3 plastering work
4 concreting work
5 P.C.C WORK
10
placing of reinforcement
PRODUCTIVITY OF LABOURS
LABOURS TASK WORK PER DAYUNIT OUTPUT/QUANTITY TOTAL NOS NOS OF LABOURS
main mason 1.25 m3 10 8
majdoor for mortar 5 m4 3.3 0.66
giving bricks up to 5000 1.25
15 m 4000 nos
main mason 1 m3 10 10
majdoor for mortar 5 m4 3.3 0.66
giving bricks up to 5000 1.25
15 m 4000 nos
main mason 10 m2 0
majdoor for mortar 5 m2 0
main mason 3 m3 0
giving concrete 3 m3 0
main mason 5 m3 0
giving concrete 3 m3 0
main mason 6 m2 0
majdoor for mortar 5 m3 0
giving bricks up to 0
15 m 4000 nos
majdoor 4 m3 0
main mason 6 m2 0
majdoor for mortar 5 m3 0
giving bricks up to 0
15 m 4000 nos
per 1 toone
column 41.58
beam 24.1
stair 25.06
floor slab 27.65
column 67.7
beam 35.2
stair 26.1
floor slab 45.6