Professional Documents
Culture Documents
Index
1.0 Introduction
1.0 Introduction
The purpose of this document is to specify the methodology by which the estimate for the EAP
EPC4A Offshore work scope will be prepared. The document will describe the preparation of the
Job Cards including the definition of Base Direct Man-hours, the definition and application of the
Productivity Factor and the definition of Indirect Man-hours. The document will also describe the
relationship between the Job Card, estimating sheet and the resourced Schedule. During the
preparation of the job cards a constructability review will take place with engineering & the HUC
groups. The results of which will be processed and ultimately implemented after approval by
engineering and the HUC Coordinator. The principal tool to be adopted in capturing the Base
Direct Man-hours is an MS Access data base Job Card System.
Prior to the development of the P3 schedule the total forecast estimated man-hours will be
collected into the HUC Man-hour Estimate Summary document see section 7. This document
provides a guide to the execution durations prior to the final development of the construction
sequencing and Logic.
The offshore program will be broken down into discreet phases as detailed below and ultimately
scheduled accordingly.
• Phase A1 – This is all work that MUST be done without exception to enable the deck
extensions to be installed. It is irrespective of whether it is hot work or cold work. Generally
this is classed as non shutdown but there will be some exceptions to that rule and will be
addressed on an individual platform basis with interface required from shutdown/start up
teams.
• Phase A2 – This is the work that could be done before installing the deck extensions. HUC
PMT can remove some of this scope into phase C or E for scheduling purposes. It may also
be possible to include Phase E work during this time.
• Phase B – Heavy Lift only. Any vent booms can be included if required.
• Phase C – Post deck installation. This is generally known for the larger shutdown scope to
allow “tie ins” and any work that could not be completed in the phase A scope.
• Phase E – This is the boat landing & riser guard scope. This will contain some diving scope.
There will be physical opportunity in the field to execute some of this scope in phase A2 as
time permits.
• Phase D – Drilling program
• Phase F – Painting program.
• The purpose of the job card is to provide on efficient mechanism for communicating the scope
of work and any safety considerations that may be required to execute the work in a safe and
expeditious manner.
• The job cards will be referenced when preparing JSA documents
• The work take-off and planning will be performed in trade discipline groups.
• Estimating sheets will be prepared by discipline and the derived man-hours will be used to
populate the job cards in the MS Access Job Card Data Base. For the estimating sheets see
section 5.1 for Structural & 5.2 for Piping
• For E&I the work description and quantity is populated directly into the MS Access job card
database. The hours are applied using the E&I Norm Sheet in 4.5.
• The electronic MS Access Job card database will be used for the management of the job
cards. The job cards will identify the work description, Base Direct Man-hours by phase,
discipline and trade, system, sub system and location.
• The materials to undertake the work will also be identified on the Job Card MTO sheet see
section 5.4
• All of the necessary reference documents required to prepare the Job Cards and execute the
work will also be identified.
• The man-hours will be applied using the published John S Page Cost Estimating manuals for
Piping installation and Structural installation. These will be known as the Base Direct Man-
hours.
• Supplementary norms will be utilized to cover any “grey areas” in the Structural and Electrical
and Instrument disciplines. These are clearly defined in sections 4.3 for structural and 4.5 for
E&I.
• Any additional norms out with the John S. page norms and the supplementary norms must be
approved by the HUC Coordinator or function.
• Job cards will be broken down into manageable size work packages to facilitate accurate
sequencing.
• “Tie in” & shutdown type activities that require very accurate sequencing of shutdown work for
example by possibly having a single “tie in” spool as a job card.
2.3 Base Direct Man-hours
The Base Direct Man-hours will be estimated using the methodology as described herein and
will include the identification of work for the following Disciplines.
o Welders
o Platers
o Pipe fitters
o Riggers
o Scaffolders**
o Electrician
o Instrument Technician
o Painters
o NDT Technicians
o Firewatch***
o Divers
o Insulators
• **Scaffolding man-hours & job cards - After the completion of the P3 schedule, the scaffold
man-hours will be calculated by using “X” scaffold builders multiplied by 12 hours per shift,
multiplied by number of days from the P3 schedule. These hours do not require an
application of the Productivity Factor as the method for achieving the hrs is number of days
by number of men. It must be noted at time of writing the current EPC4A contractor uses
multidiscipline scaffolder/riggers.
