22 Oct'2022 TO 28 Oct'2022

DATE ACTIVITIES UOM PLANNNED QTY


COLUMN 1ST LIFT CONCRETING NOS 2
PCC BELOW GRADE SLAB SQM 500
### POUR-5 FORMWORK
STORMWATER TANK-2 WALL CUM 15
POUR-2 SLAB CHECKIN
POUR-2 SLAB CONCRETING CUM 330
###
POUR-5 FORMWORK
COLUMN 1ST LIFT CONCRETING NOS 2

COLUMN 2ND LIFT CONCRETING NOS 4


### NOS 2
FOOTING PCC
PCC BELOW GRADE SLAB SQM 500
POUR-5 FORMWORK
COLUMN 1ST LIFT CONCRETING NOS 2

COLUMN 2ND LIFT CONCRETING NOS 4

### RETAINING WALL EAST SIDE 1ST LIFT CONCRETING RMT 20


RETAINING WALL WEST SIDE 2ND LIFT CONCRETING RMT 20
PCC BELOW GRADE SLAB SQM 500
POUR-5 FORMWORK
FOOTING REINFORCEMENT & SHUTTERING NOS 2
COLUMN 1ST LIFT SHUTTERING NOS 4
RETAINING WALL SHUTTERING NOS 4
###
POUR-5 BOTTOM REINFORCEMENT
POUR-5 FORMWORK
POUR-3 FORMWORK
FOOTING CONCRETE NOS 2
COLUMN 1ST LIFT CONCRETING NOS 4
COLUMN 2ND LIFT CONCRETING NOS 4
###
PCC BELOW GRADE SLAB SQM 500
POUR-5 BOTTOM REINFORECEMENT
POUR-3 FORMWORK
RETAINING WALL WEST SIDE 1ST LIFT RMT 10
RETAINING WALL EAST SIDE 2ND LIFT RMT 20
PCC BELOW GRADE SLAB SQM 500
### COLUMN 1ST LIFT CONCRETING NOS 4
COLUMN 2ND LIFT CONCRETING NOS 4
POUR-5 BOTTOM REINFORECEMENT
POUR-3 FORMWORK
15 Oct'2022 TO 21 Oct'2022 22 Oct'2022 TO 28 Oct'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED QTY STATUS DATE ACTIVITIES UOM PLANNNED QTY
RETAINING WALL & RAMP EAST SIDE RAFT RMT 10 10 ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 2
FOOTING EAST SIDE NOS 1 1 ACHIEVED PCC BELOW GRADE SLAB SQM 500
### STORMWATER TANK-2 BASE SLAB NO 1 1 ACHIEVED ### POUR-5 FORMWORK
PCC BELOW GRADE SLAB SQM 300 0 NOT ACHIEVED STORMWATER TANK-2 WALL CUM 15
COLUMN 1ST LIFT CONCRETING NOS 4 4 ACHIEVED POUR-2 SLAB CHECKIN
BACKFILLING CUM 500 0 NOT ACHIEVED POUR-2 SLAB CONCRETING CUM 330
###
POUR-1 BASEMENT-3 ROOF SLAB CHECKING NO 1 1 ACHIEVED POUR-5 FORMWORK
###
POUR-2 SLAB BOTTOM REINFORCEMENT WORK ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 2
PREPARATION FOR PCC BELOW GRADE SLAB ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 4
POUR-1 BASEMENT-3 SLAB CONCRETING CUM 550 565 ACHIEVED ### NOS 2
FOOTING PCC
PCC BELOW GRADE SLAB SQM 300 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 500
### POUR-2 SLAB BOTTOM MAT WORK POUR-5 FORMWORK
COLUMN 1ST LIFT CONCRETING NOS 4 COLUMN 1ST LIFT CONCRETING NOS 2
RETAINING WALL 1ST LIFT EAST SIDE CONCRETING RMT 20 COLUMN 2ND LIFT CONCRETING NOS 4
RETAINING WALL 2ND LIFT WEST SIDE CONCRETING RMT 20 20 ACHIEVED ### RETAINING WALL EAST SIDE 1ST LIFT CONCRETING RMT 20
COLUMN 1ST LIFT CONCRETING NOS 6 2 ACHIEVED RETAINING WALL WEST SIDE 2ND LIFT CONCRETING RMT 20
### COLUMN 2ND LIFT CONCRETING NOS 4 0 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 500
RETAINING WALL RAFT WEST SIDE RMT 10 10 ACHIEVED POUR-5 FORMWORK
PCC BELOW GRADE SLAB SQM 500 500 ACHIEVED FOOTING REINFORCEMENT & SHUTTERING NOS 2
RETAINING WALL 1ST LIFT EAST SIDE CONCRETING RMT 20 20 ACHIEVED COLUMN 1ST LIFT SHUTTERING NOS 4
PCC BELOW GRADE SLAB SQM 500 500 ACHIEVED RETAINING WALL SHUTTERING NOS 4
###
COLUMN 1ST LIFT CONCRETING NOS 4 0 NOT ACHIEVED POUR-5 BOTTOM REINFORCEMENT
###
COLUMN 2ND LIFT CONCRETING NOS 6 0 NOT ACHIEVED POUR-5 FORMWORK
FOOTING EAST SIDE CONCRETING NOS 2 0 NOT ACHIEVED POUR-3 FORMWORK
POUR-1 BASEMENT-2 TO BASEMENT-1 REINFORCEMENT WORK IN PROGRESS FOOTING CONCRETE NOS 2
RETAINING WALL 2ND LIFT WEST SIDE CONCRETING RMT 20 0 NOT ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
RETAINING WALL & RAMP WALL 1ST LIFT CONCRETING RMT 20 0 NOT ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 4
###
### PCC BELOW GRADE SLAB SQM 500 0 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 500
COLUMN 1ST LIFT CONCRETING NOS 4 0 NOT ACHIEVED POUR-5 BOTTOM REINFORECEMENT
COLUMN 2ND LIFT CONCRETING NOS 4 0 NOT ACHIEVED POUR-3 FORMWORK
RETAINING WALL WEST SIDE 1ST LIFT CONCRETING RMT 10 0 NOT ACHIEVED RETAINING WALL WEST SIDE 1ST LIFT RMT 10
RETAINING WALL & RAMP WALL 1ST LIFT CONCRETING RMT 10 0 NOT ACHIEVED RETAINING WALL EAST SIDE 2ND LIFT RMT 20
### RETAINING WALL 2ND LIFT WEST SIDE CONCRETE RMT 20 0 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 500
PCC BELOW GARDE SLAB SQM 500 0 NOT ACHIEVED ### COLUMN 1ST LIFT CONCRETING NOS 4
COLUMN 2ND LIFT CONCRETING NOS 4 0 NOT ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 4
POUR-5 BOTTOM REINFORECEMENT
POUR-3 FORMWORK
08 Oct'2022 TO 14 Oct'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED QTY STATUS 15 Oct'2022 TO 21 Oct'2022
RETAINING WALL RAFT EAST SIDE RMT 10 10 ACHIEVED DATE ACTIVITIES UOM PLANNNED QTY
RETAINING WALL RAFT WEST SIDE RMT 10 0 NOT ACHIEVED RETAINING WALL & RAMP EAST SIDE RAFT RMT 10
### POUR-2 PCC BELOW GRADE SLAB SQM 350 350 ACHIEVED FOOTING EAST SIDE NOS 1
FOOTING STEP-2 NOS 2 2 ACHIEVED ### STORMWATER TANK-2 BASE SLAB NO 1
FOOTING PCC NO 1 1 ACHIEVED PCC BELOW GRADE SLAB SQM 300
BACKFILLING CUM 250 250 ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
POUR-1 SLAB BOTTOM REINFORCEMENT WORK ACHIEVED BACKFILLING CUM 500
### 10 POUR-1 BASEMENT-3 ROOF SLAB CHECKING
RETAINING WALL EAST SIDE REINFORCEMENT WORK RMT ACHIEVED NO 1
###
POUR-4 COLUMN SHUTTERING NOS 2 ACHIEVED POUR-2 SLAB BOTTOM REINFORCEMENT WORK

