1156 1170,1164FS+5 days,1167FS+10 days 1163 Piloti forati
1164 Sapatura 2 days 10/12/22 10/13/22 mc 288 144.0 1163FS+5 days 1165 1164 Sapatura
1165 Demolare capete piloti 2 days 10/14/22 10/17/22 mc 9.25 4.6 1164 1166 1165 Demolare capete piloti
1166 Beton de egalizare 1 day 10/18/22 10/18/22 mc 12 12.0 1165 1167 1166 Beton de egalizare
1167 Teste coloane forate 2 days 10/19/22 10/20/22 buc 9 4.5 1166,1163FS+10 days 1168 1167 Teste coloane forate
1168 Realizare Radier 5 days 1/27/23 2/2/23 mc 117 23.4 1161SS+3 days,1167 1179,1175SS+3 days 1168 Realizare Radier
1169 Culeea 2 74 days 10/5/22 2/7/23 1169 Culeea 2
1170 Piloti forati 4 days 10/5/22 10/10/22 buc 8 2.0 1163 1223,1171FS+5 days,1174FS+10 days 1170 Piloti forati
1171 Sapatura 2 days 10/18/22 10/19/22 mc 288 144.0 1170FS+5 days 1172 1171 Sapatura
1172 Demolare capete piloti 2 days 10/20/22 10/21/22 mc 9.25 4.6 1171 1173 1172 Demolare capete piloti
1173 Beton de egalizare 1 day 10/24/22 10/24/22 mc 12 12.0 1172 1174 1173 Beton de egalizare
1174 Teste coloane forate 2 days 10/25/22 10/26/22 buc 9 4.5 1173,1170FS+10 days 1175 1174 Teste coloane forate
1175 Realizare Radier 5 days 2/1/23 2/7/23 mc 117 23.4 1168SS+3 days,1174 1180,1177SS+2 days 1175 Realizare Radier
1176 Elevatii pile si culei 41 days 2/3/23 3/31/23 1176 Elevatii pile si culei
1177 Elevatie si banchete C1 15 days 2/3/23 2/23/23 mc 140.25 9.4 1154,1175SS+2 days 1178SS+7 days,1184 1177 Elevatie si banchete C1

Seite 11
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
1178 Elevatie si Rigla P1 10 days 2/14/23 2/27/23 mc 140.25 14.0 1177SS+7 days,1161 1179SS+7 days 1178 Elevatie si Rigla P1
1179 Elevatie si Rigla P2 10 days 2/23/23 3/8/23 mc 140.25 14.0 1178SS+7 days,1168 1180SS+7 days 1179 Elevatie si Rigla P2
1180 Elevatie si banchete C2 15 days 3/6/23 3/24/23 mc 140.25 9.4 1179SS+7 days,1175 1181,1228SS+10 days,1194 1180 Elevatie si banchete C2
1181 Montare dispozitive antiseismice si aparate reazem 5 days 3/27/23 3/31/23 buc 20 4.0 1180 1204 1181 Montare dispozitive antiseismice si aparate reazem
1182 Racordari cu terasamente 75 days 2/24/23 6/19/23 1182 Racordari cu terasamente
1183 C1 75 days 2/24/23 6/19/23 1183 C1
1184 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 2/24/23 2/27/23 mc 200 100.0 1177 1185 1184 Sapatura pentru fundatie protectie taluz/sfert de con
1185 Fundatie protectie taluz/sfert de con 5 days 2/28/23 3/6/23 mc 160 32.0 1184 1187,1186 1185 Fundatie protectie taluz/sfert de con
1186 Tevi ape pluviale 2 days 3/7/23 3/8/23 m 95 47.5 1185 1188 1186 Tevi ape pluviale
1187 Umpluturi sfert de con material granular 5 days 3/7/23 3/13/23 mc 3000 600.0 1185 1188 1187 Umpluturi sfert de con material granular
1188 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 3/14/23 3/20/23 mp 1150 230.0 1186,1187 1189 1188 Protectie taluz / sfert con cu pereu de beton C35/45
1189 Scari pe taluz 3 days 3/21/23 3/23/23 m 45 15.0 1188 1190 1189 Scari pe taluz
1190 Casiuri pe taluz 3 days 3/24/23 3/28/23 m 55 18.3 1189 1190 Casiuri pe taluz
1191 Placi racordare C1 3 days 6/14/23 6/16/23 mc 19.5 6.5 1208 1192 1191 Placi racordare C1
1192 Hidroizolatie Placa racordare 1 day 6/19/23 6/19/23 mp 62.5 62.5 1191 1192 Hidroizolatie Placa racordare
1193 C2 54 days 3/27/23 6/19/23 1193 C2
1194 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 3/27/23 3/28/23 mc 200 100.0 1180 1195 1194 Sapatura pentru fundatie protectie taluz/sfert de con
1195 Fundatie protectie taluz/sfert de con 5 days 3/29/23 4/4/23 mc 160 32.0 1194 1197,1196 1195 Fundatie protectie taluz/sfert de con
1196 Tevi ape pluviale 2 days 4/5/23 4/6/23 m 95 47.5 1195 1198 1196 Tevi ape pluviale
1197 Umpluturi sfert de con material granular 5 days 4/5/23 4/11/23 mc 3000 600.0 1195 1198 1197 Umpluturi sfert de con material granular
1198 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 4/12/23 4/21/23 mp 1150 230.0 1196,1197 1199 1198 Protectie taluz / sfert con cu pereu de beton C35/45
1199 Scari pe taluz 3 days 4/24/23 4/26/23 m 45 15.0 1198 1200 1199 Scari pe taluz
1200 Casiuri pe taluz 3 days 4/27/23 5/2/23 m 55 18.3 1199 1200 Casiuri pe taluz
1201 Placi racordare C2 3 days 6/14/23 6/16/23 mc 19.5 6.5 1208 1202 1201 Placi racordare C2
