Professional Documents
Culture Documents
LOCATION DATE
Ha Long City, Quang Ninh Province, Vietnam 13 March, 2021
OWNER / PROJECT MANAGEMENT C&S / MEPF DESIGN CONSULTANT CONTRACTOR RFA REFERENCE
DESCRIPTION
Dear Sirs
Tam Dac Contractor would like to submit the Master Schedule for the remaining piles on Level 6 and PCP14, PCP15 area
*****NF*****
RAISED BY SIGNATURE
POSITION DATE
SIGNATORY
CONTRACTOR CONSULTANT OWNER / PROJECT MANAGEMENT
2 A-FOR 53 PILES ALONG THE WESTERN RETAINING WALL/ 53 CỌC 75 days Tue 12/01/21 Fri 09/04/21
DỌC TƯỜNG CHẮN PHÍA TÂY 12/01 09/04
3 I. BORED PILE/ CỌC KHOAN NHỒI 55 days Tue 12/01/21 Sat 20/03/21
12/01 20/03
6 II. TESTING WORK/ CÔNG TÁC THÍ NGHIỆM 12 days Sun 28/03/21 Thu 08/04/21
28/03 08/04
10 B-FOR 11 REMAINING PILES OF PILECAP PCP22/ 11 CỌC CÒN LẠI 24 days Sun 21/03/21 Tue 13/04/21
CỦA ĐÀI PCP22 21/03 13/04
11 I. BORED PILE/ CỌC KHOAN NHỒI 11 days Sun 21/03/21 Wed 31/03/21
21/03 31/03
13 II. TESTING WORK/ CÔNG TÁC THÍ NGHIỆM 5 days Thu 08/04/21 Mon 12/04/21
08/04 12/04
17 C-FOR B.P OF PILECAP PCP14 & PCP15/ PHẦN CỌC CỦA ĐÀI 64 days Sat 06/03/21 Mon 10/05/21
PCP14 & PCP15 06/03 10/05
18 I. BORED PILE/ CỌC KHOAN NHỒI 49 days Sat 06/03/21 Fri 23/04/21
06/03 23/04
21 II. TESTING WORK/ CÔNG TÁC THÍ NGHIỆM 7 days Mon 03/05/21 Sun 09/05/21
03/05 09/05
Note:
+ Pile construction time and pile quality test time: 104 days.
+ This schedule depend to Earth Anchor Work and Hand-over from Client
5 STAR - BORED PILE REMAINING
January February March April May June
06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17
30
25
20
15
10
Peak Units: 9 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 14 14 14 14 14 16 16 16 14 14 14 18 18 18 6 10 10 14 6 10 6 6 6 6 6 4 4 4
Worker/Nhân công Overallocated: Allocated:
Page 1
5 STAR - BORED PILE REMAINING
January February March April May June
06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17
2
1.8
1.6
1.4
1.2
0.8
0.6
0.4
0.2
Peak Units: 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1
The drill/Máy Khoan Overallocated: Allocated:
Page 1