Professional Documents
Culture Documents
COLUMN 1ST LIFT NOS 4 4 ACHIEVED PREPARATION FOR PCC BELOW GRADE SLAB
COLUMN 2ND LIFT NOS 4 4 ACHIEVED POUR-1 BASEMENT-3 SLAB CONCRETING CUM 535
###
LIFT WALL 1ST LIFT NOS 1 1 ACHIEVED PCC BELOW GRADE SLAB SQM 300
BLOCK-2 PCC CUM 20 0 NOT ACHIEVED ### POUR-2 SLAB BOTTOM MAT WORK
PCC BELOW GRADE SLAB SQM 350 350 ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
LIFT WALL 2ND LIFT NOS 1 1 ACHIEVED RETAINING WALL 1ST LIFT EAST SIDE CONCRETING RMT 20
COLUMN 1ST LIFT NOS 4 4 ACHIEVED RETAINING WALL 2ND LIFT WEST SIDE CONCRETING RMT 20
### FOOTING CONCRETING NOS 2 NOT ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 6
RETAINING WALL 2ND LIFT EAST SIDE RMT 20 10 ACHIEVED ### COLUMN 2ND LIFT CONCRETING NOS 4
RETAINING WALL 2ND LIFT WEST SIDE RMT 20 0 NOT ACHIEVED RETAINING WALL RAFT WEST SIDE RMT 10
COLUMN 2ND LIFT NOS 4 4 ACHIEVED PCC BELOW GRADE SLAB SQM 500
LIFT WALL 2ND LIFT NOS 1 1 ACHIEVED RETAINING WALL 1ST LIFT EAST SIDE CONCRETING RMT 20
COLUMN 1ST LIFT NOS 4 4 ACHIEVED PCC BELOW GRADE SLAB SQM 500
PCC BELOW GRADE SLAB SQM 350 20 ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
### ###
BLOCK-2 PCC CUM 20 NOT ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 6
RETAINING WALL EAST SIDE 1ST LIFT RMT 20 150 NOT ACHIEVED FOOTING EAST SIDE CONCRETING NOS 2
BACKFILLING CUM 150 150 ACHIEVED POUR-1 BASEMENT-2 TO BASEMENT-1 REINFORCEMENT WORK
COLUMN 2ND LIFT NOS 4 NOT ACHIEVEDD RETAINING WALL 2ND LIFT WEST SIDE CONCRETING RMT 20
PCC BELOW GRADE SLAB SQM 350 NOT ACHIEVED RETAINING WALL & RAMP WALL 1ST LIFT CONCRETING RMT 20
###
RETAINING WALL EAST SIDE 1ST LIFT RMT 20 NOT ACHIEVED ### PCC BELOW GRADE SLAB SQM 500
RETAINING WALL WEST SIDE 2ND LIFT RMT 20 NOT ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
COLUMN 1ST LIFT NOS 4 3 ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 4
COLUMN 2ND LIFT NOS 4 4 ACHIEVED RETAINING WALL WEST SIDE 1ST LIFT CONCRETING RMT 10
PCC BELOW GRADE SLAB SQM 350 NOT ACHIEVED RETAINING WALL & RAMP WALL 1ST LIFT CONCRETING RMT 10
###
RETAINING WALL EAST SIDE 2ND LIFT RMT 20 NOT ACHIEVED ### RETAINING WALL 2ND LIFT WEST SIDE CONCRETE RMT 20
RETAINING WALL WEST SIDE 2ND LIFT RMT 20 NOT ACHIEVED PCC BELOW GARDE SLAB SQM 500
BACKFILLING CUM 250 NOT ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 4