1202 Hidroizolatie Placa racordare 1 day 6/19/23 6/19/23 mp 62.5 62.5 1201 1202 Hidroizolatie Placa racordare
1203 Suprastructura 45 days 4/3/23 6/13/23 1203 Suprastructura
1204 Montaj grinzi 10 days 4/3/23 4/19/23 buc 18 1.8 1181 1205 1204 Montaj grinzi
1205 Montaj predale 10 days 4/20/23 5/4/23 mc 99 9.9 1204 1206SS+5 days 1205 Montaj predale
1206 Montaj armatura in placa de suprabetonare si antretoaze 15 days 4/27/23 5/18/23 t 56.5 3.8 1205SS+5 days 1207SS+10 days,1210SS+5 days 1206 Montaj armatura in placa de suprabetonare si antretoaze
1207 Montaj cofraj la placa de suprabetonare 15 days 5/12/23 6/6/23 mp 200 13.3 1206SS+10 days 1208SS+10 days 1207 Montaj cofraj la placa de suprabetonare
1208 Turnare beton in placa de suprabetonare si antretoaze 10 days 5/26/23 6/13/23 mc 360 36.0 1210,1207SS+10 days 1212FS+5 days,1211,1201,1191 1208 Turnare beton in placa de suprabetonare si antretoaze
1209 Cale, trotuar, parapet 60 days 5/5/23 8/1/23 1209 Cale, trotuar, parapet
1210 Montaj guri de scurgere 5 days 5/5/23 5/11/23 buc 12 2.4 1206SS+5 days 1208 1210 Montaj guri de scurgere
1211 Prefabricat din beton pentru lisa parapet 5 days 6/14/23 6/20/23 m 196 39.2 1208 1213 1211 Prefabricat din beton pentru lisa parapet
1212 Hidroizolatie cale 10 days 6/21/23 7/4/23 mp 1075 107.5 1208FS+5 days 1213 1212 Hidroizolatie cale
1213 Borduri pe Pod 5 days 7/5/23 7/11/23 m 196 39.2 1211,1212 1214,1217 1213 Borduri pe Pod
1214 Trotuare pe pod 5 days 7/12/23 7/18/23 mc 71 14.2 1213 1215,1218 1214 Trotuare pe pod
1215 Sistem rutier 5 days 7/19/23 7/25/23 mp 620 124.0 1153,1214 1216 1215 Sistem rutier
1216 Dispozitive de acoperire a rosturilor 5 days 7/26/23 8/1/23 m 25 5.0 1215 1216 Dispozitive de acoperire a rosturilor
1217 Parapeti pietonali si plase de protectie 10 days 7/12/23 7/25/23 m 196 19.6 1213 1217 Parapeti pietonali si plase de protectie
1218 Parapeti metalici 5 days 7/19/23 7/25/23 m 296 59.2 1214 1219 1218 Parapeti metalici
1219 Marcaje rutiere 5 days 7/26/23 8/1/23 0.0 1218 1219 Marcaje rutiere
1220 Pod peste paraul Leoteasca km 45+407 40.00 207 days 10/11/22 8/30/23 1220 Pod peste paraul Leoteasca km 45+407
1221 Fundatii pile si culei 112 days 10/11/22 4/6/23 1221 Fundatii pile si culei
1222 Culeea 1s 103 days 10/11/22 3/24/23 1222 Culeea 1s
1223 Piloti forati 4 days 10/11/22 10/14/22 buc 8 2.0 1170 1227FS+10 days,1230,1224FS+5 days 1223 Piloti forati
1224 Sapatura 2 days 10/24/22 10/25/22 mc 405 202.5 1223FS+5 days 1225 1224 Sapatura
1225 Demolare capete piloti 2 days 10/26/22 10/27/22 mc 11 5.5 1224 1226 1225 Demolare capete piloti
1226 Beton de egalizare 1 day 10/28/22 10/28/22 mc 13.75 13.8 1225 1227 1226 Beton de egalizare
1227 Teste coloane forate 2 days 10/31/22 11/1/22 buc 9 4.5 1223FS+10 days,1226 1228 1227 Teste coloane forate
1228 Realizare Radier 5 days 3/20/23 3/24/23 mc 180 36.0 1227,1180SS+10 days 1251,1235SS+3 days 1228 Realizare Radier
1229 Culeea 1d 102 days 10/17/22 3/29/23 1229 Culeea 1d
1230 Piloti forati 4 days 10/17/22 10/20/22 buc 8 2.0 1223 1237,1234FS+10 days,1231FS+5 days 1230 Piloti forati
1231 Sapatura 2 days 10/28/22 10/31/22 mc 405 202.5 1230FS+5 days 1232 1231 Sapatura
1232 Demolare capete piloti 2 days 11/1/22 11/2/22 mc 11 5.5 1231 1233 1232 Demolare capete piloti
1233 Beton de egalizare 1 day 11/3/22 11/3/22 mc 13.75 13.8 1232 1234 1233 Beton de egalizare
1234 Teste coloane forate 2 days 11/4/22 11/7/22 buc 9 4.5 1230FS+10 days,1233 1235 1234 Teste coloane forate
1235 Realizare Radier 5 days 3/23/23 3/29/23 mc 180 36.0 1228SS+3 days,1234 1252,1242SS+3 days 1235 Realizare Radier
1236 Culeea 2s 101 days 10/21/22 4/3/23 1236 Culeea 2s
1237 Piloti forati 4 days 10/21/22 10/26/22 buc 8 2.0 1230 1244,1238FS+5 days,1241FS+10 days 1237 Piloti forati
1238 Sapatura 2 days 11/3/22 11/4/22 mc 405 202.5 1237FS+5 days 1239 1238 Sapatura
1239 Demolare capete piloti 2 days 11/7/22 11/8/22 mc 11 5.5 1238 1240 1239 Demolare capete piloti
1240 Beton de egalizare 1 day 11/9/22 11/9/22 mc 13.75 13.8 1239 1241 1240 Beton de egalizare
1241 Teste coloane forate 2 days 11/10/22 11/11/22 buc 8 4.0 1240,1237FS+10 days 1242 1241 Teste coloane forate
1242 Realizare Radier 5 days 3/28/23 4/3/23 mc 180 36.0 1235SS+3 days,1241 1253,1249SS+3 days 1242 Realizare Radier
