Professional Documents
Culture Documents
BRIDGEWORK
Traffic Decking
Installation of temporary traffic decking, consisting of steel beam decking and concrete panels.
A typical rate of = 1.6 m2/hr.
Structural Steelwork...
Task / Description Slow Ave Fast Units
Simple Universal Beam Steel Bridge, erect support steel H frames - 1.2 - days/no
Simple Universal Beam Steel Bridge, erect 15m truss - 3.3 - m/day
Structural Steelwork
Steel Frames
Task / Description Slow Ave Fast Units
Steel Frame and Roof Members 3.4 - 4.6 Tons/day
Wall Frame, Bow String Truss and Frame - 1.6 - Tons/day
Roof Frame, Curved Truss and Frame - 5.2 - Tons/day
Wall Frame, Glazed Frame and Atrium - 0.3 - Tons/day
Blockwork
Task / Description Slow Ave Fast Units
Thermalite Blockwork, under 100mm thick 1.8 2.5 3.2 m2/hr
Thermalite Blockwork, under 100-150mm thick 1.4 1.9 2.5 m2/hr
Thermalite Blockwork, over 150mm thick 1.2 1.6 2.1 m2/hr
Lightweight Concrete Blockwork, under 100mm thick 1.5 2.2 2.9 m2/hr
Lightweight Concrete Blockwork, under 100-150mm thick 1.4 1.9 2.1 m2/hr
Lightweight Concrete Blockwork, over 150mm thick 1.2 1.6 2 m2/hr
Heavyweight Concrete Blockwork, under 100mm thick 1.4 2.1 2.9 m2/hr
Heavyweight Concrete Blockwork, under 100-150mm thick 1.2 1.6 2.1 m2/hr
Curtain Walling
Curtain Walling rate
Assume 30m2 per week for general curtain walling
Building Frameworks
‹ Building FrameworksupHolding Down Bolts Stanchion Bases ›
Login or register to post comments
COMMENTS
Curtain walling ''catch all'' comment - is it correct?
by Damien Galllagher - 30 Sep 2011 - 15:38
Hi Richard,
I would agree with you, I think the 30m2 for general curtain walling should be per day.
Regards,
Damien
Compared to the deatiled rates this comment looks like it should be;
Roof Structure
Usually carried out with a minimum of a 2 man gang, sometimes with an additional labourer.
For a typical semi-detached house structure or similar...
Roof Trusses 1.28 no/hr
Wall Plates 2.76 m/hr
Rafters 1.17 m/hr
Ceiling Joists 32.10 m/hr
Wall panels up to 3m in hieght including both external and internal panels ; 30 panels per day (average panel 3.5m long)
Wall panels over 3m in height including both internal and external panels ; 20 panels per day (average panel 2.5m long)
Loose floor joists position and fix 175m sq per day
Loose floor joists position, fix & position and fix floor decking 125m sq per day
Floor/roof cassette assumed simple 12 X 2.4m 300m sq per day
Floor/roof cassette complex shape 150 – 200 m sq per day
Trussed roof erect, brace,sark and felt 100m sq per day (up to 8m span measured at horizantial)
Trussed roof erect, brace,sark and felt 80m sq per day (up to 12m span measured at horizantial)
Hip or valley up to 12m long 1 man a day
Medium dormer window (2.4m wide) 1 man a day
I hope this helps , but please bare in mind that the more complex projects will take longer.
Timber Frames...