You are on page 1of 8

CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

1. GENERAL 2. Health, Safety and Environment

1.1. Weather Update

Location Time Weather Manhour Prev. Today Cumm.


Workshop PTM-WCP 06.00 - 09.00 Clear Total Manhour 73518 1550 75068
Workshop PTM-WCP 09.00 - 12.00 Clear Near Miss 0 0 0
Workshop PTM-WCP 12.00 - 15.00 Rainy Medical Treatment Case (MTC) 0 0 0
Workshop PTM-WCP 15.00 - 18.00 Rainy Restricted Work Case (RWC) 0 0 0
Lost Workdays Case (LWC) 0 0 0

1.2. Number of Personnel On Board (POB) First Aid Case (FAC) 0 0 0


Fatality 0 0 0
Detail Position Personnel (Pax) Remarks Total Recordable Incident Rate 0 0 0
INDIRECT MANPOWER Motor Vehicle Incident 0 0 0
Project Manager 1 Manpower Outside Boundary Fire/Property Damage 0 0 0
Const. Superintendent/ Lead 1 Manpower Outside Boundary Life Saving Rules 0 0 0
General Affair (Procurement) 1 Manpower Outside Boundary Safety Card 0 0 0
QC Cordinator 1 Manpower Outside Boundary
Quality Control Inspector 3 Manpower Inside Boundary 3 SITE DOCUMENTATION
QC/QA Admin 1 Manpower Outside Boundary Description Prev. Today Cumm.
Project Engineer 1 Manpower Outside Boundary Site Query - - -
Project Control 1 Manpower Outside Boundary NCR - - -
Site Planner 2 Manpower Outside Boundary
Drafter 1 Manpower Outside Boundary
Surveyor 2 Manpower Inside Boundary PTW - New 4 0 4
DIRECT MANPOWER PTW - Revalidated 2 0 2
Admin HRD Site 1 Manpower Outside Boundary
Admin Project 1 Manpower Outside Boundary PTW - Hold 7 0 7
PTW Coordinator 1 Manpower Inside Boundary PTW - Closed 0 0 0
HSE Coordinator 1 Manpower Outside Boundary
Safety Officer 1 Manpower Outside Boundary
Safety Standby 4 Manpower Inside Boundary
Paramedic 2 Manpower Inside Boundary
Blaster Painting 5 Manpower Outside Boundary
Logistic 2 Manpower Outside Boundary
Material Control 1 Manpower Outside Boundary
WORKSHOP PIPING FABRICATION
Supervisor Fabrication 1 Manpower Outside Boundary
Welder 9 Manpower Outside Boundary
Fitter 4 Manpower Outside Boundary
Technician 1 Manpower Outside Boundary
CIVIL FABRICATION
Supervisor Civil 1 Manpower Outside Boundary
Carpenter 1 Manpower Outside Boundary
Rebarman 2 Manpower Outside Boundary
Helper 13 Manpower Outside Boundary
CIVIL SUB-CONTRACTOR
Supervisor Civil 1 Manpower Outside Boundary
Carpenter 3 Manpower Outside Boundary
Rebarman 3 Manpower Outside Boundary
Helper 12 Manpower Outside Boundary
PIPELINE
Operator Excavator 3 Manpower Inside Boundary
Operator Trailer 1 Manpower Inside Boundary
Operator TMC 1 Manpower Inside Boundary
Operator Dumb Truck 2 Manpower Inside Boundary
Supevisor Pipeline 1 Manpower Inside Boundary
Fitter 4 Manpower Inside Boundary
Grinder 4 Manpower Inside Boundary
Welder 9 Manpower Inside Boundary
Helper 4 Manpower Inside Boundary
TRENCHING LOWERING BACKFILL
Supevisor TLB 1 Manpower Outside Boundary
Helper TLB 5 Manpower Outside Boundary
SUPPORTING
Scaffolder 3 Manpower Outside Boundary
Rigger 7 Manpower Inside Boundary
Driver 5 Manpower Outside Boundary
Electrical Technician 3 Manpower Inside Boundary
Helper Surveyor 2 Manpower Inside Boundary
Helper Blaster Painting 1 Manpower Outside Boundary
NDT 5 Manpower Inside Boundary
Security Camp 1 Manpower Outside Boundary
Security Warkshop 1 Manpower Outside Boundary
Humas 2 Manpower Outside Boundary
OB 3 Manpower Outside Boundary
Satgas 2 Manpower Outside Boundary

