Overtime Accomplishment Report

This document provides a request for overtime hours across multiple dates in April 2021 for a 120TPH Mabini Feedmill Project. It includes the target and actual number of workers, their positions, and the scope of work completed each date at various work sites including the feedmill tower, finished goods warehouse, raw materials warehouse, and intake building. Managers are requesting overtime to complete tasks like formwork dismantling, rebar installation, scaffolding, and other construction activities.

Uploaded by

Kate Perez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
737 views20 pages

Overtime Accomplishment Report

This document provides a request for overtime hours across multiple dates in April 2021 for a 120TPH Mabini Feedmill Project. It includes the target and actual number of workers, their positions, and the scope of work completed each date at various work sites including the feedmill tower, finished goods warehouse, raw materials warehouse, and intake building. Managers are requesting overtime to complete tasks like formwork dismantling, rebar installation, scaffolding, and other construction activities.

Uploaded by

Kate Perez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
  • Project Overview and Details

PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT

SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

WITH ACCOMPLISHMENT
OT DATE REPORT FROM SITE
Apr-11 WITH ACCOM REPORT
Apr-12 NO REPORT
Apr-13 NO OT REQUEST
Apr-14 NO REPORT
Apr-15 WITH ACCOM REPORT
Apr-16 WITH ACCOM REPORT(FG ONLY)
Apr-17 NO REPORT
Apr-18 NO REPORT
Apr-19 WITH ACCOM REPORT
Apr-20 NO REPORT
Apr-21 NO REPORT
Apr-22 NO REPORT
Apr-23 NO OT REQUEST
Apr-24 NO REPORT
Apr-25 WITH ACCOM REPORT
Apr-26 NO OT REQUEST
Apr-27 NO REPORT
Apr-28 NO REPORT
Apr-29 NO REPORT
Apr-30 NO REPORT
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 30, 2021 FRIDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FEEDMILL TOWER
1 FOREMAN
1 LEADMAN 2 DISMANTLING OF STEEL FORMWORKS
4 WELDER
1 LEADMAN
9 CARP/MASON
1 STEELMAN 2 RECTIFICATION OF HONEY COMB
3 HELPER
1 FOREMAN
1 FOREMAN
6 WELDER
MOCK UP OF BATTERBOARD AND TEMPLATE
1 PLUMBER 2 FOR ANCHOR BOLTS
1 PAINTED
1 TINSMITH
3 STEELMAN
2 RET. WALL BEAM REBAR INSTALLATION
1 FOREMAN
4 STEELMAN 2 FABRICATION OF TIES FOR TOWER BEAM
RAW MATERIALS WAREHOUSE
1 CARP/MASON
PLASTERING @GL A2 AND G2 AND REPAIR OF
1 LEADMAN 2 RCP CONNECTION
3 HELPER
1 CARP/MASON 2 COMPACTION @ GL G2 TO N2
INTAKE BLDG

4 STEELMAN 2 INSTALLATION OF TIES FOR INTAKE PEDESTAL

1 LEADMAN INSTALLATION OF HORIZONTAL AND VERTICAL


9 CARP/MASON 2 BRACING FOR INTERIOR FORMWORKS AT
2 HELPER SECOND LIFT OF INTAKE
6 STEELMAN 2 FABRICATION OF TIES FOR INTAKE BEAMS
1 LEADMAN ASSIST AND SUPPORT FOR ALIGNING OF
2 FORMWORKS
5 SCAFFOLDER
INDIRECT SUPPORT
1 OPERATOR BT
2 HAULING OF SHORING AT FMT
1 RIGGER
1 OPERATOR BT
2 CURING AT FMT AND DUSK CONTROL AT SITE
1 RIGGER
3 OPERATOR BH
HAULING OF SOIL AT SEASIDE AND DUMPING OF
2 DT DRIVER 2
SOIL AT FG
5 SPOTTER
1 MECHANIC
2 REPAIR WALKBEHIND & PLATE COMPACTOR
1 ASSIST MECHANIC

MONITORING AND MAINTENANCE OF POWER


3 ELECTRICIAN SUPPLY FOR OVERTIME WORK
2
1 FUELMAN
2 DRIVER
2 UTILITY

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 29, 2021 THURSDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
1 FOREMAN
1 LEADMAN CORRECTION OF BRACING AT PEDESTAL / REFIXING
4
5 WELDER OF ANCHOR BOLT
1 QA/QC AIDE
1 LEADMAN
INSTALLATION OF SCAFFOLD FOR PEDESTAL AT GL
4 SCAFFOLDER 2
E/22 AND N /24
1 HELPER
5 HELPER BACKFILLING AND COMPACTION AT GL 39
4
1 FOREMAN (OUTSIDE PERIMETER)
2 DISMANTLING OF TIES GL E/ 26-28
ALLIGNMENT OF ANCHOR BOLT AND SURVEY
4 SURVEY AIDE 2
WORKS
FEEDMILL TOWER
8 STEELMAN 4 COMPACTION OF SOIL @ GL 14 / G-D
1 LEADMAN FABRICATION OF REBAR FOR FMT REBARS FOR
2
3 STEELMAN RET. WALL BEAM
1 HELPER
2
4 CARP/MASON DISMANTLING OF FORMWORKS OUTER 14
5 CARP/MASON 6
1 FOREMAN
HONEY COMB CHIPPING AND RECTIFICATION FOR
5 CARP/MASON 2 1ST LIFT 1ST BATCH PEDESTAL
4 HELPER
1 FOREMAN
3 WELDER 6 TEMPLATE DRILLING (36MM) / TIE ROD CUTTING
GL 14
1 PURCHASER
1 LEADMAN
2 RETWALL BEAM REBAR INSTALLATION
15 STEELMAN
RAW MATERIALS WAREHOUSE
1 TINSMITH
1 PAINTER
6 INSTALLATION OF CLEVIS HANGER SUPPORT
1 PLUMBER
1 WELDER
2 CARP/MASON
2 BACKFILLING AND COMPACTION FOR PIPE OUTLET
3 HELPER
INTAKE BLDG
4 STEELMAN 2 FABRICATION OF TIES FOR INTAKE BEAM
2 LEADMAN
INSTALLATION OF FORMWORKS FOR SECOND LIFT
5 HELPER 2 OF RET. WALL (EXTERIOR)
10 CARP/MASON
1 FOREMAN
4 HELPER GRAVEL BEDDING @ TRENCH CANAL AND
2
BACKFILLING AND COMPACTION @ GL G2 TO N2
1 CARP/MASON
INDIRECT SUPPORT
2 OPERATOR LIFTING AT RAWMAT/FMT AND BACKFILLING AT
2 SPOTTER FMT
SITE SERVICE AND SERVICE OF MANPOWER AND
2 DRIVER
STAFF
1 DRIVER
OBT TO MANILA
1 RIGGER
2 OPERATOR
2 DT DRIVER SEGREGATE AND HAULING OF ROCK AND GOOD
6
3 SPOTTER SOIL @ SEASIDE.
1 RIGGER
1 OPERATOR
2 DUST CONTROL AND WATER SUPPLY CURING
1 RIGGER
MONITORING AND MAINTENANCE OF POWER
3 ELECTRICIAN 6 SUPPLY FOR OT WORKS
2 UTILITY 2 HOUSEKEEPING AT BCDC AND ARCHEN OFFICE
1 FUELMAN 2 FUEL MONITORING
1 MECHANIC
2 REPAIR CUTTING OUTFIT
1 ASSIST MECHANIC
1 TIMEKEEPER 2 TIMEKEEPING AND MONITORING OF MANPOWER

