Professional Documents
Culture Documents
Student Names:------------------------------------------------------------------------------
1. Planning 18
• Optimisation of Time and
Resources
• Project Time and cost
• Critical Path and Activities
• List of resources required
and their numbers
• Printed Gantt Chart
• Printed Activity Network
• MS Project 2010 file-
Master Plan
• Calender set up
• Relationships logic
• Resourcing
appropriate
• Over-allocation
removed
• Critical Path
highlighted
2. Tracking/Execution 12
• Written report describing
current status of the
project
• Printed Gantt chart
showing progress
• Printed Tracking Gantt
Chart
• Printed Variances tables
for time and cost.
• MS Project 2010 Tracking
File.
• Baseline properly set
• Input delays as
mentioned
• Tracked Progress
approx 50%
4
Scanned by CamScanner
PROJECT MANAGEMENT
TECHNIQUES
AT3 - MS PROJECT REPORT
Cost $65,792
Duration 96 days
Building two units together because of which the numbers of resources have been increased
for all the activities, hence doubling the resources. The priority was to complete the project
on time as per the client’s requirement which was taken into consideration to develop the
project strategy.
3 Create Site Plans for both units 2 days Thu 1/03/18 Fri 2/03/18 Draftperson[200%] $1,280.00
4 Arrange council permit for both units 2 days Mon 5/03/18 Tue 6/03/18 3 Draftperson[200%] $1,280.00
5 Prepare site for both units 7 days Tue 27/03/18 Fri 6/04/18 4FS+14 days Labourer[600%],Carpenter[200%] $6,160.00
6 Organize Materials for both units 4 days Tue 27/03/18 Tue 3/04/18 5SS Supervisor[200%] $1,792.00
7 Lay Foundations 7 days Mon 9/04/18 Tue 17/04/18 5,6 Concreter[200%],Carpenter[200%],Labourer $6,832.00
8 Plumbing for Sewerage for both units 3 days Wed 18/04/18 Fri 20/04/18 7 Plumber[200%] $1,680.00
12 Erect framing for both units 4 days Tue 24/04/18 Mon 30/04/18 10 Carpenter[800%] $4,864.00
13 Lay Roofing for both units 12 days Tue 1/05/18 Wed 16/05/18 12 Roof Tiler[400%],Labourer[400%] $10,368.00
14 Brickwalls for both units 6 days Thu 17/05/18 Thu 24/05/18 13 Bricklayer[800%] $4,992.00
15 Fit windows and doors 3 days Fri 25/05/18 Tue 29/05/18 14,12 Carpenter[400%] $1,824.00
18 Electrical Cables for both Units 2 days Wed 30/05/18 Thu 31/05/18 16 Electrician[200%] $1,056.00
19 Internal Plumbing for both units 3 days Wed 30/05/18 Fri 1/06/18 18SS Plumber[200%] $1,680.00
20 Plaster walls for both units 6 days Mon 4/06/18 Mon 11/06/18 18,19 Plasterer[600%] $4,032.00
21 Internal Doors and Trim for both units 4 days Tue 12/06/18 Fri 15/06/18 20 Carpenter[400%] $2,432.00
22 Install Kitchen for both units 4 days Mon 18/06/18 Thu 21/06/18 21 Cabinet Maker[400%] $2,624.00
23 Install Bathrooms for both units 6 days Mon 18/06/18 Mon 25/06/18 22SS Cabinet Maker[200%],Plumber[200%] $5,328.00
24 Final Electrical Fittings 2 days Tue 26/06/18 Wed 27/06/18 22,23 Electrician[200%] $1,056.00
25 Final Plumbing fittings for both units 2 days Tue 26/06/18 Wed 27/06/18 24SS Plumber[200%] $1,120.00
26 Paint both units 6 days Thu 28/06/18 Thu 5/07/18 25 Painter[600%] $4,032.00
27 Council Approval for both units 1 day Fri 6/07/18 Fri 6/07/18 26 $0.00
28 Construction Complete for both units 0 days Tue 17/07/18 Tue 17/07/18 27FS+7 days $0.00
The start date of the project of is 8th March 2018 and the project finishes on 3rd August
2018. The cost of the project is $73,360. The total duration is 104 days. Since the project is
half way through, the work completed is 50%, 46% of project duration.