1243 Culeea 2d 100 days 10/27/22 4/6/23 1243 Culeea 2d
1244 Piloti forati 4 days 10/27/22 11/1/22 buc 8 2.0 1237 1370,1245FS+5 days,1248FS+10 days 1244 Piloti forati
1245 Sapatura 2 days 11/9/22 11/10/22 mc 405 202.5 1244FS+5 days 1246 1245 Sapatura
1246 Demolare capete piloti 2 days 11/11/22 11/14/22 mc 11 5.5 1245 1247 1246 Demolare capete piloti
1247 Beton de egalizare 1 day 11/15/22 11/15/22 mc 13.75 13.8 1246 1248 1247 Beton de egalizare
1248 Teste coloane forate 2 days 11/16/22 11/17/22 buc 8 4.0 1247,1244FS+10 days 1249 1248 Teste coloane forate
1249 Realizare Radier 5 days 3/31/23 4/6/23 mc 180 36.0 1242SS+3 days,1248 1254,1251SS+2 days 1249 Realizare Radier
1250 Elevatii pile si culei 36 days 4/4/23 5/29/23 1250 Elevatii pile si culei
1251 Elevatie si banchete C1s 10 days 4/4/23 4/20/23 mc 437.75 43.8 1228,1249SS+2 days 1252SS+7 days,1258 1251 Elevatie si banchete C1s
1252 Elevatie si banchete C1d 10 days 4/13/23 5/2/23 mc 437.75 43.8 1251SS+7 days,1235 1253SS+7 days 1252 Elevatie si banchete C1d
1253 Elevatie si banchete C2s 10 days 4/27/23 5/11/23 mc 437.75 43.8 1252SS+7 days,1242 1254SS+7 days 1253 Elevatie si banchete C2s
1254 Elevatie si banchete C2d 10 days 5/9/23 5/22/23 mc 437.75 43.8 1253SS+7 days,1249 1255,1269 1254 Elevatie si banchete C2d
1255 Montare dispozitive antiseismice si aparate reazem 5 days 5/23/23 5/29/23 buc 20 4.0 1254 1280 1255 Montare dispozitive antiseismice si aparate reazem
1256 Racordari cu terasamente 57 days 4/21/23 7/14/23 1256 Racordari cu terasamente
1257 C1 57 days 4/21/23 7/14/23 1257 C1
1258 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 4/21/23 4/24/23 mc 155 77.5 1251 1259 1258 Sapatura pentru fundatie protectie taluz/sfert de con
1259 Fundatie protectie taluz/sfert de con 5 days 4/25/23 5/2/23 mc 122.5 24.5 1258 1262,1260,1261 1259 Fundatie protectie taluz/sfert de con
1260 Dren din geotextil 2 days 5/3/23 5/4/23 mp 300 150.0 1259 1263 1260 Dren din geotextil
1261 Tevi ape pluviale 2 days 5/3/23 5/4/23 m 45 22.5 1259 1263 1261 Tevi ape pluviale
1262 Umpluturi sfert de con material granular 5 days 5/3/23 5/9/23 mc 1700 340.0 1259 1263 1262 Umpluturi sfert de con material granular
1263 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 5/10/23 5/16/23 mp 800 160.0 1260,1261,1262 1264 1263 Protectie taluz / sfert con cu pereu de beton C35/45
1264 Scari pe taluz 3 days 5/17/23 5/19/23 m 45 15.0 1263 1265 1264 Scari pe taluz
1265 Casiuri pe taluz 3 days 5/22/23 5/24/23 m 55 18.3 1264 1265 Casiuri pe taluz
1266 Placi racordare C1 3 days 7/11/23 7/13/23 mc 62 20.7 1283 1267 1266 Placi racordare C1
1267 Hidroizolatie Placa racordare 1 day 7/14/23 7/14/23 mp 175 175.0 1266 1267 Hidroizolatie Placa racordare
1268 C2 36 days 5/23/23 7/14/23 1268 C2
1269 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 5/23/23 5/24/23 mc 155 77.5 1254 1270 1269 Sapatura pentru fundatie protectie taluz/sfert de con
1270 Fundatie protectie taluz/sfert de con 5 days 5/25/23 5/31/23 mc 122.5 24.5 1269 1273,1271,1272 1270 Fundatie protectie taluz/sfert de con
1271 Dren din geotextil 2 days 6/6/23 6/7/23 mp 300 150.0 1270 1274 1271 Dren din geotextil
1272 Tevi ape pluviale 2 days 6/6/23 6/7/23 m 45 22.5 1270 1274 1272 Tevi ape pluviale
1273 Umpluturi sfert de con material granular 5 days 6/6/23 6/12/23 mc 1700 340.0 1270 1274 1273 Umpluturi sfert de con material granular
1274 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 6/13/23 6/19/23 mp 800 160.0 1271,1272,1273 1275 1274 Protectie taluz / sfert con cu pereu de beton C35/45
1275 Scari pe taluz 3 days 6/20/23 6/22/23 m 45 15.0 1274 1276 1275 Scari pe taluz
1276 Casiuri pe taluz 3 days 6/23/23 6/27/23 m 55 18.3 1275 1276 Casiuri pe taluz
1277 Placi racordare C2 3 days 7/11/23 7/13/23 mc 62 20.7 1283 1278 1277 Placi racordare C2
1278 Hidroizolatie Placa racordare 1 day 7/14/23 7/14/23 mp 175 175.0 1277 1278 Hidroizolatie Placa racordare
1279 Suprastructura 27 days 5/30/23 7/10/23 1279 Suprastructura
1280 Montaj grinzi 10 days 5/30/23 6/15/23 buc 12 1.2 1255 1281 1280 Montaj grinzi
1281 Montaj armatura in placa de suprabetonare si antretoaze 10 days 6/16/23 6/29/23 t 71.5 7.2 1280 1282SS+2 days,1285SS+2 days 1281 Montaj armatura in placa de suprabetonare si antretoaze
