Quantity out put per day

Sl No DESCRIPTION UNIT QUANTITY MAN POWER REQUIREMENT PER DAY

1 Excavation- Man Power Cum 4 2 Helpers

Excavator Cum 160

2 Back Filling Behind Retaining Wall Cum 10 2 Helpers

3 PCC Cum 5 1 Mason 2 Helper

4 Footing (R.C.C.Works)

Reinforcement Kgs 200 1 Barbender 2 Barbender Helper

Shuttering Sqm 20 1 Carpenter 1 Carpenter Helper

Concrete Cum 3 1 Mason 2 Helper

5 Column (R.C.C.Works)

Reinforcement Kgs 190 1 Barbender 2 Barbender Helper

Shuttering Sqm 20 1 Carpenter 1 Carpenter Helper

Concrete Cum 3 1 Mason 2 Helper

6 Column (R.C.C.Works)

Reinforcement Kgs 170 1 Barbender 2 Barbender Helper

Shuttering Sqm 10 1 Carpenter 2 Carpenter Helper

Concrete Cum 3 1 Mason 2 Helper

7 Block work

Block work 100mm Sqm 20 2 Mason 3 Helper

Block work 200mm Sqm 16 2 Mason 3 Helper

8 Plastering

Internal plastering Sqm 8 1 Mason 2 Helper

External plastering Sqm 8 1 Mason 2 Helper

9 Painting

Internal painting Sqm 50 2 Painter 3 Painter Helper

External painting Sqm 40 2 Painter 3 Painter Helper

10 Tiling

Wall Tiling Sqm 8 1 Mason 1 Helper

Floor Tiling Sqm 10 1 Mason 1 Helper

11 Granite works Sqm 8 1 Mason 1 Helper

12 Door Frame Fixing No's 8 1 Carpenter 1 Carpenter Helper

13 Door Shutter Fixing No's 3 1 Carpenter 1 Carpenter Helper

14 Fixing of Windows No's 12 1 Carpenter 1 Carpenter Helper