Professional Documents
Culture Documents
OANH
N. C. Oanh
LPG Thi Vai ,Posco Engineering,Baria Vung tau city,Viet Nam. E-mail: nguyencongoanh@yahoo.com.
ABSTRACT: This paper presents a case study of field behavior of braced sheet pile wall in soft ground. The
focuses are on stress strain behaviors with field monitoring of lateral displacement of the braced sheet pile wall and
settlement of the surrounding area during the 11m deep excavation of the pump pit. The relationship between
lateral displacement along the sheet pile wall and the settlement of the soft ground is found afterward. Furthermore,
comparison of calculated and monitored data is shown to get insight into actual behavior of the braced cut wall.
Observation procedure was used in control the safety of this underground work.
ID No./ pp. 7
N. C. OANH
-10
Elevation (m)
-20
Cs=0.15 Cc=1.00
γ=1.5g/cm 3
e =2.0
Compre ssion:Cc
-30 Swelling:Cs
Spe c. Gravity
-40 wc Unit We ight
LL
PL
-50
Figure 3 Physical mechanical properties
-5
Elevation (m)
-10
-15 u0
-20
-25
-30
CPTU-01 CPTU-02 CPTU-03 CPTU-04 (at RWI Pit) VST (in March 2010)
VST-01 VST-02 VST-03 VST-04 VST-05 (at RWI Pit)
Sandy soil was found in boreholes BH-07 and BH-08 natural water content close to liquid limit, unit weight
from the depth of 18 to 21m though its thickness is of around 15.5 g/cm3 and void ratio ranging from 1.7
ranging from 18 to 25m for the whole site. Figure 2 to 3.20. The average void ratio to be used in the finite
shows the layout plan of soil investigation in the element analysis is 2.0. It is found that even the
River Water Intake area. Figure 3 clearly separates reclaimed sand have consolidated the soft clay by its
two layers of soils in the ground. The soft clay has self-weight.
ID No./ pp. 7
N. C. OANH
60
VST-01 The increase in (qt-σ’v0) in these depth confirms
VST-02
VST-03 Sand seam
the existence of these sand seams. As found in the
VST-04 laboratory test results, un-drained shear strength to
su (kPa)
40 VST-05
VST(March 2010) effective over-burdened stress ratio is of 0.23 as the
s u/σ'v0=0.23 average value according to vane shear test and
20
piezocone penetration as shown in Figure 4 and
Figure 5. Furthermore, cone factor Nkt=15 is found to
0 40 80 120 160 be consistent with vane shear test data. This ratio is
σ ' v0 (kPa) used to calculate the effective friction angle of the
Figure 5 su vs. over-burdened stress ratio soft clay following critical state soil theory for the
finite element analysis of the deep excavation
Not much effect from the reclaimed sand to the supported by braced sheet pile wall. The friction
soft clay deposit resulted in the fact that the soft clay angle is determined as 27 degrees. Compression and
is now lightly over consolidated with pre-over swelling indices are 1.0 and 0.15 respectively as
burdened pressure of around 4 to 5KPa because the shown in Figure 3.
effective stress increase by the sand fill was not large
enough to bring the soil to normally consolidated 3. MONITORING INSTRUMENT
state. Piezocone penetration testing was done for the Furthermore, the field instrumentation used in
whole site to investigate the detail of soft clay profile evaluation of the safety factor of the exaction work
from area to area. The testing results plotted in Figure was considered as observational facilities in the
4 show that the soft clay is almost same from top to construction of river water intake sump with deep
bottom of the soft clay layer though there is sand excavation work carried out.
seam found from elevation -1.0m to -5.0m with high
un-drained shear strength at shallow depth.
ID No./ pp. 7
N. C. OANH
Two cases of finite element analyses are calculated monitored data in five excavation stages. With the
with plane strain condition. In the first case (Case-1) revision of modeling in hydraulic jack forces at the
conducted during the engineering stage of this river first three bracing levels, resulted in the consistent
water intake structure, there is no consideration of between calculated Case-2 and monitored data from
hydraulic jack forces at bracing levels 1, 2 and 3 3rd excavation to 5th excavation. Therefore, it is clear
from the top of excavation pit. While in the second that jack forces at the first three bracing levels affect
case, (Case-2) conducted after getting the monitored lateral displacement profile of the braced sheet pile
data from inclinometer I-01 and settlement plates SP- wall. Furthermore, Case-1, Case-2 and monitored
01 to SP-07, there is consideration of hydraulic jack data show that the deflection zone of sheet pile wall
force of 60kN/m, 160kN/m and 160kN/m is ranging from the top to elevation of around -15m
respectively at bracing levels 1, 2 and 3 from the top. to -17.5m. Maximum lateral displacement of sheet
pile tip is of 30mm in 5th stage of excavation as
shown in Figure 10.
