RE: QUOTATION FOR RETROFIT TO EXISTING CHAINLINK FENCE AT


CARNIVORE RESTRAUNT-NAIROBI

Date: 15/12/2021

Item Description of Works Unit Qty Unit Total Cost


Cost
Chain-link Retrofit Works

Preliminary works
A Excavate soil pushing the chain link along the entire length and LM 450 130 58,500.00
cart away and spread within the site

B Allow for excavating through concrete surround to remove broken Item 1


concrete poles and replace with new (M.S). 53 no. 25,500 25,500.00
C Ditto to concrete haunching anchoring the chain link to the ground Item 1
to enable straightening and tensioning of the chainlink. 18,500 18,500.00

New Works
D Supply and erect standard cranked pre-cast concrete posts to No 53
replace the broken ones 1,800 95,400.00

E Ditto 100mm x100mm pre-cast cranked concrete struts 3.0m long. No 6


1,600 9,600.00
F Supply and fix standard chain link 14gauge. Overall height of chain Rolls 3
link 8FTabove the ground and fixed onto standard cranked pre- 10,000 30,000.00
cast concrete posts (MS) with 6 lines of 12% gauge galvanized
wire.
G Galvanized wire Rolls 1 4,500 4,500.00
H Binding wire Rolls 1 3,500 3,500.00
I 200x200 class 20 mass concrete to anchor the chain link to the CM 9 9,500 85,500.00
ground.
J Ditto to concrete posts surround inside the poles pits CM 5 9,500 47,500.00
K Allow for re-fixing of net shade Item 1
8,250 8,250.00

www.civitechltd.com
Sub-Total 1
386,750.00
ADD 16% V.A.T
61,880.00
GRAND TOTAL SUMMARY CARRIED TO FORM OF TENDER
448,630.00