ACTION
NO. MINUTES
WHO WHEN
01 HSSE Concern
1. Summary report
Manhours update
a. WK-4 : 1624 hours
b. Cumulative : 2976 hours
NMPI update
a. WK-4 : 5 items
b. Cumulative : 9 items PCC Info
TNT update
a. WK-3 : 2 people
b. Cumulative : 4 people
2. Update audit finding
a. Blue zone PCC
ACTION
NO. MINUTES
WHO WHEN
02 Progress
1. Update progress plan vs actual
a. Plan : 5,33 %
L2/L3
b. Actual : 10,33 %
c. Variance : 5,02 %
2. Check item does not achieve target
Target to complete the retaining wall for foundation building PCC Start 22-10-2021
existing on beside site
Excavation UGT PCC Plan Start 06-11-
2021
Tank Sinking
PCC Plan 12-11-2021
Soak well and drainage
3. Resources plan & issue
a. Manpower loading: 29 people PCC On progress
b. Issue: Retaining wall for foundation building beside site a
4. Material list by PCC/L3 dan shell
a. Material supply by PCC
PCC
i. Electrical panel
PCC
ii. Mechanical (except Air conditioning) PCC
iii. Civil – steel structure, tempered glass etc.
iv. Material payment both modular
b. Material supply by SHELL API
i. Fuels system, UST, Dispenser, etc. Heksagon
ii. RVIe, Fascia, Monolith Trifecta
iii. Computer, FAX
SOLINGEN
iv. Box deposit SOLINGEN
v. APAR/APAB Others
vi. Outdoor and Indoor lamp IP-54 Others
vii. LUCI
5. Identify critical path
PCC
a. NDT Steel Structure - Workshop
L2/L3
b. Retaining wall, start on Oct 28th, finish on Nov 11st, PCC
c. UST installation Nov 15th
6. Communication Gap intern of PCC+L3+L2
N/A
03 Engineering concern
1. Deviation drawing
N/A
2. Spec change
N/A
3. Material approval
a) Submission of payment booth modular drawing
b) Submission of steel structure drawing
c) Submission of electrical panel drawing
4. Outstanding approval – waiting submission form the PCC
PT. Meinhardt Indonesia Meeting Notes Page 3
ACTION
NO. MINUTES
WHO WHEN
04 Control Quality Checklist
1. Item optional (verify)
a. Site installation
b. Demolition/Removal
2. Item Mandatory (verify)
a. Site Preparation/Cut & Backfill and Retaining wall
3. Item Hold point (verify)
a. Site Preparation/Cut & Backfill and Retaining wall
4. Schedule hold point
a. Every weekly meeting, the PCC and L3’s supposedly
submits the CQC document which is aligned with the
current activities.
b. Prior of the pre-Handover all the document of the CQC
05 Other issue raises up during meeting
1. Additional of transformer 53 kVA due to network issue PCC
2. Panel FAT
3. Gen-set by SEWATAMA
PCC
4. Excavation plan PCC
5. UST installation L3
6. Median delivery preparation L3
7. PT API start to work L2/L3
8. PT Hexagon Start to work PCC
L2/L3
9. HO Select Sop
10. Socialization shell & MHT policies
a. Socialization of the WWP
b. Implementation of the WWP
11. Invoice – every 2 weeks will be submitted by the PCC
12. Document closed out (required)
a. As build drawing
b. Asset register – 15 days prior of the final handover
c. CQC document – aligned with the current activities
These minutes were prepared by PT Meinhardt Indonesia. These notes reflect the writer understanding of discussions at the
meeting. In case any of those present have different recollections, please advise the writer within 2 days