COLUMN LAPPING POUR -4 NOS 6
COLUMN SHUTTERING POUR-5 & DG AREA NOS 4
Sunday, October 2, 2022
SLAB SHUTTERING POUR-1 SQM 100
BACKFILLING CUM 150
COLUMN LAPPING POUR-6 NOS 4
FOOTING REINFORCEMENT - EAST SIDE NOS 3
Monday, October 3, 2022 RETAINING WALL LAPPING 1ST LIFT EAST SIDE RMT 10
COLUMN SHUTTERING POUR-4 NOS 4
LIFTWALL SHUTTERING 2ND LIFT POUR-5 NOS 1
SLAB SHUTTERING POUR-1 SQM 100
FOOTING REINFORCEMENT -EAST SIDE NOS 3
RETAINING WALL SHUTTERING 1ST LIFT EAST SIDE RMT 10
Tuesday, October 4, 2022 SLAB SHUTTERING POUR-1 SQM 100
LIFT REINFORCEMENT POUR-3 NOS 2
COLUMN REINFORCEMENT NOS 4
RAMP RAFT REINFORCEMENT RMT 10
FOOTING SHUTTERING EAST SIDE NOS 3
RETAINING WALL SHUTTERING 2ND LIFT WEST SIDE RMT 20
Wednesday, October 5, 2022 SLAB SHUTTERING POUR-1 SQM 100
LIFT WALL SHUTTERING 2ND LIFT NOS 2
COLUMN REINFORCEMENT 1ST LIFT NOS 4
RETAINING WALL SHUTTERING 1ST LIFT WEST SIDE RMT 20
Sunday, October 2, 2022 COLUMN LAPPING POUR -4 NOS 6
COLUMN SHUTTERING POUR-5 & DG AREA NOS 4
SLAB SHUTTERING POUR-1 SQM 100
BACKFILLING CUM 150
Monday, October 3, 2022 COLUMN LAPPING POUR-6 NOS 4
FOOTING REINFORCEMENT - EAST SIDE NOS 3
RETAINING WALL LAPPING 1ST LIFT EAST SIDE RMT 10
COLUMN SHUTTERING POUR-4 NOS 4
LIFTWALL SHUTTERING 2ND LIFT POUR-5 NOS 1
SLAB SHUTTERING POUR-1 SQM 100
Tuesday, October 4, 2022 FOOTING REINFORCEMENT -EAST SIDE NOS 3
RETAINING WALL SHUTTERING 1ST LIFT EAST SIDE RMT 10
SLAB SHUTTERING POUR-1 SQM 100
LIFT REINFORCEMENT POUR-3 NOS 2
COLUMN REINFORCEMENT NOS 4
Wednesday, October 5, 2022 RAMP RAFT REINFORCEMENT RMT 10
FOOTING SHUTTERING EAST SIDE NOS 3
RETAINING WALL SHUTTERING 2ND LIFT WEST SIDE RMT 20
SLAB SHUTTERING POUR-1 SQM 100
LIFT WALL SHUTTERING 2ND LIFT NOS 2
COLUMN REINFORCEMENT 1ST LIFT NOS 4
RETAINING WALL SHUTTERING 1ST LIFT WEST SIDE RMT 20
Sunday, October 2, 2022 COLUMN LAPPING POUR -4 NOS 6
COLUMN SHUTTERING POUR-5 & DG AREA NOS 4
SLAB SHUTTERING POUR-1 SQM 100
BACKFILLING CUM 150
Monday, October 3, 2022 COLUMN LAPPING POUR-6 NOS 4
FOOTING REINFORCEMENT - EAST SIDE NOS 3
RETAINING WALL LAPPING 1ST LIFT EAST SIDE RMT 10
COLUMN SHUTTERING POUR-4 NOS 4
LIFTWALL SHUTTERING 2ND LIFT POUR-5 NOS 1
SLAB SHUTTERING POUR-1 SQM 100
Tuesday, October 4, 2022 FOOTING REINFORCEMENT -EAST SIDE NOS 3
RETAINING WALL SHUTTERING 1ST LIFT EAST SIDE RMT 10
