Project : INSTAL & FABRIKASI PIPA + COVER FILTER DRUM Date : 13-Jun-23
Location : PT.INDOFERMEX DEPOK Client : STEVEN
Reported By : RANDA ERLANGGA
Manpower & Manhours HSE Performance
No Ket Jam Jml Manhours No Item Total Keterangan
MB 1 Fatality 0
1 Manpower 8 10 80 2 Lost Time Incident 0
2 Manpower 2 10 20 3 Medical Treatment Case 0
0 0 0 4 First Aid Case 0
Tata 5 Environmental Violation 0
1 Manpower 0 0 0 6 Fire Incident 0
2 Manpower OT 0 0 0 7 Covid Case 0
Total Manpower MB 10 8 Permit 2
Total Manhours MB 100 9
Equipment Inspection
No Item Total Keterangan No Item Total Keterangan
1 Mesin gerinda 3 6 APAR 1
2 mesin las 2 7 porklif 0
3 panel listrik 0 8 segel 0
4 blower 2 9 Fullbody harness 0
5 sling belt 0 10 crane 0
Permit Release Over time
NO Item Lokasi Total Actifity Actifity NO Time Lokasi Hse Activity
room produksi welding pip , fabrikasi & instal didepan kantor welding pip , fabrikasi & instal
1 Hot work 3 1 13:00 - 17:00 RE
lama suport ,pipa cream dan garam produksi suport ,pipa cream dan garam
didepan kantor
3 ketinggian
produksi
Today Activity
1. Lokasi : Di depan office 2. Lokasi : room packing lama
SPV & HSE : Irsan Hatta & Randa E. SPV & HSE : Irsan Hatta & Randa E.
Activity : Tbm pagi ,pengarahan kerja dan safety,mengingatkan team yg bekerja Activity : welding pip , fabrikasi & instal suport ,pipa cream dan garam
diketinggian selalu perhatikan tumpuan kaki dan harness selalu di cantolkan,dan pasaat
pemeotongan pipa di atas hati2 material yg dipotong jatuh kebawah menimpa orang.