COLUMN 1ST LIFT NOS 4 4 ACHIEVED PREPARATION FOR PCC BELOW GRADE SLAB

COLUMN 2ND LIFT NOS 4 4 ACHIEVED POUR-1 BASEMENT-3 SLAB CONCRETING CUM 535
###
LIFT WALL 1ST LIFT NOS 1 1 ACHIEVED PCC BELOW GRADE SLAB SQM 300
BLOCK-2 PCC CUM 20 0 NOT ACHIEVED ### POUR-2 SLAB BOTTOM MAT WORK
PCC BELOW GRADE SLAB SQM 350 350 ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
LIFT WALL 2ND LIFT NOS 1 1 ACHIEVED RETAINING WALL 1ST LIFT EAST SIDE CONCRETING RMT 20
COLUMN 1ST LIFT NOS 4 4 ACHIEVED RETAINING WALL 2ND LIFT WEST SIDE CONCRETING RMT 20
### FOOTING CONCRETING NOS 2 NOT ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 6
RETAINING WALL 2ND LIFT EAST SIDE RMT 20 10 ACHIEVED ### COLUMN 2ND LIFT CONCRETING NOS 4
RETAINING WALL 2ND LIFT WEST SIDE RMT 20 0 NOT ACHIEVED RETAINING WALL RAFT WEST SIDE RMT 10
COLUMN 2ND LIFT NOS 4 4 ACHIEVED PCC BELOW GRADE SLAB SQM 500
LIFT WALL 2ND LIFT NOS 1 1 ACHIEVED RETAINING WALL 1ST LIFT EAST SIDE CONCRETING RMT 20
COLUMN 1ST LIFT NOS 4 4 ACHIEVED PCC BELOW GRADE SLAB SQM 500
PCC BELOW GRADE SLAB SQM 350 20 ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
### ###
BLOCK-2 PCC CUM 20 NOT ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 6
RETAINING WALL EAST SIDE 1ST LIFT RMT 20 150 NOT ACHIEVED FOOTING EAST SIDE CONCRETING NOS 2
BACKFILLING CUM 150 150 ACHIEVED POUR-1 BASEMENT-2 TO BASEMENT-1 REINFORCEMENT WORK
COLUMN 2ND LIFT NOS 4 NOT ACHIEVEDD RETAINING WALL 2ND LIFT WEST SIDE CONCRETING RMT 20
PCC BELOW GRADE SLAB SQM 350 NOT ACHIEVED RETAINING WALL & RAMP WALL 1ST LIFT CONCRETING RMT 20
###
RETAINING WALL EAST SIDE 1ST LIFT RMT 20 NOT ACHIEVED ### PCC BELOW GRADE SLAB SQM 500
RETAINING WALL WEST SIDE 2ND LIFT RMT 20 NOT ACHIEVED COLUMN 1ST LIFT CONCRETING NOS 4
COLUMN 1ST LIFT NOS 4 3 ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 4
COLUMN 2ND LIFT NOS 4 4 ACHIEVED RETAINING WALL WEST SIDE 1ST LIFT CONCRETING RMT 10
PCC BELOW GRADE SLAB SQM 350 NOT ACHIEVED RETAINING WALL & RAMP WALL 1ST LIFT CONCRETING RMT 10
###
RETAINING WALL EAST SIDE 2ND LIFT RMT 20 NOT ACHIEVED ### RETAINING WALL 2ND LIFT WEST SIDE CONCRETE RMT 20
RETAINING WALL WEST SIDE 2ND LIFT RMT 20 NOT ACHIEVED PCC BELOW GARDE SLAB SQM 500
BACKFILLING CUM 250 NOT ACHIEVED COLUMN 2ND LIFT CONCRETING NOS 4
COLUMN LAPPING POUR -4 NOS 6
COLUMN SHUTTERING POUR-5 & DG AREA NOS 4
Sunday, October 2, 2022
SLAB SHUTTERING POUR-1 SQM 100
BACKFILLING CUM 150
COLUMN LAPPING POUR-6 NOS 4
FOOTING REINFORCEMENT - EAST SIDE NOS 3
Monday, October 3, 2022 RETAINING WALL LAPPING 1ST LIFT EAST SIDE RMT 10
COLUMN SHUTTERING POUR-4 NOS 4
LIFTWALL SHUTTERING 2ND LIFT POUR-5 NOS 1
SLAB SHUTTERING POUR-1 SQM 100
FOOTING REINFORCEMENT -EAST SIDE NOS 3
RETAINING WALL SHUTTERING 1ST LIFT EAST SIDE RMT 10
Tuesday, October 4, 2022 SLAB SHUTTERING POUR-1 SQM 100
LIFT REINFORCEMENT POUR-3 NOS 2
COLUMN REINFORCEMENT NOS 4
RAMP RAFT REINFORCEMENT RMT 10
FOOTING SHUTTERING EAST SIDE NOS 3
RETAINING WALL SHUTTERING 2ND LIFT WEST SIDE RMT 20
Wednesday, October 5, 2022 SLAB SHUTTERING POUR-1 SQM 100
LIFT WALL SHUTTERING 2ND LIFT NOS 2
COLUMN REINFORCEMENT 1ST LIFT NOS 4
RETAINING WALL SHUTTERING 1ST LIFT WEST SIDE RMT 20
Sunday, October 2, 2022 COLUMN LAPPING POUR -4 NOS 6
COLUMN SHUTTERING POUR-5 & DG AREA NOS 4
SLAB SHUTTERING POUR-1 SQM 100
BACKFILLING CUM 150
Monday, October 3, 2022 COLUMN LAPPING POUR-6 NOS 4
FOOTING REINFORCEMENT - EAST SIDE NOS 3
RETAINING WALL LAPPING 1ST LIFT EAST SIDE RMT 10
COLUMN SHUTTERING POUR-4 NOS 4
LIFTWALL SHUTTERING 2ND LIFT POUR-5 NOS 1
SLAB SHUTTERING POUR-1 SQM 100
Tuesday, October 4, 2022 FOOTING REINFORCEMENT -EAST SIDE NOS 3
RETAINING WALL SHUTTERING 1ST LIFT EAST SIDE RMT 10
SLAB SHUTTERING POUR-1 SQM 100
LIFT REINFORCEMENT POUR-3 NOS 2
COLUMN REINFORCEMENT NOS 4
Wednesday, October 5, 2022 RAMP RAFT REINFORCEMENT RMT 10
FOOTING SHUTTERING EAST SIDE NOS 3
RETAINING WALL SHUTTERING 2ND LIFT WEST SIDE RMT 20
SLAB SHUTTERING POUR-1 SQM 100
LIFT WALL SHUTTERING 2ND LIFT NOS 2
COLUMN REINFORCEMENT 1ST LIFT NOS 4
RETAINING WALL SHUTTERING 1ST LIFT WEST SIDE RMT 20
Sunday, October 2, 2022 COLUMN LAPPING POUR -4 NOS 6
COLUMN SHUTTERING POUR-5 & DG AREA NOS 4
SLAB SHUTTERING POUR-1 SQM 100
BACKFILLING CUM 150
Monday, October 3, 2022 COLUMN LAPPING POUR-6 NOS 4
FOOTING REINFORCEMENT - EAST SIDE NOS 3
RETAINING WALL LAPPING 1ST LIFT EAST SIDE RMT 10
COLUMN SHUTTERING POUR-4 NOS 4
LIFTWALL SHUTTERING 2ND LIFT POUR-5 NOS 1
SLAB SHUTTERING POUR-1 SQM 100
Tuesday, October 4, 2022 FOOTING REINFORCEMENT -EAST SIDE NOS 3
RETAINING WALL SHUTTERING 1ST LIFT EAST SIDE RMT 10
SLAB SHUTTERING POUR-1 SQM 100
LIFT REINFORCEMENT POUR-3 NOS 2
COLUMN REINFORCEMENT NOS 4
Wednesday, October 5, 2022 RAMP RAFT REINFORCEMENT RMT 10
FOOTING SHUTTERING EAST SIDE NOS 3
RETAINING WALL SHUTTERING 2ND LIFT WEST SIDE RMT 20
SLAB SHUTTERING POUR-1 SQM 100
LIFT WALL SHUTTERING 2ND LIFT NOS 2
COLUMN REINFORCEMENT 1ST LIFT NOS 4
RETAINING WALL SHUTTERING 1ST LIFT WEST SIDE RMT 20
24 SEP'2022 TO 30 SEP'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED STATUS PREVIOUS PLANNED DATES