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 28, 2021 WEDNESDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
7 STEELMAN 2 CORRECTION OF CONFINMENT BARS OF TIES
2 HELPER 2 ALIGNMENT OF ANCHOR BOLTS
2 HELPER BACKFILLING AND COMPACTION OF SOIL AT LINE
2
1 FOREMAN 39
FEEDMILL TOWER
1 FOREMAN
FABRICATION AND INSTALLATION FOR
4 MC 2 HONEYCOMB RECTIFICATION
3 HELPER
1 FOREMAN
6 DRILLING OF TEMPLATES FOR ANCHOR BOLTS
6 WELDER
8 STEELMAN 2 BACKFILLING AND COMPACTION ALINE 21
5 STEELMAN 2 INSTALLATION OF TIES FOR PEDESTAL 2ND LIFT
1 FOREMAN
1 LEADMAN 2 DISMANTLING OF STEELFORMS
5 WELDER
1 LEADMAN
7 CM DISMANTLING OF FORMWORKS AND SHORING
6
2 HELPER JACK
1 SM
4 HELPER 2 CHIPPING OF PEDESTAL
4 STEELMAN 2 SEGREGATION OF PIPES
RAW MATERIALS WAREHOUSE
MODIFICATION OF MOBILE SCAFFOLDS FOR
7 SCAFFOLDER 2
ELECTRICAL WORKS

1 LEADMAN INSTALLATION OF IMC PIPE FOR LIGHTING LAYOUT


5 ELECTRICIAN 2 AND MONITORING/MAINTENANCE OF POWER
1 WELDER SUPPLY AND LIGHTING
1 LEADMAN
1 CM
6 BACKFILLING AND COMPACTION AT GL. 2
5 HELPER
1 FOREMAN
2 WELDER
1 TINSMITH FABRICATION AND INSTALLATION OF CLEVIS
2
1 PLUMBER GANGER AND PAINTING WORKS
1 PAINTER
2 HELPER
2 BACKFILLING AND COMPACTION AT LINE 2
2 MC
INTAKE BLDG
6 STEELMAN 2 FABRICATION OF TIES FOR
1 LEADMAN
INSTALLATION OF CONCRETE SPACER AND
11 CARPENTER 2 FORMWORKS
4 HELPER
INDIRECT SUPPORT
2 OPERATOR
2 DT DRIVER HAULING OF SOIL FROM SEASIDE TO DUMPSITE
2 SPOTTER
1 OPERATOR
BACKFILLING AT FMT
1 SPOTTER
1 OPERATOR
DUST CONTROL
1 RIGGER
2 RIGGER
1 OPERATOR
2 UTILITY
LIFTING OF MATERIALS
3 SERVICE DRIVER
1 FUELMAN
1 TIMEKEEPER

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 27, 2021 TUESDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
2 FOREMAN
1 LEADMAN
4 CORRECTION OF ANCHOR BOLT AT PEDESTAL
3 WELDER
3 HELPER
2 CARP/MASON
2 BACKFILLING AND COMPACTION AT GL 39 / F - J
3 HELPER
FEEDMILL TOWER
7 STEELMAN
2 FABRICATION OF TIES FOR PEDESTAL 2ND LIFT
1 LEADMAN
1 LEADMAN
2 FABRICATION OF GI FRAMING FOR ANCHOR BOLTS
2 WELDER
1 TINSMITH
1 HELPER
1 PLUMBER
6 INSTALLATION OF ANGLE BAR SUPPORT AND
1 PURCHASER
TEMPLATE FABRICATION FOR ANCHOR BOLTS
2 WELDER
1 PAINTER
5 WELDER 2
RAW MATERIALS WAREHOUSE
3 STEELMAN 2 GL1 PEDESTAL REBAR WORKS

2 HELPER 4 COMPACTION GL 2 ,B-G

4 SCAFFOLDER 2 MODIFICATION OF MOBILE SCAFFOLDS

INTAKE BLDG

3 CARP/MASON 2 INSTALLATION OF WATER STOP FOR THE 2ND LIFT


OF RET. WALL

1 FOREMAN
1 LEADMAN INSTALLATION OF CONCRETE SPACER AND
2
6 CARP/MASON FORMWORKS
4 HELPER
INDIRECT SUPPORT
2 OPERATOR
2 DT DRIVER 6 SEASIDE AND DUMPSITE CLEARING
1 SPOTTER
1 OPERATOR
2 BACKFILLING AT FMT
1 SPOTTER
1 OPERATOR
2 DUST CONTROL AND WATER SUPPY CURING
4 RIGGER

3 DRIVER SITE SERVICE AND SERVICE OF MANPOWER AND


STAFF

1 FUELMAN FUEL ISSUANCE AND MONITORING

1 MECHANIC
2 WATER SPRAYER AND ENGINE TROUBLE
1 ASSTS MECHANIC

4 SURVEY AIDE 2 ALIGNMENT OF ANCHOR BOLTS AT GL E AND N

MONITORING AND MAINTENANCE OF POWER


2 ELECTRICIAN 6 SUPPLY FOR OVERTIME WORKS

1 WAREHOUSE ASST 2 SORTING AND ARRANGING TOOLS AND


1 WAREHOUSE ASSIST 3 CONSUMABLES
1 QC/ AIDE 2 MONITORING OF CURING (2ND BATCH)

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 25, 2021 SUNDAY


TARGET ACTUAL REMARKS
NO. OF POSITION NO. OF HRS SCOPE OF WORK NO. OF POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
1 FOREMAN FORMWORKS INSTALLATION FOR PEDESTALS AT
8 E24 TO E28 / MOULDING OF CONCRETE SPACER
3 CARPENTER/MASON (TARGET: 5 PEDESTALS)

