CLIENT PROJECT REF NO REVISION

5 Star Hotel Project DG/STOA/20/RFA-070 005

LOCATION DATE
Ha Long City, Quang Ninh Province, Vietnam 13 March, 2021
OWNER / PROJECT MANAGEMENT C&S / MEPF DESIGN CONSULTANT CONTRACTOR RFA REFERENCE

DONG GIA JSC STOA ARCHITECTS TAM DAC E&C DG/STOA/TD/20/RFA-070

REQUEST FOR APPROVAL


PHASE BUILDING FLOOR ELEMENT DRAWING NO SECTION REFERENCE
LOCATION
Mass Pile
ATTENTION DGJSC / STOA DATE REQUIRED 16 March, 2021

FOR √ CLIENT √ CONSULTANT CONTRACTOR

DESCRIPTION
Dear Sirs

Tam Dac Contractor would like to submit the Master Schedule for the remaining piles on Level 6 and PCP14, PCP15 area

Thanks and regards.

*****NF*****

RAISED BY Phùng Văn Cảnh SIGNATURE

POSITION Project Manager DATE 13 March, 2021


FOR CLIENT CONSULTANT CONTRACTOR

Approved Approved with Comments Revised and Resubmit


APPROVAL
Disapproved Noted Others

DGJSC / STOA RESPONSE

RAISED BY SIGNATURE

POSITION DATE
SIGNATORY
CONTRACTOR CONSULTANT OWNER / PROJECT MANAGEMENT

SIGNATURE / NAME / DATE SIGNATURE / NAME / DATE SIGNATURE / NAME / DATE


DG/STOA/20/RFA-070
MASTER SCHEDULE
PROJECT : 5 STAR HOTEL
ITEM WORK: CONSTRUCTION OF THE REMAINING B.P FOR LEVEL6 AND LEVEL1 AREA
ID Task Name Quantity Duration Start Finish January 2021 February 2021 March 2021 April 2021 May
06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14
1 BORED PILE WORK SCHEDULE - TIẾN ĐỘ 104 Tue 12/01/21 Mon 10/05/21 104 days
12/01 10/05
THI CÔNG CỌC KHOAN NHỒI days

2 A-FOR 53 PILES ALONG THE WESTERN RETAINING WALL/ 53 CỌC 75 days Tue 12/01/21 Fri 09/04/21
DỌC TƯỜNG CHẮN PHÍA TÂY 12/01 09/04

3 I. BORED PILE/ CỌC KHOAN NHỒI 55 days Tue 12/01/21 Sat 20/03/21
12/01 20/03

4 1‐ Tập kết thiết bị thi công và lắp đặt/ Mobilize  2 days Tue 12/01/21 Wed 13/01/21


12/01 13/01
more equipment & installation

5 2‐ Khoan tạo lổ ‐ hạ lồng thép ‐ đổ bê tông/ Drilling ‐ 53 nos 53 days Thu 14/01/21 Sat 20/03/21


14/01 20/03
rebar installation ‐ concrete casting

6 II. TESTING WORK/ CÔNG TÁC THÍ NGHIỆM 12 days Sun 28/03/21 Thu 08/04/21
28/03 08/04

7 1‐ SONIC TEST/ SIÊU ÂM 53 nos 5 days Sun 28/03/21 Thu 01/04/21


28/03 01/04

8 2-GROUTING/ RÓT VỮA 53 nos 5 days Sun 04/04/21 Thu 08/04/21


04/04 08/04

9 III. FINISH/ HOÀN THÀNH 1 day Fri 09/04/21 Fri 09/04/21


09/04 09/04

10 B-FOR 11 REMAINING PILES OF PILECAP PCP22/ 11 CỌC CÒN LẠI 24 days Sun 21/03/21 Tue 13/04/21
CỦA ĐÀI PCP22 21/03 13/04

11 I. BORED PILE/ CỌC KHOAN NHỒI 11 days Sun 21/03/21 Wed 31/03/21
21/03 31/03

12  Khoan tạo lổ ‐ hạ lồng thép ‐ đổ bê tông/ Drilling ‐  11 nos 11 days Sun 21/03/21 Wed 31/03/21


21/03 31/03
rebar installation ‐ concrete casting

13 II. TESTING WORK/ CÔNG TÁC THÍ NGHIỆM 5 days Thu 08/04/21 Mon 12/04/21
08/04 12/04

14 1‐ SONIC TEST/ SIÊU ÂM 11 nos 2 days Thu 08/04/21 Fri 09/04/21


08/04 09/04

15 2-GROUTING/ RÓT VỮA 11 nos 1 day Mon 12/04/21 Mon 12/04/21


12/04 12/04

16 III. FINISH/ HOÀN THÀNH 1 day Tue 13/04/21 Tue 13/04/21


13/04 13/04

17 C-FOR B.P OF PILECAP PCP14 & PCP15/ PHẦN CỌC CỦA ĐÀI 64 days Sat 06/03/21 Mon 10/05/21
PCP14 & PCP15 06/03 10/05

18 I. BORED PILE/ CỌC KHOAN NHỒI 49 days Sat 06/03/21 Fri 23/04/21
06/03 23/04

19 1‐ Tập kết thiết bị thi công và lắp đặt/ Mobilize  9 days Sat 06/03/21 Sun 14/03/21


06/03 14/03
more equipment & installation

20 2‐ Khoan tạo lổ ‐ hạ lồng thép ‐ đổ bê tông/ Drilling ‐ 45 nos 40 days Mon 15/03/21 Fri 23/04/21


15/03 23/04
rebar installation ‐ concrete casting

21 II. TESTING WORK/ CÔNG TÁC THÍ NGHIỆM 7 days Mon 03/05/21 Sun 09/05/21
03/05 09/05

22 1‐ SONIC TEST/ SIÊU ÂM 45 nos 3 days Mon 03/05/21 Wed 05/05/21


03/05 05/05

23 2-GROUTING/ RÓT VỮA 45 nos 2 days Sat 08/05/21 Sun 09/05/21


08/05 09/05

24 III. FINISH/ HOÀN THÀNH 1 day Mon 10/05/21 Mon 10/05/21

Note:
+ Pile construction time and pile quality test time: 104 days.
+ This schedule depend to Earth Anchor Work and Hand-over from Client
5 STAR - BORED PILE REMAINING
January February March April May June
06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17
30

25

20

15

10

Peak Units: 9 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 14 14 14 14 14 16 16 16 14 14 14 18 18 18 6 10 10 14 6 10 6 6 6 6 6 4 4 4
Worker/Nhân công Overallocated: Allocated:

Page 1
5 STAR - BORED PILE REMAINING
January February March April May June
06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17
2

1.8

1.6

1.4

1.2

0.8

0.6

0.4

0.2

Peak Units: 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1
The drill/Máy Khoan Overallocated: Allocated:

Page 1