1282 Montaj cofraj la placa de suprabetonare 10 days 6/20/23 7/3/23 mp 635 63.5 1281SS+2 days 1283SS+2 days 1282 Montaj cofraj la placa de suprabetonare
1283 Turnare beton in placa de suprabetonare si antretoaze 10 days 6/27/23 7/10/23 mc 471 47.1 1285,1282SS+2 days 1287FS+5 days,1286,1266,1277 1283 Turnare beton in placa de suprabetonare si antretoaze
1284 Cale, trotuar, parapet 50 days 6/20/23 8/30/23 1284 Cale, trotuar, parapet

Seite 12
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
1285 Montaj guri de scurgere 5 days 6/20/23 6/26/23 buc 4 0.8 1281SS+2 days 1283 1285 Montaj guri de scurgere
1286 Prefabricat din beton pentru lisa parapet 5 days 7/11/23 7/17/23 m 200 40.0 1283 1288 1286 Prefabricat din beton pentru lisa parapet
1287 Hidroizolatie cale 10 days 7/18/23 7/31/23 mp 1040 104.0 1283FS+5 days 1288 1287 Hidroizolatie cale
1288 Borduri pe Pod 5 days 8/1/23 8/7/23 m 200 40.0 1286,1287 1289 1288 Borduri pe Pod
1289 Sistem rutier 5 days 8/8/23 8/16/23 mp 960 192.0 1288 1290,1291 1289 Sistem rutier
1290 Dispozitive de acoperire a rosturilor 5 days 8/17/23 8/23/23 m 56 11.2 1289 1290 Dispozitive de acoperire a rosturilor
1291 Parapeti metalici 5 days 8/17/23 8/23/23 m 400 80.0 1289 1292 1291 Parapeti metalici
1292 Marcaje rutiere 5 days 8/24/23 8/30/23 0.0 1291 1292 Marcaje rutiere
1293 Pod pe DJ203G peste autostrada km 47+890 88.00 207 days 1/19/23 11/16/23 1293 Pod pe DJ203G peste autostrada km 47+890
1294 Fundatii pile si culei 89 days 1/19/23 5/29/23 1294 Fundatii pile si culei
1295 Culeea 1 80 days 1/19/23 5/16/23 1295 Culeea 1
1296 Piloti forati 4 days 1/19/23 1/24/23 buc 8 2.0 765 1300FS+10 days,1303,1297FS+5 days 1296 Piloti forati
1297 Sapatura 2 days 2/1/23 2/2/23 mc 288 144.0 1296FS+5 days 1298 1297 Sapatura
1298 Demolare capete piloti 2 days 2/3/23 2/6/23 mc 9 4.5 1297 1299 1298 Demolare capete piloti
1299 Beton de egalizare 1 day 2/7/23 2/7/23 mc 12 12.0 1298 1300 1299 Beton de egalizare
1300 Teste coloane forate 2 days 2/8/23 2/9/23 buc 9 4.5 1296FS+10 days,1299 1301 1300 Teste coloane forate
1301 Realizare Radier 5 days 5/10/23 5/16/23 mc 117 23.4 1300,775SS+10 days 1324,1308SS+3 days 1301 Realizare Radier
1302 Pila 1 79 days 1/25/23 5/19/23 1302 Pila 1
1303 Piloti forati 4 days 1/25/23 1/30/23 buc 8 2.0 1296 1307FS+10 days,1310,1304FS+5 days 1303 Piloti forati
1304 Sapatura 2 days 2/7/23 2/8/23 mc 288 144.0 1303FS+5 days 1305 1304 Sapatura
1305 Demolare capete piloti 2 days 2/9/23 2/10/23 mc 9 4.5 1304 1306 1305 Demolare capete piloti
1306 Beton de egalizare 1 day 2/13/23 2/13/23 mc 12 12.0 1305 1307 1306 Beton de egalizare
1307 Teste coloane forate 2 days 2/14/23 2/15/23 buc 9 4.5 1303FS+10 days,1306 1308 1307 Teste coloane forate
1308 Realizare Radier 5 days 5/15/23 5/19/23 mc 117 23.4 1301SS+3 days,1307 1325,1315SS+3 days 1308 Realizare Radier
1309 Pila 2 78 days 1/31/23 5/24/23 1309 Pila 2
1310 Piloti forati 4 days 1/31/23 2/3/23 buc 8 2.0 1303 1317,1311FS+5 days,1314FS+10 days 1310 Piloti forati
1311 Sapatura 2 days 2/13/23 2/14/23 mc 288 144.0 1310FS+5 days 1312 1311 Sapatura
1312 Demolare capete piloti 2 days 2/15/23 2/16/23 mc 9 4.5 1311 1313 1312 Demolare capete piloti
1313 Beton de egalizare 1 day 2/17/23 2/17/23 mc 12 12.0 1312 1314 1313 Beton de egalizare
1314 Teste coloane forate 2 days 2/20/23 2/21/23 buc 8 4.0 1313,1310FS+10 days 1315 1314 Teste coloane forate
1315 Realizare Radier 5 days 5/18/23 5/24/23 mc 117 23.4 1308SS+3 days,1314 1326,1322SS+3 days 1315 Realizare Radier
1316 Culeea 2 77 days 2/6/23 5/29/23 1316 Culeea 2
1317 Piloti forati 4 days 2/6/23 2/9/23 buc 8 2.0 1310 1318FS+5 days,1321FS+10 days 1317 Piloti forati
1318 Sapatura 2 days 2/17/23 2/20/23 mc 288 144.0 1317FS+5 days 1319 1318 Sapatura
1319 Demolare capete piloti 2 days 2/21/23 2/22/23 mc 9 4.5 1318 1320 1319 Demolare capete piloti
1320 Beton de egalizare 1 day 2/23/23 2/23/23 mc 12 12.0 1319 1321 1320 Beton de egalizare
1321 Teste coloane forate 2 days 2/24/23 2/27/23 buc 8 4.0 1317FS+10 days,1320 1322 1321 Teste coloane forate
1322 Realizare Radier 5 days 5/23/23 5/29/23 mc 117 23.4 1315SS+3 days,1321 1327,1324SS+2 days 1322 Realizare Radier