SLAB SHUTTERING POUR-1 SQM 100
LIFT REINFORCEMENT POUR-3 NOS 2
COLUMN REINFORCEMENT NOS 4
Wednesday, October 5, 2022 RAMP RAFT REINFORCEMENT RMT 10
FOOTING SHUTTERING EAST SIDE NOS 3
RETAINING WALL SHUTTERING 2ND LIFT WEST SIDE RMT 20
SLAB SHUTTERING POUR-1 SQM 100
LIFT WALL SHUTTERING 2ND LIFT NOS 2
COLUMN REINFORCEMENT 1ST LIFT NOS 4
RETAINING WALL SHUTTERING 1ST LIFT WEST SIDE RMT 20
24 SEP'2022 TO 30 SEP'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED STATUS PREVIOUS PLANNED DATES
### BACKFILLING CUM 300 300 ACHIEVED RETAINING WALL WEST SIDE SIDE RAFT RMT 9 9/19/2022
### BACKFILLING CUM 800 800 ACHIEVED COLUMN 1ST LIFT NOS 4 9/21/2022
1 ACHIEVED
LIFT WALL & STAIRCASE WALL - 2ND LIFT NOS 3 1 2 NOT ACHIEVED ### LIFT & SC WALL 1ST LIFT NOS 2
9/22/2022
COLUMN - 1ST LIFT NOS 4 4 ACHIEVED BACKFILLING CUM 150 9/21/2022
COLUMN-2ND LIFT NOS 6 6 ACHIEVED PCC BELOW GRADE SLAB SQM 150 9/23/2022
###
RETAINING WALL RAFT WEST SIDE RMT 10 NOT ACHIEVED COLUMN 2ND LIFT NOS 4 9/22/2022
21-09-2022,22-09-2022,23-09-
PCC BELOW GRADE SLAB SQM 225 225 ACHIEVED ### BACKFILLING CUM 600 2022
BACKFILLING CUM 300 300 ACHIEVED RETAINING WALL 1ST LIFT WEST SIDE RMT 20 21-09-202
COLUMN - 2ND LIFT NOS 6 6 ACHIEVED RETAINING WALL EAST SIDE RAFT RMT 9 9/20/2022
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 ACHIEVED FOOTING EAST SIDE NOS 2 9/23/2022
###
### RETAINING WALL RAFT EAST SIDE RMT 9 NOT ACHIEVED RETAINING WALL SOUTH SIDE 2ND LIFT RMT 15 9/21/2022
FOOTING EAST SIDE NOS 2 2 ACHIEVED COLUMN 2ND LIFT NOS 6 9/23/2022
BACKFILLING CUM 300 300 ACHIEVED LIFT WALL & SC WALL 2ND LIFT NOS 2 9/19/2022
2 ACHIEVED
COLUMN -1ST LIFT NOS 6 2 RETAINING WALL 1ST LIFT EAST SIDE RMT 20
4 NOT ACHIEVED 9/22/2022
LIFT WALL & STAIRCASE WALL -1ST LIFT NOS 2 2 ACHIEVED COLUMN 1ST LIFT RMT 4 9/23/2022
### RETAINING WALL 1ST LIFT WEST SIDE RMT 15 NOT ACHIEVED ### LIFT WALL& SC WALL 1ST LIFT NOS 2
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 NOT ACHIEVED RAMP RAFT RMT 20
FOOTING EAST SIDE NOS 2 2 ACHIEVED FOOTING EAST SIDE NOS 2
BACKFILLING CUM 300 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 300
COLUMN -2ND LIFT NOS 8 4 COLUMN 2ND LIFT NOS 6
RETAINING WALL 1ST LIFT EAST SIDE RMT 20 NOT ACHIEVED LIFT WALL & SC WALL 2ND LIFT NOS 2
ACHIEVED
FOOTING EAST SIDE NOS 2 2 RETAINING WALL WEST SIDE 2ND LIFT RMT 20
