MAN POWER LOADING PLAN
Project Name:
Client:
Main Contractor:
Location:
Description Total Man Month
Mar
I. DIRECT 1. Civil Work
Substations
1 Foreman 0
2 Masonry 0
3 Welder + Assistant 0
4 Helper 0
Power Transmission
1 Foreman 0
2 Masonry 0
3 Helper 0
Sub Total 1 0 0
2. Electro-Mechanical Work
1 Foreman 0
2 Masonry 0
3 Welder 0
4 Helper 0
Sub Total 2 0 0
2. Commissioning
1 Foreman 0
2 Masonry 0
3 Welder 0
4 Helper 0
Sub Total 3 0 0
TOTAL DIRECT MAN POWER 0 0
I. DIRECT Project Management Team
1 Project Manager 0
2 Construction Manager 0
3 Commissioning Lead Engineer 0
4 Civil Supoervisor 0
5 Electro Mechanical Supervisor 0
6 Transmission Line Civil Supervisor 0
6 Transmission Line Stringing Supervisor 0
7 Public Relation (PR) 0
8 HSE Supervisor 0
9 QA/QC Lead Engineer 0
10 Material Control 0
11 Project Control 0
12 Project Admin 0
13 Driver 0
TOTAL DIRECT MAN POWER 0 0
GRAND TOTAL MAN POWER 0 0
LOADING PLAN
2021
Apr May Jun Jul Aug Sep Oct Nov
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0