Total Personnel On Board (PTM-WCP) 155


CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

3.1. Permit to Work (PTW)

PTW Number Time Issued Time Approved Status Location Remarks

WP-PTMWCP-001 06:30 07:30 Validation Suban 27 Survey and Stake Out Menggunakan Total Station and Auto level

WP0000022472 06:30 07:30 Validation Flowline Probing dan Pilot Hole Flowline Suban ROW Flowline

WP0000023619 06:30 07:30 Hold Flowline Loading Unloading and Stringging pipe 16" Inch Using Excavator Flowline Suban 27 ROW suban4

WP0000024028 06:30 07:30 Validation Flowline Team 1. Fit Up Welding Joint Pipe 16" Flowline 27 ROW Suban 4 Area

WP0000023163 06:30 07:30 Hold Flowline Team 2. Fit Up Welding Joint Pipe 16" Flowline 27 ROW Suban 4 Area

WP0000023337 06:30 07:30 Hold Suban 27 Lifting Assist for Levelling and Fit Up Pipe 16" using Excavator at FL Suban 27 ROW Suban 4
Laydown near
WP0000023673 06:30 07:30 Hold Loading Unloading Pipa using crane 51 Ton at Laydown near Suban 14
Suban 14
WP0000023792 06:30 07:30 Validation Flowline NDT Radiography Fowline Suban 27, ROW

WP0000023337 06:30 07:30 Hold ROW Suban 4 Lifting Assist for Levelling and Fit Up Pipe 16" using Excavator at FL Sbn 27 ROW Suban 4

WP-PTMWCP-004 06:30 07:30 Validation Suban 27 Manual Digging,Mechanical Excavation Dan Backfill, Soil Disposal Using Dump Truck Dan Excavator

WP-PTMWCP-003 06:30 07:30 Validation Suban 27 Loading Unloading Precast Using TMC 16 Ton Dan Isntall Precast Using Excavator At Well Suban 27

PTW-TEMP-ISSOW-0007 06:30 07:30 Validation Suban 9 Unloading And Installation Separator, Surge Drum And Square Tank Using Crane 51 Ton

2. DOWNTIME

Cum.
Description Prev. Today Remarks
(Hours)
Rainy 51 2 53 Has been raining, time 14.30 - 15.30 & 17.00 - 18.00 Work is momentarily halted due to rainy
Mechanical Breakdown 0 0 0
Permit 16 0 16
Social Issue 4 0 4
Operating Activities 0 0 0
Drilling 0 0 0

3. LIGHT VEHICLES

DRIVER NAME VEHICLE TYPE TIME PREV. MILEAGE CURRENT ROUTE


VEHICLE NO. REG. NO
MIL.
Budi Setiadi Toyota Hilux 4WD BH 3176 XX PTM/WCP-SWF-001 06.00-18.00 - - Suban area
Dede Toyota Hilux 4WD BH 8841 XX PTM/WCP-SWF-002 06.00-18.00 - - Suban area
Habibi Pajero B 2647 XX PTM/WCP-SWF-003 06.00-18.00 - - Suban area
Rio Elf - - 06.00-18.00 - - Suban area
Yuhendri Elf - - 06.00-18.00 - - Suban area

4. HEAVY EQUIPMENTS

EQUIPMENT TYPE / MANUF. CAPACITY QTY UNIT WORKING HOURS STANDBY REASON FOR STANDBY
TMC Renger 260 JW 16 Ton 1 Unit 007.00 - 18.00 Workshop
Excavator Volvo PC 200 3 Unit 007.00 - 18.00 Flowline
Excavator Komatsu PC 200 1 Unit 007.00 - 18.01 Flowline
Excavator Suny PC 75 1 Unit 007.00 - 18.01 Suban 27
Trailer Quester 1 UNIT 007.00 - 18.00 Workshop
Dumb Truck HINO 300 - 2 Unit 007.00 - 18.00 Workshop
Crane TADANO 51 Ton 1 Unit 007.00 - 18.00 Workshop

