Sr. No. ITEM PRODUCTIVITY
Unit Qty LABOR EQUIPMENT

EXCAVATION & EARTHWORKS Operator Helper Labour Mason Shovel Digger Roller Compactor

1 Excavation for foundation pits in normal ground m3 150 1 1 1

2 Excavation for foundations in strips/trenches in normal ground m3 130 1 1 1

3 Hand excavation in normal ground upto 1.5m lift m3 3 1

4 Foundation bed levelling & compaction m2 90 2 1

5 Backfilling in 150mm layers in buildings below slab on grade m3 180 2 1 0.75 1

6 Backfilling around building in 150mm layers m3 200 2 1 0.75 1


DISMANTLING & DISPOSAL (Manual) Labour Concrete Breaker Rapid Breaker

1 Plain concrete / Block walls m3 5 2 1

2 Hard Rock/ Reinforced concrete m3 2 2 2

3 Concrete paving m2 100 2 1

4 Asphalt & Subase m2 16 1 1


5 Pile Head Cutting - 300 mm Dia No 5 1 1
6 Pile Head Cutting - 600 mm Dia No 5 2 1
MISCELLANEOUS Waterproofer Labour Mason

1 Waterproofing Membrane m2

2 Polythene Sheets m2

3 Protection Screed m2

4 Tower Crane Erection No


Shutter Making Carpenter Helper Wood Cutting Machine

1 Columns (Square or Rectangular) m2 14 1 1 1


2 Wall shutter m2 22 1 1 1
3 Beam Bottom m2 14 1 1 1
4 Beam Sides m2 20 1 1 1
5 Stair case /steps m2 8 1 1 1

Page 1 of 1
MEP LABOR PRODUCTIVITY

8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
PLUMBING & DRAINAGE Plumber Helper
1 Water Supply Pipes (PEX) LM
2 Water Supply Pipes (PRP) LM
3 Valves & Accessories of varying diameter No
4 Water Booster Pumpset No 2 1 1
5 Water Transfer Pumpset No
6 Water Treatment with Accessories No
7 Storage Tank No
8 Water Heater No 3 1 1
9 Water Meter No
10 Waste Water Drainage Pipes & Fittings below grade LM
11 Waste Water Drainage Pipes & Fittings above grade LM
12 Sump Pumpset No
13 Drains & Grating No
14 W/C - Asian No 2 1 1
15 W/C - Western No 3 1 1
16 Shower set No
17 Urinal No
18 MOP sink No
19 Bidet No 3 1 1
HVAC WORKS AC Technician Helper
1 Chilled water Piping LM 25 1 1
2 Chilled water Pipes Insulation with Canvase Cloth LM 20 1 1
2
3 Duct Work with Insulation m 10 1 1
4 Fresh Air Handling Units (FAHU) Installation No 1 1 1
5 Fan Coil Units (FCU) Installation No 2 1 1
6 Exhaust Fan Installaion No 2 1 1
7 Dampers & Control No
8 Grills & Diffusers Installation No 8 1 1
9 Closed Control Units No
10 Chemical Dosing No
11 Chilled Water Pump No
12 BMS No

Page 1 of 2
MEP LABOR PRODUCTIVITY

8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
ELECTRICAL WORKS Electrician Helper
1 Duct Laying LM 50 1 1
2 P.V.C Conduits Layings LM 200 1 1
3 G.I Conduits Layings LM 50 1 1
4 Cable Pulling ( 10 to 50 Sq mm ) LM 100 1 1
5 Cable Pulling ( 50 to 90 Sq mm ) LM 50 1 1
6 Cable Pulling ( 100 to 200 Sq mm ) LM 30 3 5
7 Cable Pulling ( 200 Sq mm and Above ) LM 30 3 5
8 Cable Trays (100mm-300mm ) i/c Support System LM 50 1 1
9 Cable Trays (300mm-600mm) i/c Support System LM 40 1 1
10 Cable Trays (600mm-900mm) i/c Support System LM 30 1 1
11 Wiring LM 300 1 1
12 Termination No 50 1 1
13 DB Installation No 2 1 1
14 MDB/SMDB Installation No 1 4 2
15 LV Panels Installation No
16 Motor Control Centres No
17 Sockets Installation No 80 1 1
18 Switches Installation No 80 1 1
19 Light Fixtures Installation No 50 1 1
20 Earthing System No
21 Generator set No
22 Main Cable Laying LM
22 CCTV System No
23 Telephone Equipment Installation No 5 1 1
FIRE FIGHTING & FIRE ALARM SYSTEM Fire Fighters Helper
1 Piping Network LM
2 Fire Hose Cabinets No
3 Fire Extinguishers and Cabinets No
4 Sprinklers No
5 Valves & Accessories No
6 Fire Protection Pumpset No
7 Fire gas Suppression System No
8 Fire Alarm Control Panel No
9 Smoke & Heat Detectors No
10 Monitor Module No
11 Control Module No
12 Voice Evacuation System No