RETAINING WALL WEST SIDE RAFT RMT 9 9/19/2022

COLUMN 1ST LIFT NOS 4 4 ACHIEVED 9/21/2022


### LIFT & SC WALL 1ST LIFT NOS 2 2 ACHIEVED 9/22/2022
BACKFILLING CUM 150 150 ACHIEVED 9/21/2022
PCC BELOW GRADE SLAB SQM 150 150 ACHIEVED 9/23/2022
COLUMN 2ND LIFT NOS 4 4 ACHIEVED 9/22/2022
21-09-2022,22-09-2022,23-09-
### BACKFILLING CUM 600 600 ACHIEVED
2022
RETAINING WALL 1ST LIFT WEST SIDE RMT 20 20 ACHIEVED 21-09-202
RETAINING WALL EAST SIDE RAFT RMT 9 9/20/2022
FOOTING EAST SIDE NOS 2 2 ACHIEVED 9/23/2022
###
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 15 9/21/2022
COLUMN 2ND LIFT NOS 6 6 ACHIEVED 9/23/2022
LIFT WALL & SC WALL 2ND LIFT NOS 2 2 ACHIEVED 9/19/2022
RETAINING WALL 1ST LIFT EAST SIDE RMT 20 9/22/2022
COLUMN 1ST LIFT RMT 4 3 9/23/2022
### LIFT WALL& SC WALL 1ST LIFT NOS 2 2 ACHIEVED
RAMP RAFT RMT 20
FOOTING EAST SIDE NOS 2 2 ACHIEVED
PCC BELOW GRADE SLAB SQM 300 300 ACHIEVED
COLUMN 2ND LIFT NOS 6 4
LIFT WALL & SC WALL 2ND LIFT NOS 2 2 ACHIEVED
RETAINING WALL WEST SIDE 2ND LIFT RMT 20 9/22/2022
###
RETAINING WALL WEST SIDE 1ST LIFT RMT 19 9/22/2022
BACKFILLING CUM 300
COLUMN 1ST LIFT NOS 4
RETAINING WALL 1ST LIFT EAST SIDE RMT 12
RETIING WALL 2ND LIFT WEST SIDE RMT 20 9/23/2022
LIFT WALL & SC WALL 1ST LIFT NOS 2
###
COLUMN 2ND LIFT NOS 6
FOOTING EAST SIDE NOS 2
PCC BELOW GRADE SLAB SQM 500
RETIING WALL 2ND LIFT WEST SIDE RMT 20
COLUMN 1ST LIFT NOS 4
COLUMN 2ND LIFT NOS 6
### LIFT & SC WALL 2ND LIFT NOS 2
FOOTING EAST SIDE NOS 3
PCC BELOW GARDE SLAB SQM 500 325
BACK FILLING CUM 300