9/22/2022
###
RETAINING WALL 2ND LIFT WEST SIDE RMT 20 NOT ACHIEVED RETAINING WALL WEST SIDE 1ST LIFT RMT 19 9/22/2022
###
LIFT WALL & STAIRCASE WALL 1ST LIFT NOS 3 1 1 ACHIEVED BACKFILLING CUM 300
2 NOT ACHIEVED
RETAINING WALL WEST SIDE 1ST LIFT RMT 20 NOT ACHIEVED COLUMN 1ST LIFT NOS 4
PCC BELOW GRADE SLAB SQM 500 500 ACHIEVED RETAINING WALL 1T LIFT EAST SIDE RMT 12
BACKFILLING CUM 300 NOT ACHIEVED RETIING WALL 2ND LIFT WEST SIDE RMT 20 9/23/2022
FOOTING EAST SIDE NOS 2 NOT ACHIEVED LIFT WALL & SC WALL 1ST LIFT NOS 2
###
COLUMN 1ST LIFT NOS 6 NOT ACHIEVED COLUMN 2ND LIFT NOS 6
COLUMN 2ND LIFT NOS 6 NOT ACHIEVED FOOTING EAST SIDE NOS 2
RETAINING WALL EAST SIDE 1ST LIFT RMT 25 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 500
### RETAINING WALL WEST SIDE 2ND LIFT RMT 20 NOT ACHIEVED RETIING WALL 2ND LIFT WEST SIDE RMT 20
LIFT WALL & STAIRCASE WALL -2ND LIFT NOS 2 NOT ACHIEVED COLUMN 1ST LIFT NOS 4
PCC BELOW GRADE SLAB SQM 500 350 350 ACHIEVED COLUMN 2ND LIFT NOS 6
150 NOT ACHIEVED
###
BACKFILLING CUM 300 300 NOT ACHIEVED LIFT & SC WALL 2ND LIFT NOS 2
EXTRA ACHIEVED RAMP RAFT RMT 15 ACHIEVED FOOTING EAST SIDE NOS 3
PCC BELOW GARDE SLAB SQM 500
BACK FILLING CUM 300
### RETAINING WALL 1ST LIFT WEST SIDE RMT 15 16TH SEP 2022
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 16TH SE 2022
FOOTING EAST SIDE NOS 2 2 ACHIEVED
BACKFILLING CUM 300
COLUMN -2ND LIFT NOS 8 2
RETAINING WALL 1ST LIFT EAST SIDE RMT 20 15TH SEP 2022
FOOTING EAST SIDE NOS 2 1
RETAINING WALL 2ND LIFT WEST SIDE RMT 20
###
LIFT WALL & STAIRCASE WALL 1ST LIFT NOS 3 1 15TH SEP 2022
RETAINING WALL WEST SIDE 1ST LIFT RMT 20 16TH SEP 2022
PCC BELOW GRADE SLAB SQM 500 500 ACHIEVED
BACKFILLING CUM 300
FOOTING EAST SIDE NOS 2
COLUMN 1ST LIFT NOS 6
COLUMN 2ND LIFT NOS 6
RETAINING WALL EAST SIDE 1ST LIFT RMT 25
###
RETAINING WALL WEST SIDE 2ND LIFT RMT 20
LIFT WALL & STAIRCASE WALL -2ND LIFT NOS 2
PCC BELOW GRADE SLAB SQM 500 122
BACKFILLING CUM 300 300
EXTRA ACHIEVED RAMP RAFT RMT 15 ACHIEVED
RETAINING WALL WEST SIDE RMT 10 10 Achieved 5TH SEP 2022 ### BACKFILLING CUM 300 16TH SEP 2022
###
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 10 10 Achieved 3RD SEP 2022 ### BACKFILLING CUM 800
COLUMN - 1ST LIFT NOS 6 6 Achieved 8TH SEP 2022 LIFT WALL & STAIRCASE WALL - 2ND LIFT NOS 3