Page 2 of 2
LABOR PRODUCTIVITY
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
1 PCC below footings
2
a Formwork m 40 1 1
3
b Concrete m 20 2 3
2 PCC below slab on grade
2
a Formwork m 25 1 1
3
b Concrete m 40 2 3
3 Column footings / Pile Caps
2
a Formwork m 30 2 2
b Reinforcement (fabrication & fix) kg 170 1
3
c Concrete m 55 2 2
4 Strip footings
2
a Formwork m 25 2 2
b Reinforcement (fabrication & fix) kg 170 1
3
c Concrete m 55 2 2
5 Pedestals (Neck Columns)
2
a Formwork m 25 2 1
b Reinforcement (fabrication & fix) kg 160 1
3
c Concrete m 20 1 2
6 Tie Beams
2
a Formwork m 30 2 1
b Reinforcement (fabrication & fix) kg 180 1
3
c Concrete m 20 2 2
7 Slab on grade
2
a Formwork & Joints m of slab 200 2 1
2
b Mesh Reinforcement m 300 2
c Bar Reinforcement (fabrication & fix) kg 250 1
3
d Concrete - Trowel finished m 40 2 3
8 Retaining Walls
2
a Formwork m 30 3 1
b Reinforcement (fabrication & fix) kg 160 1
3
c Concrete m 18 1 2
2
d De-Shuttering m
9 Shear Walls
2
a Formwork m
b Reinforcement (fabrication & fix) kg
3
c Concrete m
2
d De-Shuttering m
10 Columns upto 0.5 sqm in area (using fabricated forms)
2
a Formwork m 14 2 1
b Reinforcement (fabrication & fix) kg 160 1
3
c Concrete m 9 1 2
2
d De-Shuttering m

Page 1 of 5
LABOR PRODUCTIVITY
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
11 Beams
2
a Formwork m 20 2 2
b Reinforcement (fabrication & fix) kg 160 1
3
c Concrete m 15 1 2
2
d De-Shuttering m
12 Slabs (Solid)
2
a Formwork m 15 1 1
b Reinforcement (fabrication & fix) kg 200 1
3
c Concrete m 75 3 3
2
d De-Shuttering m
13 Slabs (Hourdy)
2
a Formwork m
b Reinforcement (fabrication & fix) kg
3
c Concrete m
2
d De-Shuttering m
14 Parapets
2
a Formwork m 20 2 2
b Reinforcement (fabrication & fix) kg 175 1
3
c Concrete m 12 1 1
15 Cantilevers
2
a Formwork m 12 1 1
b Reinforcement (fabrication & fix) kg 180 1
3
c Concrete m 50 3 3
16 Stairs
2
a Formwork m 15 1 1
b Reinforcement (fabrication & fix) kg 170 1
3
c Concrete m 20 1 1
17 Ramps
2
a Formwork m
b Reinforcement (fabrication & fix) kg
3
c Concrete m
18 Lintels
2
a Formwork m 8 1 1
b Reinforcement (fabrication & fix) kg 180 1
3
c Concrete m 5 1 1

