Work Schedule

ID Task Name Duration Start Finish Predecessors


Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
1 10 nos SIngle storied RCC Wash Block 360 days Feb 29 '24 Mar 10 '25
2 Mobilization of all Equipment, 20 days Feb 29 '24 Mar 19 '24
Materials & Manpower
3 Wash Block-01 140 days Mar 20 '24 Aug 22 '24
4 Earth Excavation 5 days Mar 20 '24 Mar 24 '24 2
5 Footing 5 days Mar 25 '24 Mar 29 '24 4
6 Short column & Beam 15 days Mar 30 '24 Apr 22 '24 5
7 Column & Slab of 1st floor 10 days Apr 23 '24 May 2 '24 6
8 Brick work 15 days May 3 '24 May 17 '24 7
9 Sanitary & Electric work 15 days May 18 '24 Jun 1 '24 8
10 Interior work 10 days Jun 2 '24 Jun 11 '24 9
11 Tiles 10 days Jun 12 '24 Jun 28 '24 10
12 Boring work 5 days Jun 29 '24 Jul 3 '24 11
13 Others work 50 days Jul 4 '24 Aug 22 '24 12
14 Wash Block-02 150 days Mar 25 '24 Sep 6 '24
15 Earth Excavation 5 days Mar 25 '24 Mar 29 '24 4
16 Footing 5 days Mar 30 '24 Apr 3 '24 15
17 Short column & Beam 15 days Apr 23 '24 May 7 '24 6
18 Column & Slab of 1st floor 10 days May 8 '24 May 17 '24 17
19 Brick work 15 days May 18 '24 Jun 1 '24 18
20 Sanitary & Electric work 15 days Jun 2 '24 Jun 23 '24 19
21 Interior work 10 days Jun 24 '24 Jul 3 '24 20
22 Tiles 10 days Jul 4 '24 Jul 13 '24 21
23 Boring work 5 days Jul 14 '24 Jul 18 '24 22
24 Others work 50 days Jul 19 '24 Sep 6 '24 23
25 Wash Block-03 160 days Mar 30 '24 Sep 21 '24
26 Earth Excavation 5 days Mar 30 '24 Apr 3 '24 15
27 Footing 5 days Apr 4 '24 Apr 17 '24 26
28 Short column & Beam 15 days May 8 '24 May 22 '24 17
29 Column & Slab of 1st floor 10 days May 23 '24 Jun 1 '24 28
30 Brick work 15 days Jun 2 '24 Jun 23 '24 29
31 Sanitary & Electric work 15 days Jun 24 '24 Jul 8 '24 30
32 Interior work 10 days Jul 9 '24 Jul 18 '24 31
33 Tiles 10 days Jul 19 '24 Jul 28 '24 32
34 Boring work 5 days Jul 29 '24 Aug 2 '24 33
35 Others work 50 days Aug 3 '24 Sep 21 '24 34
36 Wash Block-04 140 days Apr 4 '24 Sep 6 '24
37 Earth Excavation 5 days Apr 4 '24 Apr 17 '24 26
38 Footing 5 days Apr 18 '24 Apr 22 '24 37
39 Short column & Beam 15 days Apr 23 '24 May 7 '24 38
40 Column & Slab of 1st floor 10 days May 8 '24 May 17 '24 39
41 Brick work 15 days May 18 '24 Jun 1 '24 40
42 Sanitary & Electric work 15 days Jun 2 '24 Jun 23 '24 41
43 Interior work 10 days Jun 24 '24 Jul 3 '24 42
44 Tiles 10 days Jul 4 '24 Jul 13 '24 43
45 Boring work 5 days Jul 14 '24 Jul 18 '24 44
46 Others work 50 days Jul 19 '24 Sep 6 '24 45
47 Wash Block-05 140 days Apr 18 '24 Sep 11 '24
48 Earth Excavation 5 days Apr 18 '24 Apr 22 '24 37
49 Footing 5 days Apr 23 '24 Apr 27 '24 48
50 Short column & Beam 15 days Apr 28 '24 May 12 '24 49
51 Column & Slab of 1st floor 10 days May 13 '24 May 22 '24 50
52 Brick work 15 days May 23 '24 Jun 6 '24 51
53 Sanitary & Electric work 15 days Jun 7 '24 Jun 28 '24 52
54 Interior work 10 days Jun 29 '24 Jul 8 '24 53
55 Tiles 10 days Jul 9 '24 Jul 18 '24 54
56 Boring work 5 days Jul 19 '24 Jul 23 '24 55