1323 Elevatii pile si culei 41 days 5/25/23 7/25/23 1323 Elevatii pile si culei
1324 Elevatie si banchete C1 15 days 5/25/23 6/19/23 mc 141 9.4 1301,1322SS+2 days 1325SS+7 days,1331 1324 Elevatie si banchete C1
1325 Elevatie si Rigla P1 10 days 6/8/23 6/21/23 mc 141 14.1 1324SS+7 days,1308 1326SS+7 days 1325 Elevatie si Rigla P1
1326 Elevatie si Rigla P2 10 days 6/19/23 6/30/23 mc 141 14.1 1325SS+7 days,1315 1327SS+7 days 1326 Elevatie si Rigla P2
1327 Elevatie si banchete C2 15 days 6/28/23 7/18/23 mc 141 9.4 1326SS+7 days,1322 1328,1341 1327 Elevatie si banchete C2
1328 Montare dispozitive antiseismice si aparate reazem 5 days 7/19/23 7/25/23 buc 20 4.0 1327 1351 1328 Montare dispozitive antiseismice si aparate reazem
1329 Racordari cu terasamente 75 days 6/20/23 10/4/23 1329 Racordari cu terasamente
1330 C1 75 days 6/20/23 10/4/23 1330 C1
1331 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 6/20/23 6/21/23 mc 200 100.0 1324 1332 1331 Sapatura pentru fundatie protectie taluz/sfert de con
1332 Fundatie protectie taluz/sfert de con 5 days 6/22/23 6/28/23 mc 160 32.0 1331 1334,1333 1332 Fundatie protectie taluz/sfert de con
1333 Tevi ape pluviale 2 days 6/29/23 6/30/23 m 95 47.5 1332 1335 1333 Tevi ape pluviale
1334 Umpluturi sfert de con material granular 5 days 6/29/23 7/5/23 mc 3000 600.0 1332 1335 1334 Umpluturi sfert de con material granular
1335 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 7/6/23 7/12/23 mp 1150 230.0 1333,1334 1336 1335 Protectie taluz / sfert con cu pereu de beton C35/45
1336 Scari pe taluz 3 days 7/13/23 7/17/23 m 45 15.0 1335 1337 1336 Scari pe taluz
1337 Casiuri pe taluz 3 days 7/18/23 7/20/23 m 55 18.3 1336 1337 Casiuri pe taluz
1338 Placi racordare C1 3 days 9/29/23 10/3/23 mc 21 7.0 1355 1339 1338 Placi racordare C1
1339 Hidroizolatie Placa racordare 1 day 10/4/23 10/4/23 mp 62.5 62.5 1338 1339 Hidroizolatie Placa racordare
1340 C2 54 days 7/19/23 10/4/23 1340 C2
1341 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 7/19/23 7/20/23 mc 200 100.0 1327 1342 1341 Sapatura pentru fundatie protectie taluz/sfert de con
1342 Fundatie protectie taluz/sfert de con 5 days 7/21/23 7/27/23 mc 160 32.0 1341 1344,1343 1342 Fundatie protectie taluz/sfert de con
1343 Tevi ape pluviale 2 days 7/28/23 7/31/23 m 95 47.5 1342 1345 1343 Tevi ape pluviale
1344 Umpluturi sfert de con material granular 5 days 7/28/23 8/3/23 mc 3000 600.0 1342 1345 1344 Umpluturi sfert de con material granular
1345 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 8/4/23 8/10/23 mp 1150 230.0 1343,1344 1346 1345 Protectie taluz / sfert con cu pereu de beton C35/45
1346 Scari pe taluz 3 days 8/11/23 8/17/23 m 45 15.0 1345 1347 1346 Scari pe taluz
1347 Casiuri pe taluz 3 days 8/18/23 8/22/23 m 55 18.3 1346 1347 Casiuri pe taluz
1348 Placi racordare C2 3 days 9/29/23 10/3/23 mc 21 7.0 1355 1349 1348 Placi racordare C2
1349 Hidroizolatie Placa racordare 1 day 10/4/23 10/4/23 mp 62.5 62.5 1348 1349 Hidroizolatie Placa racordare
1350 Suprastructura 45 days 7/26/23 9/28/23 1350 Suprastructura
1351 Montaj grinzi 10 days 7/26/23 8/8/23 buc 18 1.8 1328 1352 1351 Montaj grinzi
1352 Montaj predale 10 days 8/9/23 8/24/23 mc 106 10.6 1351 1353SS+5 days 1352 Montaj predale
1353 Montaj armatura in placa de suprabetonare si antretoaze 15 days 8/18/23 9/7/23 t 56.5 3.8 1352SS+5 days 1354SS+10 days,1357SS+5 days 1353 Montaj armatura in placa de suprabetonare si antretoaze
1354 Montaj cofraj la placa de suprabetonare 15 days 9/1/23 9/21/23 mp 215 14.3 1353SS+10 days 1355SS+10 days 1354 Montaj cofraj la placa de suprabetonare
1355 Turnare beton in placa de suprabetonare si antretoaze 10 days 9/15/23 9/28/23 mc 365 36.5 1357,1354SS+10 days 1359FS+5 days,1358,1338,1348 1355 Turnare beton in placa de suprabetonare si antretoaze
1356 Cale, trotuar, parapet 60 days 8/25/23 11/16/23 1356 Cale, trotuar, parapet
1357 Montaj guri de scurgere 5 days 8/25/23 8/31/23 buc 12 2.4 1353SS+5 days 1355 1357 Montaj guri de scurgere
1358 Prefabricat din beton pentru lisa parapet 5 days 9/29/23 10/5/23 m 196 39.2 1355 1360 1358 Prefabricat din beton pentru lisa parapet
1359 Hidroizolatie cale 10 days 10/6/23 10/19/23 mp 1144 114.4 1355FS+5 days 1360 1359 Hidroizolatie cale