COLUMN- 1ST LIFT NOS 6 6 Achieved COLUMN - 1ST LIFT NOS 4
### COLUMN - 2ND LIFT NOS 4 4 Achieved 7TH SEP 2022 COLUMN-2ND LIFT NOS 6
FOOTING WEST SIDE NOS 2 3 Achieved 6TH SEP 2022 ### RETAINING WALL RAFT WEST SIDE RMT 10 15TH SEP 2022
1Achieved
LIFT WALL & STAIRCASE WALL POUR-3 NOS 3 1 8TH SEP 2022 PCC BELOW GRADE SLAB SQM 225
2 Not Achieved
COLUMN - 1ST LIFT NOS 6 6 Achieved BACKFILLING CUM 300
###
RETAINING WALL RAFT WEST SIDE RMT 20 20 Achieved 6TH SEP 2022 COLUMN - 2ND LIFT NOS 6
RETAINING WALL WEST SIDE 1ST LIFT RMT 10 0 RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 14TH SEP 2022
COLUMN - 2ND LIFT NOS 8 8 Achieved 8TH SEP 2022 & 9TH SEP 2022 ### RETAINING WALL RAFT EAST SIDE RMT 9 16TH SEP 2022
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 Achieved 5TH SEP 2022 FOOTING EAST SIDE NOS 2 14TH SEP 2022
### RETAINING WALL WEST SIDE 2ND LIFT RMT 15 15 Achieved BACKFILLING CUM 300
FOOTING EAST SIDE NOS 2 2 Achieved 9TH SEP 2022 COLUMN -1ST LIFT NOS 6
BACKFILLING CUM 300 300 Achieved 4TH SEP 2022 LIFT WALL & STAIRCASE WALL -1ST LIFT NOS 2 12TH SEP 2022
COLUMN 1ST LIFT NOS 4 4 Achieved ### RETAINING WALL 1ST LIFT WEST SIDE RMT 15 16TH SEP 2022
COLUMN 2ND LIFT NOS 6 6 Achieved RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 16TH SE 2022
### FOOTING EAST SIDE NOS 2 0 Not Achieved FOOTING EAST SIDE NOS 2
RETAINING WALL RAFT EAST SIDE RMT 20 20 Achieved BACKFILLING CUM 300
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 15 Not Achieved 7TH SEP 2022 COLUMN -2ND LIFT NOS 8
BACKFILLING CUM 300 300 Achieved 5TH SEP 2022 RETAINING WALL 1ST LIFT EAST SIDE RMT 20 15TH SEP 2022
COLUMN 1ST LIFT NOS 6 6 Achieved FOOTING EAST SIDE NOS 2
RETAINING WALL RAFT WEST SIDE RMT 15 20 Achieved RETAINING WALL 2ND LIFT WEST SIDE RMT 20
###
### RETAINING WALL EAST SIDE 1ST LIFT RMT 20 0 Not Achieved LIFT WALL & STAIRCASE WALL 1ST LIFT NOS 3 15TH SEP 2022
LIFT WALL & STAIRCASE WALL- POUR-3 NOS 3 0 Not Achieved 9TH SEP 2022 RETAINING WALL WEST SIDE 1ST LIFT RMT 20 16TH SEP 2022
BACKFILLING CUM 300 0 Not Achieved 6TH SEP 2022 PCC BELOW GRADE SLAB SQM 500
COLUMN - 2ND LIFT NOS 8 8 Achieved BACKFILLING CUM 300
FOOTING EAST SIDE NOS 2 0 Not Achieved FOOTING EAST SIDE NOS 2
RETAINING WALL RAFT EAST SIDE RMT 15 15 Not Achieved COLUMN 1ST LIFT NOS 6
###
RETAINING WALL WEST SIDE 1ST LIFT RMT 20 0 Not Achieved COLUMN 2ND LIFT NOS 6
