PROJECT WORKSHOP HIA HAJU SITE MACO

Project : WORKSHOP 3 Bays


Contractor : PT. LSS Global Kontraktor
Contract No :
Location : Site MACO

CONSTRUCTION DAILY ACTIVITIES REPORT


Report No Working Hour Date of Report Weather
07.00 to 17.00 22/10/2022 Cerah

Total Hours Major


Manpower QTY Unit QTY Unit Total Hours
Normal Overtime Equipment &
Project Manager 0 person 0 0 Mesin pompa 1 Unit
Site Manager 0 person 0 0 Pacul 2 Unit
Supervisor 0 person 0 0 Gerinda potong 2 Unit
Site Engineer 0 person 0 0 Mesin Molen 1 Unit
Drafter/Site Engineer 0 person 0 0 Gergaji kayu 3 Unit
QA/QC Coordinator 0 person 0 0 Palu 3 Unit
QA/QC Site 0 person 0 0 Gancu 3 Unit
HSE Officer 0 person 0 0
HSE Man/SafetyMan 0 person 0 0
Admin 0 person 0 0
Foreman 0 person 0 0
Operator
Excavator 0 person 0 0
Dump Truck 0 person 0 0
Rigger 0 person 0 0
Surveyor 0 person 0 0
Asisten Surveyor 0 person 0 0
Driver 0 person 0 0
Civil Crew 11 person 88 0
Helper 0 person 0 0

Total 11 88 0 Total 15 0

Safety
Total Man-Hours Last 24 Hours : 0 Hours Fatality : 0
Total Cummulative Man-Hours : 0 Hours Lost Time Incidents : 0
Total Man Hours Since Last LTA : 0 Hours Day Lost : 0
Medical Treathment Case : 0
Total Recordable Accident Rate : 0

First Aid Case : 0


Near Miss : 0
Total Non Recordable Accident : 0

DESCRIPTION OF WORK PERFORM TODAY : DESCRIPTION OF WORK PERFORMED TOMMORROW :


SITE HAJU Jumlah SITE HAJU Jumlah
Labour Labour
- Pengecoran sloof 10 - Pembongkaran Bekisting 4
- urugan kembali 4
- Bowplank pondasi 2

Volume Total
Pencapaian Pekerjaan harian Total Volume Sisa Volume
Tercapai Satuan Satuan Keseluruhan Satuan Satuan
Pekerjaan Pekerjaan
harian Pencapaian
- Pengecoran sloof 0,5 m3 8,7 m3 5,85 m3 2,85 m3

Planning Pekerjaan 23 okt 2022 Volume Total Volume Sisa Volume Status Pekerjaan
Satuan Satuan Satuan
Rencana Pekerjaan Pekerjaan
- Pembongkaran Bekisting
- Urugan Galian kembali
- Bowplank pondasi

Volume Total Volume Sisa Volume Kendala


Rekap Pekerjaan yang sudah terplaning Satuan Satuan Satuan
Tercapai Pekerjaan Pekerjaan
- Urugan Galian kembali 0 m3 0 m3 0 m3 menunggu alat berat
- Pengecoran Sloof 0,5 m3 1 m3 0,5 m3 selesai
0
0

WEATHER CONDITION START FINISH


Mendung 7:00 13:00
Cerah 13:00 17:00
Cerah 17:00 21:00

Remarks By Contractor (Delays, Interrptions, Problems, Deviations, Extra Work Activities, Unusual Occurence's, etc. Relevant to Today's Work

- Project oil trap area menunggu validasi lokasi dan dimensi dari pihak SIS
- Project ws tyre di HOLD menunggu keputusan pihak SIS terkait issue yang berkembang kalau diarea tersebut ada bangunan diluar master plan
Prepared By : Verified By :
PT. LSS Global Kontraktor PT. Saptaindra Sejati

(_Cahyo ) (_____________________________)
Site manager