1 LEADMAN
1 FOREMAN 8 CORRECTION OF ANCHOR BOLT AT GL E/ 33 - 39
(TARGET: 7 PEDESTALS)
1 WELDER
2 HELPER 8 COMPACTION AT GRID 39 (TARGET: 1 LAYER)
4 STEELMAN 8 INSTALLATION OF STIRRUPS FOR FTB
1 LEADMAN INSTALLATION OF SCAFFOLD FOR PEDESTAL AT GL.
4 SCAFFOLDER 8 J39 TO M39 / HAULING AND INSTALLATION
1 HELPER (TARGET: 4 PEDESTAL)
FEEDMILL TOWER
2 CARPENTER/MASON 8 HONEYCOMB RECTIFICATION
COMPACTION AT GL. 21 5TH LAYER (TO FINISH
8 STEELMAN 8
LAST LAYER)
RAW MATERIALS WAREHOUSE
1 FOREMAN
1 TINSMITH RECTIFICATION OF ROOFING (TARGET: 1 BAY)
1 PAINTER 8
5 WELDER 1 HELPER
1 PLUMBER INSTALLATION OF BATTERBOARD AND TEMPLATES 1 PAINTER 8 INSTALLATION OF BATTERBOARD AND 3 TEMPLATES
AT GL 1 PEDESTALS (TARGET:4 PEDESTALS) TEMPLATES AT GL 1 PEDESTALS
1 STEELMAN 2 WELDER
SOIL BACKFILLING AND COMPACTION AT L1 AND J1 2 STEELMAN SOIL BACKFILLING AND COMPACTION AT L1
1 LEADMAN 8 2 FOOTINGS
(TARGET:2 PEDESTALS) 2 HELPER AND J1
8
ALIGNMENT OF BOTTOM GIRTS AT GL. A2 -A9
4 STEELMAN 2 STEELMAN ALIGNMENT OF BOTTOM GIRTS AT GL. A2 -A9 FINISHED 6 SPAN
(TARGET: 6 SPAN)
4 CARPENTER/MASON CRADLE AND RCP LAYING/ GROUTING COLLAR 2 CARPENTER/MASON RCP LAYING FINISHED ;6
8 LAYING OF RCP AND GROUTING
5 HELPER (TARGET: TO COMPLETE LAYING) 3 HELPER JOINTS GROUT
8
2 LEADMAN SOIL BACKFILLING AND COMPACTION FOR TRENCH
C0ANAL (TARGET: TO COMPLETE)
INSTALLATION OF IMC PIPE FOR LIGHTING LAYOUT
1 LEADMAN 1 LEADMAN/ELECTRICIAN
AT GRID D TO G
4 ELECTRICIAN 1 SM/ELECTRICIAN INSTALLATION OF IMC PIPE FOR LIGHTING LAY
8 MONITORING AND MAINTENANCE OF POWER 8
1 CARPENTER/MASON 1 CARPENTER/ELECTRICIAN OUT
SUPPLY
1 WELDER
CUTTING OF SOG 3 AND 4 DIVERT MANPOWER
3 CARPENTER/MASON CUTTING OF SOG 3 AND 4 ( TARGET: TO 3 CARPENTER/MASON 3-6 MTRS CUT
TO CUTTING OF PHENOLIC FOR TEMPLATES
COMPLETE)
8 (FMT ACTIVITY)
1 HELPER FORMWORKS FOR FTB AT GL. 14 TO 14'/A-B 7 CARPENTER/MASON 8 FORMWORKS FOR FTB AT GL. 14 TO 14'/A-B 2 SPAN FORMWORKS
1 FOREMAN ( TARGET: TO COMPLETE)
1 FOREMAN INSTALLATION OF REBARS FOR GRIDLINE 1
1 LEADMAN INSTALLATION OF REBARS FOR GRIDLINE 1
8 PEDESTAL / VERTICAL BARS AND STIRRUPS 4 STEELMAN 8 2 PEDESTAL
PEDESTAL / VERTICAL BARS AND STIRRUPS
4 STEELMAN (TARGET: 5 PEDESTALS)
INSTALLATION OF TIES FOR GRIDLINE N24 TO N25
4 STEELMAN 8
AND P24 TO P25 (TARGET: TO COMPLETE)

INSTALLATIONOF ACCESS SCAFFOLDS FOR


ELECTRICAL WORKS AT RAW MATERIALS
8 SCAFFOLDER 8 7 STEELMAN 8 MODIFICATION OF MOBILE SCAFFOLDING
WAREHOUSE / ASSEMBLING 1 SET TOWER
SCAFFOLDING (TARGET: TO COMPLETE 1 SET)

5 SCAFFOLDER 8 INSTALLATION OF SCAFFOLDS AT GRID G 5 SCAFFOLDER 8 INSTALLATION OF SCAFFOLDS AT GRID G

1 FOREMAN
1 TINSMITH
1 WELDER 8 FABRICATION AND INSTALLATION OF CLEVIS
HANGER SUPPORT
1 STEELMAN
1 PLUMBER
CONCRETE CURING MONITORING OF PEDESTALS INDIRECT SUPPORT
1 QC AIDE 8 AT FMT, SOG AT RAW MAT AND RETAINING WALL
4 OPERATOR AT INTAKE
4 SPOTTER *HAULING OF BOULDERS AT SEASIDE
*LIFTING/TRANSFERING OF COMPACTION
2 DT DRIVER EQUIPMENTS
8
1 RIGGER *DUST CONTROL
*HAULING OF MATERIALS
*CURING OF PEDESTALS

1 HELPER/MECHANIC 8
REPAIRING OF EQUIPMENTS
1 MECHANIC 8
SITE AND WAREHOUSE MONITORING AND
2 WAREHOUSEMAN 8
TOOLKEEPING
1 TIME KEEPER 8 MONITORING OF MANPOWER
1 HILUX DRIVER 8
1 DRIVER 8 SERVICE OF EMPLOYEES AND HAULING OF
MATERIALS
1 TRAVIS DRIVER 8
1 FUEL MAN 8 MONITORING OF FUEL

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 24, 2021 SATURDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
1 LEADMAN 2
6 SCAFFOLDER INSTALLATION OF SCAFFOLDING FOR PEDESTAL @
GL 39/F-M
1 HELPER
INSTALLATION OF FTB STIRRUPS GL N/28-29 AND
7 STEELMAN 2 GL N/24-25
FEEDMILL TOWER
4 STEELMAN 2 COMPACTION FOR GL 21 LAST LAYER
RAW MATERIALS WAREHOUSE
1 FOREMAN
1 PAINTER
1 HELPER
3 WELDER 2 ROOFING @ GL D/2-12 RECTIFICATION
1 PLUMBER
1 PURCHASER
1 TINSMITH
2 CARPENTER/MASON 2 BACKFILLING & COMPACTION @ GL A
5 STEELMAN
2 INSTALLATION OF REBARS @ GL 1 PEDESTAL
1 FOREMAN
INDIRECT SUPPORT
2 DT DRIVER
2 SPOTTER 6 HAULING OF GOOD SOIL AND CLEARING @ SEASIDE
2 OPERATOR BACKHOE
1 OPERATOR 5 TONNER 2 CURING WATER SUPPLY
3 DRIVER SERVICE MANPOWER/STAFF SERVICE AT SITE
1 FUELMAN 2 FUEL MONITORING CONSUMABLE
1 ASSIST MECH 2 REPAIRING TAMPERING HAMMER
2 UTILITY 2 HOUSEKEEPING
8 SCAFFOLDER 2 INSTALLATION OF ACCESS SCAFFOLD AT GL N
1 LEADMAN
2 ELECTRICIAN 2 INSTALLATION OF INC PIPE FOR LIGHTING LAYOUT
1 WELDER
MONITORING AND MAINTENANCE OF POWER
2 ELECTRICIAN 2
SUPPLY