ID Task Name Duration Start Finish Predecessors Resource Names Cost % % Work Actual Work
Complete Complet
e
1 Project 104 days Thu 8/03/18 Fri 3/08/18 $73,360.00 46% 50% 2,080 hrs
2 Plan and Site 41 days Thu 8/03/18 Tue 8/05/18 $24,304.00 100% 100% 1,296 hrs
3 Create Site Plans for both units 4 days Thu 8/03/18 Tue 13/03/18 Draftperson[200%] $2,560.00 100% 100% 64 hrs
4 Arrange council permit for both units 4 days Wed 14/03/18 Mon 19/03/18 3 Draftperson[200%] $2,560.00 100% 100% 64 hrs
5 Prepare site for both units 7 days Wed 11/04/18 Thu 19/04/18 4FS+14 days Labourer[600%],Carpenter[200%] $6,160.00 100% 100% 448 hrs
6 Organize Materials for both units 4 days Wed 11/04/18 Mon 16/04/18 5SS Supervisor[200%] $1,792.00 100% 100% 64 hrs
7 Lay Foundations 7 days Fri 20/04/18 Tue 1/05/18 5,6 Concreter[200%],Carpenter[200%],Labourer[400%] $6,832.00 100% 100% 448 hrs
8 Plumbing for Sewerage for both units 3 days Wed 2/05/18 Fri 4/05/18 7 Plumber[200%] $1,680.00 100% 100% 48 hrs
9 Pour Slab 2 days Mon 7/05/18 Tue 8/05/18 8 Concreter[600%],Carpenter[200%],Labourer[200%] $2,720.00 100% 100% 160 hrs
10 Foundation Complete 0 days Tue 8/05/18 Tue 8/05/18 9 $0.00 100% 100% 0 hrs
11 To Lock up 28 days Wed 9/05/18 Fri 15/06/18 $25,696.00 44% 46% 784 hrs
12 Erect framing for both units 7 days Wed 9/05/18 Thu 17/05/18 10 Carpenter[800%] $8,512.00 100% 100% 448 hrs
13 Lay Roofing for both units 12 days Fri 18/05/18 Mon 4/06/18 12 Roof Tiler[400%],Labourer[400%] $10,368.00 44% 44% 336 hrs
14 Brickwalls for both units 6 days Tue 5/06/18 Tue 12/06/18 13 Bricklayer[800%] $4,992.00 0% 0% 0 hrs
15 Fit windows and doors 3 days Wed 13/06/18 Fri 15/06/18 14,12 Carpenter[400%] $1,824.00 0% 0% 0 hrs
18 Electrical Cables for both Units 2 days Mon 18/06/18 Tue 19/06/18 16 Electrician[200%] $1,056.00 0% 0% 0 hrs
19 Internal Plumbing for both units 3 days Mon 18/06/18 Wed 20/06/18 18SS Plumber[200%] $1,680.00 0% 0% 0 hrs
20 Plaster walls for both units 6 days Thu 21/06/18 Thu 28/06/18 18,19 Plasterer[600%] $4,032.00 0% 0% 0 hrs
21 Internal Doors and Trim for both units 4 days Fri 29/06/18 Wed 4/07/18 20 Carpenter[400%] $2,432.00 0% 0% 0 hrs
22 Install Kitchen for both units 4 days Thu 5/07/18 Tue 10/07/18 21 Cabinet Maker[400%] $2,624.00 0% 0% 0 hrs
23 Install Bathrooms for both units 6 days Thu 5/07/18 Thu 12/07/18 22SS Cabinet Maker[200%],Plumber[200%] $5,328.00 0% 0% 0 hrs
24 Final Electrical Fittings 2 days Fri 13/07/18 Mon 16/07/18 22,23 Electrician[200%] $1,056.00 0% 0% 0 hrs
25 Final Plumbing fittings for both units 2 days Fri 13/07/18 Mon 16/07/18 24SS Plumber[200%] $1,120.00 0% 0% 0 hrs
26 Paint both units 6 days Tue 17/07/18 Tue 24/07/18 25 Painter[600%] $4,032.00 0% 0% 0 hrs
27 Council Approval for both units 1 day Wed 25/07/18 Wed 25/07/18 26 $0.00 0% 0% 0 hrs
28 Construction Complete for both units 0 days Fri 3/08/18 Fri 3/08/18 27FS+7 days $0.00 0% 0% 0 hrs