57 Others work 50 days Jul 24 '24 Sep 11 '24 56
Work Schedule
ID Task Name Duration Start Finish Predecessors
Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
58 Wash Block-06 140 days Jul 29 '24 Dec 15 '24
59 Earth Excavation 5 days Jul 29 '24 Aug 2 '24 33
60 Footing 5 days Aug 3 '24 Aug 7 '24 59
61 Short column & Beam 15 days Aug 8 '24 Aug 22 '24 60
62 Column & Slab of 1st floor 10 days Aug 23 '24 Sep 1 '24 61
63 Brick work 15 days Sep 2 '24 Sep 16 '24 62
64 Sanitary & Electric work 15 days Sep 17 '24 Oct 1 '24 63
65 Interior work 10 days Oct 2 '24 Oct 11 '24 64
66 Tiles 10 days Oct 12 '24 Oct 21 '24 65
67 Boring work 5 days Oct 22 '24 Oct 26 '24 66
68 Others work 50 days Oct 27 '24 Dec 15 '24 67
69 Wash Block-07 140 days Jul 14 '24 Nov 30 '24
70 Earth Excavation 5 days Jul 14 '24 Jul 18 '24 44
71 Footing 5 days Jul 19 '24 Jul 23 '24 70
72 Short column & Beam 15 days Jul 24 '24 Aug 7 '24 71
73 Column & Slab of 1st floor 10 days Aug 8 '24 Aug 17 '24 72
74 Brick work 15 days Aug 18 '24 Sep 1 '24 73
75 Sanitary & Electric work 15 days Sep 2 '24 Sep 16 '24 74
76 Interior work 10 days Sep 17 '24 Sep 26 '24 75
77 Tiles 10 days Sep 27 '24 Oct 6 '24 76
78 Boring work 5 days Oct 7 '24 Oct 11 '24 77
79 Others work 50 days Oct 12 '24 Nov 30 '24 78
80 Wash Block-08 140 days Jul 19 '24 Dec 5 '24
81 Earth Excavation 5 days Jul 19 '24 Jul 23 '24 55
82 Footing 5 days Jul 24 '24 Jul 28 '24 81
83 Short column & Beam 15 days Jul 29 '24 Aug 12 '24 82
84 Column & Slab of 1st floor 10 days Aug 13 '24 Aug 22 '24 83
85 Brick work 15 days Aug 23 '24 Sep 6 '24 84
86 Sanitary & Electric work 15 days Sep 7 '24 Sep 21 '24 85
87 Interior work 10 days Sep 22 '24 Oct 1 '24 86
88 Tiles 10 days Oct 2 '24 Oct 11 '24 87
89 Boring work 5 days Oct 12 '24 Oct 16 '24 88
90 Others work 50 days Oct 17 '24 Dec 5 '24 89
91 Wash Block-09 140 days Oct 22 '24 Mar 10 '25
92 Earth Excavation 5 days Oct 22 '24 Oct 26 '24 66
93 Footing 5 days Oct 27 '24 Oct 31 '24 92
94 Short column & Beam 15 days Nov 1 '24 Nov 15 '24 93
95 Column & Slab of 1st floor 10 days Nov 16 '24 Nov 25 '24 94
96 Brick work 15 days Nov 26 '24 Dec 10 '24 95
97 Sanitary & Electric work 15 days Dec 11 '24 Dec 25 '24 96
98 Interior work 10 days Dec 26 '24 Jan 4 '25 97
99 Tiles 10 days Jan 5 '25 Jan 14 '25 98
100 Boring work 5 days Jan 15 '25 Jan 19 '25 99
101 Others work 50 days Jan 20 '25 Mar 10 '25 100
102 Wash Block-10 140 days Oct 7 '24 Feb 23 '25
103 Earth Excavation 5 days Oct 7 '24 Oct 11 '24 77
104 Footing 5 days Oct 12 '24 Oct 16 '24 103
105 Short column & Beam 15 days Oct 17 '24 Oct 31 '24 104
106 Column & Slab of 1st floor 10 days Nov 1 '24 Nov 10 '24 105
107 Brick work 15 days Nov 11 '24 Nov 25 '24 106
108 Sanitary & Electric work 15 days Nov 26 '24 Dec 10 '24 107
109 Interior work 10 days Dec 11 '24 Dec 20 '24 108
110 Tiles 10 days Dec 21 '24 Dec 30 '24 109
111 Boring work 5 days Dec 31 '24 Jan 4 '25 110
112 Others work 50 days Jan 5 '25 Feb 23 '25 111