5. TOOLS

TOOLS TYPE / MANUF. CAPACITY QTY UNIT WORKING HOURS STANDBY REASON FOR STANDBY
Hammer Wrench varies - - 2 Unit 8 - -
Hammer Bronze 5 kg 2 Unit 9 -
Stamper 1 Unit 8
Welding Machine 2 Unit 8
Grinding Machine 2 Unit 8
Compressor 1 Unit 8

6. SITE CONSTRUCTION NARRATIVE

TODAY
1. FABRICATION PIPING AT WORKSHOP AREA
1.1 HSE
- Pre job safety meeting at Workhop Area
- Remind all workers to comply with supervisor's instructions and safe work procedures
- Remind all workers to always wear personal protective equipment during work

1.2 Piping Activities


- Welding total of 73 joint for Suban 9 Area.
- Pipe 2" total joint = 14 Joint
- Pipe 3" total joint = 53 Joint
- Pipe 4" total joint = 6 Joint
- Unloading pipe spool of 2", 3", 4" using Crane 51 Ton Suban 9
- Progress of blasting and painting on piping 12"
- Dwg No: 3242. Sheet: 9 of 15. Join: 47 & Dwg No: 3241. Sheet: 8 of 15. Join: 57

2. CIVIL ACTIVITY
2.1 HSE AT MESS CAMP AREA
- Pre job safety meeting at Camp Area
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

2.2 Civil Activities Camp Mess Area & Sub-Contractor


- Subcont Fabrication Rebar Pedestal Foundation Type F-8 qty= 11 ea
- Subcont Install Bekisting Pedestal Foundation Type F-6 qty= 6 ea
- Continue Fabrication Install Bekisting Pedestal Foundation Type F-7 qty= 8 ea
- Preparation Pouring Concrete Pedestal Foundation type F-7 qty= 8 ea
- Fabrication Rebar Footing Foundation Type F-11 qty= 5 ea

2.3 Installation Precast Suban 27 Area


- Continued performance of backfilling foundation today type F-9 Prev= 6 ea today= 2 ea cum= 8 ea
- Compacting sand bedding using a stamper

3. SUBAN FLOWLINE AREA


- Total joint Pipeline 16" = 198 Joint
- Total stringing (270 Pipe = 3,240 meter)

4. SUBAN 9 AREA
- Unloading Pipe Spool of 2", 3", 4" using Crane 51 Ton Suban 9

NEXT DAY PLAN


1. FABRICATION PIPING AT WORKSHOP AREA
- Continuing Unloading & Install Container

2. FABRICATION CIVIL At Camp Area


- pouring concrete Pedestal cable tray foundation qty= 9 ea
- Continue Pouring Concrete Footing Foundation Type F-7 qty= 8 ea
- Pouring Concrete Footing Foundation Type F-10 qty= 6 ea
- Pouring Concrete Footing Instrument Stachion Foundation qty= 6 ea

3. SUBAN FLOWLINE AREA


- Continue Repair Welding double joint pipe 16"
- Continue NDT RT on Pipeline 16" KP-02
- Continue Pipe stringing

7. CAMP AREA ACCOMODATION STATUS

TOTAL (Pax) FILLED AVAILABLE


80 80 0

8. PROGRESS ACTIVITIES

8.1 Pipeline Installation Activities

Volume
Cumm.
No Description of work Unit Prev. Remarks
Total Work Today Cum. Progress (%)
Acumm
INSTALLATION OF PIPELINE 16"
1, Stringing Meter 5018,82 3.240 0 3240 65%
2, Fit-up & Welding Joint 497 198 0 198 40%
3, NDT RT Joint 497 124 0 124 25%
4, NDT RT ACC Joint 497 67 8 75 15%
5, NDT RT Repair Joint 497 23 0 23 4,6%
6, NDT RT RSC Joint 497 26 0 26 5,2%
7, Field Joint Coating Joint 497 0 0 0 0%
8, Trenching M 5000 0 0 0 0%
9, Lowering M 5000 0 0 0 0%
10, BackFill M 5000 0 0 0 0%
11, Crossing Road Point 6 0 0 0 0%
12, Bending EA 48 0 0 0 0%
13, Marker & Sign M 55 0 0 0 0%
14, Chatodic Protection M 16 0 0 0 0%
15, Land Clearing M 5018,82 3.240 0 3240 65%