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 22, 2021 THURSDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
1 LEADMAN INSTALLATION OF SCAFFOLD FOR PEDESTAL
5 SCAFFOLDER 2 REBAR TO BEAM WORKING FLATFORM @ GL
4 HELPER N/24-25 AND P /24-25

2 INSTALLATION OF FORMWORKS @ GL 39 /F-M

5 STEELMAN 2 INSTALLATION OF TIES AT GL N 26-28


1 LEADMAN
1 STEELMAN 2 CUTTING OF FRAMING @ GL E /39 -31
1 HELPER
6 STEELMAN 2 CHIPPING FOR RECTIFICATION OF PEDESTAL
1 WELDER 2 WELDING FOR ACCESS AT ARCHEN .
FEEDMILL TOWER
6 SCAFFOLDER 2 INSTALLATION OF EXTRA SHORING FOR RET. WALL
3 STEELMAM 2 CHECKING OF ALIGNMENT FOR REBAR AND
5 STEELMAN 4 RESCUE FOR CHIPPING OF PEDESTAL
5 HELPER
1 FOREMAN
2 CHECKING ALIGNMENT FOR PEDESTAL
1 LEADMAN
5 CARP/MASON
1 FOREMAN
1 LEADMAN
1 HELPER 2 FABRICATION OF GI - FRAMES FOR PEDESTAL
1 WELDER
1 QA/QC AIDE
3 CARP/MASON
4
2 HELPER
3 CARP/MASON ALIGNMENT OF SHORING INSTALLATION
1 STEELMAN 2
1 HELPED
1 LEADMAN
1 LEADMAN
3 HELPER 6 ALIGNMENT AND FIXING (OUTSIDE AND INSIDE) @
GL 15 / N-D
1 STEELMAN
1 CARP/MASON
RAW MATERIALS WAREHOUSE
1 FOREMAN
4 WELDER
1 HELPER
1 TINSMITH 6 PRIMER COATING PIPING HEADER TO GUTTER /
CROSS BRACING ALIGNMENT @ GL N
1 PAINTER
1 PLUMBER
1 PURCHASER
8 STEELMAN 2
1 FOREMAN HAULING OF REBAR / FABRICATE AND CUTTING
6
1 LEADMAN
2 CARP/MASON
2 FORMWORKS INSTALLATION GL 13 / G
1 HELPER
1 LEADMAN
2 STEELMAN 2 ALIGNMENT OF GRID A / GATE RELOCATION
2 HELPER
INDIRECT SUPPORT

2 ELECTRICIAN 6 MONITORING AND MAINTENANCE OF POWER


SUPPLY
3 OPERATOR
1 SPOTTER 6 SEGRAGATE OF GOOD SOIL AND ROCK
3 RIGGER
1 OPERATOR
2 DUST CONTROL AND WATER CURING
1 SPOTTER
1 MECHANIC
1 HELPER MECHANIC
1 FUELMAN
2 REPAIRING COMPACTOR
3 DRIVER
2 UTILITY
2 WAREHOUSE ASSIST

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 21, 2021 WEDNESDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
1 LEADMAN 6
ABRICATION OF STIRRUPS FO FOOTING TIE BEAM
1 STEELMAN
2 AT GL. N/27 TO 30 AND N/23 TO 24
7 STEELMAN
1 LEADMAN
1 SCAFFOLDER 4
1 HELPER INSTALLATION OF SCAFFOLD FOR REBAR WORKS
AT N/27 TO 29
3 HELPER
2
4 SCAFFOLDER
1 HELPER
3 CARPENTER/MASON 4
1 FOREMAN FORMWORK INSTALLATION FOR PEDESTALS AT GL.
39/ F-N
2 HELPER
2
1 QC AIDE
1 STEELMAN 6
INSTALLATION OF STIRRUPS FOR FTB AT N/30 TO 31
9 STEELMAN 2
FEEDMILL TOWER
1 FOREMAN
1 TINSMITH
INSTALLATION OF STEEL FORMS FOR 2ND BATCH
1 PLUMBER 2 PEDESTAL 1ST LIFT
1 PAINTER
8 WELDER
2 HELPER
INSTALLATION OF HORIZONTAL, VERTICAL
1 LEADMAN 2
BRACING AND TIE ROD
1 FOREMAN
2 HELPER
4 CARPENTER 2 ALIGNMENT AND FIXING OF FORMWORKS AT GL.
1 LEADMAN
RAW MATERIALS WAREHOUSE

4 STEELMAN ALIGNMENT OF PURLINS ALONF GRID N

INDIRECT SUPPORT
1 HELPER ASSIST MECHANIC TO REPAIR PAYLOADER AND
1 OPERATOR PLATE COMPACTOR
2 OPERATOR
1 DT DRIVER HAULING OF SOIL FROM SEASIDE TO DUMPSITE
2 RIGGER

2 ELECTRICIAN
2 DRIVER
1 UTILITY
1 FUEL MAN

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 20, 2021 TUESDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
1 FOREMAN 6 BACKFILLING COMPACTION GL39