1360 Borduri pe Pod 5 days 10/20/23 10/26/23 m 196 39.2 1358,1359 1361,1364 1360 Borduri pe Pod
1361 Trotuare pe pod 5 days 10/27/23 11/2/23 mc 71 14.2 1360 1362,1365 1361 Trotuare pe pod
1362 Sistem rutier 5 days 11/3/23 11/9/23 mp 690 138.0 1361 1363 1362 Sistem rutier
1363 Dispozitive de acoperire a rosturilor 5 days 11/10/23 11/16/23 m 25 5.0 1362 1363 Dispozitive de acoperire a rosturilor
1364 Parapeti pietonali si plase de protectie 10 days 10/27/23 11/9/23 m 196 19.6 1360 1364 Parapeti pietonali si plase de protectie
1365 Parapeti metalici 5 days 11/3/23 11/9/23 m 296 59.2 1361 1366 1365 Parapeti metalici
1366 Marcaje rutiere 5 days 11/10/23 11/16/23 0.0 1365 1366 Marcaje rutiere
1367 Pod pea DJ203C peste paraulSarata km0+776 40.00 83 days 11/2/22 3/20/23 1367 Pod pea DJ203C peste paraulSarata km0+776
1368 Fundatii pile si culei 16 days 11/2/22 11/23/22 1368 Fundatii pile si culei
1369 Culeea 1 14 days 11/2/22 11/21/22 1369 Culeea 1
1370 Piloti forati 2 days 11/2/22 11/3/22 buc 4 2.0 1244 1374FS+10 days,1376,1371FS+5 days 1370 Piloti forati
1371 Sapatura 2 days 11/11/22 11/14/22 mc 165 82.5 1370FS+5 days 1372 1371 Sapatura
1372 Demolare capete piloti 2 days 11/15/22 11/16/22 mc 5.5 2.8 1371 1373 1372 Demolare capete piloti
1373 Beton de egalizare 1 day 11/17/22 11/17/22 mc 6.5 6.5 1372 1374 1373 Beton de egalizare
1374 Teste coloane forate 2 days 11/18/22 11/21/22 buc 5 2.5 1370FS+10 days,1373 1382 1374 Teste coloane forate
1375 Culeea 2 14 days 11/4/22 11/23/22 1375 Culeea 2
1376 Piloti forati 2 days 11/4/22 11/7/22 buc 4 2.0 1370 1380FS+10 days,669,1377FS+5 days 1376 Piloti forati
1377 Sapatura 2 days 11/15/22 11/16/22 mc 165 82.5 1376FS+5 days 1378 1377 Sapatura
1378 Demolare capete piloti 2 days 11/17/22 11/18/22 mc 5.5 2.8 1377 1379 1378 Demolare capete piloti
1379 Beton de egalizare 1 day 11/21/22 11/21/22 mc 6.5 6.5 1378 1380 1379 Beton de egalizare
1380 Teste coloane forate 2 days 11/22/22 11/23/22 buc 5 2.5 1376FS+10 days,1379 1383 1380 Teste coloane forate
1381 Elevatii pile si culei 20 days 11/22/22 1/10/23 1381 Elevatii pile si culei
1382 Elevatie si banchete C1 10 days 11/22/22 12/6/22 mc 145 14.5 1374 1383SS+7 days,1387 1382 Elevatie si banchete C1
1383 Elevatie si banchete C2 10 days 12/2/22 12/15/22 mc 145 14.5 1382SS+7 days,1380 1384,674SS+10 days,1397 1383 Elevatie si banchete C2
1384 Montare dispozitive antiseismice si aparate reazem 3 days 12/16/22 1/10/23 buc 8 2.7 1383 1407 1384 Montare dispozitive antiseismice si aparate reazem
1385 Racordari cu terasamente 34 days 12/7/22 2/13/23 1385 Racordari cu terasamente
1386 C1 33 days 12/7/22 2/10/23 1386 C1
1387 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 12/7/22 12/8/22 mc 50 25.0 1382 1388 1387 Sapatura pentru fundatie protectie taluz/sfert de con
1388 Fundatie protectie taluz/sfert de con 5 days 12/9/22 12/15/22 mc 40 8.0 1387 1390,1389 1388 Fundatie protectie taluz/sfert de con
1389 Tevi ape pluviale 2 days 12/16/22 1/9/23 m 50 25.0 1388 1391 1389 Tevi ape pluviale
1390 Umpluturi sfert de con material granular 5 days 12/16/22 1/12/23 mc 265 53.0 1388 1391 1390 Umpluturi sfert de con material granular
1391 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 1/13/23 1/19/23 mp 185 37.0 1389,1390 1392 1391 Protectie taluz / sfert con cu pereu de beton C35/45

Seite 13
ID Name Total length Duration Start Finish U.M BOQ Productivitate Predecessors Successors Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
M A M J J A S O N D J F M A M J J A S O N D J F M
1392 Scari pe taluz 3 days 1/20/23 1/24/23 m 18 6.0 1391 1393 1392 Scari pe taluz
1393 Casiuri pe taluz 3 days 1/25/23 1/27/23 m 26 8.7 1392 1393 Casiuri pe taluz
1394 Placi racordare C1 3 days 2/7/23 2/9/23 mc 21 7.0 1410 1395 1394 Placi racordare C1
1395 Hidroizolatie Placa racordare 1 day 2/10/23 2/10/23 mp 62.5 62.5 1394 1395 Hidroizolatie Placa racordare
1396 C2 27 days 12/16/22 2/13/23 1396 C2
1397 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 12/16/22 1/9/23 mc 50 25.0 1383 1398 1397 Sapatura pentru fundatie protectie taluz/sfert de con
1398 Fundatie protectie taluz/sfert de con 5 days 1/10/23 1/16/23 mc 40 8.0 1397 1400,1399 1398 Fundatie protectie taluz/sfert de con