8.2 Piping Activities Suban 27

Total Fabrication Piping


Cumm.
No Description of work Unit Prev. Remarks
Total Work Today Cum. Progress (%)
Acumm
FABRICATION PIPING 12" (WELDING JOINT)
1, Handling, Cutting & Fit up Dia Inch 6582,1 432 0 432 6,56%
2, Welding Dia Inch 6582,1 432 0 432 6,56%
3, NDT ACC Joint 1156 17 0 17 1,47%
4, NDT Repair Joint 0 0 0 0 0%
5, Blasting m2 0 0 0 0 0%
6, Painting Primer m2 0 0 0 0 0%
7, Painting Top m2 0 0 0 0 0%
8, Inspection Dwg 0 0 0 0 0%
Total
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

8.3 Piping Activities Suban 9

Total Fabrication Pipe Spool


Cumm.
No Description of work Unit Prev. Remarks
Total Work Today Cum. Progress (%)
Acumm
FABRICATION PIPE SPOOL (WELDING JOINT) For Suban 9
1, Welding Piping 2" Dia Inch 30 24 4 28 93%
2, Welding Piping 3" Dia Inch 171 153 6 159 93%
3, Welding Piping 4" Dia Inch 28 24 0 24 86%
4, NDT Joint 83 0 0 0 0%
Total

8.4 Fabrication of Pipe Support Structure

Total of Pipe Support Structure


No Description of work Unit Top Remarks
Cutting Fit-Up Welding S/Blasting Primer
Coat
WELL-27 FACILITIES 49
1, PS Type - 1.1 1 100% 100% 80%
2, PS Type - 2.1A 5 80%
3, PS Type - 2.2 12 80% 50%
4, PS Type - 2.2A 11 80% 60%
5, PS Type - 3 2 100% 100% 100%
6, PS Type - 4 1 80% 80% 80%
7, PS Type - 4.A 12 80% 80% 80%
8, PS Type - 4.B 1 80% 80% 80%
9, PS Type - 7.1A 1 100% 100% 100%
10, PS Type - 1.2 1 80% 80% 80%
11, Shelter RTU/SCADA 1 30%
12, Lighting Arestor Tower 1 10%
SUBAN GAS PLANT 39
1, PS Type - 2.1A 1
2, PS Type - 3.A 11 80% 80%
3, PS Type - 5 2
4, PS Type - 6 2
5, PS Type - 6.A 3
6, PS Type - 7 4
7, PS Type - 7.A 12
8, PS Type - 8 1 100% 80%
9, PS Type - 8.A 2 100% 80%
10, PS Type - 9 1
Total

Volume
Cumm.
No Description of work Unit Remarks
Total Work Prev. Acumm Today Cum. Progress (%)

A INSTALLATION OF PRECAST FOUNDATION


WR 005 Foundation Structure Total 723 16 18 1,65%
a. Foundation Pipe Support 238 16 18
Type F-1 EA 2 0 0 0 0%
Type F-2 EA 3 0 0 0 0%
Type F-3 EA 3 0 0 0 0%
Type F-4 EA 2 0 0 0 0%
Type F-5 EA 31 0 0 0 0%
Type F-6 EA 45 1 0 1 2%
Type F-6A EA 1 0 0 0 0%
Type F-7 EA 17 7 0 7 41%
Type F-7.1 EA 16 0 0 0 0%
Type F-8 EA 16 0 0 0 0%
Type F-8A EA 3 0 0 0 0%
Type F-9 EA 72 6 2 8 11%
Type F-9A EA 11 2 0 2 18%
Type F-10 EA 16 0 0 0 0%
b FOUNDATION CABLE TRAY 121 0 0
Type 1 EA 72 0 0 0 0%
Type 2 EA 39 0 0 0 0%
Type 2A EA 10 0 0 0 0%
c. LIGHTNING, SCADA & LIGHTING POLE 16 0 0
Lightning Pole EA 5 0 0 0 0%
SCADA Pole EA 1 0 0 0 0%
Lighting Pole EA 10 0 0 0 0%
d. WALKWAY & SERVICE PLATFORM 26 0 0
Walkway EA 16 0 0 0 0%
Platform Type 1 EA 7 0 0 0 0%
Platform Type 2 EA 1 0 0 0 0%
Platform Type 3 EA 1 0 0 0 0%
Platform Type 4 EA 1 0 0 0 0%
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