5 CARPENTER/MASON 2 TRANSFER TO FMT SHORING AND FORMWORKS


FOR PEDESTAL

INSTALLATION OF VERTICAL BARS @ GL N/ 24, E /


6 STEELMAN 2
22

INSTALLATION OF U-BAR, FIXATION OF ANCHOR


10 STEELMAN 2 BOLT @ GL E/26-28 N31 AND INSTALLATION OF
FTB TIES GL N/23-24

FEEDMILL TOWER
1 FOREMAN
3 WELDER
1 HELPER
1 PAINTER 6 FORMWORKS FOR PEDESTAL 1ST LIFT 2ND BATCH
1 PLUMBER (TARGET: 5 COLUMNS)
1 PURCHASER
1 TINSMITH
3 WELDER 2
1 LEADMAN
INSTALLATION OF SHORING FORM (TARGET: 3
3 STEELMAN 4
SPAN)
2 HELPER
4 CARPENTER/MASON
TIEROD AND VERTICAL BRACING INSTALLATION @
2 HELPER 4 GL 15-17 (OUTSIDE) TARGET: 5 SPAN
1 PAINTER
1 LEADMAN
4 CARPENTER/MASON 4 ALIGNMENT OF FORMWORKS FOR RET WALL @ GL
15-17 (OUTSIDE) TARGET: 4 SPAN
2 HELPER
1 FOREMAN
1 LEADMAN HAULING AND ASSIST IN VERTICAL BRACING AND
6 ALIGNMENT OF FORMWORKS @ GL 15-17
3 HELPER (TARGET: 4 SPAN)
1 CARPENTER/MASON
1 LEADMAN INSTALLATION OF H-FRAME FOR RET WALL
7 SCAFFOLDER 2 PEDESTAL FORMWORK WORKING PLATFORMS
3 HELPER (TARGET: 2 PEDESTAL AND 2 SPAN RET WALL)
1 LEADMAN
4 CARPENTER/MASON 4 INSTALLATION OF BRACING , TIE ROD AND
SHORING FOR RET WALL (TARGET: 5 SPAN)
6 HELPER
6 STEELMAN 2 BACKFILLING AND COMPACTION AT GL D AND 21
(1ST LAYER)
8 STEELMAN 2
HAULING OF GI PIPE AND SHORING FOR RET WALL
1 STEELMAN
6 60 PCS)
1 FOREMAN
4 CARPENTER/MASON
4 INSTALLATION OF TIE ROD AND SHORING FOR RET
3 HELPER
WALL (TARGET: 5 SPAN)
2 CARPENTER/MASON 2
1 FOREMAN
INSTALLTION OF BRACING, SHORING AND TIE ROD
5 HELPER 2 FOR RET WALL (TARGET: 2 SPAN)
3 CARPENTER/MASON
INDIRECT SUPPORT
2 DT Driver
2 OPERATOR 6 HAULING OF GOOD SOIL FROM SEASIDE TO FGWH
4 SPOTTER
2 DRIVER
4pm-Onwards SERVICE OF MANPOWER/STAFF
1 DRIVER )(OBT TO DARA)
1 ASST MECHANIC 2 EQUIPMENT REPAIRING AND MONITORING
1 FUELMAN/HELPER 2 MONITORING OF FUEL CONSUMABLE
1 DRIVER
2 HAULING OF MATERIAL
2 RIGGER
1 OPERATOR
1 SPOTTER 2 CONCRETE CURING DUST CONTROL AT SITE
1 RIGGER

MONITORING OF WAREHOUSE RELEASING AND


1 WAREHOUSE ASSIST 3
RECEIVING MATERIALS EQUIPMENT AND TOOLS

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 19, 2021 MONDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
1 FOREMAN
6 BACKFILLING AND COMPACTION AT LINE 39
5 HELPER
FEEDMILL TOWER
2 FOREMAN
1 TINSMITH
1 PLUMBER FORMWORK INSTALLATION FOR PEDESTAL 2ND
6 LIFT
6 WELDER
1 STEELMAN
5 HELPER
1 LEADMAN FORMWORK BRACING AND INSTALLATION OF TIE
6 2 CARPENTER/MASON 2 FORMWORKS, BRACING AND TIE ROD
1 STEELMAN ROD
2 CARPENTER
1 LEADMAN
3 HELPER INSTALLATION OF FORMWORK FOR RETAINING 3 HELPER
6 6 INSTALLATION FOR RET WALL INSIDE GL 14-17
4 CARPENTER/MASON WALL 2 CARPENTER/MASON
1 FOREMAN 1 GEN FOREMAN
1 LEADMAN
2 SCAFFOLDER 2 INSTALLATION OF SCAFFOLD AND PLATFORM FOR
ACCESS
3 HELPER
1 FOREMAN
2 STRUCTURAL FITTER
4 DISMANTLING OF GI PIPE
5 WELDER
3 HELPER
1 LEADMAN HAULING AND INSTALLATION OF SHORING FOR 26 STEELMAN 2 FABRICATION OF REBARS FOR FTB/HAULING
6 RET WALL PIPES FOR SHORING
34 STEELMAN 9 STEELMAN 6
14 CARPENTER/MASON
2 LEADMAN INSTALLATION OF BRACING AND SHORING FOR
2
1 STEELMAN RET WALL
7 HELPER
1 FOREMAN
4 FABRICATION OF TIE ROD
1 WELDER
3 WELDER
2 STRUC.F/WELDER 2
1 HELPER/WELDER
1 FOREMAN/WELDER FABRICATION AND INSTALLATION OF STEEL
FORMS
1 LEADMAN/WELDER
8
2 WELDER
1 HELPER/WELDER
1 LEADMAN
3 CARPENTER/MASON 2 INSTALLATION OF INNER AND OUTER BRACE
FOR GRIDLINE H15-N15
5 HELPER
3 CARPENTER/MASON INSTALLATION OF INNER AND OUTER BRACE
2
1 HELPER FOR GRIDLINE F-H/15-17
1 CARPENTER/MASON
2
1 HELPER
1 CARPENTER/MASON INSTALLATION OF INNER AND OUTER BRACE
FOR GRIDLINE GRID D-N/14
5 HELPER 6
1 STEELMAN
INDIRECT SUPPORT
1 FUEL MAN MONITORING OF FUEL
3 ELECTRICIAN MONITORING AND MAINTENANCE OF POWER
1 LEADMAN SUPPLY AND LIGHTING
1 LEADMAN
2 WELDER
ASSIST IN GATE RELOCATION
1 STEELMAN
1 HELPER
2 DT DRIVER
2 BACKHOE OPERATOR HAULING OF BOULDERS FROM SEASIDE TO
6
DUMPING AREA
2 SPOTTER
2 RIGGER
2 SPOTTER 6 LIFTING/HAULING OF MATERIALS
2 OPERATOR
3 SERVICE DRIVER
1 UTILITY

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 18, 2021 SUNDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
4 HELPER 2 BACKFILLING AND COMPACTION AT LOADING BAY

4 STEELMAN 2 REBAR FOOTING AND VERTICAL BARS AT GL. N/24


9 STEELMAN INSTALLATION OF ANCHOR BOLT AND BENDING OF
2
1 FOREMAN VERTICAL AT GL. E/24 - 28
FEEDMILL TOWER
17 CARPENTER
9 HELPER INSTALLATION OF FORMWORKS, BRACING, TIE
1 LEADMAN ROD AND SHORING
1 FOREMAN
8 WELDER
3 FOREMAN
1 LEADMAN
INSTALLATION OF STEEL FORM AND SHORING FOR
1 TINSMITH 2ND BATCH PEDESTAL (1ST LIFT)
1 PLUMBER
1 STEELMAN
1 PAINTER
3 CARPENTER
INSTALLATION OF BRACING FOR RER WALL
1 HELPER
5 STEELMAN INSTALLATION OF SHORING FOR RET WALL
1 FOREMAN
3 CARPENTER INSTALLATION OF FORMWORKS AND SHORING
FOR PEDESTALS
2 HELPER
1 LEADMAN
6 SCAFFOLDER INSTALLATION OF SCAFFOLDS AND PLATFORM FOR
ACCESS
3 HELPER
RAW MATERIALS WAREHOUSE
FABRICATION OF FTB REBARS FOR GL. 14'/A TO D
14 STEELMAN AND INSTALLATION OF PEDESTAL TIES AND
ANCHOR BOLT SETTING AT GL. G13

