PROJECT: PROPOSED THREE STOREY RESIDENCE WITH ROOF DECK AND PENTHOUSE
UNIT TOTAL
ITEM DESCRIPTION QTY UNIT COST COST
I. EARTHWORK
1. EXCAVATION 207.9 cu.m. 200 41580
2. EARTHFILL 15 cu.m. 90 1350
3. GRAVELFILL 45 cu.m. 350 15750
4. SOIL POISONING 2 gal. 150 300
SUBTOTAL 58980
II. CONCRETE
1. CEMENT 648.99 bags
2. GRAVEL 72.11 cu.m.
3. SAND 36.056 cu.m.
SUBTOTAL
III. MASONRY 1. CHB
` 4" CHB 3537 pcs.
`6" CHB 1740 pcs.
2. MORTAR
`SAND 64.48 cu.m.
`CEMENT 349 bags
3. PLASTER
`SAND 5 cu.m.
`CEMENT 50 bags
4. STEEL BARS 292 pcs.
SUBTOTAL
IV. SCAFFOLDS
AND FORMS
SCAFFOLDING
COLUMNS (2" X 3") 1669 bd.ft
BEAMS (2" X 3") 982 bd.ft
SLAB (2" X 3") 701 bd.ft
FLOOR SLAB (4'' X 8'') 27 pcs.
FORMS
PLYWOOD (4'' X 8'') 21 bd.ft.
FRAME (4'' X 8'') 788 bd.ft.
SUBTOTAL
V. ROOF FRAMING
G.I SHEETS 12' 11 pcs.
G.I SHEETS 10' 11 pcs.
UMBRELLA NAILS 5 kgs.
FLASHING 10 pcs.
GUTTER 4 pcs.
DOWNSPOUT 8 pcs.
ELBOW 4 pcs.
1-L
VULCASEAL SEALANT 3 can
SUBTOTAL
VI. TILE WORKS
WALL TILES 1736 pcs.
FLOOR TILES 525 pcs.
GROUT 0.9023 cu.m.
SUBTOTAL