You are on page 1of 3

Sheet1

BUILDING 1 BUILDING 2
CIVIL WORK CIVIL WORK
Description QUANTITY UNITS Description QUANTITY UNITS
Excavation 1950 cuft. Excavation 1970 cuft.
BRICK WORK BRICK WORK
Total Nos of bricks 47950 nos Total Nos of bricks 39000 nos
cement 165 bags cement 138 bags
sand 1132 cuft. sand 965 cuft.
PLASTER WORK PLASTER WORK
cement 57 bags cement 56 bags
sand 309 cuft. sand 300 cuft.
P.C.C. SUB FLOOR(1:4:8) P.C.C. SUB FLOOR(1:4:8)
cement 29 bags cement 25 bags
sand 132 cuft. sand 114 cuft.
coarse aggregate 265 cuft. coarse aggregate 227 cuft.
R.C.C COLUMNS R.C.C COLUMNS
9”X9” R.C.C. 14 nos 9”X9” R.C.C. 8 nos
cement 112 bags cement 64 bags
sand 168 cuft. sand 96 cuft.
coarse aggregate 336 cuft. coarse aggregate 192 cuft.
steel 80 kg steel 50 kg
R.C.C SLAB R.C.C SLAB
cement 94 bags cement 79 bags
sand 167 cuft. sand 140 cuft.
coarse aggregate 333 cuft. coarse aggregate 280 cuft.
steel 860 kg steel 800 kg
FLOOR TILE FLOOR TILE
AREA 860 sq.ft. AREA 740 sq.ft.
cement 12 bags cement 10 bags
sand 85 cuft. sand 73 cuft.
WALL TILE FOR BATHROOM WALL TILE FOR BATHROOM
AREA 570 SQ.ft. AREA 2200 SQ.ft.
cement 15 bags cement 60 bags
DOORS WITH FRAME DOORS WITH FRAME
SIZE 3'-6”X8'-0” 3 nos SIZE 3'-6”X8'-0” 2 nos
SIZE 2'-6”X8'-0” 3 nos SIZE 2'-6”X7'-0” 12 nos
WINDOWS WITH FRAME WINDOWS WITH FRAME
SIZE 6'-0”X6'-6” 3 nos
VENTILATOR WITH FRAME VENTILATOR WITH FRAME
SIZE 3'-0”X1'-6” 3 nos SIZE 6'-0”X1'-6” 4 nos

INTERIOR WORKS INTERIOR WORKS


FURNITURE P.O.P DOWN CEILING 740 SQ.ft.
M.D. TABLE 1 nos PAINT WORK 2000 SQ.ft.
M.D.CHAIRS 1 nos PLUMBING WORKS
M.D. VISITING CHAIR 3 nos SANITARY FIXTURE
3 SEATER SOFA 1 nos W.C. 13 nos
2 SEATER SOFA 1 nos WASH BASIN WITH TAP 8 nos
1 SEATER SOFA 4 nos URINALS WITH TAP 8 nos
BED 2 nos ELECTRICAL WORKS
L.C.D. 3 nos CEILING LIGHTS
WOODEN CABINET 1 nos 9W L.E.D. 12 nos
P.O.P DOWN CEILING 860 SQ.ft. 3W L.E.D. 12 nos
PAINT WORK 4675 SQ.ft. SWITCH 6 AMP 10 nos
SOCKET 6 AMP 4 nos
PLUMBING WORKS
SANITARY FIXTURE
W.C. 3 nos
WASH BASIN 3 nos
BATHING ENCLOSURE WITH TAP 3 nos

ELECTRICAL WORKS
CEILING LIGHTS
9W L.E.D. 14 nos
6W L.E.D. 6 nos
3W WALL WASHER 18 nos
SWITCH 6 AMP 49 nos
SOCKET 6 AMP 30 nos
AC SWITCH 16 AMP 6 nos
AC SOCKET 16 AMP 6 nos