e. WIND SHOCK, KO POT, VENT STACK, SMALL SHELTER FOR CIP & RTU, SOLAR PANEL 19 0 0
Wind Shock EA 1 0 0 0 0%
Instrument KO POT EA 1 0 0 0 0%
Vent Stack Foundation EA 1 0 0 0 0%
Small Shelter for CIP EA 4 0 0 0 0%
Small Shelter for RTU EA 8 0 0 0 0%
Solar Panel EA 4 0 0 0 0%
f. WATCH TOWER 13 0 0
Watch Tower EA 5 0 0 0 0%
PIT EA 1 0 0 0 0%
Corrosion Coupon EA 1 0 0 0 0%
Secondart Contaimebt EA 3 0 0 0 0%
Intrument Trench EA 2 0 0 0 0%
IBC Tank EA 1 0 0 0 0%
g. Fence & Gate 283 0 0
Fences EA 275 0 0 0 0%
Main Gate EA 6 0 0 0 0%
Personal Gate EA 2 0 0 0 0%
h. IN SITU 7 0 0 0%
Floor SCADA RTU EA 1 0 0 0 0%
Corrosion Inhibator Injection EA 5 0 0 0 0%
Guard House EA 1 0 0 0 0%

Volume
Cumm.
No Description of work Unit Remarks
Total Work Prev. Acumm Today Cum. Progress (%)

B FABRICATION OF PRECAST FOUNDATION


WR 005 Foundation Structure Total 719 33 0 33 7%
a. Foundation Pipe Support 238 32 32
Type F-1 EA 2 0 0 0 0%
Type F-2 EA 3 1 0 1 33%
Type F-3 EA 3 0 0 0 0%
Type F-4 EA 2 0 0 0 0%
Type F-5 EA 31 2 0 2 6%
Type F-6 EA 45 1 0 1 2%
Type F-6A EA 1 0 0 0 0%
Type F-7 EA 17 9 0 9 53%
Type F-7.1 EA 16 0 0 0 0%
Type F-8 EA 16 0 0 0 0%
Type F-8A EA 3 0 0 0 0%
Type F-9 EA 72 6 0 6 8%
Type F-9A EA 11 11 0 11 100% Complete
Type F-10 EA 16 2 0 2 13%
b FOUNDATION CABLE TRAY 121 0 0
Type 1 EA 72 0 0 0 0%
Type 2 EA 39 0 0 0 0%
Type 2A EA 10 0 0 0 0%
c. LIGHTNING, SCADA & LIGHTING POLE 16 0 0
Lightning Pole EA 5 0 0 0 0%
SCADA Pole EA 1 0 0 0 0%
Lighting Pole EA 10 0 0 0 0%
d. WALKWAY & SERVICE PLATFORM 26 0 0
Walkway EA 16 0 0 0 0%
Platform Type 1 EA 7 0 0 0 0%
Platform Type 2 EA 1 0 0 0 0%
Platform Type 3 EA 1 0 0 0 0%
Platform Type 4 EA 1 0 0 0 0%
e. WIND SHOCK, KO POT, VENT STACK, SMALL SHELTER FOR CIP & RTU, SOLAR PANEL 19 1 1
Wind Shock EA 1 0 0 0 0%
Instrument KO POT EA 1 0 0 0 0%
Vent Stack Foundation EA 1 1 0 1 100%
Small Shelter for CIP EA 4 0 0 0 0%
Small Shelter for RTU EA 8 0 0 0 0%
Solar Panel EA 4 0 0 0 0%
f. WATCH TOWER 13 0 0
Watch Tower EA 5 0 0 0 0%
PIT EA 1 0 0 0 0%
Corrosion Coupon EA 1 0 0 0 0%
Secondart Contaimebt EA 3 0 0 0 0%
Intrument Trench EA 2 0 0 0 0%
IBC Tank EA 1 0 0 0 0%
g. Fence & Gate 283 0 0
Fences EA 275 0 0 0 0%
Main Gate EA 6 0 0 0 0%
Personal Gate EA 2 0 0 0 0%
h. IN SITU 3 0 0
Floor SCADA RTU EA 1 0 0 0 0%
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