1399 Tevi ape pluviale 2 days 1/17/23 1/18/23 m 50 25.0 1398 1401 1399 Tevi ape pluviale
1400 Umpluturi sfert de con material granular 5 days 1/17/23 1/23/23 mc 265 53.0 1398 1401 1400 Umpluturi sfert de con material granular
1401 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 1/24/23 1/30/23 mp 185 37.0 1399,1400 1402 1401 Protectie taluz / sfert con cu pereu de beton C35/45
1402 Scari pe taluz 3 days 1/31/23 2/2/23 m 18 6.0 1401 1403 1402 Scari pe taluz
1403 Casiuri pe taluz 3 days 2/3/23 2/7/23 m 26 8.7 1402 1404 1403 Casiuri pe taluz
1404 Placi racordare C2 3 days 2/8/23 2/10/23 mc 21 7.0 1410,1403 1405 1404 Placi racordare C2
1405 Hidroizolatie Placa racordare 1 day 2/13/23 2/13/23 mp 62.5 62.5 1404 1405 Hidroizolatie Placa racordare
1406 Suprastructura 19 days 1/11/23 2/6/23 1406 Suprastructura
1407 Montaj grinzi 10 days 1/11/23 1/24/23 buc 5 0.5 1384 1408 1407 Montaj grinzi
1408 Montaj armatura in placa de suprabetonare si antretoaze 5 days 1/25/23 1/31/23 t 32.5 6.5 1407 1409SS+2 days,1412SS+2 days 1408 Montaj armatura in placa de suprabetonare si antretoaze
1409 Montaj cofraj la placa de suprabetonare 5 days 1/27/23 2/2/23 mp 290 58.0 1408SS+2 days 1410SS+2 days 1409 Montaj cofraj la placa de suprabetonare
1410 Turnare beton in placa de suprabetonare si antretoaze 5 days 1/31/23 2/6/23 mc 210 42.0 1412,1409SS+2 days 1414FS+5 days,1413,1394,1404 1410 Turnare beton in placa de suprabetonare si antretoaze
1411 Cale, trotuar, parapet 37 days 1/27/23 3/20/23 1411 Cale, trotuar, parapet
1412 Montaj guri de scurgere 2 days 1/27/23 1/30/23 buc 4 2.0 1408SS+2 days 1410 1412 Montaj guri de scurgere
1413 Prefabricat din beton pentru lisa parapet 5 days 2/7/23 2/13/23 m 98 19.6 1410 1415 1413 Prefabricat din beton pentru lisa parapet
1414 Hidroizolatie cale 5 days 2/14/23 2/20/23 mp 500 100.0 1410FS+5 days 1415 1414 Hidroizolatie cale
1415 Borduri pe Pod 5 days 2/21/23 2/27/23 m 98 19.6 1413,1414 1419,1416 1415 Borduri pe Pod
1416 Trotuare pe pod 5 days 2/28/23 3/6/23 mc 36 7.2 1415 1417,1420 1416 Trotuare pe pod
1417 Sistem rutier 5 days 3/7/23 3/13/23 mp 320 64.0 1416 1418 1417 Sistem rutier
1418 Dispozitive de acoperire a rosturilor 5 days 3/14/23 3/20/23 m 25 5.0 1417 1418 Dispozitive de acoperire a rosturilor
1419 Parapeti pietonali 10 days 2/28/23 3/13/23 m 99 9.9 1415 1419 Parapeti pietonali
1420 Parapeti metalici 5 days 3/7/23 3/13/23 m 199 39.8 1416 1421 1420 Parapeti metalici
1421 Marcaje rutiere 5 days 3/14/23 3/20/23 0.0 1420 1421 Marcaje rutiere
1422 Pod pe DJ203C peste paraul Leoteasca km 3+774 30.00 86 days 5/26/22 9/26/22 1422 Pod pe DJ203C peste paraul Leoteasca km 3+774
1423 Fundatii pile si culei 16 days 5/26/22 6/17/22 1423 Fundatii pile si culei
1424 Culeea 1 14 days 5/26/22 6/15/22 1424 Culeea 1
1425 Piloti forati 2 days 5/26/22 5/27/22 buc 4 2.0 2FS+5 days 1429FS+10 days,1431,1426FS+5 days 1425 Piloti forati
1426 Sapatura 2 days 6/6/22 6/7/22 mc 165 82.5 1425FS+5 days 1427 1426 Sapatura
1427 Demolare capete piloti 2 days 6/8/22 6/9/22 mc 5.5 2.8 1426 1428 1427 Demolare capete piloti
1428 Beton de egalizare 1 day 6/10/22 6/10/22 mc 6.5 6.5 1427 1429 1428 Beton de egalizare
1429 Teste coloane forate 2 days 6/14/22 6/15/22 buc 5 2.5 1425FS+10 days,1428 1437 1429 Teste coloane forate
1430 Culeea 2 14 days 5/30/22 6/17/22 1430 Culeea 2
1431 Piloti forati 2 days 5/30/22 5/31/22 buc 4 2.0 1425 1435FS+10 days,6,1432FS+5 days 1431 Piloti forati
1432 Sapatura 2 days 6/8/22 6/9/22 mc 165 82.5 1431FS+5 days 1433 1432 Sapatura
1433 Demolare capete piloti 2 days 6/10/22 6/14/22 mc 5.5 2.8 1432 1434 1433 Demolare capete piloti
1434 Beton de egalizare 1 day 6/15/22 6/15/22 mc 6.5 6.5 1433 1435 1434 Beton de egalizare
1435 Teste coloane forate 2 days 6/16/22 6/17/22 buc 5 2.5 1431FS+10 days,1434 1438 1435 Teste coloane forate
1436 Elevatii pile si culei 20 days 6/16/22 7/13/22 1436 Elevatii pile si culei
1437 Elevatie si banchete C1 10 days 6/16/22 6/29/22 mc 105 10.5 1429 1438SS+7 days,1442 1437 Elevatie si banchete C1
1438 Elevatie si banchete C2 10 days 6/27/22 7/8/22 mc 105 10.5 1437SS+7 days,1435 1439,11SS+10 days,1452 1438 Elevatie si banchete C2