• Three job cards will be created by splitting those calculated hours as follows.
• *** Fire watch man-hours - The Firewatcher Base Direct man-hours will be calculated based
on the duration of the P3 schedule using the same method as the Scaffolders of a number
of men multiply by 12 hours multiply by number of days from the P3 schedule. The volume
EPC4A HUC Estimating Methodology Rev 0 Page 4 of 21 1/15/08
EPC 4A HUC Estimating
of hotwork being undertaken will be taken into consideration when establishing the
required number of Fire watch.
2.4 Offshore Nigeria Productivity Factors
• The productivity factor for offshore Nigeria will include for those items detailed in section 2.5
• The productivity factors will then be applied to the Base Direct Man-hours from the job cards.
The productivity factor will be applied in the P3 schedules.
• The job cards will be sequenced by the HUC planning team with the scheduler to populate the
P3 schedule.
• The correct sequencing of job cards will develop the construction logic from which we will
develop the necessary resource leveling.
• As the estimating/job card program matures and the manpower saturation level has been
reviewed, the theoretical manning levels will be adjusted.
• The direct manpower totals will be optimized by trade/discipline to achieve the optimum crew
mix to liquidate the work.
• It has been assumed that the project will utilize multidiscipline scaffolder/riggers also
firewatchers can be used from within the trade disciplines. An extra % will be added to allow
for specific scaffold builders and specific firewatchers.
N.B. In the event of a specific norm not being available a comparable norm will be utilized after
agreement with Discipline Leads & HUC Coordinator. Any such cases will be documented.
FLOW TRANSMITTER
THERMOCOUPLE
4.0 ELECTRONIC Eex FT 12.0 PILOT RELAY SDY 3.0
ASSEMBLY
PROOF
MANUAL E.S.D.
PRESSURE SWITCH Eex
PS 3.0 STATION ESD 4.0 PIG SIGNAL ZI 2.0
PROOF
INSTALLATION
PRESSURE
SAND PROBE
PRESSURE GAUGE PI 3.0 TRANSMITTER PT 12.0 NP 4.0
PNEUMATIC
ELECTRONIC Eex
PRESSURE
PRESSURE INDICATING
PIT 6.0 CONTROLLER PC 15.2 PRESSURE RECORDER PR 15.2
TRANSMITTER
PNEUMATIC
Table 2: Instrument Stainless Steel Tubing and Compression Fittings Installation Norms
Installation of 316L SS Reference
Standard SS Compression Standard
tubing Source
(including brackets and (hours per
Fittings Hours per fitting
clipping) foot)
Sect 9 Item
1/4" 0.4 1/4" 0.4
01
Sect 9 Item
3/8" 0.5 3/8" 0.4
01
Sect 9 Item
1/2" 0.52 1/2" 0.4
01
Table 3: Cable Installation Norms
Standard
Reference Standard (glanding Reference
Cable Type (hours per Cable Testing Reference Source
Source and terminate) Source
foot)
(pull,
Note: Multiply by 1.5
(Common To All permanent
if using Barrier
Platforms). tie & final
Glands
dressing)
3/C #10 AWG, 600V, CLX Sect 8 Item