Corrosion Inhibator Injection EA 1 0 0 0 0%


Guard House EA 1 0 0 0 0%

C FABRICATION PRECAST FOUNDATION TYPE F-7


1, Rebar Footing Foundation Pipe Support Type F-7 EA 17 17 0 17 100% Complete
2, Rebar Pedestal Foundation Pipe Support Type F-7 EA 17 17 0 17 100% Complete
3, Fabrication Footing Formwork Foundation Pipe Support Type F-7 EA 17 17 0 17 100% Complete
4, Fabrication Pedestal Formwork Foundation Pipe Support Type F-7 EA 17 17 0 17 100% Complete
5, Pouring Concrete Footing Foundation Pipe Support Type F-7 EA 17 17 0 17 100% Complete
6, Pouring Concrete Pedestal Foundation Pipe Support Type F-7 EA 17 9 0 9 53%
7, Install Anchor Pedestal Foundation Pipe Support Type F-7 EA 17 17 0 17 100%
D FABRICATION PRECAST FOUNDATION TYPE F-2
1, Rebar Footing Foundation Pipe Support Type F-2 EA 3 3 0 3 100% Complete
2, Rebar Pedestal Foundation Pipe Support Type F-2 EA 3 3 0 3 100% Complete
3, Fabrication Footing Formwork Foundation Pipe Support Type F-2 EA 3 3 0 3 100% Complete
4, Fabrication Pedestal Formwork Foundation Pipe Support Type F-2 EA 3 1 0 1 33%
5, Pouring Concrete Footing Foundation Pipe Support Type F-2 EA 3 1 0 1 33%
6, Pouring Concrete Pedestal Foundation Pipe Support Type F-2 EA 3 1 0 1 33%
7, Install Anchor Pedestal Foundation Pipe Support Type F-2 EA 3 1 0 1 33%
E FABRICATION PRECAST FOUNDATION TYPE F-9
1, Rebar Footing Foundation Pipe Support Type F-9 EA 72 9 0 9 13%
2, Rebar Pedestal Foundation Pipe Support Type F-9 EA 72 9 0 9 13%
3, Fabrication Footing Formwork Foundation Pipe Support Type F-9 EA 72 9 0 9 13%
4, Fabrication Pedestal Formwork Foundation Pipe Support Type F-9 EA 72 9 0 9 13%
5, Pouring Concrete Footing Foundation Pipe Support Type F-9 EA 72 6 0 6 8%
6, Pouring Concrete Pedestal Foundation Pipe Support Type F-9 EA 72 6 0 6 8%
7, Install Anchor Pedestal Foundation Pipe Support Type F-9 EA 72 6 0 6 8%
F FABRICATION PRECAST FOUNDATION TYPE F-5
1, Rebar Footing Foundation Pipe Support Type F-5 EA 31 4 0 4 13%
2, Rebar Pedestal Foundation Pipe Support Type F-5 EA 31 4 0 4 13%
3, Fabrication Footing Formwork Foundation Pipe Support Type F-5 EA 31 4 0 4 13%
4, Fabrication Pedestal Formwork Foundation Pipe Support Type F-5 EA 31 2 0 2 6%
5, Pouring Concrete Footing Foundation Pipe Support Type F-5 EA 31 2 0 2 6%
6, Pouring Concrete Pedestal Foundation Pipe Support Type F-5 EA 31 2 0 2 6%
7, Install Anchor Pedestal Foundation Pipe Support Type F-5 EA 31 2 0 2 6%
G FABRICATION PRECAST FOUNDATION TYPE F-10
1, Rebar Footing Foundation Pipe Support Type F-10 EA 16 4 0 4 25%
2, Rebar Pedestal Foundation Pipe Support Type F-10 EA 16 2 0 2 13%
3, Fabrication Footing Formwork Foundation Pipe Support Type F-10 EA 16 8 0 8 50%
