You are on page 1of 15

Logistics

Description Qty.
50 Tons Crane 7
Kenworth 1
Fork Lift 10 Tons 2
Low Bed Truck 6
FlatTruck 13
Expandable truck 1
Mini Bus 1
shaffal 1

Rig Down, Move, Rig Up Period Breakdown


CUMULATIVE Cranes
DAYS Trailers Trips
Rig Down Move Rig Up Old Location New Location
1 30% 11% 5% 16 4x50T+10 t fork lift 3x50T+10T.fork lift
2 60% 25% 15% 16 4x50T+10 t fork lift 3x50T+10T.fork lift
3 80% 45% 50% 23 4x50T+10 t fork lift 3x50T+10T.fork lift
4 100% 75% 50% 25 3x50T+10T.fork lift 4x50T+10 t fork lift
5 0% 90% 75% 20 2x50T+10T.fork lift 5x50T+10 t fork lift
6 0% 100% 85% 14 2x50T+10T.fork lift 5x50T+1x10 t fork lift
7 100% 5x50T+1x10 t fork lift

*Note: To ensure that there is sufficient amount of slings and shackles of different size

*Note: To Prepare and check the availability of Misc. tools required prior to RIG MOVE

*Note: To ensure that that all vehicles ,cranes and fork lift are all fueled up every day before rig move

On forth day end will release 2 cranes at the end of day ,and keep two trucks .
On fifth day end release another Two cranes ,all trucks and one fork lift .
On sixth day end release the second fork liftand all crane

At least 12 each x 12 ton shackles


5 each x 6 ft x 5/8"size soft eye wire sling
12each x 30 ft x1 1/8" size soft eye
Man Power
Position No.
Rig Super Intendent 1
Tool Pusher 2
Safety Officer 1
Rig Doctor 1
Materials Man 1
CH. Mechanic 1
Mechanic 2
CH.Electrician 1
Electrician 2
Welder 1
Driller 2
As. Driller 2
Derrick man 4
Floor man 8
Roustabout 6

Total 35

*Note: Both crew will be working between the two location during day light duration 12 Hours in Total
Pre Move
* Equipment to be moved to the new location pre Rig Move:

Item Equipment
1 Tubulars & Pipes Basket
2 Flare line
3 Gas vent line
4 Tesco units
5 Driller cabine
6 Rig Floor slid Escape
7 Welder Shop
8 M.Pump Container
9 Iron roughneck
10 Matting Board
11 2 Kelly+ Rat Hole +Bell Nipple
12 Belly Board
13 water well Lines
14 Mud logger
15 Schl.Stores
16 Mathy line Unit
17 Man Rider
18 Mud Lab.
19 Escape line Concreat Block
20 Most of but not all Fire Extinguish
21 Man Lift Basket
22 Handling Tools Basket
23 Save Heaven #1 ( 6 load )
24 Save Heaven # 2 ( 6 load )
25 Save Heaven # 3 ( 6 load )
26 Welder steel sheets rack
27
28

PREPARATIONS:

1 To arrange trucks and cranes (4 cranes + 4 Trucks ) + 4 R/A ,2 Drk men


2 Inspect rig move routes (Roads and Paths)
3 Inspect new location foot prints, spots and dimensions for old and new locations prior to rig move .
4 Identify required slings & other lifting materials
5 Pre move meetings ,Identify critical loads
6 Identify and eliminate hazards
7 Extra support if required during rig move such as: portable electrical generator,
air compressor, portable lightings if necessary to work during night, drinking water, etc.
8 To make sure all required tools for rig down and rig up operations are available and arrange in place to be used
9 Check ground leveling under substructure and mud system on the the new location
LOADS MOVEMENT SEQUENCE LIST

# Equipment to be moved Loads


1 shaker tank with soild equipment 1
2 Inter mediate tank 1
3 Suction tank 1
4 Reserve tank #1 1
5 Reserve tank #2 1
6 Mixing tank 1
7 Water tank #1 1
DAY ONE