50
0 Inward
the pit
-50 Calculated uplift Outward
the pit
-100
-32 -24 -16 -8 0 8
Distance from sheet pile wall (m)
Figure 9 uplift at bottom of the excavation pit
From 1st to 3rd excavation the results of analyses
Figure 7(b) Shaded displacement at 5th excavation show that calculated models are more conservative
Figure 7(a) and Figure 7(b) show total than actual condition. The increase of lateral
displacement of the whole domain after the 5th movement at the end of 5th excavation is due to other
excavation. The maximum uplift movement of possible reasons which will be explained later on.
bottom of excavation pit is around 72mm as shown in The ground loss profiles of calculated Case-2 are a
Figure 9. The uplift movement is increasing from bit smaller than monitored data as specified in Figure
sheet pile face to center of the excavation pit. 11. The differences may be attributed to over-cutting
of earth at some areas in the excavation pit, resulted
However, outward of the pit, there is ground loss
behavior as shown in Figure 9 and the ground loss at in actual excavation depth was larger than that
pit bottom elevation is ranging from 3mm to nearly considered in finite element analysis. Furthermore, it
25mm at 6m from sheet pile wall. The total uplift was found that at the end of 4th and 5th excavation,
movement here can be attributed to rebounding of there was twisting of bracing beam at level 4 and 5
soft clay and large lateral displacement of sheet pile. from the top so lateral displacement increase
The results of lateral displacement are plotted in aggressively. However, lateral movement of sheet
Figure 10 right at the end of each excavation stage. pile has been stopped from 22 May 2012 to now
The plots show that there are big differences in because drastic action was taken as soon as there was
lateral displacement of calculated Case-1 and evidence that the lateral movement of sheet pile was
increasing more and more.
ID No./ pp. 7
N. C. OANH
1st excavation 2nd excavation 3rd excavation 4th excavation 5th excavation
0 60 120 0 60 120 0 60 120 0 60 120 0 60 120
5
-5
Elevation (m)
-10
-15
-20 15 M ar 2012
22 M ay 2012
07 Feb 2012 21 Feb 2012 08 M ar 2012 09 June 2012
-25 14 Jan 2012
Original calculation Original calculation Original calculation Original calculation
Original calculation
Revised calculation Revised calculation Revised calculation Revised calculation Revised calculation
-30
Inclinometer I-01, Lateral displacement (mm)
1st excavation 2nd excavation 3rd excavation 4th excavation 5th excavation
0 60 120 0 60 120 0 60 120 0 60 120 0 60 120
Distance to Depth of excavation R/D
0.0
0.4
0.8
1.2
1.6
2.0
2.4
2.8 12 Jan 2012 09 Feb 2012 23 Feb 2012 08 M ar 2012 22 M ar 2012
Revised calculation Revised calculation Revised calculation Revised calculation 29 M ar 2012
Revised calculation
3.2
Vertical displacement (mm), R: Distance from sheet pile; D: Depth of excavation 10.5m
Figure 11 Comparison of calculated and monitored ground loss from the face of sheet pile wall
4. CONCLUSIONS parameters applied in the FEA are acceptable.
Therefore, with field testing results a full FEA can be
Monitoring instrumentation is recommended for the
done with appropriate characterization of soil
deep excavation work to control safety factor in real
parameters if triaxial stress path tests are not
time.
available.
Observational method plays important role in this
5. REFERENCES
deep excavation if used in conjunction with sufficient
monitoring system of inclinometers and settlement Ashraf S. Osman and Malcolm D. Bolton (2006).
plates. If possible, piezometers and observation wells Ground Movement Predictions for Braced
can be used together with the above as additional Excavations in Undrained Clay. J. Geotech.
instruments of monitoring. Geoenviron. Eng. 132, pp. 465-477
A. J. Powderham (2002). The observational
Jacking forces at bracing beam levels show good
method—learning from projects. Proceedings of
effects in prevention of lateral movement of sheet
the ICE - Geotechnical Engineering, Volume 155,
pile wall.
Issue 1, pp. 59–69.
Finite element analyses (FEA) show good results Arul M. Britto, Mike J. Gunn (1987). Critical State
in comparison between calculated and monitored Soil Mechanics via Finite Elements. Ellis
data. This confirms that effective stress soil Horwood Ltd , Publisher.
ID No./ pp. 7
N. C. OANH
ID No./ pp. 7