Page 1
Sheet1

BUILDING 3 BUILDING 4
CIVIL WORK CIVIL WORK
Description QUANTITY UNITS Description QUANTITY UNITS
Excavation 1880 cuft. Excavation 1740 cuft.
BRICK WORK BRICK WORK
Total Nos of bricks 50000 nos Total Nos of bricks 45000 nos
cement 174 bags cement 158 bags
sand 1220 cuft. sand 1100 cuft.
PLASTER WORK PLASTER WORK
cement 62 bags cement 56 bags
sand 334 cuft. sand 300 cuft.
P.C.C. SUB FLOOR(1:4:8) P.C.C. SUB FLOOR(1:4:8)
cement 43 bags cement 31 bags
sand 201 cuft. sand 142 cuft.
coarse aggregate 402 cuft. coarse aggregate 283 cuft.
R.C.C COLUMNS R.C.C COLUMNS
9”X9” R.C.C. 12 nos 9”X9” R.C.C. 10 nos
cement 96 bags cement 80 bags
sand 144 cuft. sand 120 cuft.
coarse aggregate 288 cuft. coarse aggregate 240 cuft.
steel 70 kg steel 60 kg
R.C.C SLAB R.C.C SLAB
cement 138 bags cement 96 bags
sand 243 cuft. sand 170 cuft.
coarse aggregate 486 cuft. coarse aggregate 340 cuft.
steel 1400 kg steel 1000 kg
FLOOR TILE FLOOR TILE
AREA 1300 sq.ft. AREA 920 sq.ft.
cement 18 bags cement 12 bags
sand 129 cuft. sand 100 cuft.
WALL TILE FOR KITCHEN WALL TILE FOR BATHROOM
AREA 500 SQ.ft. AREA 543 SQ.ft.
cement 14 bags cement 14 bags
DOORS WITH FRAME DOORS WITH FRAME
SIZE 5'-0”X8'-0” 2 nos SIZE 3'-6”X8'-0” 3 nos
SIZE 3'-6”X8'-0” 2 nos SIZE 2'-6”X8'-0” 3 nos
WINDOWS WITH FRAME WINDOWS WITH FRAME
SIZE 6'-0”X4'-6” 5 nos SIZE 6'-0”X6'-6” 1 nos
VENTILATOR WITH FRAME
SIZE 3'-0”X1'-6” 3 nos

INTERIOR WORKS INTERIOR WORKS


P.O.P DOWN CEILING 1300 SQ.ft. FURNITURE
PAINT WORK 4000 SQ.ft. M.D. TABLE 1 nos
PLUMBING WORKS M.D.CHAIRS 1 nos
SANITARY FIXTURE M.D. VISITING CHAIR 3 nos
SINK WITH TAPS 3 nos 3 SEATER SOFA 2 nos
ELECTRICAL WORKS L.C.D. 3 nos
CEILING LIGHTS P.O.P DOWN CEILING 860 SQ.ft.
9W L.E.D. 16 nos PAINT WORK 4675 SQ.ft.
SWITCH 6 AMP 12 nos PLUMBING WORKS
SOCKET 6 AMP 12 nos SANITARY FIXTURE
SWITCH 16 AMP 10 nos W.C. 2 nos
SOCKET 16 AMP 10 nos WASH BASIN 3 nos
URINALS WITH TAP 2 nos
BATHING ENCLOSURE WITH TAP 1 nos
ELECTRICAL WORKS
CEILING LIGHTS
9W L.E.D. 8 nos
6W L.E.D. 6 nos
3W WALL WASHER 7 nos
SWITCH 6 AMP 28 nos
SOCKET 6 AMP 16 nos
AC SWITCH 16 AMP 2 nos
AC SOCKET 16 AMP 2 nos

Page 2
Sheet1

BUILDING 5
CIVIL WORK
Description QUANTITY UNITS
Excavation 870 cuft.
BRICK WORK
Total Nos of bricks 21000 nos
cement 74 bags
sand 516 cuft.
PLASTER WORK
cement 27 bags
sand 143 cuft.
P.C.C. SUB FLOOR(1:4:8)
cement 16 bags
sand 75 cuft.
coarse aggregate 150 cuft.
R.C.C COLUMNS
9”X9” R.C.C. 6 nos
cement 48 bags
sand 72 cuft.
coarse aggregate 144 cuft.
steel 45 kg
R.C.C SLAB
cement 31 bags
sand 55 cuft.
coarse aggregate 109 cuft.
steel 300 kg
FLOOR TILE
AREA 255 sq.ft.
cement 4 bags
sand 26 cuft.
WALL TILE FOR BATHROOM
AREA 455 SQ.ft.
cement 12 bags
DOORS WITH FRAME
SIZE 3'-6”X8'-0” 2 nos
SIZE 2'-6”X8'-0” 1 nos
WINDOWS WITH FRAME
SIZE 6'-0”X6'-6” 1 nos
VENTILATOR WITH FRAME
SIZE 3'-0”X1'-6” 1 nos

INTERIOR WORKS
FURNITURE
TABLE 1 nos
CHAIRS 2 nos
P.O.P DOWN CEILING 255 SQ.ft.
PAINT WORK 1500 SQ.ft.
PLUMBING WORKS
SANITARY FIXTURE
W.C. 1 nos
WASH BASIN 3 nos
URINALS WITH TAP 4 nos
ELECTRICAL WORKS
CEILING LIGHTS
6W L.E.D. 6 nos
3W WALL WASHER 2 nos
SWITCH 6 AMP 9 nos
SOCKET 6 AMP 3 nos