PRODUCTIVITY
RESOURCES - LABOR AND EQUIPMENT
Sr. No. ITEM
Unit Qty LABOR EQUIPMENT
EXCAVATION & EARTHWORKS Operator Helper Labour Mason Shovel Digger Roller Compactor
1 Waterproofing Membrane m2
2 Polythene Sheets m2
3 Protection Screed m2
4 Beam Sides m2 20 1 1 1
5 Stair case /steps m2 8 1 1 1
Page 1 of 18
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
a Formwork m2 40 1 1
b Concrete m 3
20 2 3
2 PCC below slab on grade
a Formwork m2 25 1 1
b Concrete m 3
40 2 3
a Formwork m2 30 2 2
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m 3
55 2 2
4 Strip footings
a Formwork m2 25 2 2
c Concrete m3 20 1 2
6 Tie Beams
a Formwork m2 30 2 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m3 20 2 2
7 Slab on grade
a Formwork & Joints m2 of slab 200 2 1
b Mesh Reinforcement m 2
300 2
c Bar Reinforcement (fabrication & fix) kg 250 1
8 Retaining Walls
a Formwork m2 30 3 1
d De-Shuttering m 2
9 Shear Walls
a Formwork m2
d De-Shuttering m 2
Page 2 of 18
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
11 Beams
a Formwork m2 20 2 2
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m3 15 1 2
d De-Shuttering m2
12 Slabs (Solid)
a Formwork m2 15 1 1
13 Slabs (Hourdy)
a Formwork m2
b Reinforcement (fabrication & fix) kg
c Concrete m3
d De-Shuttering m2
14 Parapets
a Formwork m2 20 2 2
a Formwork m2 12 1 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m 3
50 3 3
16 Stairs
a Formwork m2 15 1 1
c Concrete m3
18 Lintels
a Formwork m2 8 1 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m 3
5 1 1
Page 3 of 18
BLOCK WORK Block Mason Helper
Miscellaneous
1 Cover Block m2 9 1 1
Page 4 of 18
TILING WORK Tiler Helper
6 Granite/Marble threshold No 10 1 1
7 Granite/Marble Floor Tiles m 2
10 1 1
1 Suspension System m 2
35 1 1
2 Ceiling Tiles m2 60 1 1
13 Stucco Paint m2
Page 5 of 18
WOOD WORKS Joiner Helper
6 Wardrobes nos
7 Handrail LM
5 Aluminium Cladding m2
6 Skylights m2
Page 6 of 18
MEP LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
PLUMBING & DRAINAGE Plumber Helper
1 Water Supply Pipes (PEX) LM
2 Water Supply Pipes (PRP) LM
3 Valves & Accessories of varying diameter No
4 Water Booster Pumpset No 2 1 1
5 Water Transfer Pumpset No
6 Water Treatment with Accessories No
7 Storage Tank No
8 Water Heater No 3 1 1
9 Water Meter No
10 Waste Water Drainage Pipes & Fittings below grade LM
11 Waste Water Drainage Pipes & Fittings above grade LM
12 Sump Pumpset No
13 Drains & Grating No
14 W/C - Asian No 2 1 1
15 W/C - Western No 3 1 1
16 Shower set No
17 Urinal No
18 MOP sink No
19 Bidet No 3 1 1
Page 7 of 18
ELECTRICAL WORKS Electrician Helper
1 Duct Laying LM 50 1 1
2 P.V.C Conduits Layings LM 200 1 1
3 G.I Conduits Layings LM 50 1 1
4 Cable Pulling ( 10 to 50 Sq mm ) LM 100 1 1
5 Cable Pulling ( 50 to 90 Sq mm ) LM 50 1 1
6 Cable Pulling ( 100 to 200 Sq mm ) LM 30 3 5
7 Cable Pulling ( 200 Sq mm and Above ) LM 30 3 5
8 Cable Trays (100mm-300mm ) i/c Support System LM 50 1 1
9 Cable Trays (300mm-600mm) i/c Support System LM 40 1 1
10 Cable Trays (600mm-900mm) i/c Support System LM 30 1 1
11 Wiring LM 300 1 1
12 Termination No 50 1 1
13 DB Installation No 2 1 1
14 MDB/SMDB Installation No 1 4 2
15 LV Panels Installation No
16 Motor Control Centres No
17 Sockets Installation No 80 1 1
18 Switches Installation No 80 1 1
19 Light Fixtures Installation No 50 1 1
20 Earthing System No
21 Generator set No
22 Main Cable Laying LM
22 CCTV System No
23 Telephone Equipment Installation No 5 1 1
Page 8 of 18
MATERIAL AND LABOR STANDARD RATES
UNIT CO
Sr. No. ITEM
Unit Qty Material
CONCRETE WORKS
1 Lean Concrete
a Formwork m2 1.00 350.00
b Concrete , 2500 psi m 3
1.00
3 Column footings / Pile Caps
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete , 3500 psi m 3
1.00
Concrete , 4000 psi m4 2.00
4 Strip footings
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3 1.00
Concrete, 4000 psi
5 Pedestals
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m 3
1.00
Concrete, 4000 psi
6 Tie Beams
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3 1.00
Concrete, 4000 psi
7 Slab on grade
a Formwork & Joints m2 of slab 1.00
