ID Task Name Duration Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24

Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SM TWT F S SMTWT F S SMTWT F S SMTWT F S S
1 Official Speaker`s 187 days 2/19 11/5
Residence

2 Pre-Construction 20 days 2/19 3/15

3 Contract Signing 1 day 2/19 2/19

4 Submit 7 days 2/20 2/28


Bond/Insurance

5 Site Facilities Set 12 days 2/29 3/15


Up

6 Sub-Structures 32 days 3/20 5/2

7 Site Clearance 3 days 3/20 3/22

8 Setting Out 2 days 3/25 3/26

9 Excavations 5 days 3/27 4/2

10 Lean Concrete 1 day 4/3 4/3

11 Foundation 10 days 4/4 4/17


Concrete(Rebars/Fwk/Concrete)

12 Foundation Walling 5 days 4/18 4/24

13 Backfilling 2 days 4/25 4/26

14 Floor 4 days 4/29 5/2


Bed(Antitermite/DPM/BRC/Concrete)

15 Ground Floor 29 days 5/3 6/12

16 Columns(Rebars/Fwk/Concrete)
3 days 5/3 5/7

17 Walling 10 days 5/8 5/21

18 Suspended 16 days 5/22 6/12


Slab/Beams(Rebars/Fwk/casting)

19 Staircase(Rebars/Fwk/Concrete)
16 days 5/22 6/12

20 Electrical Works 16 days 5/22 6/12


1st installations

21 Mechanical works 16 days 5/22 6/12


1st installations

22 First Floor 45 days 5/22 7/23

23 Columns(Rebars/Fwk/Concrete)
3 days 5/22 5/24

24 Walling 10 days 5/27 6/7

25 Suspended 16 days 6/10 7/1


Slab/Beams(Rebars/Fwk/casting)

26 Roof Construction 16 days 7/2 7/23

27 Electrical Works 16 days 6/10 7/1


1st installations

28 Mechanical works 16 days 6/10 7/1


1st installations

29 Finishes 77 days 7/2 10/16

30 Internal Plaster 21 days 7/24 8/21


work

31 External Finishes 14 days 8/1 8/20

32 Aluminium 14 days 8/29 9/17


Windows

33 Ceiling Finishes 8 days 7/2 7/11

34 Screed 6 days 9/4 9/11

35 Joinery Fittings 12 days 7/12 7/29

36 Doors 12 days 9/4 9/19

37 Tiles 14 days 9/14 10/2

38 Paint Works 24 days 9/13 10/16

39 Electrical Works 60 days 7/24 10/15


2nd installations

40 Mechanical works 60 days 7/24 10/15


2nd installations

41 External Works 45 days 7/17 9/17

42 Snagging & Handover 14 days 10/17 11/5

Project: speakers residence Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Mon 2/12/24 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1