COLUMN 1ST LIFT NOS 16 7 44% 1,200,000.00 525,000.00


COLUMN 2ND LIFT NOS 28 14 50% 210,000.00 105,000.00
LIFT & STAIRCASE WALL 1ST LIFT NOS 6 4 67% 720,000.00 480,000.00
LIFT & STAIRCASE WALL 2ND LIFT NOS 6 4 67% 630,000.00 420,000.00
RETAINING WALL RAFT RMT 18 0 0% 131,625.00 -
RAMP RAFT RMT 20 0 0% 51,750.00 -
RETAINING WALL -1ST LIFT RMT 71 20 28% 1,497,656.25 421,875.00
RETAINING WALL - 2ND LIFT RMT 75 0 0% 421,875.00 -
FOOTINGS NOS 9 4 44% 1,080,000.00 480,000.00
BACKFILLING CUM 1350 750 56% 3,375,000.00 ###
PCC BELOW GRADE SLAB SQM 1450 775 53% 6,525,000.00 ###
15,842,906.25 ###
17 SEP'2022 TO 23 SEP'2022 24 SEP'2022 TO 30 SEP'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED STATUS DATE ACTIVITIES UOM PLANNNED QTY PREVIOUS PLANNED DATES

### BACKFILLING CUM 300 300 ACHIEVED RETAINING WALL WEST SIDE SIDE RAFT RMT 9 9/19/2022

### BACKFILLING CUM 800 800 ACHIEVED COLUMN 1ST LIFT NOS 4 9/21/2022
1 ACHIEVED
LIFT WALL & STAIRCASE WALL - 2ND LIFT NOS 3 1 2 NOT ACHIEVED ### LIFT & SC WALL 1ST LIFT NOS 2
9/22/2022
COLUMN - 1ST LIFT NOS 4 4 ACHIEVED BACKFILLING CUM 150 9/21/2022
COLUMN-2ND LIFT NOS 6 6 ACHIEVED PCC BELOW GRADE SLAB SQM 150 9/23/2022
###
RETAINING WALL RAFT WEST SIDE RMT 10 NOT ACHIEVED COLUMN 2ND LIFT NOS 4 9/22/2022
21-09-2022,22-09-2022,23-09-
PCC BELOW GRADE SLAB SQM 225 225 ACHIEVED ### BACKFILLING CUM 600 2022
BACKFILLING CUM 300 300 ACHIEVED RETAINING WALL 1ST LIFT WEST SIDE RMT 20 21-09-202
COLUMN - 2ND LIFT NOS 6 6 ACHIEVED RETAINING WALL EAST SIDE RAFT RMT 9 9/20/2022
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 ACHIEVED FOOTING EAST SIDE NOS 2 9/23/2022
###
### RETAINING WALL RAFT EAST SIDE RMT 9 NOT ACHIEVED RETAINING WALL SOUTH SIDE 2ND LIFT RMT 15 9/21/2022
FOOTING EAST SIDE NOS 2 2 ACHIEVED COLUMN 2ND LIFT NOS 6 9/23/2022
BACKFILLING CUM 300 300 ACHIEVED LIFT WALL & SC WALL 2ND LIFT NOS 2 9/19/2022
2 ACHIEVED
COLUMN -1ST LIFT NOS 6 2 RETAINING WALL 1ST LIFT EAST SIDE RMT 20
4 NOT ACHIEVED 9/22/2022
LIFT WALL & STAIRCASE WALL -1ST LIFT NOS 2 2 ACHIEVED COLUMN 1ST LIFT RMT 4 9/23/2022
### RETAINING WALL 1ST LIFT WEST SIDE RMT 15 NOT ACHIEVED ### LIFT WALL& SC WALL 1ST LIFT NOS 2
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 NOT ACHIEVED RAMP RAFT RMT 20
FOOTING EAST SIDE NOS 2 2 ACHIEVED FOOTING EAST SIDE NOS 2
BACKFILLING CUM 300 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 300
COLUMN -2ND LIFT NOS 8 4 COLUMN 2ND LIFT NOS 6
RETAINING WALL 1ST LIFT EAST SIDE RMT 20 NOT ACHIEVED LIFT WALL & SC WALL 2ND LIFT NOS 2
ACHIEVED
FOOTING EAST SIDE NOS 2 2 RETAINING WALL WEST SIDE 2ND LIFT RMT 20
9/22/2022
###
RETAINING WALL 2ND LIFT WEST SIDE RMT 20 NOT ACHIEVED RETAINING WALL WEST SIDE 1ST LIFT RMT 19 9/22/2022
###
LIFT WALL & STAIRCASE WALL 1ST LIFT NOS 3 1 1 ACHIEVED BACKFILLING CUM 300
2 NOT ACHIEVED
RETAINING WALL WEST SIDE 1ST LIFT RMT 20 NOT ACHIEVED COLUMN 1ST LIFT NOS 4
PCC BELOW GRADE SLAB SQM 500 500 ACHIEVED RETAINING WALL 1T LIFT EAST SIDE RMT 12
BACKFILLING CUM 300 NOT ACHIEVED RETIING WALL 2ND LIFT WEST SIDE RMT 20 9/23/2022
FOOTING EAST SIDE NOS 2 NOT ACHIEVED LIFT WALL & SC WALL 1ST LIFT NOS 2
###
COLUMN 1ST LIFT NOS 6 NOT ACHIEVED COLUMN 2ND LIFT NOS 6
COLUMN 2ND LIFT NOS 6 NOT ACHIEVED FOOTING EAST SIDE NOS 2
RETAINING WALL EAST SIDE 1ST LIFT RMT 25 NOT ACHIEVED PCC BELOW GRADE SLAB SQM 500
### RETAINING WALL WEST SIDE 2ND LIFT RMT 20 NOT ACHIEVED RETIING WALL 2ND LIFT WEST SIDE RMT 20
LIFT WALL & STAIRCASE WALL -2ND LIFT NOS 2 NOT ACHIEVED COLUMN 1ST LIFT NOS 4

PCC BELOW GRADE SLAB SQM 500 350 350 ACHIEVED COLUMN 2ND LIFT NOS 6
150 NOT ACHIEVED
###
BACKFILLING CUM 300 300 NOT ACHIEVED LIFT & SC WALL 2ND LIFT NOS 2
EXTRA ACHIEVED RAMP RAFT RMT 15 ACHIEVED FOOTING EAST SIDE NOS 3
PCC BELOW GARDE SLAB SQM 500
BACK FILLING CUM 300

COLUMN 1ST LIFT NOS 16 6 38% #REF! #REF!