1439 Montare dispozitive antiseismice si aparate reazem 3 days 7/11/22 7/13/22 buc 10 3.3 1438 1462 1439 Montare dispozitive antiseismice si aparate reazem
1440 Racordari cu terasamente 36 days 6/30/22 8/19/22 1440 Racordari cu terasamente
1441 C1 36 days 6/30/22 8/19/22 1441 C1
1442 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 6/30/22 7/1/22 mc 50 25.0 1437 1443 1442 Sapatura pentru fundatie protectie taluz/sfert de con
1443 Fundatie protectie taluz/sfert de con 5 days 7/4/22 7/8/22 mc 40 8.0 1442 1445,1444 1443 Fundatie protectie taluz/sfert de con
1444 Tevi ape pluviale 2 days 7/11/22 7/12/22 m 40 20.0 1443 1446 1444 Tevi ape pluviale
1445 Umpluturi sfert de con material granular 5 days 7/11/22 7/15/22 mc 262 52.4 1443 1446 1445 Umpluturi sfert de con material granular
1446 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 7/18/22 7/22/22 mp 185 37.0 1444,1445 1447 1446 Protectie taluz / sfert con cu pereu de beton C35/45
1447 Scari pe taluz 3 days 7/25/22 7/27/22 m 18 6.0 1446 1448 1447 Scari pe taluz
1448 Casiuri pe taluz 3 days 7/28/22 8/1/22 m 26 8.7 1447 1449 1448 Casiuri pe taluz
1449 Placi racordare C1 3 days 8/16/22 8/18/22 mc 21 7.0 1448,1466 1450 1449 Placi racordare C1
1450 Hidroizolatie Placa racordare 1 day 8/19/22 8/19/22 mp 62.5 62.5 1449 1450 Hidroizolatie Placa racordare
1451 C2 29 days 7/11/22 8/19/22 1451 C2
1452 Sapatura pentru fundatie protectie taluz/sfert de con 2 days 7/11/22 7/12/22 mc 50 25.0 1438 1453 1452 Sapatura pentru fundatie protectie taluz/sfert de con
1453 Fundatie protectie taluz/sfert de con 5 days 7/13/22 7/19/22 mc 40 8.0 1452 1455,1454 1453 Fundatie protectie taluz/sfert de con
1454 Tevi ape pluviale 2 days 7/20/22 7/21/22 m 40 20.0 1453 1456 1454 Tevi ape pluviale
1455 Umpluturi sfert de con material granular 5 days 7/20/22 7/26/22 mc 262 52.4 1453 1456 1455 Umpluturi sfert de con material granular
1456 Protectie taluz / sfert con cu pereu de beton C35/45 5 days 7/27/22 8/2/22 mp 185 37.0 1454,1455 1457 1456 Protectie taluz / sfert con cu pereu de beton C35/45
1457 Scari pe taluz 3 days 8/3/22 8/5/22 m 18 6.0 1456 1458 1457 Scari pe taluz
1458 Casiuri pe taluz 3 days 8/8/22 8/10/22 m 26 8.7 1457 1459 1458 Casiuri pe taluz
1459 Placi racordare C2 3 days 8/16/22 8/18/22 mc 21 7.0 1458,1466 1460 1459 Placi racordare C2
1460 Hidroizolatie Placa racordare 1 day 8/19/22 8/19/22 mp 62.5 62.5 1459 1460 Hidroizolatie Placa racordare
1461 Suprastructura 22 days 7/14/22 8/12/22 1461 Suprastructura
1462 Montaj grinzi 10 days 7/14/22 7/27/22 buc 6 0.6 1439 1463 1462 Montaj grinzi
1463 Montaj predale 3 days 7/28/22 8/1/22 mc 36 12.0 1462 1464 1463 Montaj predale
1464 Montaj armatura in placa de suprabetonare si antretoaze 5 days 8/2/22 8/8/22 t 21.5 4.3 1463 1465SS+2 days,1468SS+2 days 1464 Montaj armatura in placa de suprabetonare si antretoaze
1465 Montaj cofraj la placa de suprabetonare 5 days 8/4/22 8/10/22 mp 105 21.0 1464SS+2 days 1466SS+2 days 1465 Montaj cofraj la placa de suprabetonare
1466 Turnare beton in placa de suprabetonare si antretoaze 5 days 8/8/22 8/12/22 mc 135 27.0 1468,1465SS+2 days 1470FS+5 days,1469,1449,1459 1466 Turnare beton in placa de suprabetonare si antretoaze
1467 Cale, trotuar, parapet 37 days 8/4/22 9/26/22 1467 Cale, trotuar, parapet
1468 Montaj guri de scurgere 2 days 8/4/22 8/5/22 buc 4 2.0 1464SS+2 days 1466 1468 Montaj guri de scurgere
1469 Prefabricat din beton pentru lisa parapet 5 days 8/16/22 8/22/22 m 76 15.2 1466 1471 1469 Prefabricat din beton pentru lisa parapet
1470 Hidroizolatie cale 5 days 8/23/22 8/29/22 mp 400 80.0 1466FS+5 days 1471 1470 Hidroizolatie cale
1471 Borduri pe Pod 5 days 8/30/22 9/5/22 m 76 15.2 1469,1470 1475,1472 1471 Borduri pe Pod
1472 Trotuare pe pod 5 days 9/6/22 9/12/22 mc 28 5.6 1471 1473,1476 1472 Trotuare pe pod
1473 Sistem rutier 5 days 9/13/22 9/19/22 mp 240 48.0 1472 1474 1473 Sistem rutier
1474 Dispozitive de acoperire a rosturilor 5 days 9/20/22 9/26/22 m 25 5.0 1473 1474 Dispozitive de acoperire a rosturilor
1475 Parapeti pietonali 10 days 9/6/22 9/19/22 m 76 7.6 1471 1475 Parapeti pietonali
1476 Parapeti metalici 5 days 9/13/22 9/19/22 m 176 35.2 1472 1477 1476 Parapeti metalici
1477 Marcaje rutiere 5 days 9/20/22 9/26/22 0.0 1476 1477 Marcaje rutiere