Professional Documents
Culture Documents
net/publication/257947267
CITATIONS READS
2 3,794
1 author:
Abbas M. Abd
University of Diyala
70 PUBLICATIONS 169 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Abbas M. Abd on 19 July 2015.
Abstract
The completion of any project in its period of time, which listed in the contract is
one of the most difficult matter, that can not be achieved unless several activities
must be done during the project life cycle. The main factors that affected the
delay in project completion are investigated in this study, taking into account the
circumstances of each factor relative to the other. The direct investigation,
interviews with the team of project ( design, in situ office, consultant ) and the
questionnaire methodologies was used to collect data about the project stages and
problems.
The study illustrate the main factors that causes delay in project completion, the
extreme item was finance related, building materials related and project
management related factors. The rate of them to total delay were 22 %, 18.4 %
and 14.7 % respectively, and total delay caused by them was 55.1 % of total
project delay.
In finance the critical value was of delay in payment, weather; in the building
materials the critical one was of the delay in supplying materials, while for the
project management item the risk was in the fail in the in situ management.
Introduction
Delay in construction projects can be defined as the time difference between the
date of project completion stated in the contract and the date of the actual
completion.
It is in general for construction management, that the project may be regarded as
successful if the building is completed on time, within budget, and is of the desired
quality. It is commonly that whereas two out of those three can often be achieved,
three out of the three cannot because of the complexities involved in a
construction contract, and in particular the many different trades and professions
that are commonly involved.
Realistic construction time is now increasingly of the essential elements because it
often serves as a crucial benchmark for assessing the performance of a project
and the efficiency of the project organization. A fundamental specification of the
construction contract is the project period or time of project execution, which is
established prior to bidding. The successful execution of construction projects
and keeping them within estimated cost and prescribed schedules depend upon a
methodology that requires expert engineering judgment.
Project completion for the owner means that he can make use of his new assets on
time by habitation, renting, or selling. Any delay in project completion will
disturb his plans. The client will not be able to make use of the property, and his
business will be affected in almost all areas, especially finance. For the contractor,
any delay in completion of the project gives rise to indirect overhead expenses
and additional payments to the project staff and workforce. It also means that he
will possibly be subjected to compensation claims. His next project might be
cancelled as a result of delays in the present project, and loss of future
opportunities will be made more likely by damage to his reputation and
credibility. The consultants and all other parties involved will also lose if the
project is delayed: they will at least lose time, which may mean losing money.
Despite the great effort that has been put into the evolution of construction
project planning and control during the last four decades, delay is still a very
common feature of construction projects, and most experience extensive delays.
These often result in adversarial relationships between construction stake holders
(clients, contractors, consultants, etc.): distrust, litigation, arbitration, cash-flow
problems, and a general feeling of apprehension towards each other.
Types of Delay:
There are several types of delay in construction projects according to the liability
of these projects, the occurrence of the delay and the effects of the delay. The
major delay types are a following (1):
1- according to the liability of the construction parties:
this type falls of delay into two major categories, excusable and non excusable
delay. It excuses a contractor from performing within the contract period and
justifies an extension of time to perform. This type of delay can also have an
impact on non-critical activities which need more detailed analysis to determine
whether additional time extension is warranted or if the reduction of float time
can be justified. Generally, whether delays are excusable depends on contract
provisions. Acts of God, unexpected weather, labor disputes, owner design
problems, owner-initiated changes and similar factors may cause excusable
delays.
Delays are generally excusable when another party caused but could have
avoided them, or when they were due to environmental factors
beyond the control or foresight of anyone. Excusable delays can be further
classified into compensable and non-compensable Excusable delay is "a delay to
completion which is caused by matters deemed to be outside the control of the
contractor"
3- According to effect
Delay in some activities may result in delay to the overall project completion and
in other activities it may have no impact upon completion. In other words, delay
can be classified into two major categories according to the effect on the time
schedule:
A. Critical delays
Delays that result in extended project completion times are known as critical
delays. In the case of excusable critical delays, the contractor will generally be
entitled to a time extension. Changing the type of structural steel members
while the contractor is erecting structural steel is a clear example of a critical
delay that is likely to delay the contractor’s overall completion of the project.
B. Non-critical delays
Non-critical delays are delays incurred off the critical path which do not delay
ultimate project performance. If the delay in this case is excusable, the contractor
does not have the right to receive a time extension, because this type of delay does
not have an effect on the overall completion of the project. However, non critical
delays may affect the contractor’s cost performance; in this case, the contractor
may have the right to receive additional performance costs. The types of delay are
classified as:
Non-excusable: Construction company gets no time or money and pays
liquidated damages
Excusable Non-Compensable: Construction company gets time, but no
money
Excusable Compensable: Construction company gets both time and money
Concurrent: Construction Company will not get either time or money and
no liquidated damages will be applied.
Causes of Delay:
The main causes of delay are (2):
1- Design-Related Delay
A. This is one of the most critical categories among the five delay categories
because all of the causes were identified as key delays, i.e. a delay is most likely to
happen due to a design-related problem. According to the survey, design-related
delays are considered to be excusable compensable delays.
2- Construction Related Delay
A. In the construction stage, the contractor always has the responsibility and the
construction company will get no time or money if a delay occurs. Delays due to
lack of inspections are the most common in this stage.
3- Financial/Economic-Related Delay
A Delayed payments were selected as the only key delay. According to the results,
delays rarely occur because of Financial/Economic reasons. The Owner of the
project always has the responsibility, which means that the delay will be
excusable compensable.