INDIRECT SUPPORT
CONCRETE CURING MONITORING OF PEDESTALS
AT FMT, SOG AT RMWH

SITE AND WAREHOUSE


2 WAREHOUSEMAN
MONITORING/TOOLKEEPING
1 LEADMAN MONITORING AND MAINTENANCE OF POWER
1 ELECTRICIAN SUPPLY
1 TIMEKEEPER MONITORING OF MANPOWER
SERVICE OF EMPLOYEES AND HAULING OF
2 SERVICE DRIVER MATERIALS
1 FUEL MAN MONITORING OF FUEL
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 17, 2021 SATURDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
COMPACTION GL 39 (INSIDE) AND BACKFILLING AT
7 CARP/MASON 2
39 (OUTSIDE)

11 STEELMAN ALIGNMENT OF VERTICAL BARS PEDESTAL AND


2 INSTALLATION OF ANCHOR BOLT (TARGET: FINISH
1 FOREMAN ALIGNMENT OF VERTICAL BARS PEDESTAL)

3 CARP/MASON
INSTALLATION OF BRACING AND SHORING @ GL
2 17/ F-H FOR [Link] (TARGET : FINISH BRACING)
1 HELPER
2 CARP/MASON
1 STEELMAN 2 INSTALLATION OF BRACING AND SHORING @GL 14
(TARGET : FINISH BRACING)
2 SAFETYCREW

FOOTING REBAR AND VERTICAL BAR @ GL N /24


10 STEELMAN 2 AND COMPACTION (TARGET : 1 FOOTING
ACCOMPLISHMENT)

INSTALLATION OF TIES AND ANCHOR BOTS @ GL


3 STEELMAN 2 N31 AND N32 (TARGET : 2 PEDESTAL)

FEEDMILL TOWER
4 STEELMAN
2 WELDER 2 FORMWORKS AND BRACING INSTALLATION
(TARGET : HORIZONTAL @ GL14 / L-N)
2 HELPER
1 LEADMAN
2 CARP/MASON INSTALLATION OF BRACING AND SHORING FOR GL
2 14 RET. WALL (TARGET : FINISH BRACING)
1 FOREMAN
INDIRECT SUPPORT

MONITORING AND MAINTENANCE OF POWER


2 ELECTRICIAN 2 SUPPLY

2 OPERATOR BACKHOE
2 HAULING AT SEASIDE
2 DT DRIVER
2 DRIVER 2 SERVICE MANPOWER/STAFF
1 ASSIST MECHANIC 2 REPAIR EQUIPMENT
1 FUELMAN/HELPER 2 FUEL MONITORING AND CONSUMABLES

1 OPERATOR
2 DUSTCONTROL / CONCRETE POURING CURING

1 RIGGER
1 TIMEKEEPER 2 MONITORING OF MANPOWER

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 16, 2021 FRIDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
INSTALLATION AND FABRICATION OF U-BAR AT GL FABRICATION AND INSTALLATION OF U-BAR AT
9 STEELMAN 2 E/38-39 (TARGET: 2PEDESTAL) 9 STEELMAN 2 GL N/33-36 4 PEDESTAL

1 CARPENTER/MASON 2 1 LAYER COMPACTION


COMPACTION AND TAMPERING OF SOIL AT GL 39 5 CARPENTER/MASON 8 SOIL COMPACTION AT GL 39/E-N
3 CARPENTER/MASON 6
1 CARPENTER/MASON 2 INSTALLATION OF FORMS AT GL E38-39 (TARGET: 2
1 HELPER 2 FORMS INSTALLATION AT GL N/38 AND 39 2 PEDESTAL
1 HELPER 6 PEDESTAL)
FEEDMILL TOWER
3 STEELMAN 6
1 HELPER FORMWROKS INSTALLATION FOR RET WALL
(TARGET: 2 SPAN)
1 HELPER 2
1 LEADMAN
6
2 CARPENTER/MASON INSTALLATION OF FORMS FOR INSIDE WALL
3 HELPER PEDESTAL (TARGET: 3 PEDESTAL)
2
1 FOREMAN
1 LEADMAN
3 WELDER DISMANTLING OF FORMWORKS (TARGET: 10
4
1 SF/WLEDER PEDESTAL) (SHORING AND CUTTING OF REBARS
1 HELPER ON STEELFORMS)
1 WELDER 2
3 CARPENTER/MASON INSTALLATION OF FORMWORKS @ F15-F17, F17-
2
1 HELPER H17,H5-H17 (TARGET: 1 SPAN)
1 LEADMAN
6
1 SAFETY CREW/HELPER FORMWORKS @ GRID 14 (TARGET: 2 SPAN)
1 SAFETY CREW/HELPER 2
1 FOREMAN
2 WELDER
1 HELPER DISMANTLING AND INSTALLATION OF
6 FORMWORKS FOR PEDESTAL (STEEL FORMS)
1 PLUMBER (TARGET: 4 PEDESTAL)
1 PAINTER
1 TINSMITH
3 CARPENTER/MASON INSTALLATION OF FORMS @ D15, E15, F15 AND
2 J15 (TARGET: 1 SPAN)
2 HELPER
1 LEADMAN
1 STEELMAN 6 INSTALLATION OF FORMS @ GRID D4-M4
1 CARPENTER/MASON (TARGET:3 SPAN)
3 CARPENTER/MASON 2

INSTALLATION OF TIES AND HORIZONTAL BAR FOR


21 STEELMAN 2 ELEVATOR (TARGET: 2M HEIGHT REBAR ALL
PERIMETER)

1 LEADMAN
4 SCAFFOLDER HAULING GI SUPPORT AND INSTALLATION OF H-
2
FRAMES (TARGET: 1.5 SPAN)
3 HELPER
6 STEELMAN 2 FABRICATION OF REBAR FOR PEDESTAL TIES
2 SURVEY AIDE 2 STAKE OUT @ FMT AND LEVELING WORKS
INDIRECT SUPPORT
2 DT DRIVER 6
3 BACKHOE OPERATOR HAULING OF GOOD SOIL FROM SEASIDE TO FGWH
2 SPOTTER
1 OPERATOR 2
WATER DELIVERY/DUST CONTROL AT SITE
1 SPOTTER
1 HELPER/ASST MECH. 2 EQUIPMENT CHECKING
4PM
3 DRIVER SITE SERVICE AND SERVICE STAFF AND MANPOWER
ONWARDS
1 ELECTRICIAN 6 MONITORING AND MAINTENANCE OF POWER
1 STEELMAN/ELECTRICIAN SUPPLY FOR OVERTIME WORK
1 FUEL MAN/HELPER 2 MONITORING OF FUEL CONSUMABLE
1 TIMEKEEPER 2 MONITORING OF MANPOWER

