Professional Documents
Culture Documents
Every project requires a method to control and manage the execution and delivery of
the project. Project managers across the globe have followed different methods of
monitoring a project.
This method allows project managers to assess a project's progress over time and
allow project teams to understand the health and performance of their projects.
Generally, projects are measured against a budget by looking at actual dollars spent
and the project's percentage complete. The key measure of percentage complete is
usually dependent upon the estimators guess and varies widely from one individual
to another. Earned value will give project managers a more accurate measurement
of a project's status.
Projects today usually employ a concept known as the Work breakdown Structure or
WBS. A WBS is supposed to be a direct representation of the work scope in the
project, documenting the hierarchy and description of the tasks to be performed and
relationship to the product deliverables. Although most of the projects do employ a
WBS in scheduling a project, the use of the WBS usually stops at that,
SCHEDULING a project.
WBS in its true manifest is a hierarchical break down of all authorized work scope
into appropriate elements for planning, budgeting, scheduling, cost accounting, work
authorization, measuring progress, and management control. The WBS must be
extended to the level necessary for management action and control based on the
complexity of the work.
Each element of the WBS forms the elementary building block of the structure known
as “resource loaded and budgeted schedule of a project”. This resource loaded and
budgeted schedule then forms the bedrock of the concept known as the EVM.
Every line item of a WBS must be assigned the following three variables.
a. Duration
b. Budget
c. Resource
Assignment of the three variables to each line item of the WBS provides the
following information about the project.
a. Project Schedule
b. Project Budget
c. Project Resource
The resource loaded and budgeted schedule of the project so obtained is used as
the reference for project execution, monitoring and reporting. This is known as the
base line schedule. This base line schedule has a value assigned to each WBS
element which is known as the budgeted cost of the WBS element. As the project
progresses, with the completion of each WBS line item, the budgeted value of the
WBS element is earned as a measure of project progress. Hence the name Earned
Value Management.
Earned Value Management allow the project manager to answer the following three
questions, as they relate to the project:
In Earned Value Management, unlike in traditional management, there are three data
sources:
Earned Value takes these three data sources and is able to compare the budgeted
value of work scheduled with the “earned value of physical work completed” and the
actual value of work completed.
The following are key parameters as used in the Earned Value management of
project management.
1. Planned Value (PV): This is the total value of the project. This is the answer to
the question “How Much work Is to Be Done?”
2. Earned Value (EV): This is the measure of mount of work done as on a
particular instant of time. This is the answer to the question “How Much Work
has been done?”
3. Actual Cost (AC): This is the cost incurred to achieve the earned value at the
particular instant of time. This is the answer to the question “What has been
spent for the Earned Value?”
PS: The topic of EVM is fairly big and detailed nuances of the same cannot be
brought out in a short paper. However I feel that this should help
practicing as well as aspiring project manages to get over the perceived
unsurmountable complexity of EVM. If well planned and followed, EVM
can serve to be the perfect GPS for project navigation through its
lifecycle.
References:
1. Project Management Institute. (2004) A Guide to the Project
Management Body of Knowledge (PMBOK® Guide). (Third ed.)
Newtown Square, PA: Project Management Institute
2. Project Management Institute. (2005) Practice standard for earned
value management (PMI Global Standard) (2005 ed.) Newtown
Square, PA: Project Management Institute
3. Reichel, C. W. (2006). Earned value management systems (EVMS):
"you too can do earned value management" Paper presented at PMI®
Global Congress 2006—North America, Seattle, WA. Newtown
Square, PA: Project Management Institute.