Total 11 88 0 Total 15 0
Safety
Total Man-Hours Last 24 Hours : 0 Hours Fatality : 0
Total Cummulative Man-Hours : 0 Hours Lost Time Incidents : 0
Total Man Hours Since Last LTA : 0 Hours Day Lost : 0
Medical Treathment Case : 0
Total Recordable Accident Rate : 0
Volume Total
Pencapaian Pekerjaan harian Total Volume Sisa Volume
Tercapai Satuan Satuan Keseluruhan Satuan Satuan
Pekerjaan Pekerjaan
harian Pencapaian
- Pengecoran sloof 0,5 m3 8,7 m3 5,85 m3 2,85 m3
Planning Pekerjaan 23 okt 2022 Volume Total Volume Sisa Volume Status Pekerjaan
Satuan Satuan Satuan
Rencana Pekerjaan Pekerjaan
- Pembongkaran Bekisting
- Urugan Galian kembali
- Bowplank pondasi
Remarks By Contractor (Delays, Interrptions, Problems, Deviations, Extra Work Activities, Unusual Occurence's, etc. Relevant to Today's Work
- Project oil trap area menunggu validasi lokasi dan dimensi dari pihak SIS
- Project ws tyre di HOLD menunggu keputusan pihak SIS terkait issue yang berkembang kalau diarea tersebut ada bangunan diluar master plan
Prepared By : Verified By :
PT. LSS Global Kontraktor PT. Saptaindra Sejati
(_Cahyo ) (_____________________________)
Site manager