You are on page 1of 4

BILL OF MATERIALS & COST ESTIMATE FOR THE PROPOSED 2- STOREY RESL. BLDG..

DUPLEX TYPE

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT


ITEM I - CONCRETE & MASONRY WORKS
3,586 PCS. #4 CHB 11 39,446
489 BAGS CEMENT 265 129,585
23 CU.M. SAND 400 9,200
20 CU.M. GRAVEL 850 19,550
542 PCS. 10 MM Ø BAR 143 77,506
42 PCS. 12 MM Ø BAR 205 8,610
120 PCS. 16 MM Ø BAR 365 43,800
2 ROLLS TIEWIRE # 16 80 4,000
10 CU.M. EARTHFILL 400 4,000
SUB TOTAL - 335,697
ITEM II - TRUSSES & ROOFING WORKS
7 PCS. 2 x 4 CHANNEL BAR 1,800 12,600
15 PCS. 2 x 3 C PURLINS 600 9,000
9 PCS. .05 x 18’ LONG SPAN ROOFING SHEETS 150/FT. 24,300
2 PCS. 1/4 x 1 < BAR 540 1,080
3 PCS 1/4 x 1 FLAT BAR 320 960
9 PCS. .05 x 8’ WALL FLASHING 650 5,850
4 PCS. .05 x 8’ GUTTER 400 1,600
4 PCS. .05 x 8’ FASCIA COVER 400 1,600
2 GALS. EPOXY PRIMER 950 1,900
1 GAL. LACQUER THINNER 450 450
4 PCS. PAINT BRUSH 95 380
3 BOXES WELDING ROD 320 960
400 PCS. TEKSCREW 2” 2 800
2 LTS. VULCA SEAL 600 1,200
SUB TOTAL - 62,680
ITEM III - CEILING WORKS
34 PCS. 1/4 THK. HARDIFLEX 450 15,300
115 PCS. METAL FURRING 130 14,950
6 BOXES REVITS 5/32 x 1/2 280 1,680
4 PCS. DRILL BIT 120 480
1 LT. EPOXY PRIMER 600 600
SUB TOTAL - 33,010
ITEM IV - DOORS & WINDOWS
2 SETS .80 x 2.10 M. PANEL DOOR 5,000 10,000
2 SETS .70 x 2.10 M. PANEL DOOR 4,000 8,000
4 SETS .70 x 2.10 M. FLUSH DOOR 2,800 11,200
2 SETS .60 x 2.10 M. ALUM. DOOR 2,500 5,000
2 SETS 1.00 x 1.00 M. SLIDING WINDOW 4,500 9,000
4 SETS 1.20 x 1.20 M. SLIDING WINDOW 5,500 22,000
2 SETS .60 x 1.20 M. SLIDING WINDOW 2,500 5,000
2 SETS .40 x .50 M. SLIDING WINDOW 1,500 3,000
SUB TOTAL - 73,200
ITEM V - TILE WORKS
64 PCS. .30 x .30 M. TILES CR. UNGLAZED 32 2,048
210 PCS. .30 x .30 M. TILES - CR SIDINGS 32 6,770
18 PCS. .60 x .60 M. TILES @ KIT. TOP 160 2,880
110 PCS. .30 x 30 M. TILES-STAIR 32 3,520
370 PCS. .40 x .40 M. TILES - LIVING,KIT.,BR. 56 20,720
100 PCS. .30 x .30 M. TILES - TERRACE 32 3,200
SUB TOTAL -
ITEM VI - FORMWORKS & SCAFFOLDINGS
150 PCS. 2 x 3 x 12 COCOLUMBER @28/BDFT. 25,200
120 PCS. 2 x 2 x 12 COCOLUMBER @28/BDFT. 13,440
26 PCS. 1/2 THK. ORD. PLYWOOD @650 16,900
40 KLS. COMMON NAILS 70 2,800
SUB TOTAL - 58,340
ITEM VII - PLUMBING WORKS
2 SETS KITCHEN SINK 3,000 6,000
2 SETS WATER CLOSET 5,600 11,200
3 PCS. 3ӯ PVC PIPE 460 1,380
8 PCS. 2ӯ PVC PIPE 240 1,920
3 PCS. 4ӯ PVC PIPE 580 1,740
4 PCS. 2” Ø PVC TEE 45 180
14 PCS. 2” Ø PVC ELBOW 45 630
2 PCS. 3ӯ PVC WYE 95 190
2 PCS. 3ӯ PCV ELBOW 45 90
30 MTS. 1/2ӯ P.E. PIPE 45 1,350
SUB TOTAL - 24,680
ITEM VIII - RAILING WORKS
18 PCS. 2 x 2 - TUBULAR 750 13,500
2 BOXES WELDING ROD 320 640
1 GAL. EPOXY PRIMER 950 950
2 PCS. PAINT BRUSH # 3 85 170
15 PCS. 1 x 1 - TUBULAR 380 1,900
SUB TOTAL - 17,160
ITEM IX- ELECTRICAL WORKS
L.S. 45,000
SUB TOTAL - 45,000
ITEM X - PAINTING WORKS
L.S. 45,000
SUB TOTAL - 45,000
SUMMARY

ITEM I - CONCRETE & MASONRY WORKS 335,697


ITEM II - TRUSSES & ROOFING WORKS 62,680
ITEM III - CEILING WORKS 33,010
ITEM IV - DOORS & WINDOWS 73,200
ITEM V - TILE WORKS 39,088
ITEM VI - FORMWORKS & SCAFFOLDINGS 58,340
ITEM VII - PLUMBING WORKS 24,680
ITEM VIII - RAILING WORKS 17,160
ITEM IX - PAINTING WORKS L.S. 45,000
ITEM X - ELECTRICAL WORKS L.S. 45,000
TOTAL MATERIAL COST 733,855
5% CONTENGENCY 36,692.75
770,547.75
TOTAL LABOR COST 462,328.65
GRAND TOTAL ₱ 1,232,876.40

APPROVED:

____________________________
CIVIL ENGINEER

LIC. NO._________________________
PTR. NO. ________________________
TIN ___________________________

---------------------------------------