ID Task Task Name Duration Start Finish

Mode Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30
1 Repair of EZZAOUIA damaged pipe 172 days Mon 08/07/19 Sat 21/12/19
2 Mobilization 1 day Mon 08/07/19 Mon 08/07/19
3 Kick-off meeting 1 day Mon 08/07/19 Mon 08/07/19
4 Camp Installation 3 days Tue 09/07/19 Thu 11/07/19
5 EZZ#9 Replacement 45 days? Fri 12/07/19 Sat 24/08/19
6 Survey works 3 days Fri 12/07/19 Sun 14/07/19
7 PSL2 Pipe stringing 5 days Sun 14/07/19 Fri 19/07/19
8 PSL2 Pipe Welding 27 days Fri 19/07/19 Wed 14/08/19
9 Excavation works 8 days Sat 27/07/19 Sat 03/08/19
10 Beding & lowering-in 5 days Wed 14/08/19 Mon 19/08/19
11 Backfilling 5 days Wed 14/08/19 Mon 19/08/19
12 Flushing & Filling 2 days Mon 19/08/19 Wed 21/08/19
13 Hydraulic test & inerting 3 days? Wed 21/08/19 Sat 24/08/19
14 3'' HDPE line 60 days Thu 01/08/19 Fri 27/09/19
15 Execution beginning 0 days Thu 01/08/19 Thu 01/08/19 01/08
16 Survey works 2 days Thu 01/08/19 Fri 02/08/19
17 HDPE: EZZ#9 to CPF 8 days Sat 03/08/19 Sat 10/08/19
18 HDPE: EZZ#9 to EZZ#3 48 days Sat 10/08/19 Wed 25/09/19
19 HDPE hydraulic test 2 days Thu 26/09/19 Fri 27/09/19
20 EZZ#10 Injection Line 9 days Fri 18/10/19 Sun 27/10/19
21 Execution beginning 0 days Fri 18/10/19 Fri 18/10/19 18/10
22 Survey works 1 day Fri 18/10/19 Sat 19/10/19
23 PSL2 pipe stringing 1 day Sat 19/10/19 Sun 20/10/19
24 PSL2 pipe welding 3 days Sun 20/10/19 Wed 23/10/19
25 Excavation works 3 days Mon 21/10/19 Wed 23/10/19
26 Beding & lowering-in 1 day Wed 23/10/19 Thu 24/10/19
27 Backfilling 1 day Thu 24/10/19 Fri 25/10/19
28 Flushing & Filling 1 day Fri 25/10/19 Sat 26/10/19
29 Hydraulic test & inerting 1 day Sat 26/10/19 Sun 27/10/19
30 EZZ#10 FL risers 9 days Fri 18/10/19 Sun 27/10/19
31 Flow lines RISERS spools 40 days Tue 10/09/19 Fri 18/10/19

Page 1
ID Task Task Name Duration Start Finish
Mode Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30
32 Execution beginning 0 days Tue 10/09/19 Tue 10/09/19 10/09
33 EZZ#1 FL risers 10 days Fri 13/09/19 Sun 22/09/19
34 50-110B1-4-WS-IH 10 days Fri 13/09/19 Sun 22/09/19
35 EZZ#2 FL risers 8 days Mon 23/09/19 Mon 30/09/19
36 50-105B1-4-WS-IH 8 days Mon 23/09/19 Mon 30/09/19
37 EZZ#17 FL risers 8 days Fri 11/10/19 Fri 18/10/19
38 EZZ#18 FL risers + EXTRAS (FLUL 25 days Sat 14/09/19 Mon 07/10/19
39 + FL risers)
EZZ#11 FL risers 26 days Sun 15/09/19 Thu 10/10/19
40 Process lines PREFABRICATION 45 days Thu 15/08/19 Fri 27/09/19
41 Execution beginning 0 days Thu 15/08/19 Thu 15/08/19 15/08
42 50-117A1-6-PW + 117 EXTRAS + 10 days Thu 15/08/19 Sat 24/08/19
43 50-150A1-4-PW
50-125A1-3-CR-IH-ET 7 days Sat 24/08/19 Sat 31/08/19
44 50-143A1-4-CR-IH-ET 13 days Sat 31/08/19 Thu 12/09/19
45 50-137A1-4-CR 4 days Fri 13/09/19 Mon 16/09/19
46 50-185A1-4-CR 1 day Sun 22/09/19 Mon 23/09/19
47 50-214A1-6-PW 3 days Thu 15/08/19 Sat 17/08/19
48 50-126A1-8-PW 11 days Sat 17/08/19 Wed 28/08/19
49 50-183A1-6-PW 25 days Tue 03/09/19 Fri 27/09/19
50 50-128A1-PW-IH-ET 6 days Wed 28/08/19 Tue 03/09/19
51 Process lines MOUNTING 59 days Fri 18/10/19 Fri 13/12/19
52 Execution beginning 0 days Fri 18/10/19 Fri 18/10/19 18/10
53 50-117A1-6-PW + 117 EXTRAS + 15 days Mon 28/10/19 Mon 11/11/19
54 50-150A1-4-PW
50-125A1-3-CR-IH-ET 11 days Mon 28/10/19 Fri 08/11/19
55 50-143A1-4-CR-IH-ET 11 days Fri 18/10/19 Mon 28/10/19
56 50-137A1-4-CR 11 days Fri 18/10/19 Mon 28/10/19
57 50-185A1-4-CR 3 days Wed 13/11/19 Fri 15/11/19
58 50-214A1-6-PW 1 day Tue 12/11/19 Tue 12/11/19
59 50-126A1-8-PW 9 days Mon 02/12/19 Tue 10/12/19
60 50-183A1-6-PW 20 days Wed 13/11/19 Mon 02/12/19
61 50-128A1-PW-IH-ET 3 days Wed 11/12/19 Fri 13/12/19
62 Process line area Restoration 5 days Sat 14/12/19 Wed 18/12/19

Page 2
ID Task Task Name Duration Start Finish
Mode Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Nov '19 Dec '19
24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30
63 Demobilization 1 day Wed 18/12/19 Thu 19/12/19
64 As-buit File 1 day Thu 19/12/19 Fri 20/12/19

Page 3