Description Qty.
50 Tons Crane 7
Kenworth 1
Fork Lift 10 Tons 2
Low Bed Truck 6
FlatTruck 13
Expandable truck 1
Mini Bus 1
shaffal 1
*Note: To ensure that there is sufficient amount of slings and shackles of different size
*Note: To Prepare and check the availability of Misc. tools required prior to RIG MOVE
*Note: To ensure that that all vehicles ,cranes and fork lift are all fueled up every day before rig move
On forth day end will release 2 cranes at the end of day ,and keep two trucks .
On fifth day end release another Two cranes ,all trucks and one fork lift .
On sixth day end release the second fork liftand all crane
Total 35
*Note: Both crew will be working between the two location during day light duration 12 Hours in Total
Pre Move
* Equipment to be moved to the new location pre Rig Move:
Item Equipment
1 Tubulars & Pipes Basket
2 Flare line
3 Gas vent line
4 Tesco units
5 Driller cabine
6 Rig Floor slid Escape
7 Welder Shop
8 M.Pump Container
9 Iron roughneck
10 Matting Board
11 2 Kelly+ Rat Hole +Bell Nipple
12 Belly Board
13 water well Lines
14 Mud logger
15 Schl.Stores
16 Mathy line Unit
17 Man Rider
18 Mud Lab.
19 Escape line Concreat Block
20 Most of but not all Fire Extinguish
21 Man Lift Basket
22 Handling Tools Basket
23 Save Heaven #1 ( 6 load )
24 Save Heaven # 2 ( 6 load )
25 Save Heaven # 3 ( 6 load )
26 Welder steel sheets rack
27
28
PREPARATIONS:
8 Water tank #2 1
9 supercharger pump Skid 1
10 Mud pump #1, 1
11 Mud pump #2, 1
12 Trip tank Poor boy Skid. 1
13 Cooling tank 1
14 Load and move choke manifold . 1
15 Top drive, hook, troque Tube 1 Day 1 18%
16 Top drive unit 1 T. Loads 16
1 !3 5/5" 5 K Bop,T.Block, kill+choke valves 1
2 Stand pipe manifold+kill,Choke hose 1
3 Closing unit,HPU,Suit case, Bridge Crane 1
4 Dog house, Wash Machine Travelling Block 1
5 Mud lab,fire Pump,Degasser&Rotary table 1
6 Flare lines ,gas lines,Flow lines 1
7 Mud pump manifold,Air hoist rack 1
8 Monkey board ,Stabbing board 1
DAY TWO
9 Catwalks, Stairs 1
10 V Doors, Stairs, Rot. Duckt Hose 1
11 Drlg. Line spool, Stairs(mud sys+ rig floor ) 1
12 Floor parts ( cover plates ),welding machine 1
Top drive Loop
13 Crawn Block+next section 1
14 Third section 2
15 Bttom section 2
16 seat back 1
17 Day 2 36%
T. Loads 18
1 Drawwork 2
2 A frame 2
3 substracture 9
4 Substructure Matting board 2
DAY THREE
5 VFD 1
6 Engines 4
7 Fuel tanks 2
8 Grass Hopper 1
9 compressor room 1
10 Maintenance workshop 1
DAY THR Day 3 64%
T. Loads 23
1 Rig camp 25
DAY FOUR
Day 4 94%
T. Loads 25
1 Mud chemicals 5
DAY FIVE
2 save havin 9
3 secrity tour 1
4 casing 5 Day 5 100%
T. Loads 20
1 casing 10
DAY SIX
scurity cravan 1
2 scurity gate with concarite 3
3 T. Loads 14
TOTAL 85
DAY (1) LOADS SEQUENCE RIG
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 shaker tank with soild equipment 1
4x50T+F.lift 2x50T+f.lift 89% 11%
2 inter mediate tank 1
3 suction tank 1 2Drlr,2Drk N.p,2Drk m
4 reserve tank #1 1 2A.D,5FLR 3 Flr+1R.A
5 reserve tank #2 1 2 R.A
6 mixing tank 1
7 water tank #1 1
8 Water tank #2 1
9 supercharger pump Skid 1
10 Mud pump #1, 1
11 Mud pump #2, 1
12 Trip tank Poor boy Skid. 1
13 Cooling tank 1
14 Load and move choke manifold . 1
15 Top drive, hook, troque Tube 1
16 Top drive unit 1
17
18
TOTAL 16
1 Off load shaker tank and Mud system and spot in place
NEW LOCATION
1 Off load shaker tank and Mud system and spot in place
2 Off load super charger and cooling tank
3 Off load Mud pumps .
4 Off load choke manifold, .
NEW LOCATIO
DAY (2) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 !3 5/5" 5 K Bop,T.Block, kill+choke valves 1
4x50T+F.lift 2x50T+f.lift 89% 11%
2 Stand pipe manifold+kill,Choke hose 1
3 closing unit,HPU,Suit case, Bridge Crane 1 2Drlr,2Drk N.p,2Drk m
4 Dog house, Wash Machine Travelling Block 1 2A.D,5FLR 3 Flr+1R.A
5 Mud lab,fire Pump,Degasser&Rotary table 1 2 R.A
6 Flare lines ,gas lines,Flow lines 1
7 Mud pump manifold,Air hoist rack 1
8 Monkey board ,Stabbing board 1
9 Catwalks, Stairs 1
10 V Doors, Stairs, Rot. Duckt Hose 1
11 Drlg. Line spool, Stairs(mud sys+ rig floor ) 1
12 Floor parts ( cover plates ),welding machine 1
Top drive Loop
13 Crawn Block+next section 1
14 Third section 1
15 Bttom section 1
16 A frame 1
TOTAL 16
3 Lowering substructure,Reposition raising line and lowerig the mast & dismantale D/W hoses ,
Electrical to dismantle all electrice cables, weight indecator line.
4 Un spooling drilling line
5 Dismantale D/W hoses , electrical to dismantle all electrice cables, weight indecator line.
6 Disconnecte mast sections
7 R/D draw works & rotary table
8 Dismantle substracture
9 Dismantle engines
TOTAL 23
4 cont. rigging up
DAY (4) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 Rig camp 25
2x50T+F.lift 4x50T+Flift 40% 60%
N.p,4Drk m
4R.A,4FLR 4 Flr+2R.A
2Drlr+2AD
TOTAL 25
4 Connect hydraulic service lines with kooemy unit. Supply Koomey unit with electricity
5 Continue electric rig up work on rig camp and mud system
6 Assemble Catwalk
7 Connect drawworks cooling system
8 Connect all HP mud lines
9 Release all rental trucks
DAY (6) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 NIL 0
0 3x50T+2F.lift 0% 100%
2
3
4
5
6
7
8
9
TOTAL 0
1 NIL
2
3
4
1 Raisig mast
2 Raising substructure
3 Install rotary table &prepare Rig floor
4 Remove raising line
NEW LOCATION