WP-PTMWCP-001 06:30 07:30 Validation Suban 27 Survey and Stake Out Menggunakan Total Station and Auto level
WP0000022472 06:30 07:30 Validation Flowline Probing dan Pilot Hole Flowline Suban ROW Flowline
WP0000023619 06:30 07:30 Hold Flowline Loading Unloading and Stringging pipe 16" Inch Using Excavator Flowline Suban 27 ROW suban4
WP0000024028 06:30 07:30 Validation Flowline Team 1. Fit Up Welding Joint Pipe 16" Flowline 27 ROW Suban 4 Area
WP0000023163 06:30 07:30 Hold Flowline Team 2. Fit Up Welding Joint Pipe 16" Flowline 27 ROW Suban 4 Area
WP0000023337 06:30 07:30 Hold Suban 27 Lifting Assist for Levelling and Fit Up Pipe 16" using Excavator at FL Suban 27 ROW Suban 4
Laydown near
WP0000023673 06:30 07:30 Hold Loading Unloading Pipa using crane 51 Ton at Laydown near Suban 14
Suban 14
WP0000023792 06:30 07:30 Validation Flowline NDT Radiography Fowline Suban 27, ROW
WP0000023337 06:30 07:30 Hold ROW Suban 4 Lifting Assist for Levelling and Fit Up Pipe 16" using Excavator at FL Sbn 27 ROW Suban 4
WP-PTMWCP-004 06:30 07:30 Validation Suban 27 Manual Digging,Mechanical Excavation Dan Backfill, Soil Disposal Using Dump Truck Dan Excavator
WP-PTMWCP-003 06:30 07:30 Validation Suban 27 Loading Unloading Precast Using TMC 16 Ton Dan Isntall Precast Using Excavator At Well Suban 27
PTW-TEMP-ISSOW-0007 06:30 07:30 Validation Suban 9 Unloading And Installation Separator, Surge Drum And Square Tank Using Crane 51 Ton
2. DOWNTIME
Cum.
Description Prev. Today Remarks
(Hours)
Rainy 51 2 53 Has been raining, time 14.30 - 15.30 & 17.00 - 18.00 Work is momentarily halted due to rainy
Mechanical Breakdown 0 0 0
Permit 16 0 16
Social Issue 4 0 4
Operating Activities 0 0 0
Drilling 0 0 0
3. LIGHT VEHICLES
4. HEAVY EQUIPMENTS
EQUIPMENT TYPE / MANUF. CAPACITY QTY UNIT WORKING HOURS STANDBY REASON FOR STANDBY
TMC Renger 260 JW 16 Ton 1 Unit 007.00 - 18.00 Workshop
Excavator Volvo PC 200 3 Unit 007.00 - 18.00 Flowline
Excavator Komatsu PC 200 1 Unit 007.00 - 18.01 Flowline
Excavator Suny PC 75 1 Unit 007.00 - 18.01 Suban 27
Trailer Quester 1 UNIT 007.00 - 18.00 Workshop
Dumb Truck HINO 300 - 2 Unit 007.00 - 18.00 Workshop
Crane TADANO 51 Ton 1 Unit 007.00 - 18.00 Workshop
5. TOOLS
TOOLS TYPE / MANUF. CAPACITY QTY UNIT WORKING HOURS STANDBY REASON FOR STANDBY
Hammer Wrench varies - - 2 Unit 8 - -
Hammer Bronze 5 kg 2 Unit 9 -
Stamper 1 Unit 8
Welding Machine 2 Unit 8
Grinding Machine 2 Unit 8
Compressor 1 Unit 8
TODAY
1. FABRICATION PIPING AT WORKSHOP AREA
1.1 HSE
- Pre job safety meeting at Workhop Area
- Remind all workers to comply with supervisor's instructions and safe work procedures
- Remind all workers to always wear personal protective equipment during work
2. CIVIL ACTIVITY
2.1 HSE AT MESS CAMP AREA
- Pre job safety meeting at Camp Area
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES
4. SUBAN 9 AREA
- Unloading Pipe Spool of 2", 3", 4" using Crane 51 Ton Suban 9
8. PROGRESS ACTIVITIES
Volume
Cumm.
No Description of work Unit Prev. Remarks
Total Work Today Cum. Progress (%)
Acumm
INSTALLATION OF PIPELINE 16"
1, Stringing Meter 5018,82 3.240 0 3240 65%
2, Fit-up & Welding Joint 497 198 0 198 40%
3, NDT RT Joint 497 124 0 124 25%
4, NDT RT ACC Joint 497 67 8 75 15%
5, NDT RT Repair Joint 497 23 0 23 4,6%
6, NDT RT RSC Joint 497 26 0 26 5,2%
7, Field Joint Coating Joint 497 0 0 0 0%
8, Trenching M 5000 0 0 0 0%
9, Lowering M 5000 0 0 0 0%
10, BackFill M 5000 0 0 0 0%
11, Crossing Road Point 6 0 0 0 0%
12, Bending EA 48 0 0 0 0%
13, Marker & Sign M 55 0 0 0 0%
14, Chatodic Protection M 16 0 0 0 0%
15, Land Clearing M 5018,82 3.240 0 3240 65%
Volume
Cumm.
No Description of work Unit Remarks
Total Work Prev. Acumm Today Cum. Progress (%)
e. WIND SHOCK, KO POT, VENT STACK, SMALL SHELTER FOR CIP & RTU, SOLAR PANEL 19 0 0
Wind Shock EA 1 0 0 0 0%
Instrument KO POT EA 1 0 0 0 0%
Vent Stack Foundation EA 1 0 0 0 0%
Small Shelter for CIP EA 4 0 0 0 0%
Small Shelter for RTU EA 8 0 0 0 0%
Solar Panel EA 4 0 0 0 0%
f. WATCH TOWER 13 0 0
Watch Tower EA 5 0 0 0 0%
PIT EA 1 0 0 0 0%
Corrosion Coupon EA 1 0 0 0 0%
Secondart Contaimebt EA 3 0 0 0 0%
Intrument Trench EA 2 0 0 0 0%
IBC Tank EA 1 0 0 0 0%
g. Fence & Gate 283 0 0
Fences EA 275 0 0 0 0%
Main Gate EA 6 0 0 0 0%
Personal Gate EA 2 0 0 0 0%
h. IN SITU 7 0 0 0%
Floor SCADA RTU EA 1 0 0 0 0%
Corrosion Inhibator Injection EA 5 0 0 0 0%
Guard House EA 1 0 0 0 0%
Volume
Cumm.
No Description of work Unit Remarks
Total Work Prev. Acumm Today Cum. Progress (%)
9. CONCERNS / NOTES
1. N/A
11. COMPANY COMMENTS
HSE Concern :
1. -
Engineering Concern :
1. -
QC Concern :
1. -
Construction Concern :
1. -
12. PROGRESS PICTURES
A. CIVIL ACTIVITIES AT FABRICATION CAMP OFFICE & INSTALLATION PRECAST AT SUBAN 27 AREA
Subcont Install Bekisting Pedestal Foundation Type F - Continue Fabrication Install Bekisting Pedestal Foundation
Leveling the sand before compacting
6 qty= 6 ea Type F-7 qty= 8 ea
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES
Compacting sand bedding using a stamper Continued performance of backfilling foundation today type
B.SUBAN 9 AREA
Unloading Pipe Spool of 2", 3", 4" using Crane 51 Ton Unloading Pipe Spool of 2", 3", 4" using Crane 51 Ton
Suban 9 Suban 9.