4- Management/Administrative-Related Delay
A Similar to the previous category, this also has just one key delay: Contract
Modifications. However, the two parties involved (owner and contractor) must
bear the responsibility depending on the cause of the delay. The type of delay is
also dependent on what caused the delay.
5- Regulations and Code-Related Key Delays
A. This category has the most influence on delay, especially on projects built in
coastal areas. Very often, the Government is responsible and, in this case, the
delays are considered excusable compensable.
Case study
For test the previous logical reasons of delay, The flats project in Diyala
university was taken as a case study. This project is one of the largest project
constructed on Diyala governorate. The project cost is more than three pillions ID
which equal to two millions US dollars. The time for completion is 9 months. This
project have been delayed about 100 % of actual period, the details of this period
of delay is distributed as in table( 1 ).
The detailed study of the delay causes consist of two main categories; the
arrangement delay causes which related to design related, construction related,
finance related, management related factors. All these factors should be take in
consideration to analyze the causes of delay in all project types. The second
category is the in situ delay causes which consist of building materials, Tools and
Equipments, Human resources and Project management.
The studying of these factors will surround the main resources of delay for the
project under consideration. The following factors are the main cause of delay
and they will discussed in details later and each item will symbol with character
to make the analyzing and tabling more easy. The details of these factors are
listed as below:
The project which taken as a case study exposed to accurate analyzing in all
direction; the contractor team , the in situ office staff and the designer team
and the consultant team. The data was collected from the real person who
mange the different stages of project via the direct participation with the
teams, interviews and questionnaire of opinions along the period of
construction.
1, C1
45
40
35
30
25 1
20 2
1, B1
15 3
1, A1
10
1, D1
5
0
A B C D
Figure (1) showed that the item 1C1 ( delay in payment ) is the most critical
item in project delay over all its life cycle. The accumulative delay is due to
finance related factors which represent 60/128 days or 46.9 % of total
arrangement delay.
2, A1
25
2, B1 2, D1
20
15
1
2
10
3
2, C1
0
A B C D
From figure (1), the extreme value is for the delay of the payment of the
contracts which may cause financial deficiencies that result in break the
continuity of work progress. This type of delay can consider as excusable
compensable delays and the contractor have the right to receive a time
extension, because this type of delay have an effect on the overall completion
of the project. However, this critical delays may affect the contractor’s cost
performance; in this case, the contractor may have the right to receive
additional performance costs. This type of delay represent 75% of finance
related causes as in figure ( 3 ), and about 35% of the arrangement delay
causes and finally about 16.5 % of total delay causes.
unadequate
financial admin.
8%
liquid deficiencies
17%
Delay in
payments
75%
Finance Related
causes
22%
other causes
44.9%
Building Materials
Causes
Project 18.4%
Management
Causes
14.7%
From other side of view, the three extreme causes of delay in the project are:
1- Finance related (1C) with rate of 22 % of total delay causes.
2- Building materials (2A) with rate of 18.4 % of total delay causes.
3- Project management (2D) with rate of 14.7 % of total delay causes.
The three factors above are represent about 55.1 % of total delay causes in the
project during its life cycle as showed if figure ( 5 ). So the brief result will be in
finance the critical value was of delay in payment, weather; in the building
materials the critical one was of the delay in supplying materials, while for the
project management item the risk was in the fail in the in situ management.
References :
الملخص
إن إنجاز أي مشروع إنشائي ضمن المدة المحددة في عقد المقاولة هو منن األمنور الصنعبة التحقينخ خصو نا
عندما تكون ظروف التنفيذ مختلفة عن الظرف الطبيعي للعمل .وهذا بدوره أمر ال يمكن تحقيقه بندون إنجناز
عدد من الفعاليات خالل دورة حياة المشرع.
إن العوامل األساسنية المنثررة فني عنصنر التنأخير فني إنجناز المشنروع دند تنل التحقنخ منهنا فني هنذه الدراسنة
اخذين بنظر االعتبار الظروف المحيطة بكل عامل نسبة إلى بادي العوامل األخرى.حيث جرى اعتماد أسنلوب
التحقخ المباشر والمقابالت الشخصية مع فريخ التصميل والتنفيذ والفريخ االستشاري للمشروع إضافة إلنى
أسلوب االستبيان الذي شمل عدد من المهندسين ذوي االختصاص في الموضوع .وذلك بهدف جمع البيانات
بأكبر ددر ممكن من الددة لتو يف األسباب المثدية إلى التأخير في إنجاز المشروع ضمن المدة المحددة.
خلصت الدراسة إلى تحديد العوامل الرئيسية المسببة في التأخير وكانت القيمة الحرجة فني ذلنك بسنبن عنصنر
التمويننل يليننه مننواد البنننا وأخيننرا عنصننر اإلدارة بالنسننن % 22و % 4..1و % 41.1علننى التننوالي.
وكانت هذه العنا ر الثالرة تمثل نسبة %...4من مجمل التأخير الكلي للمشروع.
ومن بين فقرات عنصر التمويل كان تأخير تسليل دفعنات المقناول أهنل أسنباب التنأخير ،أمنا فيمنا يخنص عنصنر
مواد البنا فقد كان تأخير تجهين منواد البننا الفقنرة األكثنر تسنببا فني التنأخير فني حنين كنان ضنمن عنصنر
اإلدارة فقرة إدارة المشروع هي الحرجة من حيث التأخير.