COLUMN 2ND LIFT NOS 26 16 62% #REF! #REF!
LIFT & STAIRCASE WALL 1ST LIFT NOS 5 1 20% #REF! #REF!
LIFT & STAIRCASE WALL 2ND LIFT NOS 5 3 60% #REF! #REF!
RETAINING WALL RAFT RMT 19 0 0% #REF! #REF!
RETAINING WALL -1ST LIFT RMT 60 0 0% #REF! #REF!
RETAINING WALL - 2ND LIFT RMT 75 20 27% #REF! #REF!
FOOTINGS NOS 8 6 75% #REF! #REF!
BACKFILLING CUM 2600 2000 77% #REF! #REF!
PCC BELOW GRADE SLAB SQM 1225 1075 88% #REF! #REF!
#REF! #REF!
17 SEP'2022 TO 23 SEP'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED STATUS PREVIOUS PLANNED DATES

### BACKFILLING CUM 300 300 ACHIEVED 16TH SEP 2022

### BACKFILLING CUM 800 800 ACHIEVED


LIFT WALL & STAIRCASE WALL - 2ND LIFT NOS 3 1
COLUMN - 1ST LIFT NOS 4 4 ACHIEVED
COLUMN-2ND LIFT NOS 6 6 ACHIEVED
###
RETAINING WALL RAFT WEST SIDE RMT 10 15TH SEP 2022
PCC BELOW GRADE SLAB SQM 225 225 ACHIEVED
BACKFILLING CUM 300 300 ACHIEVED
COLUMN - 2ND LIFT NOS 6 6 ACHIEVED
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 ACHIEVED 14TH SEP 2022
### RETAINING WALL RAFT EAST SIDE RMT 9 16TH SEP 2022
FOOTING EAST SIDE NOS 2 2 ACHIEVED 14TH SEP 2022
BACKFILLING CUM 300
COLUMN -1ST LIFT NOS 6 2
LIFT WALL & STAIRCASE WALL -1ST LIFT NOS 2 2 ACHIEVED 12TH SEP 2022

### RETAINING WALL 1ST LIFT WEST SIDE RMT 15 16TH SEP 2022
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 16TH SE 2022
FOOTING EAST SIDE NOS 2 2 ACHIEVED
BACKFILLING CUM 300
COLUMN -2ND LIFT NOS 8 2
RETAINING WALL 1ST LIFT EAST SIDE RMT 20 15TH SEP 2022
FOOTING EAST SIDE NOS 2 1
RETAINING WALL 2ND LIFT WEST SIDE RMT 20
###
LIFT WALL & STAIRCASE WALL 1ST LIFT NOS 3 1 15TH SEP 2022
RETAINING WALL WEST SIDE 1ST LIFT RMT 20 16TH SEP 2022
PCC BELOW GRADE SLAB SQM 500 500 ACHIEVED
BACKFILLING CUM 300
FOOTING EAST SIDE NOS 2
COLUMN 1ST LIFT NOS 6
COLUMN 2ND LIFT NOS 6
RETAINING WALL EAST SIDE 1ST LIFT RMT 25
###
RETAINING WALL WEST SIDE 2ND LIFT RMT 20
LIFT WALL & STAIRCASE WALL -2ND LIFT NOS 2
PCC BELOW GRADE SLAB SQM 500 122
BACKFILLING CUM 300 300
EXTRA ACHIEVED RAMP RAFT RMT 15 ACHIEVED

COLUMN 1ST LIFT NOS 16 6 38% 72 432,000.00 1,296,000.00


COLUMN 2ND LIFT NOS 26 14 54% 26 156,000.00 468,000.00
LIFT & STAIRCASE WALL 1ST LIFT NOS 5 1 20% 60 360,000.00 1,080,000.00
LIFT & STAIRCASE WALL 2ND LIFT NOS 5 3 60% 75 450,000.00 1,350,000.00
RETAINING WALL RAFT RMT 19 0 0% 24.9375 149,625.00 448,875.00
RETAINING WALL -1ST LIFT RMT 60 0 0% 84.375 506,250.00 1,518,750.00
RETAINING WALL - 2ND LIFT RMT 75 20 27% 26.25 157,500.00 472,500.00
FOOTINGS NOS 8 5 63% 105.84 635,040.00 1,905,120.00
BACKFILLING CUM 2600 1700 65% 2600 6,500,000.00 6,500,000.00
PCC BELOW GRADE SLAB SQM 1225 847 69% 122.5 612,500.00 612,500.00
9,958,915.00 15,651,745.00
10 SEP'2022 TO 16 SEP'2022 17 SEP'2022 TO 23 SEP'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED STATUS PREVIOUS PLANNED DATES DATE ACTIVITIES UOM PLANNNED QTY PREVIOUS PLANNED DATES

