Professional Documents
Culture Documents
Purpose 1
References 2
Item Identification 4
Appendices
2.1 References
Process Industry Practices PIC001, P&ID Documentation Criteria
The third part of the equipment number is its sequential identification number
within the system and classification. Therefore, the first tank used in process
system 3-5 would be identified as item 3-5-A-1. The second tank would be 3-5-A-
2, and so forth.
Special situations:
When an object is added to a P&ID or MFD, always use the next available
NEW name. Do NOT re-use an existing name. For example, a tank is
placed into service and is named 3-5-A-3. Subsequent to this tank
installation, many additional tanks are installed. Tank 3-5-A-3 is removed
several years after it was installed. The naming sequence for installing a
new tank has progressed to 3-5-A-8. If a NEW tank installation is now
required, the tank should be named 3-5-A-9. DO NOT re-use the tank
name 3-5-A-3.
5.1 Purpose
3M is a member company of the Process Industry Practices organization (PIP).
PIP has written a practice for the development of Piping and Instrumentation
drawings (P&IDs), PIC001. 3M is adopting PIC001 as the basis for drawing P&IDs;
however some exceptions and additions to PIC001 based on 3M requirements
need to be made. Since PIC001 cannot be modified by individual companies, the
purpose of this section is to list deviations from PIP PIC001 specific to 3M.
Section 4.2.1.14 of PIC001 refers to using typical details. Details may be used as
long as they do not require implied components.
Section 4.3 of PIC001 refers to Appendix A-2 for equipment symbols. Additional
symbols allowed on 3M P&IDs are included in 3M Drawing E-12-1501-0108.
Section 4.3.1.4 of PIC001 refers to equipment identification. Note that the method
in PIC001 is for illustrative purposes only and is not a requirement of the practice.
See 3M Manual 13, Section L, Paragraph 4 for 3M equipment identification
methods.
Section 4.4.2 of PIC001 refers to line service codes contained in Appendix A-3. 3M
line service codes are listed in 3M Manual 13 Section C. Where conflicts arise
between 3M and PIP line service codes, 3M line service codes should be used in
pipeline naming.
Section 4.4.4.5 of PIC001 refers to not showing root valves. Implied components
are not allowed per Section 3.0 of PIC001.
Section 4.5.2.2 refers to not showing root valves. Implied components are not
allowed per Section 3.0 of PIC001.
The plug valve symbol in Appendix A-3 page 4 shall not be used. See 3M Drawing
E-12-1501-0108 for the 3M plug valve symbol.
Filters shall be tagged as piping specialties if the inside diameter of the housing is
under 6 inches; if the filter housing is 6 inch inside diameter or larger, it shall be
tagged as equipment.
The PFD is not a construction document and should not be included with project
bid or construction packages. The PFD is a 3M Confidential document.
6.2 References
The ‘Piping Guide’, David R. Sherwood and Dennis J. Whistance, Syentek Inc.
6.3 Definitions
Process Flow Diagram (PFD): an unscaled simplified graphic representation of
a process.
6.4 General
For issues not directly addressed in this document refer to PIP PIC001 and 3M
Manual 13 Section L, Paragraph 5.
6.5 Format
The drawing size is 22" x 34" (3M D size). Layout each PFD to avoid clutter.
Use multiple sheets if necessary. Show primary process flow on each PFD
from left to right. For issues of layout, lines, and text refer to PIP PIC001 and
3M Manual 13 Section L, Paragraph 5.
See Appendix A of PIC001 for PFD symbols. For symbols not covered by
Appendix A refer to 3M Manual 13, Section L, Paragraph 5.
6.7 Instrumentation
Show instrumentation that is essential to process control, and provides a clear
understanding of the process control scheme. Show process and utility control
valves, along with a simplified control loop. Do not show control valve instrument
bubbles.
6.8 Piping
Process and utility lines on the PFD shall be designated by stream number. The
process line stream number shall be as follows:
P-1
Where P represents a process line and 1 is a sequence number. Note the origin
and destination of process lines on the PFD.
Do not show bypass lines, line size, line class (pipe specification), vent or drain
connections on the PFD. Show the following piping only if required by a
governing code or regulation, or if they are essential to the process: isolating,
sampling, and pressure relief.
Other important stream properties such as phase, viscosity, and composition may
be included. In addition, stream tables may be supplied showing various phases
of the process such as startup, normal, etc.