4, Fabrication Pedestal Formwork Foundation Pipe Support Type F-10 EA 16 2 0 2 13%
5, Pouring Concrete Footing Foundation Pipe Support Type F-10 EA 16 2 0 2 13%
6, Pouring Concrete Pedestal Foundation Pipe Support Type F-10 EA 16 2 0 2 13%
7, Install Anchor Pedestal Foundation Pipe Support Type F-10 EA 16 2 0 2 13%
H FABRICATION PRECAST FOUNDATION LIGHTING POLE
1, Rebar Footing Foundation Lighting pole EA 10 7 0 7 70%
2, Rebar Pedestal Foundation Lighting pole EA 10 7 0 7 70%
3, Fabrication Footing Formwork Foundation Lighting pole EA 10 6 0 6 60%
4, Fabrication Pedestal Formwork Foundation Lighting pole EA 10 6 0 6 60%
5, Pouring Concrete Footing Foundation Lighting pole EA 10 0 0 0 0%
6, Pouring Concrete Pedestal Foundation Lighting pole EA 10 0 0 0 0%
7, Install Anchor Pedestal Foundation Lighting pole EA 10 0 0 0 0%
I FABRICATION PRECAST FOUNDATION CABLE TRAY TYPE 1
1, Rebar Footing Foundation Cable Tray Runner EA 71 71 0 71 100%
2, Rebar Pedestal Foundation Cable Tray Runner EA 71 71 0 71 100%
3, Fabrication Footing Formwork Foundation Cable Tray Runner EA 71 15 0 15 21%
4, Fabrication Pedestal Formwork Foundation Cable Tray Runner EA 71 0 0 0 0%
5, Pouring Concrete Footing Foundation Cable Tray Runner EA 71 0 0 0 0%
6, Pouring Concrete Pedestal Foundation Cable Tray Runner EA 71 0 0 0 0%
7, Install Anchor Pedestal Foundation Cable Tray Runner EA 71 0 0 0 0%
J FABRICATION PRECAST FOUNDATION SMALL SHELTER FOR RTU
1, Rebar Footing Foundation Small Shelter for RTU EA 8 8 0 8 100% Complete
2, Rebar Pedestal Foundation Small Shelter for RTU EA 8 8 0 8 100% Complete
3, Fabrication Footing Formwork Foundation Small Shelter for RTU EA 8 2 0 2 25%
4, Fabrication Pedestal Formwork Foundation Small Shelter for RTU EA 8 2 0 2 25%
5, Pouring Concrete Footing Foundation Small Shelter for RTU EA 8 2 0 2 25%
6, Pouring Concrete Pedestal Foundation Small Shelter for RTU EA 8 0 0 0 0%
7, Install Anchor Pedestal Foundation Small Shelter for RTU EA 8 0 0 0 0%
K FABRICATION PRECAST FOUNDATIONTYPE F-6
1, Rebar Footing Foundation Type F-6 EA 30 30 0 30 100%
2, Rebar Pedestal Foundation Type F-6 EA 30 30 0 30 100%
3, Fabrication Footing Formwork Foundation Type F-6 EA 30 30 0 30 100%
4, Fabrication Pedestal Formwork Foundation Type F-6 EA 30 0 0 0 0%
5, Pouring Concrete Footing Foundation Type F-6 EA 30 10 0 10 33%
6, Pouring Concrete Pedestal Foundation Type F-6 EA 30 0 0 0 0%
7, Install Anchor Pedestal Foundation Type F-6 EA 30 0 0 0 0%
L FABRICATION PRECAST CORROSION INHIBATOR INJECTION FOUNDATION
1, Rebar Footing Corrosion Inhibator Injection Foundation EA 5 5 0 5 100%
2, Rebar Pedestal Corrosion Inhibator Injection Foundation EA 5 5 0 5 100%
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