RETAINING WALL WEST SIDE RMT 10 10 Achieved 5TH SEP 2022 ### BACKFILLING CUM 300 16TH SEP 2022
###
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 10 10 Achieved 3RD SEP 2022 ### BACKFILLING CUM 800
COLUMN - 1ST LIFT NOS 6 6 Achieved 8TH SEP 2022 LIFT WALL & STAIRCASE WALL - 2ND LIFT NOS 3
COLUMN- 1ST LIFT NOS 6 6 Achieved COLUMN - 1ST LIFT NOS 4
### COLUMN - 2ND LIFT NOS 4 4 Achieved 7TH SEP 2022 COLUMN-2ND LIFT NOS 6
FOOTING WEST SIDE NOS 2 3 Achieved 6TH SEP 2022 ### RETAINING WALL RAFT WEST SIDE RMT 10 15TH SEP 2022
1Achieved
LIFT WALL & STAIRCASE WALL POUR-3 NOS 3 1 8TH SEP 2022 PCC BELOW GRADE SLAB SQM 225
2 Not Achieved
COLUMN - 1ST LIFT NOS 6 6 Achieved BACKFILLING CUM 300
###
RETAINING WALL RAFT WEST SIDE RMT 20 20 Achieved 6TH SEP 2022 COLUMN - 2ND LIFT NOS 6
RETAINING WALL WEST SIDE 1ST LIFT RMT 10 0 RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 14TH SEP 2022
COLUMN - 2ND LIFT NOS 8 8 Achieved 8TH SEP 2022 & 9TH SEP 2022 ### RETAINING WALL RAFT EAST SIDE RMT 9 16TH SEP 2022
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 Achieved 5TH SEP 2022 FOOTING EAST SIDE NOS 2 14TH SEP 2022
### RETAINING WALL WEST SIDE 2ND LIFT RMT 15 15 Achieved BACKFILLING CUM 300
FOOTING EAST SIDE NOS 2 2 Achieved 9TH SEP 2022 COLUMN -1ST LIFT NOS 6
BACKFILLING CUM 300 300 Achieved 4TH SEP 2022 LIFT WALL & STAIRCASE WALL -1ST LIFT NOS 2 12TH SEP 2022
COLUMN 1ST LIFT NOS 4 4 Achieved ### RETAINING WALL 1ST LIFT WEST SIDE RMT 15 16TH SEP 2022
COLUMN 2ND LIFT NOS 6 6 Achieved RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 16TH SE 2022
### FOOTING EAST SIDE NOS 2 0 Not Achieved FOOTING EAST SIDE NOS 2
RETAINING WALL RAFT EAST SIDE RMT 20 20 Achieved BACKFILLING CUM 300
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 15 Not Achieved 7TH SEP 2022 COLUMN -2ND LIFT NOS 8
BACKFILLING CUM 300 300 Achieved 5TH SEP 2022 RETAINING WALL 1ST LIFT EAST SIDE RMT 20 15TH SEP 2022
COLUMN 1ST LIFT NOS 6 6 Achieved FOOTING EAST SIDE NOS 2
RETAINING WALL RAFT WEST SIDE RMT 15 20 Achieved RETAINING WALL 2ND LIFT WEST SIDE RMT 20
###
### RETAINING WALL EAST SIDE 1ST LIFT RMT 20 0 Not Achieved LIFT WALL & STAIRCASE WALL 1ST LIFT NOS 3 15TH SEP 2022
LIFT WALL & STAIRCASE WALL- POUR-3 NOS 3 0 Not Achieved 9TH SEP 2022 RETAINING WALL WEST SIDE 1ST LIFT RMT 20 16TH SEP 2022
BACKFILLING CUM 300 0 Not Achieved 6TH SEP 2022 PCC BELOW GRADE SLAB SQM 500
COLUMN - 2ND LIFT NOS 8 8 Achieved BACKFILLING CUM 300
FOOTING EAST SIDE NOS 2 0 Not Achieved FOOTING EAST SIDE NOS 2
RETAINING WALL RAFT EAST SIDE RMT 15 15 Not Achieved COLUMN 1ST LIFT NOS 6
###
RETAINING WALL WEST SIDE 1ST LIFT RMT 20 0 Not Achieved COLUMN 2ND LIFT NOS 6
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 Achieved RETAINING WALL EAST SIDE 1ST LIFT RMT 25
###
BACKFILLING CUM 300 0 Not Achieved 7TH SEP 2022 RETAINING WALL WEST SIDE 2ND LIFT RMT 20
STORMWATER TANK WALL CUM 6 Achieved LIFT WALL & STAIRCASE WALL -2ND LIFT NOS 2
COLUMN-1ST LIFT NOS 4 PCC BELOW GRADE SLAB SQM 500
Extra Achieved
LIFT WALL POUR-1 - 2ND LIFT NOS 1 BACKFILLING CUM 300
POUR-1 STAIRCASE & R/W NOS 1
10 SEP'2022 TO 16 SEP'2022
DATE ACTIVITIES UOM PLANNNED QTY ACHIEVED STATUS PREVIOUS PLANNED DATES

RETAINING WALL WEST SIDE RMT 10 10 Achieved 5TH SEP 2022


###
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 10 10 Achieved 3RD SEP 2022
COLUMN - 1ST LIFT NOS 6 6 Achieved 8TH SEP 2022
COLUMN- 1ST LIFT NOS 6 6 Achieved
### COLUMN - 2ND LIFT NOS 4 4 Achieved 7TH SEP 2022
FOOTING WEST SIDE NOS 2 3 Achieved 6TH SEP 2022
LIFT WALL & STAIRCASE WALL POUR-3 NOS 3 0 8TH SEP 2022
COLUMN - 1ST LIFT NOS 6 6 Achieved
###
RETAINING WALL RAFT WEST SIDE RMT 20 20 Achieved 6TH SEP 2022
RETAINING WALL WEST SIDE 1ST LIFT RMT 10 0
COLUMN - 2ND LIFT NOS 8 8 Achieved 8TH SEP 2022 & 9TH SEP 2022
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 Achieved 5TH SEP 2022
### RETAINING WALL WEST SIDE 2ND LIFT RMT 15 15 Achieved
FOOTING EAST SIDE NOS 2 2 Achieved 9TH SEP 2022
BACKFILLING CUM 300 300 Achieved 4TH SEP 2022
COLUMN 1ST LIFT NOS 4 4 Achieved

COLUMN 2ND LIFT NOS 6 6 Achieved


### FOOTING EAST SIDE NOS 2 0
RETAINING WALL RAFT EAST SIDE RMT 20 20 Achieved
RETAINING WALL 2ND LIFT SOUTH SIDE RMT 15 15 7TH SEP 2022
BACKFILLING CUM 300 0 5TH SEP 2022
COLUMN 1ST LIFT NOS 6 6 Achieved
RETAINING WALL RAFT WEST SIDE RMT 15 20 Achieved
### RETAINING WALL EAST SIDE 1ST LIFT RMT 20 0
LIFT WALL & STAIRCASE WALL- POUR-3 NOS 3 0 9TH SEP 2022
BACKFILLING CUM 300 0 6TH SEP 2022
COLUMN - 2ND LIFT NOS 8 5
FOOTING EAST SIDE NOS 2 0
RETAINING WALL RAFT EAST SIDE RMT 15 15
###
RETAINING WALL WEST SIDE 1ST LIFT RMT 20 0
RETAINING WALL SOUTH SIDE 2ND LIFT RMT 20 20 Achieved
BACKFILLING CUM 300 0 7TH SEP 2022
Extra Achieved STORMWATER TANK WALL CUM 6 Achieved
COLUMN-1ST LIFT 4
LIFT WALL POUR-1 - 2ND LIFT
POUR-1 STAIRCASE & R/W 1

