You are on page 1of 10

Globestar

Mobil Producing Nigeria Unlimited

Offshore Construction and Installation


Program Project (OCIP Project)

6271.5081

E & I Estimation Guide Line


1 DOCUMENT PURPOSE

The purpose of this document is to detail how CONTRACTOR estimates the Man-
hours for Electrical and Instrumentation disciplines.

It describes:
 The activities used on the job card
 The basis used for Man-hours estimating
 The coefficients used in time estimating

2 BASSIS OF TIME ESTIMATE

For electrical and instrument activities, the norms to be used for offshore
installation come from different estimator’s manual from John S. Page:
 Estimator's electrical manhour manual
 Estimator's piping manhour manual (for instruments installation)
 Cost Estimating Manual for Pipelines & Marine Structures

We also consider some norms from document issued by Company for EPC4A project
(e.g. for cable pulling): “EPC4A HUC Estimating Methodology Rev 0”.
Any “grey areas” should be covered by supplementary norms but can also be
estimate by preparator based on experience or realistic assumptions.
The productivity factor is to be considered as 1 for E&I work.
For demolition, we will use 50% of installation norms (cf. EPC4A HUC Estimating
Methodology Rev 0).

3 LIST OF PRODUCTIVE PERSONNEL

The teams performing E&I Job cards will be made of the following productive
personnel:
 Instrument Technician
 Tubing Fitter
 Electrician
 E&I Helper
 Firewatcher

4 CALCULATION BASIS AND RESOURCE ALLOCATION

4.1 GENERAL ACTIVITIES


4.1.1 Work Preparation
10% of total Man-hours listed on the Job cards are to be considered.
This activity shall always be listed as the first activity on the Job cards.

4.1.2 Housekeeping
10% of total Man-hours listed on the Job cards are to be considered.
This activity shall always be listed as the last activity on the Job cards.
4.2 ELECTRICAL AND INSTRUMENTATION ACTIVITIES
4.2.1 Tubing Installation

Man-Hours
INSTALLATION / DEMOLITION OF TUBING TYPICAL TEAM
(Hrs per feet)

Installation of Stainless Steel Tubing 1/4" 0.60 Instrument Tubing Team

Installation of Stainless Steel Tubing 3/8" 0.65 Instrument Tubing Team


Installation of Stainless Steel Tubing 1/2" 0.75 Instrument Tubing Team
Installation of Stainless Steel Tubing 3/4" 0.82 Instrument Tubing Team

Installation of Stainless Steel Tubing 1" 0.90 Instrument Tubing Team


Demolition of Stainless Steel Tubing 1/4" 0.30 Instrument Tubing Team

Demolition of Stainless Steel Tubing 3/8" 0.33 Instrument Tubing Team


Demolition of Stainless Steel Tubing 1/2" 0.38 Instrument Tubing Team

Demolition of Stainless Steel Tubing 3/4" 0.41 Instrument Tubing Team


Demolition of Stainless Steel Tubing 1" 0.45 Instrument Tubing Team

Reference document “Cost Estimating Manual for Pipelines & Marine Structures”,
Page 296.
Above Hours include checking out of storage, handling to erection location and
complete installation (means with clamps, union, fittings, and fusible plugs)
including average time for mark-up.
Preparator to consider extra hours in regards of valves or filter regulators to be
installed.
Hours do not include installation of instruments, trays or supports.

4.2.2 Process Instrument Installation


CALIBRATION INSTALLATION
typical
INSTRUMENT Man-Hours Man-Hours TYPICAL TEAM
symbol
(each) (each)

Temperature Gauge TI 4 3 Instrument Tech Team


Temperature Indicating Instrument Tech Team
TIT / TT 5 4
transmitter

Temperature Switch Pneumatic TS 6 4 Instrument Tech Team


Temperature Transmitter Instrument Tech Team
TT 12
Electronic

Thermo-well TW NA 2 Instrument Tech Team*


Pressure Pilot switch Instrument Tech Team
PSL / PSH 4 3
pneumatic-L or -H

Pressure Switch Electronic PS 2.5 3 Instrument Tech Team


Pressure Gauge PG / PI 2 3 Instrument Tech Team
Pressure Transmitter Instrument Tech Team
PIT / PT 4 3
Pneumatic

Pressure Transmitter Electronic PIT / PT 2.5 3 Instrument Tech Team


Pressure Controller Pneumatic PC / PIC 8 5 Instrument Tech Team
Pressure Controller Electronic PC / PIC 7 5 Instrument Tech Team
Pressure Recorder PR 8 5 Instrument Tech Team

Differential Pressure Indicating Instrument Tech Team


DPIC 8 5
Pneumatic

Level Control Switch Pneumatic LS 2.5 4 Instrument Tech Team


Level Transmitter Pneumatic LT 8 4 Instrument Tech Team

Level Transmitter Electronic LT 6 4 Instrument Tech Team


Level indicator LI 10 Instrument Tech Team

Level Controller Pneumatic LC 10 5 Instrument Tech Team


Level Gauge 12" Long LG NA 4 Instrument Tech Team *
Flow Transmitter Electronic FT NA 4 Instrument Tech Team *

Flow meter (turbine, coriolis) FM NA 4 Instrument Tech Team *


Flow Indicator FI NA 4 Instrument Tech Team

Flow element FE NA 4 Instrument Tech Team


Flow recorder Pneumatic FR 8 5 Instrument Tech Team

Flow Pressure Temperature Instrument Tech Team


FPTR 8 5
Recorder

Pig Signal with Pneumatic Instrument Tech Team


ZIS NA 3
Switch
Pig signal ZI NA 2 Instrument Tech Team

Sand Probe Pneumatic NP 2 4 Instrument Tech Team


Pressure Relief valve PSV 2 4 Instrument Tech Team *

Control Valve CV 1.5 2 Instrument Tech Team *


Shutdown Valve SDV 1.5 4 Instrument Tech Team *

Pilot Relay SDY 1 3 Instrument Tech Team


Limit switch ZSC/ZSO 1 3 Instrument Tech Team

Reference document “EPC4A HUC Estimating Methodology Rev 0“.


Demolition: use 50% of installation norms (cf. EPC4A HUC Estimating
Methodology).
Above Hours include checking out of storage, handling, installing. Hours do not
include installation of tubing, cable trays or supports; do not include termination of
cables.

4.2.3 Miscellaneous Instrument Installation

Man-Hours
INSTRUMENT INSTALLATION TYPICAL TEAM
(each)

Stand-supports for instruments, Junct. Box (clamped) 1.36 Electrical Team 1


Master Control Panel / Well-Head Control Panel 24 Instrument Tech Team

RTU / SCADA system installation 24 Electrical Team 2


RTU / SCADA Antenna Installation 8 Electrical Team 2
Instrument Junction Box (24 inch) 4.89 Electrical Team 2
Auto / Man select 1.94 Instrument Tech Team

On / off Switch 1.90 Instrument Tech Team


Push Button 3.86 Instrument Tech Team

Air Supply Set 2 Instrument Tech Team


5-Ways Valve 3 Instrument Tech Team

3-Ways Valve or Gauge valve 2 Instrument Tech Team


PIC / Chart Recorder PANEL 6.81 Instrument Tech Team

Instrument / Panel Grounding 1 Electrical Team 1


Horn 4 Instrument Tech Team

Manual S.D Station (ESD) 4 Instrument Tech Team

Demolition: use 50% of installation norms (cf. EPC4A HUC Estimating


Methodology).

4.2.4 Cable or Tubing Tray Installation


Man-Hours
TRAY INSTALLATION (Hours per TYPICAL TEAM
feet)

Tray Fibre Glass 18" Width 0.64 Electrical Team 1

Tray Fibre Glass 12" Width 0.52 Electrical Team 1


Tray Fibre Glass 6" Width 0.42 Electrical Team 1

Tray Fibre Glass 4" Width 0.32 Electrical Team 1


Tray Stainless Steel or Aluminium 18" Width 1.10 Electrical Team 2

Tray Stainless Steel or Aluminium 12" Width 0.90 Electrical Team 2


Tray Stainless Steel or Aluminium 9" Width 0.82 Electrical Team 2
Tray Stainless Steel or Aluminium 6" Width 0.74 Electrical Team 2

Tray Stainless Steel or Aluminium 4" Width 0.54 Electrical Team 2


Cable Tray Cover 18" Width 0.20 Electrical Team 2

Cable Tray Cover 12" Width 0.16 Electrical Team 2


Cable Tray Cover 9" Width 0.14 Electrical Team 2

Cable Tray Cover 6" Width 0.13 Electrical Team 2


Cable Tray Cover or Aluminium 4" Width 0.10 Electrical Team 2

4.2.5 Electrical Installation

Man-Hours
ELECTRICAL INSTALLATION TYPICAL TEAM
(each)

stand-supports for Junction boxes, lighting fixtures, etc 1.36 Electrical Team 1
lighting junction box 0.56 Electrical Team 1
3-way junction box 0.66 Electrical Team 1

Distribution Board / Distribution Panel / Power Board 7.72 Electrical Team 2


ECB Disconnect switch / outdoor circuit breaker 4 Electrical Team 1
Resistor box 4 Electrical Team 1

Solar Panel 12 Electrical Team 2


Solar Panel JB/ PV combiner box 3.30 Electrical Team 1

Solar Panel Battery Charging Unit 6.36 Electrical Team 2


Navigation-aids Lights (lanterns) 6 Electrical Team 1

Navigation-aids monitoring system 8 Electrical Team 1


Sodium Overhead light / outdoor lighting fixtures 4.55 Electrical Team 1

Fluorescent fitting 4 Electrical Team 1


socket outlet (receptacle) 0.5 Electrical Team 1

Lighting switch 0.5 Electrical Team 1


fog horn system 6 Electrical Team 1

wind generator 6 Electrical Team 2


System charger / controller 6 Electrical Team 2

Battery charger 6 Electrical Team 2


Battery Box 2 Electrical Team 2

Modification of Multi Cable Transit (MCT cable penetration) 3 Electrical Team 1


Cad welding 4 Cadweld Team

Installation of bonding jumpers 0.5 Electrical Team 1


Installation of Servit post 1 Electrical Team 1

Note: modification of MCT has been reduced from 4h to 3h as it seems realistic. We


did not consider 0.55h from EPC4A project as it is far to be enough considering the
difficulty of dismantling & reinstatement of a MCT.

Man-Hours
MISCELLEANOUS INSTALLATION (Hours per TYPICAL TEAM
foot)

Installation of Bird spikes 0.25 Electrical Team 1

4.2.6 Electrical and Instrument Cable Pulling


Man-
Hours TYPICAL TEAM
CABLE PULLING, FINAL DRESSING AND PERMANENT TIE (Hrs
per See comments
foot)

1/C # 350 MCM, 600V, Flexible Metallic Armoured cable or Metal Clad 0.20 Electrical pulling Team

1/C # 600 MCM, 600V, Flexible Metallic Armoured cable or Metal Clad 0.24 Electrical pulling Team

3/C # 14 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.08 Electrical pulling Team

3/C # 12 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.09 Electrical pulling Team

3/C # 10 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.10 Electrical pulling Team
3/C # 8 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.11 Electrical pulling Team

3/C # 6 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.13 Electrical pulling Team

3/C # 4 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.14 Electrical pulling Team
3/C # 2 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.16 Electrical pulling Team

3/C # 1 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.18 Electrical pulling Team

3/C # 1/0 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.19 Electrical pulling Team

3/C # 2/0 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.21 Electrical pulling Team

3/C # 3/0 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.23 Electrical pulling Team

3/C # 4/0 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.25 Electrical pulling Team

6/C # 10 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.10 Electrical pulling Team

7/C # 14 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.11 Electrical pulling Team

10/C # 14 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.11 Electrical pulling Team

19/C # 14 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.12 Electrical pulling Team

1PR # 16 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.07 Electrical pulling Team

2PR # 16 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.08 Electrical pulling Team

4PR # 16 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.09 Electrical pulling Team

8PR # 16 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.10 Electrical pulling Team

12PR # 16 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.12 Electrical pulling Team

16PR # 16 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.12 Electrical pulling Team

24PR # 16 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.12 Electrical pulling Team

2PR # 20 AWG, 600V, Flexible Metallic Armoured cable or Metal Clad 0.07 Electrical pulling Team

Serial Link cable, Armoured, RS485, Belden 0.07 Electrical pulling Team

Antenna cable, coax cable (LDFA-50A) 0.07 Electrical pulling Team

Assumptions:
 Man-Hours for pulling are from “Cost Estimating Manual for Pipelines &
Marine Structures” from John S. Page (Page 261) and “EPC4A HUC
Estimating Methodology Rev 0“.
 Other type and section of cables not found, estimates by preparators.
 Demolition: use 50% of installation norms (cf. EPC4A HUC Estimating
Methodology).

4.2.7 Electrical and Instrument cable glanding and termination

GLAND & TEST CABLE & TYPICAL TEAM


CABLES
TERMINATE DOCUMENTATION See comments

1/C # 350 MCM, 600V, Metal Clad 4.53 5 Electrical Team 2

1/C # 600 MCM, 600V, Metal Clad 7.28 6.96 Electrical Team 2

3/C # 14 AWG, 600V, Metal Clad 0.96 2.65 Electrical Team 1

3/C # 12 AWG, 600V, Metal Clad 1.31 2.73 Electrical Team 1

3/C # 10 AWG, 600V, Metal Clad 1.31 2.9 Electrical Team 1

3/C # 8 AWG, 600V, Metal Clad 1.98 3.41 Electrical Team 1


3/C # 6 AWG, 600V, Metal Clad 2.23 3.48 Electrical Team 1

3/C # 4 AWG, 600V, Metal Clad 2.23 3.48 Electrical Team 1

3/C # 2 AWG, 600V, Metal Clad 2.37 3.73 Electrical Team 1


3/C # 1 AWG, 600V, Metal Clad 2.67 3.73 Electrical Team 1

3/C # 1/0 AWG, 600V, Metal Clad 2.85* 3.9* Electrical Team 1

3/C # 2/0 AWG, 600V, Metal Clad 3* 4.1* Electrical Team 1

3/C # 3/0 AWG, 600V, Metal Clad 3.36 4.31 Electrical Team 2

3/C # 4/0 AWG, 600V, Metal Clad 4.85 5 Electrical Team 2

6/C # 10 AWG, 600V, Metal Clad 3 2.97 Electrical Team 1

7/C # 14 AWG, 600V, Metal Clad 2.19 3.54 Electrical Team 1

10/C # 14 AWG, 600V, Metal Clad 3.1 4.17 Electrical Team 1

19/C # 14 AWG, 600V, Metal Clad 4.16 5.19 Electrical Team 1

1PR # 16 POS, 600V Metal Clad 1.94 2.52 Electrical Team 1

2PR # 16 SPOS, 600V Metal Clad 2.41 2.82 Electrical Team 1

4PR # 16 SPOS, 600V Metal Clad 4.1 3.14 Electrical Team 1

8PR # 16 SPOS, 600V Metal Clad 9.06 3.41 Electrical Team 1

12PR # 16 SPOS, 600V Metal Clad 12.26 3.63 Electrical Team 1

16PR # 16 SPOS, 600V Metal Clad 15* 4 Electrical Team 1

24PR # 16 SPOS, 600V Metal Clad 17.77 4.93 Electrical Team 1

2PR # 20 AWG, 600V, Metal Clad 2.40* 2.80* Electrical Team 1

Serial Link cable, Armoured, RS485,


By other By other BY VENDOR
Belden

Antenna cable, coax cable (LDFA-50A) By other By other BY VENDOR

Assumptions:

 Man-Hours for termination and glanding are from “Cost Estimating Manual for
Pipelines & Marine Structures” from John S. Page (Page 261) and “EPC4A HUC
Estimating Methodology Rev 0“.

 Added cables are returned in red. Man-hours of these are estimate by preparators

4.3 ELECTRICAL AND INSTRUMENTATION TEAMS


We defined 7 typical teams for carrying out all works:

TRADE / composition of team


E&I Team Instrum Tubing
Electrician Helpers H Firewatcher
tech. I fitter T
Instrument Tech
1 - - 1
Team
Instrument
- 1 - 1
Tubing Team
Electrical Team 1 - - 1 1
Electrical Team 2 - - 1 2
Electrical pulling
- - 2<x<4 2<x<6
Team
Cadweld Team 1 1 1
Cable Testing
2
team

Assumptions:
 Riggers will assist us for pulling of cable from cable-reel whenever
necessary.
 Electrical pulling team shall be crew sized (x) by preparator considering
various parameters like length to be pulled, type and section of cables and
simple or complex layout.

For OCIP project, electrical pulling Team could rose up to 10 personnel, with
minima 4 personnel.
We assume Electrical Team 2 will handle pulling of standard cable (i.e. section
below 3Cx2 AWG), length to be pulled below 50 foot and simple layout.
We assume Electrical Team 2 will carry out demolition of tubing, trays and cable

4.4 GENERAL ASSUMPTIONS FOR ELECTRICAL AND INSTRUMENT JOB


CARD PREPARATION
For installation of E&I cables, consider 1 tie-rap every 0.85 foot (4 tie-raps per
meter). This will help us to estimates average quantity of tie-rap necessary.
Consider 4 cables per cable-grouping.
For installation of Instrument tubing, consider 1 gang-clamp or yoke-clamp
every 2 foot.
For installation of Instrument tubing in tray, consider 1 stainless steel tie-rap,
uncoated, every 2 foot.

You might also like