AMREF - FINISH MONDIAL PROJECT EMBU COUNTY

Bill of Quantities
Proposed 1-Door Improved Pit Latrine

Name and Tel. of Owner:


Location:
Prepared by:
Signature

Sl. No. MATERIALS DETAILS UNIT QUANTITY UNIT COST (Kshs)


1 Pit excavation excavation feet 15 200
2 Coral blocks Coral blocks feet 40 30
3 Ballast 1" - 2" chips Wheelbarrow 4 100
4 Sand river sand Wheelbarrow 9 150
5 Cement ordinary bags 5 700
6 Ordinary Iron sheets 2m long piece 10 600
7 Spurstructure Timber 2" x 3" feet 80 25
8 Roofing Timber 2" x 2" feet 18 23
9 Reinforcement wire Gauge 10 - twisted piece 3 650
10 Reinforcement wire R-6 piece 1 300
10 Wire mesh medium gauge piece 1 500
11 Binding wire wrought iron kg 2 200
12 Door frames Wooden piece 1 1500
13 Doors Wooden piece 1 2000
14 Hinges pair 1 200
15 Locks pad bolt, piece 1 100
16 Locks Tower Bolt piece 1 80
17 Ordinary nails Assorted kg 2 120
18 Roofing nails kg 2 150
19 Vent pipe with screen & cap piece 1 1000
20 Shuttering timber 8" x 1" feet 25 28
19 Facial board 6" x 1" feet 16 25
21 Labour Skilled mandays 4 1000
22 Labour Skilled mandays 4 500
23 Painting Emulsion paint emulsion 4 500
24 Gloss paint litre 2 600
25 Tarpentine litre 2 100
26 Labour lumpsum 1 2000
TOTAL
COST (Kshs)
3000
1,200
400
1,350
3,500
6,000
2,000
414
1,950
300
500
400
1,500
2,000
200
100
80
240
300
1,000
700
400
4,000
2,000
2,000
1,200
200
2,000
35,934