COLUMN 1ST LIFT NOS 28 32 114% 126 756,000.00 1,890,000.00


COLUMN 2ND LIFT NOS 26 23 88% 26 156,000.00 390,000.00
LIFT WALL & STAIRCASE WALL NOS 6 0 0% 72 432,000.00 1,080,000.00
RETAINING WALL RAFT RMT 70 75 107% 34.125 204,750.00 511,875.00
RETAINING WALL -1ST LIFT RMT 60 10 17% 78.75 472,500.00 1,181,250.00
RETAINING WALL - 2ND LIFT RMT 80 80 100% 30 180,000.00 450,000.00
FOOTINGS NOS 8 5 63% 64 384,000.00 960,000.00
BACKFILLING CUM 1200 300 25% 1200 3,000,000.00 3,000,000.00
STORMWATER TANK WALL CUM 0 6 6 36,000.00 90,000.00
LIFT & STAIRCASE WALL 2ND LIFT NOS 1 5,621,250.00 9,553,125.00
03 SEP'2022 TO 9 SEP'2022
DATE ACTIVITIES NOS PLANNNED QTY STATUS

RETAINING WALL RAFT WEST SIDE & FOOTING 10RMT 15 CUM Achieved

### COLUMN 1ST LIFT 4 NOS 20CUM Achieved


10 Rmt Achieved
RETAINING WALL 2ND LIFT 20 RMT 6 CUM
10 Rmt not achieved
TOWER CRANE FOOTING 1 NO 50 CUM Achieved
### COLUMN 1ST LIFT 2 NOS 12 CUM Achieved
BACKFILLING 2ND LAYER 300 CUM Not Achieved
RETAINING WALL WEST SIDE 10MTS 12 CUM Not Achieved
COLUMN 1ST LIFT 4 NOS 24 CUM Achieved
###
RETAINING WALL 2ND LIFT SOUTH SIDE 20 MTS 6 CUM Not Achieved
BACK FILLING 2ND LAYER 300CUM Not Achieved
COLUMN - 2ND LIFT 6 NOS 6 CUM Achieved
ISOLATED FOOTING EASTISIDE 2 NOS 25 CUM Not Achieved
### 12 Rmt Achieved
RETAINING WALL RAFT WEST SIDE 20 MTS 10CUM 8 Rmt not Achieved
BACK FILLING 2ND LAYER 300 CUM Not Achieved
POUR-1 LIFT WALL 1 NOS 18 CUM Achieved
COLUMN 1ST LIFT 4 NOS 24 CUM Achieved
### 2 Achieved
COLUMN 2ND LIFT 6 NOS 6 CUM
4 Not Achieved
RETAINING WALL 2ND LIFT SOUTH SIDE 15 MTS 4.5 CUM Not Achieved
BACK FILLING 2ND LAYER & COMPACTION 300CUM Not Achieved
POUR-3 LIFT WALL 3 NOS 30 CUM Not Achieved

COLUMN 1ST LIFT 4 NOS 1 Achieved


24 CUM 3 Not Achieved
###
COLUMN 2ND LIFT 4 NOS 4 CUM Not Achieved
ISOLATED FOOTING CAP WEST SIDE 1 NO 1.5 CUM Not Achieved
BACK FILLING 2ND LAYER & COMPACTION 300 CUM Not Achieved
POUR-3 LIFT WALL 3 NOS 30 CUM Not Achieved
COLUMN 2ND LIFT 4 NOS 4 CUM Not Achieved
###
ISOLATED FOOTING EAST SIDE 2 NOS 30 CUM Not Achieved
PCC BELOW GRADE SLAB POUR-1 500 SQM 50 CUM Not Achieved
03 SEP'2022 TO 9 SEP'2022
DATE ACTIVITIES NOS PLANNNED QTY STATUS PREVIOUS PLAN DATE

RETAINING WALL RAFT WEST SIDE & FOOTING 10RMT 15 CUM Not Achieved
### COLUMN 1ST LIFT 4 NOS 20CUM Achieved 30-Aug-22
RETAINING WALL 2ND LIFT 20 RMT 6 CUM Achieved 1-Sep-22
TOWER CRANE FOOTING 1 NO 50 CUM Achieved
### COLUMN 1ST LIFT 2 NOS 12 CUM Achieved 2-Sep-22
BACKFILLING 2ND LAYER 300 CUM Not Achieved
RETAINING WALL WEST SIDE 10MTS 12 CUM Not Achieved
COLUMN 1ST LIFT 4 NOS 24 CUM Achieved 2-Sep-22
###
RETAINING WALL 2ND LIFT SOUTH SIDE 20 MTS 6 CUM Not Achieved
BACK FILLING 2ND LAYER 300CUM Not Achieved
COLUMN - 2ND LIFT 6 NOS 6 CUM Achieved
ISOLATED FOOTING EASTISIDE 2 NOS 25 CUM Not Achieved
###
RETAINING WALL RAFT WEST SIDE 20 MTS 10CUM Not Achieved
BACK FILLING 2ND LAYER 300 CUM Not Achieved
POUR-1 LIFT WALL 1 NOS 18 CUM Achieved
COLUMN 1ST LIFT 4 NOS 24 CUM Achieved
### 2 Achieved
COLUMN 2ND LIFT 6 NOS 6 CUM
4 Not Achieved
RETAINING WALL 2ND LIFT SOUTH SIDE 15 MTS 4.5 CUM Not Achieved
BACK FILLING 2ND LAYER & COMPACTION 300CUM Not Achieved

POUR-3 LIFT WALL 3 NOS Not Achieved


30 CUM
COLUMN 1ST LIFT 4 NOS 1 Achieved
### 24 CUM 3 Not Achieved 1 achieved
COLUMN 2ND LIFT 4 NOS 4 CUM Not Achieved
ISOLATED FOOTING CAP WEST SIDE 1 NO 1.5 CUM Not Achieved
BACK FILLING 2ND LAYER & COMPACTION 300 CUM Not Achieved
POUR-3 LIFT WALL 3 NOS 30 CUM Not Achieved
COLUMN 2ND LIFT 4 NOS 4 CUM Not Achieved
###
ISOLATED FOOTING EAST SIDE 2 NOS 30 CUM Not Achieved
PCC BELOW GRADE SLAB POUR-1 500 SQM 50 CUM Not Achieved
20 AUG'2022 TO 26 AUG 2022
DATE ACTIVITIES NOS

ISOLATED FOOTING WEST SIDE 4 Nos


###
POUR-1 TOWER COLUMN 2 Nos
RETAINING WALL 20 Rmt
###
PART-1 BACK FILLING
RETAINING WALL 20 Rmt
### POUR-1 TOWER COLUMN 2 Nos
PART-1 BACK FILLING
RETAINING WALL 20 Rmt
### POUR-1 TOWER COLUMN 2 Nos
PART-1 BACK FILLING
RETAINING WALL 20 Rmt
### POUR-1 TOWER COLUMN 2 Nos
PART-1 BACK FILLING
RETAINING WALL 20 Rmt
### POUR-1 TOWER COLUMN 2 Nos
PART-1 BACK FILLING
RETAINING WALL 20 Rmt
### POUR-1 TOWER COLUMN 2 Nos
PART-1 BACK FILLING
27 AUG'2022 TO 2 SEP 2022
PLANNNED QTY STATUS DATE ACTIVITIES

