May 2024 Jun 2024 Jul 2024 Aug 2024 Sep 2024 Oct 2024

Name Duration Start Finish


31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
1 Kadengoi Water Pan 130 days? 4/8/24 8:00 AM 9/7/24 5:00 PM
2 Site Hand Over 0 days? 4/8/24 8:00 AM 4/8/24 8:00 AM
3 Preliminaries 19 days 4/8/24 8:00 AM 4/29/24 5:00 PM
4 Mobilization 7 days 4/8/24 8:00 AM 4/15/24 5:00 PM
5 Site Office/Camp Set Up 12 days 4/16/24 8:00 AM 4/29/24 5:00 PM
6 Reservoir 42 days 4/30/24 8:00 AM 6/19/24 5:00 PM
7 Clear Site 10 days 4/30/24 8:00 AM 5/10/24 5:00 PM
8 Excavations 32 days 5/11/24 8:00 AM 6/19/24 5:00 PM
9 Silt Trap 16 days 6/11/24 8:00 AM 6/28/24 5:00 PM
10 Excavations 6 days 6/11/24 8:00 AM 6/17/24 5:00 PM
11 Stone Pitching 14 days 6/13/24 8:00 AM 6/28/24 5:00 PM
12 Inlet Construction 36 days 6/12/24 8:00 AM 7/23/24 5:00 PM
13 Gabions 22 days 6/12/24 8:00 AM 7/6/24 5:00 PM
14 Concrete Works 14 days 7/8/24 8:00 AM 7/23/24 5:00 PM
15 Outlet Channel Construction 31 days 7/2/24 8:00 AM 8/6/24 5:00 PM
16 Excavations 8 days 7/2/24 8:00 AM 7/10/24 5:00 PM
17 Concrete Works 10 days 7/11/24 8:00 AM 7/22/24 5:00 PM
18 Gabions & Stone Pitches 16 days 7/19/24 8:00 AM 8/6/24 5:00 PM
19 Intake Tower 14 days 7/31/24 8:00 AM 8/15/24 5:00 PM
20 Water Trough 21 days 8/8/24 8:00 AM 8/31/24 5:00 PM
21 Pan Fence & gates 12 days 8/26/24 8:00 AM 9/7/24 5:00 PM
22 Project Close 0 days 9/7/24 5:00 PM 9/7/24 5:00 PM 9/7