b Mesh Reinforcement m2 1.00
c Bar Reinforcement (fabrication & fix) kg 1.00
Concrete, 3000 psi - plain cement smooth finished
d Concrete, 3000 psi- Trowel finished m3 1.00
8 Retaining Walls
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3 1.00
d Concrete, 4000 psi m2
9 Shear Walls
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m 3
1.00
d Concrete, 4000 psi m2
10 Columns upto 0.5 sqm in area (using fabricated forms)
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3 1.00
d Concrete, 4000 psi m 2
CONCRETE WORKS
11 Beams
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3 1.00
d Concrete, 4000 psi m 2
12 Slabs (Solid)
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete m3
1.00
d De-Shuttering m2
14 Parapets
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3 1.00
Concrete, 4000 psi
15 Cantilevers
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3
1.00
Concrete, 4000 psi
16 Stairs
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3000 psi m3 1.00
17 Ramps
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3000 psi m3 1.00
18 Lintels
a Formwork m2 1.00
b Reinforcement (fabrication & fix) kg 1.00
c Concrete, 3500 psi m3 1.00
Concrete, 4000 psi
BLOCK WORK
Super-Structure (upto 3m height) - Hollow Blocks
4 150 mm Blockwork with pointing m2 1.00
5 150 mm blockwork in non-straight walls with pointing m 2
1.00
6 100 mm blockwork in straight walls with pointing m2 1.00
7 100 mm blockwork in non-straight walls with pointing m 2
1.00
Miscellaneous
1 Cover Block m2 1.00
2 Cutting & Chasing m2 1.00
2 Block shifting GF to 3rd Floor No 1.00
PLASTER
1 Plastering Accessories fixing m2 1.00
2 Internal Plaster 12mm thick on walls m2 1.00
3 Internal Plaster 12mm thick on ceilings m 2
1.00
4 External Plaster 16mm thick (upto 3m high) m2 1.00
5 External Plaster 16mm thick (over 3m high) m 2
1.00
6 External Plaster 19mm thick (upto 3m high) m2 1.00
7 External Plaster 19mm thick (over 3m high) m 2
1.00
TILING WORK
1 Ceramic Floor Tiles m2 1.00
2 Ceramic Wall Tiles m2 1.00
3 Ceramic Tile Skirting LM 1.00
4 Ceramic floor / wall tiles grouting m2 1.00
5 Ceramic claustra work m 2
1.00
6 Granite/Marble threshold No 1.00
7 Granite/Marble Floor Tiles m 2
1.00
8 Granite/Marble Wall Tiles m2 1.00
9 Terrazzo Tiles m 2
1.00
10 Terrazzo Skirting LM 1.00
11 Terrazzo Treads & Risers LM 1.00
12 Floor Screed 50mm thick m2 1.00
13 Interlocking Pavers m 2
1.00
14 Kerbstone m 1.00
FALSE CEILING
1 Suspension System m2 1.00
2 Ceiling Tiles m 2
1.00
3 Gypsum Ceiling & Cornish (i/c Suspension System) m2 1.00
4 Dry wall partition m 2
1.00
PAINT WORK
1 Prime Coat m2 1.00
2 Surface preparation for paint m2 1.00
3 Paint 1st Coat - brush application (Emulsion Paint) m 2
1.00
4 Paint 2nd Coat - brush application (Emulsion Paint) m2 1.00
5 Paint 1st Coat - roller application (Emulsion paint) m 2
1.00
6 Paint 2nd Coat - roller application (Emulsion Paint) m2 1.00
7 Paint 1st Coat - brush application (Enamel Paint) m 2
1.00
8 Paint 2nd Coat - brush application (Enamel Paint) m2 1.00
9 Paint 1st Coat - roller application (Enamel Paint) m 2
1.00
10 Paint 2nd Coat - roller application (Enamel Paint) m2 1.00
11 Epoxy Paint on Floors per coat m 2
1.00
12 Bitumen paint for waterpoofing single coat m2 1.00
13 Stucco Paint m 2
1.00
WOOD WORKS
1 Wooden frames fixing for openings upto 5 m2 nos 1.00
2 Wooden door shutters fixing (incl hardware) nos 1.00
3 Wooden Pergola m 2
1.00
4 Wooden Vanities nos 1.00
5 Kitchen Cabinets nos 1.00
6 Wardrobes nos 1.00
7 Handrail LM 1.00
METAL WORKS
1 Steel Frames fixing for openings upto 5 m2 nos 1.00
2 Steel Shutter fixing nos 1.00
3 Handrail and Balustrade LM 1.00
4 Glazed Balustrade with Stainless steel handrail LM 1.00
5 Structural Steel Columns and Beams kg 1.00
6 Wardrobes nos 1.00
7 Passanger Lifts nos 1.00
ALUMINIUM WORKS
1 Aluminium doors for openings upto 5 m2 nos 1.00
2 Aluminium windows (glazed) nos 1.00
3 Glazed Curtain Walling m 2
1.00
4 Aluminium Louvers nos 1.00
5 Aluminium Cladding m 2
1.00
6 Skylights m 2
1.00
UNIT COST
TOTAL UNIT
Contractor COST
Sub-con Price
Mark-up