20 CUM RETAINING WALL 2ND LIFT


ACHIEVED
###
12 CUM ACHIEVED BACKFILLING
25CUM ACHIEVED TOWER AREA COLUMN
100 CUM ACHIEVED BACK FILLING
###
25CUM ACHIEVED FOOTING CAPS
12 CUM ACHIEVED TOWER AREA COLUMN
100 CUM ACHIEVED ### ISOLATED FOOTING EAST SIDE
25CUM ACHIEVED BACKFILLING
12 CUM ACHIEVED TOWER AREA COLUMN
100 CUM ACHIEVED ### RETAINING WALL RAFT - WEST SIDE
25CUM NOT ACHIEVED BACK FILLING
12 CUM NOT ACHIEVED ### GANESH CHATURTHI
100 CUM ACHIEVED TOWER AREA COLUMN
25CUM NOT ACHIEVED RETAINING WALL 2ND LIFT
###
12 CUM NOT ACHIEVED BACK FILLING
100 CUM ACHIEVED ISOLATED FOOTING EAST SIDE
25CUM NOT ACHIEVED TOWER AREA COLUMN
12 CUM NOT ACHIEVED ### RETAINING WALL RAFT - EAST SIDE
100 CUM ACHIEVED BACK FILLING
AUG'2022 TO 2 SEP 2022
NOS PLANNNED QTY PREVIOUS PLAN DATE

15 RMT 6 CUM

300 CUM
2NOS 12 CUM 24-Aug-22
400 CUM
2 NOS 5 CUM
4 NOS 24 CUM 25-Aug-22 & 26-Aug-22
2 Nos 40 CUM
300 CUM
4 NOS 24 CUM
10 RMT 5 CUM
300 CUM
GANESH CHATURTHI
6 NOS 36 CUM
20RMT 8 CUM
300 CUM
2 NOS 35 CUM
6 NOS 36 CUM
15 RMT 7 CUM
300 CUM
LOOKAHEAD SCHEDULE
08 AUG'2022 TO 13 AUG 2022
DATE ACTIVITIES QTY ACHIEVED
8-Aug-22 BLOCK -1 RAFT POUR-5 589 cum
BLOCK -1 RAFT CAP POUR-5 , 92 cum
9-Aug-22
ISOLATED FOOTINGS Not Achieved

10-Aug-22 BLOCK-1 RAFT POUR-7 1023 cum

11-Aug-22 20 cum
RETAINING WALL SOUTH SIDE

BLOCK-1 RAFT POUR-6


12-Aug-22 621 cum

BLOCK-1 RAFT CAP POUR-7 59 cum


13-Aug-22 RETAINING WALL EAST SIDE RAFT , Not Achieved
ISOLATED FOOTINGS Not Achieved
LOOKAHEAD SCHEDULE
13 AUG'2022 TO 19 AUG 2022
DATE ACTIVITIES PLANNNED ACHIEVED
### POUR-6 RAFT CAPS 100 CUM 97.3 CUM

### INDEPENDENCE DAY

1. ISOLATED FOOTING WEST SIDE 65 CUM


### 100 CUM
2. POUR-1 BACK FILLING LAYER -1
1.RETAINING WALL SOUTH SIDE 45CUM
### 150 CUM
2. POUR-1 BACK FILLING LAYER-1
1. ISOLATED FOOTING EAST SIDE. 65 CUM
### 2. RETAINING WALL EAST SIDE. 30 CUM
3. POUR-1 BACK FILLING LAYER-1 150 CUM

1.POUR-1 COLUMN CASTING 50CUM


### 2. POUR-2 BACK FILLING LAYER-1 150 CUM
3. POUR-1 LAYER-1 SOIL COMPACTION 350 SQM
13 AUG'2022 TO 19 AUG 2022
DATE ACTIVITIES PLANNNED ACHIEVED
20 AUG'2022 TO 26 AUG 2022
DATE ACTIVITIES
ISOLATED FOOTING WEST SIDE

### POUR-1 TOWER COLUMN

PART-1 BACK FILLING

RETAINING WALL
###
PART-1 BACK FILLING

FOOTING EAST SIDE

###
POUR-1 TOWER COLUMN

PART-1 BACK FILLING

RETAINING WALL RAFT & FOOTING


###
PART-1 BACK FILLING

ISOLATED FOOTING STEP-2

### POUR-1 TOWER COLUMN

PART-1 BACK FILLING

RETAINING WALL RAFT & FOOTING

### POUR-1 TOWER COLUMN

PART-1 BACK FILLING

FOOTING CAP & ISOLATED FOOTING- SOUTH SIDE

### POUR-1 TOWER COLUMN

PART-1 BACK FILLING


26 AUG 2022
PLANNNED ACHIEVED
20 CUM

12 CUM

100 CUM

25CUM

100 CUM

75CUM

20 CUM

150CUM

35CUM

150CUM

10 CUM

40 CUM

150CUM

50CUM

30CUM

150CUM

35CUM

15 CUM

150CUM
LOOKAHEAD SCHEDULE
13 AUG'2022 TO 19 AUG 2022

DATE ACTIVITIES

1.POUR-6 RAFT CONCRETING


Saturday, August 13, 2022
2. BACK FILLING WEST SIDE

Sunday, August 14, 2022 POUR-6 RAFT CAPS

Monday, August 15, 2022 INDEPENDENCE DAY

1. ISOLATED FOOTING WEST SIDE


Tuesday, August 16, 2022 2. TOWER AREA COLUMN STARTER
3. POUR-1 BACK FILLING LAYER -1

1.RETAINING WALL SOUTH SIDE


Wednesday, August 17, 2022 2. TOWER AREA COLUMN STARTER
3. POUR-1 BACK FILLING LAYER-1

1. ISOLATED FOOTING EAST SIDE.


Thursday, August 18, 2022 2. RETAINING WALL EAST SIDE.
3. POUR-1 BACK FILLING LAYER-1

1.POUR-1 COLUMN CASTING


2. COLUMN STARTER CASTING.
Friday, August 19, 2022
3. POUR-2 BACK FILLING LAYER-1
4. POUR-1 LAYER-1 SOIL COMPACTION