Page 2 of 5
LABOR PRODUCTIVITY
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
BLOCK WORK Block Mason Helper
Sub-Structure - Solid Blocks
2
1 200 mm Blockwork m 12 1 1
Super-Structure (upto 3m height) - Solid Blocks
2
1 100 mm Blockwork with pointing m 15 1 2
2
2 150 mm Blockwork with pointing m
2
3 200 mm Blockwork with pointing m 10 1 2
2
4 250 mm Blockwork with pointing m
Super-Structure (upto 3m height) - Hollow Blocks
2
1 250 mm Blockwork with pointing m
2
2 200 mm Blockwork with pointing m 16 1 2
2
3 200 mm blockwork in non-straight walls with pointing m 12 1 2
2
4 150 mm Blockwork with pointing m
2
5 150 mm blockwork in non-straight walls with pointing m
2
6 100 mm blockwork in straight walls with pointing m 18 1 2
2
7 100 mm blockwork in non-straight walls with pointing m 14 1 2
Miscellaneous
2
1 Cover Block m 9 1 1
2
2 Cutting & Chasing m
2 Block shifting GF to 3rd Floor No 240 1
PLASTER Plaster Mason Helper
2
1 Plastering Accessories fixing m 60 1 1
2
2 Internal Plaster 12mm thick on walls m 16 1 1
2
3 Internal Plaster 12mm thick on ceilings m 12 1 1
2
4 External Plaster 16mm thick (upto 3m high) m
2
5 External Plaster 16mm thick (over 3m high) m
2
6 External Plaster 19mm thick (upto 3m high) m 20 1 1
2
7 External Plaster 19mm thick (over 3m high) m 18 1 1
2
8 External plaster -Rush coat m 100 1 1
2
9 Compressed Plaster m 60 1 1
10 Sub frame fixing No 5 1 1
2
11 Tyroline over plastered or fare face concrete surface m 175 1 1

Page 3 of 5
LABOR PRODUCTIVITY
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
TILING WORK Tiler Helper
2
1 Ceramic Floor Tiles m 20 1 1
2
2 Ceramic Wall Tiles m 18 1 1
3 Ceramic Tile Skirting LM 40 1 1
2
4 Ceramic floor / wall tiles grouting m 32 1 1
2
5 Ceramic claustra work m 6 1 1
6 Granite/Marble threshold No 10 1 1
2
7 Granite/Marble Floor Tiles m 10 1 1
2
8 Granite/Marble Wall Tiles m
2
9 Terrazzo Tiles m 20 1 1
10 Terrazzo Skirting LM 40 1 1
11 Terrazzo Treads & Risers LM 30 1 1
2
12 Floor Screed 50mm thick m 27 1 1
2
13 Interlocking Pavers m 48 1 1
14 Kerbstone m 56 1 1
FALSE CEILING Ceiler Helper
2
1 Suspension System m 35 1 1
2
2 Ceiling Tiles m 60 1 1
2
3 Gypsum Ceiling & Cornish (i/c Suspension System) m 2.5 1 1
2
4 Dry wall partition m 20 1 1
PAINT WORK Painter Helper
2
1 Prime Coat m 200 1 1
2
2 Surface preparation for paint m 80 1
2
3 Paint 1st Coat - brush application (Emulsion Paint) m 100 1 1
2
4 Paint 2nd Coat - brush application (Emulsion Paint) m 100 1 1
2
5 Paint 1st Coat - roller application (Emulsion paint) m 125 1 1
2
6 Paint 2nd Coat - roller application (Emulsion Paint) m 125 1 1
2
7 Paint 1st Coat - brush application (Enamel Paint) m 60 1 1
2
8 Paint 2nd Coat - brush application (Enamel Paint) m 60 1 1
2
9 Paint 1st Coat - roller application (Enamel Paint) m 95 1 1
2
10 Paint 2nd Coat - roller application (Enamel Paint) m 70 1 1
2
11 Epoxy Paint on Floors per coat m 50 1 1
2
12 Bitumen paint for waterpoofing single coat m 50 1
2
13 Stucco Paint m

Page 4 of 5
LABOR PRODUCTIVITY
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
WOOD WORKS Joiner Helper
2
1 Wooden frames fixing for openings upto 5 m nos 8 2 1
2 Wooden door shutters fixing (incl hardware) nos 5 2 1
2
3 Wooden Pergola m
4 Wooden Vanities nos
5 Kitchen Cabinets nos
6 Wardrobes nos
7 Handrail LM
METAL WORKS Metal Workers Helper
2
1 Steel Frames fixing for openings upto 5 m nos 8 1 1
2 Steel Shutter fixing nos 5 1 2
3 Handrail and Balustrade LM 8
4 Glazed Balustrade with Stainless steel handrail LM 6
5 Structural Steel Columns and Beams kg
6 Wardrobes nos
7 Passanger Lifts nos
ALUMINIUM WORKS Aluminium Workers
2
1 Aluminium doors for openings upto 5 m nos 8 2
2 Aluminium windows (glazed) nos 6 2
2
3 Glazed Curtain Walling m
4 Aluminium Louvers nos
2
5 Aluminium Cladding m
2
6 Skylights m