0.1 1.31 Sect 8 Item 02 2.9 Sect 8 Item 09
TYPE MC, OKONITE (6mm) 01
6/C #10 AWG, 600V, CLX Sect 8 Item
0.1 3 Sect 8 Item 02 2.97 Sect 8 Item 09
TYPE MC, OKONITE (6mm) 01
3/C #2 AWG, 600V, CLX TYPE Sect 8 Item
0.16 2.37 Sect 8 Item 02 3.73 Sect 8 Item 09
MC, OKONITE (35mm) 01
2/C #10, TYPE SOOW, 90 C, Sect 8 Item
0.1 1.31 Sect 8 Item 02 2.9 Sect 8 Item 09
600V (6mm) 01
2/C #10, TYPE SOOW, 90 C, Sect 8 Item
0.1 0.96 Sect 8 Item 02 2.9 Sect 8 Item 09
600V (2.6mm) 01
3/C #12 AWG, 600V, CLX Sect 8 Item
0.09 1.31 Sect 8 Item 02 2.73 Sect 8 Item 09
TYPE MC, OKONITE (4mm) 01
1 PR #16 POS, 600V, CLX Sect 8 Item
0.07 1.94 Sect 8 Item 05 2.52 Sect 8 Item 10
TYPE MC, OKONITE (1.5mm) 01
2 PR #16 SPOS, 600V, CLX Sect 8 Item
0.08 2.41 Sect 8 Item 05 2.82 Sect 8 Item 10
TYPE MC, OKONITE (1.5mm) 01
4 PR #16 SPOS, 600V, CLX Sect 8 Item
0.09 4.1 Sect 8 Item 05 3.14 Sect 8 Item 10
TYPE MC, OKONITE (1.5mm) 01
12 PR #16 SPOS, 600V, CLX Sect 8 Item
0.12 12.26 Sect 8 Item 05 3.63 Sect 8 Item 10
TYPE MC, OKONITE (1.5mm) 01
8 PR #16 SPOS, 600V, CLX Sect 8 Item
0.1 9.06 Sect 8 Item 05 3.41 Sect 8 Item 10
TYPE MC, OKONITE (1.5mm) 01
24 PR #16 SPOS, 600V, CLX Sect 8 Item
0.12 17.77 Sect 8 Item 05 4.93 Sect 8 Item 10
TYPE MC, OKONITE (1.5mm) 01
Co-axial 0.08 3.16 2.82
Cost
WCP 24 Estimating Auto/Man Select 1.94 Sect 8 Item 16 Nav Lights 6 Sect 8 Item 16
Manual
Cost
MCP 24 Estimating On/off Switch 1.9 Sect 8 Item 16 Foghorn 12.6 Sect 8 Item 16
Manual
Cost
RTU/SCADA 24 Estimating Push Button 3.86 Sect 8 Item 16 Sodium Overhead Light 4.55 Sect 8 Item 16
Manual
RTU/SCADA Antenna
8 Hours 18" 1.1 Sect 8 Item 14 18" 0.2 Sect 8 Item 14
Installation
0.5 of the
Electrical and Instrumentation equivalent
work installation
norm
Reference Sources:
• Use “Pick and Set Decks” table on page 185 from the “Offshore Structures” section which is man-
hours per ton. - “Ref Book 1”.
• Add on for welding man-hours from page 187 in the “Set Platform Miscellaneous Steel Items and
Weld Out”. “Ref Book 1”.
The job card numbering sequence may vary depending on the requirement for hot bolting, demolition
or supports.
DATE
DRAWING NUMBER
SUBSYSTEM
SCH /
LENGTH /
JOB TASK SIZE RATING / NORM Total
QUANTITY
WEIGHT
HANDLING
DRILLING
BOLT UP
WELDING
NDT
ANY OTHER
ANY OTHER
ANY OTHER
TOTAL
DATE
DRAWING NUMBER
SUBSYSTEM
SCH /
LENGTH /
JOB TASK N.B. RATING / NORM Total
QUANTITY
WEIGHT
HANDLING PIPE (x2)
HANDLING VALVES or
SIMILAR IN LINE ITEMS
(x2)
FLANGE BOLT UP
(If Hotbolt x 3)
PIPE CUT
END PREP/BEVEL
BUTT WELD
NDT
HYDROTEST
GRATING OR DECK
MODS FOR
PENETRATIONS
MINOR PAINT TOUCH UP
ANY OTHER
ANY OTHER
TOTAL
JOB CARD #
EAP - EPC4A - JOB CARD
MAN JOB CARD
DATE PHASE PLATFORM DISCIPLINE WILLBROS CODE EXXONMOBIL CODE SYSTEM DESIGNATION
HOURS REV
12/12/2006 0 0
PROPRIETARY
Completions
Engineering
Safety
Materials
QA/QC
Others