ID Task Name Duration Start Finish

14 Apr '19 21 Apr '19 28 Apr '19 05 May '19 12 May '19 19 May '19 26 May '19 02 Jun '19 09 Jun '19 16 Jun '19 23 Jun '19 30 Jun '19 07 Jul '19 14 Jul '19 21 Jul '19 28 Jul '19 04 Aug '19 11 Aug '19 18 Aug '19 25 Aug '19 01 Sep '19 08 Sep '19 15 Sep '19 22 Sep '19 29 Sep '19 06 Oct '19 13 Oct '19 20 Oct '19 27 Oct '19 03 Nov '19 10 Nov '19 17 Nov '19 24 Nov '19 01 Dec '19 08 Dec '19 15 Dec '19 22 Dec '19 29 Dec '19
1 TANDA TANGAN KONTRAK 1 day Tue 30/04/19 Tue 30/04/19
2 PEKERJAAN PERSIAPAN LAPANGAN 238 days Tue 30/04/19 Mon 23/12/19
3 PEKERJAAN STRUKTUR GDG ADMIN 63 days Tue 07/05/19 Mon 08/07/19
4 PEKERJAAN ARSITEKTUR GDG ADMIN 56 days Tue 25/06/19 Mon 19/08/19
5 PEKERJAAN ELEKTRIKAL ARUS LEMAH GDG ADMIN 35 days Tue 23/07/19 Mon 26/08/19
6 PEKERJAAN PLUMBING GDG ADMIN 28 days Tue 06/08/19 Mon 02/09/19
7 PEKERJAAN PONDASI & BETON GDG ADMIN 35 days Tue 04/06/19 Mon 08/07/19
8 FINISHING EKSTERIOR DAN INTERIOR GEDUNG GDG ADMIN 70 days Tue 30/07/19 Mon 07/10/19
9 PEKERJAAN PANEL DAN KABEL FEEDER GDG ADMIN 35 days Tue 17/09/19 Mon 21/10/19
10 PEKERJAAN ELEKTRIKAL ARUS LEMAH GDG ADMIN 56 days Tue 27/08/19 Mon 21/10/19
11 PEKERJAAN MEKANIKAL & PLUMBING GDG ADMIN 49 days Tue 03/09/19 Mon 21/10/19
12 PEKERJAAN TEST PDA GDG TOWER 14 days Tue 11/06/19 Mon 24/06/19
13 PEKERJAAN STRUKTUR GDG TOWER 56 days Tue 25/06/19 Mon 19/08/19
14 PEKERJAAN ARSITEKTUR GDG TOWER 84 days Tue 30/07/19 Mon 21/10/19
15 PEKERJAAN ELEKTRIKAL ARUS LEMAH GDG TOWER 42 days Tue 27/08/19 Mon 07/10/19
16 PEKERJAAN PLUMBING GDG TOWER 56 days Tue 20/08/19 Mon 14/10/19
17 PEKERJAAN PONDASI & BETON GDG TOWER 42 days Tue 16/07/19 Mon 26/08/19
18 PEKERJAAN FINISHING EKSTERIOR & INTERIOR GEDUNG GDG TOWER 98 days Tue 13/08/19 Mon 18/11/19
19 PEKERJAAN ELEKTRIKAL ARUS KUAT GDG TOWER 56 days Tue 10/09/19 Mon 04/11/19
20 PEKERJAAN ELEKTRIKAL ARUS LEMAH GDG TOWER 70 days Tue 24/09/19 Mon 02/12/19
21 PEKERJAAN MEKANIKAL & PLAMBING GDG TOWER 56 days Tue 17/09/19 Mon 11/11/19
22 PEKERJAAN STRUKTUR BANGUNAN UTILITAS 63 days Tue 21/05/19 Mon 22/07/19
23 PEKERJAAN ARSITEKTUR BANGUNAN UTILITAS 77 days Tue 16/07/19 Mon 30/09/19
24 PEKERJAAN ELEKTRIKAL ARUS LEMAH BANGUNAN UTILITAS 35 days Tue 20/08/19 Mon 23/09/19
25 PEKERJAAN PLUMBING BANGUNAN UTILITAS 28 days Tue 27/08/19 Mon 23/09/19
26 PEKERJAAN GENSET BANGUNAN UTILITAS 42 days Tue 27/08/19 Mon 07/10/19
27 Pekrjaan Panel & Kabel Feeder BANGUNAN UTILITAS 42 days Tue 03/09/19 Mon 14/10/19
28 PEKERJAAN PENANGKAL PETIR BANGUNAN UTILITAS 14 days Tue 29/10/19 Mon 11/11/19
29 Peralatan Utama Hydrant BANGUNAN UTILITAS 70 days Tue 10/09/19 Mon 18/11/19
30 Pompa Booster BANGUNAN UTILITAS 28 days Tue 01/10/19 Mon 28/10/19
31 PEKERJAAN TATA UDARA BANGUNAN UTILITAS 28 days Tue 17/09/19 Mon 14/10/19
32 PEKERJAAN SALURAN AIR HUJAN & BIOFIL BANGUNAN UTILITAS 28 days Tue 17/09/19 Mon 14/10/19
33 PEKERJAAN STRUKTUR 49 days Tue 09/07/19 Mon 26/08/19
34 PEKRJAAN ARSITEKTUR 28 days Tue 20/08/19 Mon 16/09/19
35 PEKERJAAN ELETRIKAL ARUS LEMAH 28 days Tue 20/08/19 Mon 16/09/19
36 PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING 28 days Tue 20/08/19 Mon 16/09/19
37 PEKERJAAN JALAN & LANSKAP 84 days Tue 20/08/19 Mon 11/11/19
38 PEKERJAAN STRUKTUR 70 days Tue 24/09/19 Mon 02/12/19
39 PEKERJAAN MEKANIKAL ELEKTRIKAL 35 days Tue 05/11/19 Mon 09/12/19
40 PEKERJAAN FURNITURE 28 days Tue 26/11/19 Mon 23/12/19
41 BIAYA PENYAMBUNGAN PLN 148000 VA 56 days Tue 17/09/19 Mon 11/11/19
42 BIAYA PENYAMBUNGAN PDAM 35 days Tue 08/10/19 Mon 11/11/19
43 BIAYA KONSUIL / SLO, PERIZINAN ADMINISTRASI SUPERVISI 28 days Tue 29/10/19 Mon 25/11/19
44 SELESAI 1 day Tue 24/12/19 Tue 24/12/19

Project: GANT CHART Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Pekerjaan Pembangunan ATC Tow Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress Slack