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 15, 2021 THURSDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE
3 CARPENTER/MASON 3 CARPENTER/MASON 2 FORMS INSTALLATION AT GL E/31 AND 32 2 PEDESTAL
DISMANTLING OF PEDESTAL FORMS (SPARE TIME
6 HELPER 2 BEFORE 6PM) INSTALLATION OF FORMWORKS AT 6 HELPER 2 3 PEDESTAL
DISMANTLING OF FORMS AT GL N/33, 36 AND
GL E31 AND E35 (TARGET: 2 PEDESTAL) 37
1 QCAIDE
1 FOREMAN INSTALLATION AND FABRICATION OF U-BAR AT GL INSTALLATION AND FABRICATION OF U-BAR AT
2 E31 AND E32 (TARGET: 2 PEDESTAL) 10 STEELMAN 2 GL E31 AND E32 3 PEDESTAL
10 STEELMAN
FEEDMILL TOWER

8 STEELMAN 2 BACKFILLING AND COMPACTION FOR PERIMETER 6 STEELMAN 2 COMPACTION ALONG GRID 21 AND D 1 LAYER
(TARGET:1LAYER)
1 LEADMAN 1 FOREMAN
2
3 CARPENTER/MASON DISMANTLING OF FORMWORKS FOR PEDESTAL 1 LEADMAN
2 DISMANTLING OF FORMS 4 PEDESTAL
(TARGET: 4 PEDESTAL) 4 CARPENTER/MASON
4 WELDER
1 LEADMAN
4 WELDER
1 STRUCTURAL FITTER 4 DISMANTLING OF FORMWORKS FOR PEDESTAL GL-18 (D,E,F) 19(F,G,H)
1ST BATCH 20(E,F,G) AND 21(E,F,G)
1 HELPER
2 ELECTRICIAN
3 WELDER DISMANTLING OF BRACING FOR PEDESTAL
2
1 HELPER (TARGET: 4 PEDESTAL)
1 LEADMAN 1 LEADMAN
3 CARPENTER/MASON FORMWORKS INSTALLATION FOR RET WALL 11 CARPENTER/MASON
2 2 INSTALLATION OF FORMWORKS FOR RETWALL
(TARGET: 1 SPAN 6M)
1 STEELMAN 5 HELPER
INSTALLATION OF TIES FOR 2ND LIFT (TARGET: 2
10 STEELMAN 2 10 STEELMAN 2 INSTALLATION OF REBAR TIES 4 PEDESTAL TIES
PEDESTAL)
1 LEADMAN
1 STEELMAN 2 TURCO APPLICATION AND ALIGNMENT GRID 14
3 CARPENTER/MASON
1 FOREMAN
1 LEADMAN INSTALLATION OF INSIDE FORMWORKS FOR
6 1 SIDE-11 SPAN FORMWORKS
2 CARPENTER/MASON PEDESTAL AT RET WALL
3 HELPER
RAW MATERIALS WAREHOUSE
1 FOREMAN
2 WELDER FABRICATION OF SUPPORT FOR VERTICAL PIPING
2
1 PLUMBER AT GL G/2 (TARGET:4 SETS)
1 HELPER
1 PAINTER
2 PRIMER COAT PAINTING PIPING
1 TINSMITH

1 ELECTRICIAN MONITORING AND MAINTENANCE OF POWER


2
1 CARPENTER/ELECTRICIAN SUPPLY
HAULING OF MATERIALS AT SITE/SERVICE
2 DRIVER 2
MANPOWER AND STAFF
ASSIST CHIEF MECHANIC FOR CHECK-UP
1 ASSIST MECHANIC 2 EQUIPMENT
1 FUELMAN/HELPER 2 MONITORING OF FUEL CONSUMABLE
1 OPERATOR 5 TONNER
2 DUST CONTROL AT SITE
1 RIGGER
3 OPERATOR
2 HAULING OF GOOD SOIL FROM SEASIDE TO FGWH
1 DT DRIVER

1 TIMEKEEPER 2 MONITORING AND TIMEKEEPING OF MANPOWER

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 14, 2021 WEDNESDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FEEDMILL TOWER
11 STEELMAN INSTALLATION OF TIES FOR PEDESTAL (TARGET : 2
2
1 LEADMAN PEDESTAL)
5 STEELMAN FABRICATION OF REBAR FOR PEDESTAL TIES (100
2 PCS. OUTER TIES HAULING, CUTTING AND
1 LEADMAN FABRICATE
1 LEADMAN
1 STEELMAN 2 INSTALLATION OF FORMWORKS FOR RET. WALL
(FINISH INSIDE FORM)
3 CARP/MASON
1 LEADMAN
1 FOREMAN DISMANTLING OF SHORING FOR PEDESTAL
2 (TARGET : 8 PEDESTAL)
3 CARP/MASON
3 WELDER
RAW MATERIALS WAREHOUSE
BACKFILLING COMPACTION FOR TRENCH CANAL
3 CARP/MASON 2
GL A (TARGET : 3 SPAN)
3 CARP/MASON
1 HELPER RCP AND CRADLE INSTALLATION GL G/12 TARGET :
2 3 SETS GROUTING OF PEDESTAL TO STEEL
1 LEADMAN COLUMN GL A TARGET : COMPLETE TODAY
1 FOREMAN
1 OPERATOR 2 ASSIST BACKFILLING IN RCP INSTALLATION
1 FOREMAN
2 WELDER 2 FABRICATION OF VERTICAL PIPING SUPPORT FOR
GL / 2 (TARGET : 5 SETS)
1 HELPER
1 TINSMITH INSTALLATION OF 6 DP PIPING GUTTER TO
2
1 PLUMBER RUNNER (TARGET : 2 SETS)
INDIRECT SUPPORT
1 OPERATOR WATER CURING FOR ALL FRESH POURING AT
2 INTAKE RAWMAT
2 SPOTTER

SITE SERVICE AND SERVICE OF MANPOWER AND


3 DRIVER 2 STAFF

1 CARP/MASON-ELECT
6 MONITORING AND MAINTENANCE OF POWER
1 ELECTRICIAN SUPPLY FOR OVERTIME WORK

1 TIMEKEEPER 2 MONITORING OF MANPOWER


PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 12, 2021 MONDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
MANPOWER POSITION NO. OF HRS SCOPE OF WORK MANPOWER POSITION NO. OF HRS SCOPE OF WORK

FEEDMILL TOWER
1 LEADMAN
2 INSTALLATION OF TIES FOR PEDESTAL 2ND LIFT (5
PEDESTAL TARGET)
21 STEELMAN
3 CARP/MASON
1 STEELMAN FORMWORKS INSTALLATION FOR RET. WALL
2
1 LEADMAN ( TARGET 1 SPAM 1 SIDE ONLY)
1 HELPER
RAW MATERIALS WAREHOUSE
1 OPERATOR BACKFILLING OF SOIL FOR ISOLATED FOOTING
2 ( TARGET 5 ISOLATED FOOTING 2ND LAYER
2 SAFETYCREW BACKFILL)

