ITEM NO. DESCRIPTION QTY UNIT MATERIAL UNIT COST
1 CONCRETE 25 cu. m
2 FORM PLYWOOD (1/2 thk) 6 pcs
3 COCOLUMBER (2x3X8) 10 pcs
4 DEFORMED BARS @10mm 199 pcs
5 RIB SPAN (0.6MM THK) (4ft x 8ft) 22 pcs
6 C-PURLINS (2" X 6" X 20') 19 pcs
7 ANGLE BARS (2" X 2" X 3/16" X 20") 1 pcs
8 EPOXY PRIMER (GRAY) 6 gal
9 S/S GUTTER (0.6MM THK) 7.5 L.m
10 FLASHING 25 L.m
11 BENDED ACCESSORIES 1 lot
12 MS PLATE (3/4 THK) (0.5m x 0.5m) 1 pcs
13 S/S SHEET (1.2MM THK) 4 pcs
14 GRAVEL BEDDING 3/4 6 cu. m
TOTAL:
LABOR UNIT COST TOTAL AMOUNT
TOTAL:
TOTAL:
MATERIAL REQUEST FORM
DATE: PROJECT:
ITEM NO. QTY UNIT DESCRIPTION UNIT COST
1 1 pc Checkered Plate 2mm
2 4 pcs Caster Wheels
3 1 unit Truck for Hauling
CT: