This document describes the components of a basic engineering package, including an equipment list, line list, piping service index, and instrument list. The equipment list provides key details for each piece of equipment in a plant or project. The line list similarly details each pipe segment. The piping service index specifies material and ratings for different pipe classes based on service. And the instrument list outlines major monitoring and control instruments. These documents provide essential information to engineers in developing detailed design packages.
This document describes the components of a basic engineering package, including an equipment list, line list, piping service index, and instrument list. The equipment list provides key details for each piece of equipment in a plant or project. The line list similarly details each pipe segment. The piping service index specifies material and ratings for different pipe classes based on service. And the instrument list outlines major monitoring and control instruments. These documents provide essential information to engineers in developing detailed design packages.
This document describes the components of a basic engineering package, including an equipment list, line list, piping service index, and instrument list. The equipment list provides key details for each piece of equipment in a plant or project. The line list similarly details each pipe segment. The piping service index specifies material and ratings for different pipe classes based on service. And the instrument list outlines major monitoring and control instruments. These documents provide essential information to engineers in developing detailed design packages.
BASIC ENGINEERING PACKAGE EQUIPMENT LIST Equipment list is a document, prepared by Process Engineer with inputs from other disciplines/ Project department Equipment list gives the brief information of each and every equipment of the Plant/ Project in tabular form Equipment list is prepared in conjunction with the PFDs/ PIDs/ PDS BASIC ENGINEERING PACKAGE EQUIPMENT LIST Equipment list gives the following information as minimum: Equipment number Equipment name No. of units – Operating/ Standby Brief details/ specs – Capacity Heat Duty Differential head MoC Power rating Operating Temperature/ Pressure Design Temperature/ Pressure BASIC ENGINEERING PACKAGE EQUIPMENT LIST Equipment list sometimes gives the following additional information: Equipment Weight PID no. / PDS no. to which Equipment is related Plant section identification Whether connected to Emergency power Supply scope/ Vendor name BASIC ENGINEERING PACKAGE EQUIPMENT LIST BASIC ENGINEERING PACKAGE LINE LIST Line list is a document, prepared by Process Engineer with inputs from Piping Engineer Line list gives the details of each and every line in the Project/ appearing on the PIDs, in tabular form Line list is prepared in conjunction with the PFDs/ PIDs Line list forms part of the starting point documents for Piping group to go for detailing BASIC ENGINEERING PACKAGE LINE LIST Line list gives the following information as minimum: Line number Line starting point Line ending point Operating Temperature/ Pressure Design Temperature/ Pressure Insulation details Test requirements – Pneumatic/ Hydraulic Test Pressure BASIC ENGINEERING PACKAGE LINE LIST BASIC ENGINEERING PACKAGE LINE LIST BASIC ENGINEERING PACKAGE PIPING SERVICE INDEX Piping Service Index is a document prepared by Process Engineer, in conjunction with Piping Engineer Piping Service Index gives information about Material of Construction and rating of Piping material for various services in plant It is prepared and presented in tabular form, and contains following information typically: Piping class Fluid being handled Design temperature Design pressure Material of construction Corrosion allowance BASIC ENGINEERING PACKAGE PIPING SERVICE INDEX BASIC ENGINEERING PACKAGE PIPING SERVICE INDEX Key to Piping Service Index: Typical Pipe Class: A1A, A2A, B1A, A1K, A1M, A2F, A2G, A3H
First Letter : Indicates Pressure Rating (for eg. A = 150#, B =
300#, D = 600# etc.)
Third Letter : Indicates Type of material (for eg. A = Carbon
Steel, B = Alloy Steel, F = Galvanized Carbon Steel, G = FRP & PVC/ FRP etc.)
Middle Number : Indicates Difference in specs
for eg. for A, 1 = CA 1.5 mm seamless, 2 = CA 1.5 mm IBR, 6 = CA 3.0 mm etc. for eg. for B, 1 = CA 1.5 mm, 2 = CA 3.0 mm etc. for eg. for F, 1 = CA nil (Drinking water), 2 = CA nil (Instrument Air) etc. BASIC ENGINEERING PACKAGE INSTRUMENT LIST Instrument list (Preliminary/ Process) is a document, prepared by Process Engineer The Instrumentation department prepares/ upgrades a detailed Instrument list, which is part of Detailing activity at later stage. Instrument list gives the brief information of major instruments of the Plant/ Project in tabular form, appearing on PIDs Instrument list is prepared based on the information in the PFDs and PIDs Some companies prepare different lists of instruments for different families of instruments BASIC ENGINEERING PACKAGE INSTRUMENT LIST Instruments listed by Process Engineer’s Instrument list generally covers following: Flow instruments Temperature instruments Pressure instruments Level instruments Control valves Shutoff valves Analysers BASIC ENGINEERING PACKAGE INSTRU MENT LIST Instrument list prepared by Process Engineer, typically gives the following information for the major instruments: Instrument tag number Type Function – Monitor/ Control/ Interlock Location – Field/ Local panel/ Central Control panel Setpoint - for switches/ alarms Material handled – with some important physical properties like density, viscosity, vapor pressure etc. End connections/ sizes BASIC ENGINEERING PACKAGE INSTRU MENT LIST BASIC ENGINEERING PACKAGE INSTRU MENT LIST