1 LEADMAN
BACKFILLING FOR ELEVATION 2ND LAYER
4 HELPER ISOLATED COLUMN (TARGET 2ND LAYER 4
2 ISOLATED FOOTING BACKFILLING AND LEVELING
COMPLETE)
2 CARP/MASON

3 CARP/MASON BACKFILLING OF SOIL FOR ELEVATION TRENCH


2 CANAL OUTSIDE GL A / 2-14 (TARGET 4SPAN OF
6M 300MM MANUAL BACKFILL LEVELING GL A /2-
1 FOREMAN 6)

3 CARP/MASON BACKFILLING OF SOIL 20CM FIRSTLAYER @ GL 2 /


2 A-G (TARGET 5 SPAN OF 6M 150MM BACKFILL @
1 HELPER GL B-G /2)
1 FOREMAN
4 WELDER INSTALLATION OF DOWNSPOUT PIPING RUNNER
TO GUTTER (TARGET 5 SETS COMPLETE) AND
1 PLUMBER
2
1 TINSMITH INSTALLATION OF FRAME AND TEMPLATE FOR
ANCHOR BOLT SETTING GL G /13( TARGET :
1 PAINTER COMPLETE TODAY)
INDIRECT SUPPORT
2 OPERATOR
HAULING AND DISPOSAL OF SOIL
1 DT DRIVER 2
1 HELPER/ASSIST MECHANIC 15 TONNER REPAIR
2 DRIVER 2
SERVICE MANPOWER/STAFF
1 DRIVER 6
1 FUELMAN /HELPER 2 MONITORING OF FUEL CONSUMABLES
ESTABLISH REFERENCE ELEVATION AT FINISHED
3 SURVEY AIDE 2 GOODS WAREHOUSE

1 ELECTRICIAN 6 MONITORING AND MAINTENANCE OF POWER


SUPPLY FOR OVERTIME WORK

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC
PROJECT TITLE: SMFI 120TPH MABINI FEEDMILL PROJECT
SUJECT: OVERTIME ACCOMPLISHMENT REQUEST

DATE: APRIL 11, 2021 SUNDAY


TARGET ACTUAL REMARKS
NO. OF NO. OF
POSITION NO. OF HRS SCOPE OF WORK POSITION NO. OF HRS SCOPE OF WORK
MANPOWER MANPOWER
FINISHED GOODS WAREHOUSE

INSTALLATON OF ANCHOR BOLT AND TIES AT GL


10 STEELMAN 8 39/F FOR ACCOMPLISHMENT:4PEDESTAL 9 STEELMAN 8 INSTALLATION OF ANCHOR BOLT AND 2 PEDESTAL
INSTALLED FIXATION OF STIRRUPS AT GL 39/F-M

1 STEELMAN 1 STEELMAN
1 SCAFFOLDER
3 WELDER 3 WELDER
1 PAINTER INSTALLATON OF ANCHOR BOLT TEMPLATE AT GL 1 PAINTER INSTALLATON OF ANCHOR BOLT TEMPLATE AT
8 39/F-M AND GL E/24-28 FOR ACCOMPLISHMENT : 8 11 PEDESTAL
3 FOREMAN 14 PEDESTAL INSTALLED 1 FOREMAN GL 39/F-M; GL E/24-28; GL N/31-32
1 LEADMAN
1 PLUMBER 1 PLUMBER
1 TINSMITH 1 TINSMITH
1 QC AIDE INSTALLATION OF FORMWORKS FOR PEDESTAL AT 1 FOREMAN
6 CARPENTER/MASON 8 GL E FOR ACCOMPLISHMENT: 9 PEDESTALS WITH 5 CARPENTER/MASON 8 FORM PEDESTAL INSTALLATION AT GL E/31-39 7 PEDESTAL
1 HELPER FORMS AND BRACING 1 HELPER
WELDING WORKS FOR THE FIXATION OF FORM 1 FOREMAN
1 LEADMAN 1 LEADMAN FORM PEDESTAL FIXATION BRACING AT GL
8 FOR ACCOMPLISHMENT:16 PEDESTAL WITH 8 7 PEDESTAL
BRACING E/31-39
1 WELDER 2 STRUCTURAL FITTER
FEEDMILL TOWER
2 FOREMAN
10 CARPENTER/MASON FABRICATION AND INSTALLATION OF
15 HELPER 8 FORMWORKS FOR 2ND BATCH PEDESTALS (12
3 LEADMAN PEDESTALS 3 SIDE FORMWORKS)
1 PAINTER
1 FOREMAN
1 LEADMAN 8 INSTALLATION OF TIES AND HORIZONTAL BAR FOR 16 STEELMAN 2 INSTALLATION OF TIES AND HORIZONTAL BAR 8 SPAN-REBAR INSTALLATION
RET WALL (FINISH FIRST LIFT OF RETAINING WALL) FOR RET WALL FOR RETWALL
29 STEELMAN
1 LEADMAN/MC
5 CARPENTER/MASON RECTIFICATION OF ALIGNMENT FOR PEDESTAL
2 PRIOR TO CONCRETE POURING 2 SPAN ALIGNED
6 HELPER
1 LEADMAN/MC
5 CARPENTER/MASON RECTIFICATION OF ALIGNMENT FOR PEDESTAL
2 1 SIED=5 SPAN FORMWORKS
PRIOR TO CONCRETE POURING
6 HELPER
RAW MATERIALS WAREHOUSE
1 LEADMAN
4 STEELMAN 8 INSTALLATION OF REBARS FOR PEDESTAL AT LINE 1
(ADDITIONAL HEIGHT FOR P3 AT GRID 1)
2 HELPER

1 OPERATOR
8 SITE DUST CONTROL
2 SPOTTER
1 ASST MECHANIC 8 ASSIST CHIEF MECHANIC
1 FUEL ASST 8 FUEL MONITORING
1 HILUX DRIVER
8 SERVICE OF EMPLOYEES
1 NHR DRIVER
2 DT DRIVER
1 BACKHOE OPERATOR 8 HAULING OF SOIL AT SEASIDE
1 SPOTTER
MONITORING AND MAINTENANCE OF POWER
2 ELECTRICIAN 88 SUPPLY
2 WAREHOUSEMAN 8 SITE AND WAREHOUSE MONITORING
DISINFECTION AND GENERAL CLEANING AT
1 UTILITY 8 TEMFACIL
1 TIMEKEEPER 8 MONITORING OF MANPOWER
3 SURVEY AIDE 8 CHECKING OF PEDESTAL ALIGNMENT
2 SURVEY CREW 8 CLEARING AND HOUSEKEEPING AT SITE

PREPARED BY: CHECKED BY:


CHARLOTTE CORNELIO ANNA KARENINA MALABANAN
OE PC