PROJECT REVITALISASI WORKSHOP HIA HAJU SITE MACO

Project : Revitalisasi Workshop Hia Haju/ Pitstop KM 39


Contractor : PT. LSS Global Kontraktor
Contract No :
Location : Site MACO

CONSTRUCTION DAILY ACTIVITIES REPORT


Report No Working Hour Date of Report Weather
07.00 to 17.00 08/07/2022 Cerah

Total Hours Major Equipment &


Manpower QTY Unit QTY Unit Total Hours
Normal Overtime Tools
Project Manager 0 person 0 0 besi 13 mm 8 ljr
Site Manager 1 person 8 0 plesser 13 mm 4 pcs 8
Supervisor 0 person 0 0 cutting wheels 1 Unit 8
Site Engineer 1 person 8 0 las listrik 1 Unit 8
Drafter/Site Engineer 0 person 0 0 tang catut 4 pcs 8
QA/QC Coordinator 0 person 0 0
QA/QC Site 0 person 0 0
HSE Officer 1 person 8 0
HSE Man/SafetyMan 0 person 0 0
Admin 0 person 0 0
Foreman 0 person 0 0
Operator
Excavator 0 person 0 0
Dump Truck 0 person 0 0
Rigger 0 person 0 0
Surveyor 0 person 0 0
Asisten Surveyor 0 person 0 0
Driver 0 person 0 0
Civil Crew 11 person 88 0
Helper 0 person 0 0

Total 14 112 0 Total 18 32

Safety
Total Man-Hours Last 24 Hours : 0 Hours Fatality : 0
Total Cummulative Man-Hours : 0 Hours Lost Time Incidents : 0
Total Man Hours Since Last LTA : 0 Hours Day Lost : 0
Medical Treathment Case : 0
Total Recordable Accident Rate : 0

First Aid Case : 0


Near Miss : 0
Total Non Recordable Accident : 0

DESCRIPTION OF WORK PERFORM TODAY : DESCRIPTION OF WORK PERFORMED TOMMORROW :


- Fabrikasi Besi Lantai base

WEATHER CONDITION START FINISH


Cerah 7:00 13:00
Cerah 13:00 17:00
Cerah 17:00 21:00
CPY COMMENTS :

Remarks By Contractor (Delays, Interrptions, Problems, Deviations, Extra Work Activities, Unusual Occurence's, etc. Relevant to Today's Work
- Urugan Material Keras Base pit stop

Prepared By : Verified By :
PT. LSS Global Kontraktor PT. Saptaindra Sejati

(_ELFRAN RIZKY P ) (_____________________________)


Site Engineer