8 Water tank #2 1
9 supercharger pump Skid 1
10 Mud pump #1, 1
11 Mud pump #2, 1
12 Trip tank Poor boy Skid. 1
13 Cooling tank 1
14 Load and move choke manifold . 1
15 Top drive, hook, troque Tube 1 Day 1 18%
16 Top drive unit 1 T. Loads 16
1 !3 5/5" 5 K Bop,T.Block, kill+choke valves 1
2 Stand pipe manifold+kill,Choke hose 1
3 Closing unit,HPU,Suit case, Bridge Crane 1
4 Dog house, Wash Machine Travelling Block 1
5 Mud lab,fire Pump,Degasser&Rotary table 1
6 Flare lines ,gas lines,Flow lines 1
7 Mud pump manifold,Air hoist rack 1
8 Monkey board ,Stabbing board 1
DAY TWO

9 Catwalks, Stairs 1
10 V Doors, Stairs, Rot. Duckt Hose 1
11 Drlg. Line spool, Stairs(mud sys+ rig floor ) 1
12 Floor parts ( cover plates ),welding machine 1
Top drive Loop
13 Crawn Block+next section 1
14 Third section 2
15 Bttom section 2
16 seat back 1
17 Day 2 36%
T. Loads 18
1 Drawwork 2
2 A frame 2
3 substracture 9
4 Substructure Matting board 2
DAY THREE

5 VFD 1
6 Engines 4
7 Fuel tanks 2
8 Grass Hopper 1
9 compressor room 1
10 Maintenance workshop 1
DAY THR Day 3 64%
T. Loads 23
1 Rig camp 25
DAY FOUR

Day 4 94%
T. Loads 25
1 Mud chemicals 5
DAY FIVE

2 save havin 9
3 secrity tour 1
4 casing 5 Day 5 100%
T. Loads 20
1 casing 10
DAY SIX

scurity cravan 1
2 scurity gate with concarite 3
3 T. Loads 14
TOTAL 85
DAY (1) LOADS SEQUENCE RIG

LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 shaker tank with soild equipment 1
4x50T+F.lift 2x50T+f.lift 89% 11%
2 inter mediate tank 1
3 suction tank 1 2Drlr,2Drk N.p,2Drk m
4 reserve tank #1 1 2A.D,5FLR 3 Flr+1R.A
5 reserve tank #2 1 2 R.A
6 mixing tank 1
7 water tank #1 1
8 Water tank #2 1
9 supercharger pump Skid 1
10 Mud pump #1, 1
11 Mud pump #2, 1
12 Trip tank Poor boy Skid. 1
13 Cooling tank 1
14 Load and move choke manifold . 1
15 Top drive, hook, troque Tube 1
16 Top drive unit 1
17
18
TOTAL 16

WORK SCOPE ON DAY ONE:

1 Pre Job & safety meetings


2 L/D mouse hole
3 Disconnect power to mud pumps & roll up cables. Disconnect air line to
Koomy unit .
4 Dismantle catwalk.
5 Load and move beam racks, catwalk, choke manifold, v-door ramps, choke &
kill lines, Stand pipe manifold,Cmt.lines,Mud lines .
OLD LOCATION

6 Install BOP bridge crane extintion rack & remove same .


7 Clear Rig Floor ,Add more wraps on drum (55) total on drum ,R/D Top Drive,
Hook,Torque tub, Install raising line plate and lines .
8 Disconnect all electric cables from mud system & roll up cables
9 Remove degasser,mud Lab room.
10 Electrician to dismantle and roll up instrumentations cables & hoses,keep
keep weight indecator connected.
11 Load and move choke manifold
12 Disconnect electric cables on Koomey unit. Load and move koomey unit &
Hydraulic service lines
13 Prepare loads for Day 2

1 Off load shaker tank and Mud system and spot in place
NEW LOCATION

1 Off load shaker tank and Mud system and spot in place
2 Off load super charger and cooling tank
3 Off load Mud pumps .
4 Off load choke manifold, .
NEW LOCATIO
DAY (2) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 !3 5/5" 5 K Bop,T.Block, kill+choke valves 1
4x50T+F.lift 2x50T+f.lift 89% 11%
2 Stand pipe manifold+kill,Choke hose 1
3 closing unit,HPU,Suit case, Bridge Crane 1 2Drlr,2Drk N.p,2Drk m
4 Dog house, Wash Machine Travelling Block 1 2A.D,5FLR 3 Flr+1R.A
5 Mud lab,fire Pump,Degasser&Rotary table 1 2 R.A
6 Flare lines ,gas lines,Flow lines 1
7 Mud pump manifold,Air hoist rack 1
8 Monkey board ,Stabbing board 1
9 Catwalks, Stairs 1
10 V Doors, Stairs, Rot. Duckt Hose 1
11 Drlg. Line spool, Stairs(mud sys+ rig floor ) 1
12 Floor parts ( cover plates ),welding machine 1
Top drive Loop
13 Crawn Block+next section 1
14 Third section 1
15 Bttom section 1
16 A frame 1