3, Fabrication Footing Formwork Corrosion Inhibator Injection Foundation EA 5 5 0 5 100%


4, Fabrication Pedestal Formwork Corrosion Inhibator Injection Foundation EA 5 0 0 0 0%
5, Pouring Concrete Footing Corrosion Inhibator Injection Foundation EA 5 0 0 0 0%
6, Pouring Concrete Pedestal Corrosion Inhibator Injection Foundation EA 5 0 0 0 0%
7, Install Anchor Pedestal Corrosion Inhibator Injection Foundation EA 5 0 0 0 0%
M FABRICATION PRECAST INSTRUMENT STANCHION FOUNDATION
1, Rebar Footing Instrument Stanchion Foundation EA 6 6 0 6 100%
2, Rebar Pedestal Instrument Stanchion Injection Foundation EA 6 6 0 6 100%
3, Fabrication Footing Formwork Instrument Stanchionn Foundation EA 6 5 0 5 83%
4, Fabrication Pedestal Formwork Instrument Stanchion Foundation EA 6 0 0 0 0%
5, Pouring Concrete Footing Instrument Stanchionn Foundation EA 6 5 0 5 83%
6, Pouring Concrete Pedestal Instrument Stanchion Foundation EA 6 0 0 0 0%
7, Install Anchor Pedestal Instrument Stanchion Foundation EA 6 0 0 0 0%
N FABRICATION PRECAST INSTRUMENT STANCHION FOUNDATION
1, Rebar Footing Foundation Type F-8 EA 16 12 0 12 75%
2, Rebar Pedestal Foundation Type F-8 EA 16 0 8 8 50%
3, Fabrication Footing Formwork Foundation Type F-8 EA 16 0 0 0 0%
4, Fabrication Pedestal Formwork Foundation Type F-8 EA 16 0 0 0 0%
5, Pouring Concrete Footing Foundation Type F-8 EA 16 0 0 0 0%
6, Pouring Concrete Pedestal Foundation Type F-8 EA 16 0 0 0 0%
7, Install Anchor Pedestal Foundation Type F-8 EA 16 0 0 0 0%
O FABRICATION PRECAST INSTRUMENT STANCHION FOUNDATION
1, Rebar Footing Foundation Type F-11 EA 11 0 11 11 100%
2, Rebar Pedestal Foundation Type F-11 EA 11 0 0 0 0%
3, Fabrication Footing Formwork Foundation Type F-11 EA 11 0 0 0 0%
4, Fabrication Pedestal Formwork Foundation Type F-11 EA 11 0 0 0 0%
5, Pouring Concrete Footing Foundation Type F-11 EA 11 0 0 0 0%
6, Pouring Concrete Pedestal Foundation Type F-11 EA 11 0 0 0 0%
7, Install Anchor Pedestal Foundation Type F-11 EA 11 0 0 0 0%

9. CONCERNS / NOTES

10. POTENTIAL CHANGE OF WORK

No Description Of Work Status

1. N/A
11. COMPANY COMMENTS
HSE Concern :
1. -
Engineering Concern :
1. -
QC Concern :
1. -
Construction Concern :
1. -
12. PROGRESS PICTURES

A. CIVIL ACTIVITIES AT FABRICATION CAMP OFFICE & INSTALLATION PRECAST AT SUBAN 27 AREA

Subcont Install Bekisting Pedestal Foundation Type F - Continue Fabrication Install Bekisting Pedestal Foundation
Leveling the sand before compacting
6 qty= 6 ea Type F-7 qty= 8 ea
CONSTRUCTION & INSTALLATION BLANKET CONTRACT FOR SUBAN WELLSITE FACILITIES & FLOWLINES

Consorium PT. Putra Mandiritama - PT. Wiracipta Perkasa

DAILY PROGRESS REPORT

Report no. : 89/SDR/SB27/PTMWCP/XII/2024


Reported date : 03 March 2024
Issued date : 04 March 2024

Compacting sand bedding using a stamper Continued performance of backfilling foundation today type

B.SUBAN 9 AREA

Unloading Pipe Spool of 2", 3", 4" using Crane 51 Ton Unloading Pipe Spool of 2", 3", 4" using Crane 51 Ton
Suban 9 Suban 9.

C.PIPING ACTIVITIE AT WORKSHOP

Progress of blasting and painting on piping 12"


Unloading pipe spool of 2", 3", 4" at workshop for Unloading pipe spool of 2", 3", 4" at workshop for Dwg No: 3242. Sheet: 9 of 15. Join: 47
Suban 9 project using excavato. Suban 9 project using excavato. Dwg No: 3241. Sheet: 8 of 15. Join: 57

Prepared by, Approved by, Acknowledged by,


(Site Planner) (Construction Manager ) (MEPG Site Representative)

Achmad Rudiyanto Yuharmizal Suhendra Marshal

You might also like