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 Achieved RETAINING WALL EAST SIDE 1ST LIFT RMT 25
###
BACKFILLING CUM 300 0 Not Achieved 7TH SEP 2022 RETAINING WALL WEST SIDE 2ND LIFT RMT 20
STORMWATER TANK WALL CUM 6 Achieved LIFT WALL & STAIRCASE WALL -2ND LIFT NOS 2
COLUMN-1ST LIFT NOS 4 PCC BELOW GRADE SLAB SQM 500
Extra Achieved
LIFT WALL POUR-1 - 2ND LIFT NOS 1 BACKFILLING CUM 300
POUR-1 STAIRCASE & R/W NOS 1
10 SEP'2022 TO 16 SEP'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED STATUS PREVIOUS PLANNED DATES
RETAINING WALL RAFT WEST SIDE & FOOTING 10RMT 15 CUM Achieved
RETAINING WALL RAFT WEST SIDE & FOOTING 10RMT 15 CUM Not Achieved
### COLUMN 1ST LIFT 4 NOS 20CUM Achieved 30-Aug-22
RETAINING WALL 2ND LIFT 20 RMT 6 CUM Achieved 1-Sep-22
TOWER CRANE FOOTING 1 NO 50 CUM Achieved
### COLUMN 1ST LIFT 2 NOS 12 CUM Achieved 2-Sep-22
BACKFILLING 2ND LAYER 300 CUM Not Achieved
RETAINING WALL WEST SIDE 10MTS 12 CUM Not Achieved
COLUMN 1ST LIFT 4 NOS 24 CUM Achieved 2-Sep-22
###
RETAINING WALL 2ND LIFT SOUTH SIDE 20 MTS 6 CUM Not Achieved
BACK FILLING 2ND LAYER 300CUM Not Achieved
COLUMN - 2ND LIFT 6 NOS 6 CUM Achieved
ISOLATED FOOTING EASTISIDE 2 NOS 25 CUM Not Achieved
###
RETAINING WALL RAFT WEST SIDE 20 MTS 10CUM Not Achieved
BACK FILLING 2ND LAYER 300 CUM Not Achieved
POUR-1 LIFT WALL 1 NOS 18 CUM Achieved
COLUMN 1ST LIFT 4 NOS 24 CUM Achieved
### 2 Achieved
COLUMN 2ND LIFT 6 NOS 6 CUM
4 Not Achieved
RETAINING WALL 2ND LIFT SOUTH SIDE 15 MTS 4.5 CUM Not Achieved
BACK FILLING 2ND LAYER & COMPACTION 300CUM Not Achieved
15 RMT 6 CUM
300 CUM
2NOS 12 CUM 24-Aug-22
400 CUM
2 NOS 5 CUM
4 NOS 24 CUM 25-Aug-22 & 26-Aug-22
2 Nos 40 CUM
300 CUM
4 NOS 24 CUM
10 RMT 5 CUM
300 CUM
GANESH CHATURTHI
6 NOS 36 CUM
20RMT 8 CUM
300 CUM
2 NOS 35 CUM
6 NOS 36 CUM
15 RMT 7 CUM
300 CUM
LOOKAHEAD SCHEDULE
08 AUG'2022 TO 13 AUG 2022
DATE ACTIVITIES QTY ACHIEVED
8-Aug-22 BLOCK -1 RAFT POUR-5 589 cum
BLOCK -1 RAFT CAP POUR-5 , 92 cum
9-Aug-22
ISOLATED FOOTINGS Not Achieved
11-Aug-22 20 cum
RETAINING WALL SOUTH SIDE
RETAINING WALL
###
PART-1 BACK FILLING
###
POUR-1 TOWER COLUMN
12 CUM
100 CUM
25CUM
100 CUM
75CUM
20 CUM
150CUM
35CUM
150CUM
10 CUM
40 CUM
150CUM
50CUM
30CUM
150CUM
35CUM
15 CUM
150CUM
LOOKAHEAD SCHEDULE
13 AUG'2022 TO 19 AUG 2022
DATE ACTIVITIES