Record No.

EP-PJT-F26
ECONPILE (M) SDN BHD
Rev. No. 00
Eff. Date 1 Nov 2017
SUBMITTAL FORM
Page 1 of 1

:THE CONSTRUCTION AND COMPLETION OF SUB-STRUCTURE WORK


FOR NAGA3 INTEGRATED ENTERTAINMENT COMPLEX AT SAMDECH
Project Title:
SOTHEAROS BLVD, PHNOM PENH, KINDGOM OF CAMBODIA FOR NAGA
3 COMPANY LIMITED

Ref No : NAGA3/EP498/SSW/DWG/0032(C)
Issue Date : 29/3/2021

To : Jacobs Engineering Services Sdn Bhd

Cc :

Type of Submission Method Statement Others: Drawing_____________


Report
Descriptions: Please kindly find attached Diaphragm Wall Details Type 1C-2 REV.C

Submitted by (Contractor) ;

On behalf
Name: R.Sukumaran
Designation: Project Director
Date: 29/3/21
This submission is deemed approved if there is no reply two weeks from submission date

Consultant Approval / Comments

Approved. To proceed with construction / fabrication / procurement or manufacture. No


A:
resubmission required.
To proceed with construction / fabrication / procurement or manufacture provided that the works
B: is performed in accordance with the comments. Re-submittal of the documents / shop drawing is
required within 7 days in accordance with the comments.
C. Rejected. A re-submittal is required in accordance with the comments.
Comments: No further comment on the reinforcement detailing.
Toe level of the reinforcement to be decided at site based on the rock level. Unreinforced
section shall not be more than 1.50m length

Endorsed by (Client / Main-Con / Consultant) ;

_____________________
A
Name: Jaya
Designation: Project Manager
Date: 30/03/2021
NAGA 3
INTERGRATED ENTERTAINMENT COMPLEX
PHNOM PENH, KINGDOM OF CAMBODIA
CONSTRUCTION AND COMPLETION OF SUB-STRUCTURE
WORK - PILING, PILECAP, DIAPHRAGM WALL, BASEMENTS
& ASSOCIATED WORKS.

TOE LEVEL OF THE REINFORCEMENT


TO BE DECIDED AT SITE BASED ON
THE ROCK LEVEL
UNREINFORCED SECTION SHALL NOT
BE MORE THAN 1.50M

DRTAN LM ARCHITECT
55, JALAN SS15/4C, SUBANG JAYA
47500 SELANGOR DARUL EHSAN, MALAYSIA
T : +603-5635 2455 F : +603 5633 8213