You are on page 1of 5

Date

Doc. No
29-Jun-22
PAINTING INSPECTION REPORT Page
RIP-001-PG-022021
1
0
Client : PT. PETRO KIMIA GRESIK Condition Of Material : Blasting SA 2.5 SSPC SP - 10
Project : JASA REPAIR GALLERY M7101-4D DAN TOWER T22B No. Report : 003E. PCS 06.21
Location : PELABUHAN Rev. : -

Produc Name Colour (RAL) Bacth No. Thiner Bacth No. Mix Ratio DFT (µm)
Primer Coat SIGMACOVER 380 (REDBROWN) 5938718785 91-92 - 7;1 100
Second Coat SIGMACOVER 620 (DARKGREY) 5948754514 91-92 - 7:1 100
Finish Coat SIGMADUR 550 ( YELLOW ) 5939725725 91-92 - 9:1 50
PRIMER (µm) SECON (µm) FINISH (µm)
NO Material RESULT RESULT RESULT
Date : 12/6/21 Date : 20/6/22 Date : 24/6/22

1 Sanblast dan Painting Primer Progress 135 106 111 118 102 114

2 Second Painting Progress 208 209 206 218 219 212

3 Finish Painting Progress 251 390 272 255 259 285

Prepared and Cheked By, Witnessed By, Witnessed / Reviewed By,


PT. PETRO KIMIA GRESIK

Date : Date : Date :


Lampiran
No. OK :
Nama Pekerjaan : Sandblasting

Sandblasting

Sandblasting
Lampiran
No. OK :
Nama Pekerjaan : Primer Painting

Primer Painting

Primer Painting
Lampiran
No. OK :
Nama Pekerjaan : Second Painting

Second Painting

Second Painting
Lampiran
No. OK :
Nama Pekerjaan : Finish Painting

Finish Painting

Finish Painting