MOBILIZATION PLAN SCHEDULE
Project Name : FUEL STATION MAIN TANK
MONTH-1 MONTH- 2
No Description
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
A NOA (Notification of Award)
A1 Meeting
KOM
C Man Power
1 Hiring Process
2 Ready to Work
C1 Material
1 Issued RFQ
2 Issued PO
3 Material Arrive at Site
4 Inspeksi Material
5 Ready to install
D Tools
1 Purchase Order
4 Delivery to Site
6 Inspection
7 Ready to Used
E Equipments & Vehicles
5 Delivery To Site
6 Inspection
7 Issued PASS and Permit
8 Ready to Used
F Mechanical Construction
G Civil Construction
H Electrical Construction
Pekanbaru, 31 Agustus 2017
PT. PETRO ESTOMIHI
INGOT BONAR TAMPUBOLON
DIREKTUR UTAMA