TOTAL 16

WORK SCOPE ON DAY TWO:

1 Pre job & Safety Meeting


2 R/D Rotary Table
OLD LOCATION

3 Lowering substructure,Reposition raising line and lowerig the mast & dismantale D/W hoses ,
Electrical to dismantle all electrice cables, weight indecator line.
4 Un spooling drilling line
5 Dismantale D/W hoses , electrical to dismantle all electrice cables, weight indecator line.
6 Disconnecte mast sections
7 R/D draw works & rotary table
8 Dismantle substracture
9 Dismantle engines

1 Spot Degasser on mud tanks


NEW LOCATION

2 Spot mud lab.


3 Off loads trucks and spot in places
4
8
9
NEW LOCATIO
DAY (3) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 Drawwork 2
4x50T+F.lift 2x50T+f.lift 51% 49%
2 substracture 9
3 Substructure Matting board 2
4 VFD 1 Drlr,2Drk m N.p,2Drk m
5 Engines 4 2A.D,4FLR 4 Flr+2R.A
6 Fuel tanks 2 2 R.A Drlr
7 Grass Hopper 1
8 compressor room 1
9 Maintenance workshop 1

TOTAL 23

WORK SCOPE ON DAY THREE:

1 Prejob & Safety meeting


2 RigDown & load sub structure and Drawwork
3 Load substructure matting board
4 load VFD
5 load Engines
OLD LOCATION

6 Load compressor room


7 Load Grass Hopper
8 Load fuel tanks

1 Spot matting board


2 spot sub base
3 off load trucks in place
NEW LOCATION

4 cont. rigging up
DAY (4) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 Rig camp 25
2x50T+F.lift 4x50T+Flift 40% 60%

N.p,4Drk m
4R.A,4FLR 4 Flr+2R.A
2Drlr+2AD

TOTAL 25

WORK SCOPE ON DAY FOUR:

1 Prejob Safety Meeting (25 trucks x 2 convey)


2 Disconnect and roll up electric cables from caravans
3 Flush all sewage lines
OLD LOCATION

4 Disconnect all hoses &sewage lines


5 Disconnect treatment unit
6 Move camp units
7 Release two low bed truck ,

1 Cont. rigging up substructure and the mast sections


2 R/U Drawwork
3 Spot camp units
4 Connect sewage lines ,water lines,power cables
NEW LOCATION

5 Spot &connect treatment unit


6 Release two crane @the end of the day
DAY (5) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 Mud chemicals 5
50T +F.lift 3x50T+F. lift 20% 80%
2 Miscellaneous ?
3 N.p,3Drk m
4 1DRK+3RA 8 Flr+3R.A
5 2Drlr+2AD
6
7
8
9
TOTAL 5

WORK SCOPE ON DAY SIX:


OLD LOCATION

1 Load all chemicals


2 Clear old location

1 String up drilling line


2 Install monkey board
3 Install raising line
NEW LOCATION

4 Connect hydraulic service lines with kooemy unit. Supply Koomey unit with electricity
5 Continue electric rig up work on rig camp and mud system
6 Assemble Catwalk
7 Connect drawworks cooling system
8 Connect all HP mud lines
9 Release all rental trucks
DAY (6) LOADS SEQUENCE
LOGISTICS PERSONNEL
# Equipment to be moved Loads Old site New site Old site New site
1 NIL 0
0 3x50T+2F.lift 0% 100%
2
3
4
5
6
7
8
9
TOTAL 0

WORK SCOPE ON DAY SIX:


OLD LOCATION

1 NIL
2
3
4

1 Raisig mast
2 Raising substructure
3 Install rotary table &prepare Rig floor
4 Remove raising line
NEW LOCATION

5 R/U Stand pipe manifold


6 Install TD torque tube
7 R/U hook &top drive ,service loop and rotary hose
8 Install bridge crane, Flow line &V-Door+catwalk
9 R/U Stabbing board
10

You might also like