DAILY REPORT

Date: December 24, 2022


Project Title: Construction of Casino Block at Himal Water Park and Village Hotel
Pvt. Ltd.
Location: Bahuari-14, Parsa, Nepal.
Contractor: Smile Construction and Builders Pvt. Ltd.
Contract Award Date: December 13, 2022
Construction Start Date: December 15, 2022
Planned Completion May 13, 2023
Date:
Extension of time (if any): N/A
Weather / Precipitation: Temp. 26 Temp. 11 Precipitation: 0%
Foggy Day (°C) Night (°C)

1. Manpower at site:

Civil Workers Rebar Workers


Project Engineer Store keeper Foreman & f/W
Manager Skilled Unskilled
Skilled Unskilled

1 0 0 1 5 0 0 0

2. Equipment at site:

Type: Number Acceptable Quality: Yes/No Remarks


Shovel 4 Yes
Total Station 1 Yes
Wheel Barrow 2 Yes
Grinder 1 Yes
Drill Machine 1 Yes
JCB 2 Yes
Level Machine 1 Yes
Spade 1 Yes
Water Pump 1 Yes

3. Materials at site:
Smile Construction & Builders Pvt. Ltd., Adrashnagar-10, Birgunj, Nepal.

Description / Unit Quantity Delivered Quantity consumed Quantity before Total quantity
Specifications Today Today Today remaining

Aggregates Cft 0 0 0 0
Course Sand Cft 0 0 0 0
Fine Sand Cft 0 0 0 0
Admixture Lits 0 0 0 0
OPC cement Bags 0 0 0 0
Rebar Ton 0 0 0 0
Brick Nos 12000 0 1800 13800
40:60 Sand Cft 0
0 0 0
Gravel mix

4. Work Progress:
Location / Work
Activities Status
Area

Casino Block Site Clearance Works Completed

Site Layout Works On Going ( 32% )

Foundation Excavation On Going ( 90% )

Worker On Going
Setup for workers accommodation
Accommodation

5. Placement Record: Concrete, Grout, Mortar, Brickwork etc.:

Location Grid (per drawing) Volume of No of cubes taken


Placement (m3)

6. Site Coordination, QA/QC Meetings:


-MOM # & Date Item Discussed Action Points
None

7. Visitors:
Visitor/s Purpose of visit Site visit finding and recommendation

8. Other Observations and Issues (if any): No


Smile Construction & Builders Pvt. Ltd., Adrashnagar-10, Birgunj, Nepal.

9. Progress Photographs:

Water Clearing Work Water Clearing Work

Site Layout Works Site Layout Works

Reported by: Name Date


Amresh Tiwari December 24, 2022