Professional Documents
Culture Documents
Page 1
1. INTRODUCTION
Embankment Construction at Sta.: 0+021.10 to 0+220 (Pond Area) which is one of the predecessors of
Pavement Works for Road Construction. The objective of this statement is to establish the process for
constructing Embankment as per the Specification. This statement includes the items indicated in below:
No. Work Item
1 Mobilization
2 Preparation (Temporary Dyke & working platform)
2.1 Demolition
2.2 Clearing and Grubbing
2.3 Removal of Masonry/Structure/Pavement
3 Earth Works
3.1 Common Excavation (as required)
3.2 Excavation & Removal of Unsuitable Material
3.3 Embankment Construction
3.4 Capping Layer with Turfing
3.5 Removal of Temporary Dyke
Work Area:
Location Work Description Road Chainage
A1 Site Embankment sand filling GB CH=0+021.10 to 0+220.00
Page 2
1. WORK FLOW CHART
Equipment
Preparation Work
Development of Embankment area @
Excavator, Dump Truck
GB_Right Side
Development of Embankment area @
Excavator, Dump Truck
GB_Left Side
Excavator, Excavator Breaker, Dump
Demolition
Truck
Clearing, Grubbing and Bench Cutting Excavator, Bull Dozer.
Common Excavation Excavator, Dump Truck
Compaction of Foundation of
Vibratory Roller, Grader
Embankment (Subgrade)
Trial Fill and Compaction Result
Embankment Construction
Material & Testing Frequency
Filling Excavator, Dump Truck, Grader
Compaction Vibratory Roller, Water Tanker
Field Test
Field Dry Density Test Sand Cone Apparatus
Thickness
Page 3
2.2 Work Flow Chart
Embankment Construction
Commencement
Mobilization
Survey/ Layout
Page 4
3. PROCEDURE
Materials, Bed compaction and survey works for Embankment Construction as per
Specifications.
Embankment Fill and Compaction as per Specifications.
Field Compaction test as per Specifications.
Slope Protection by Geobag (additional), Capping Layer and Grass Turfing as per
Specifications.
3.1 Preparation
Prior to embankment construction, necessary preparation like survey layout, dyke making, working
platform, demolition of existing structure, clearing & grubbing, removal of unsuitable materials and
compaction of foundation embankment works will be done with necessary inspection with the Engineer.
A continuous platform shall be prepared by cutting and filling by the excavator & bull-dozer of the
existing slope of the road at location Sta. 0+60 to 0+120 location (deep location), dyke will be made by
sand filling. A certain/required quantity of dredged sand shall have dumped at Sta. 0+120 to commence
the construction of the dyke. A Bull-dozer shall be used to push forward the subsequent dumping sand
and continue the platform construction. Such dyke construction shall continue to reach the other end of
deep location (Sta. 0+60). After complete this dyke construction, excavate the additional sand &
dewatering the entrapped water between the dyke and road slope shall commence. The area shall then
be inspected by the Engineer prior to start clearing & grubbing, removal of unsuitable materials.
At Sta. 0+21.10 to 0+60 and 0+120 to 0+220 (other location), dyke will be made by geo-bags. Required
quantity of geo-bags will be filled by sand and placed one after another. An excavator shall be used to
place the geo-bags for dyke construction as shown in the work sequence. Such dyke construction shall
continue from 0+21.10 to 0+60 and 0+120 to 0+220. After complete this dyke construction by geo-
Page 5
bags, dewatering the entrapped water between the dyke and road slope shall commence. The area shall
then be inspected by the Engineer prior to start clearing & grubbing, removal of unsuitable materials.
3.1.3 Demolition
All hard materials like block, masonry and concrete fences, structures, footpaths or others on the
embankment area shall be demolished and removed. After completion of demolition and removal of
debris, joint inspection shall be conducted with the Engineer before commencement of clearing and
grubbing works.
Page 6
Fig 1: Demolition of block, masonry and concrete fences, structures, footpaths or others.
Excavated materials, if suitable in the opinion of the Engineer, shall be reuse for embankment fill.
Page 7
Fig 3: Clearing and Grubbing
Fig 4: Grading and levelling the surface Fig 5: Compaction by Vibratory Roller
Page 8
Survey work will be carried out continuously for the embankment fill and compaction to control line and
level as per design. The level will be controlled by level machine and pegs which will be fixed at
specified area and marked vertically for each 200mm thickness. Layer thickness will be checked during
and after compaction work.
After completion of each layer the pegs will also be lifted 200mm vertically.
3.2.1 Material
The material will be river sand from Meghna to use for embankment construction.
Stockpiling: The material will be collected by dredger and then stockpiled in the adjacent construction
area.
Page 9
Fig 7: Stockpiling by Hydraulic Dredging
Transport to the Filling Area: The stockpiled material will be delivered to the filling location by Dump
Trucks.
3.2.2 Filling
The embankment materials as approved as above, shall be placed in horizontal layers of uniform loose
thickness of 235 mm over the width of the embankment in conformity with the line, grade, sections,
dimensions shown on the drawing. The fill material will be brought by Dump Truck to the filling area
which will be spread and graded uniformly with motor graders. After 8 nos. of roller passes (4 nos. of
Plain Pass + 4 nos. of Vibration Pass) complying with the result of trial bed, compacted thickness will
be checked. During embankment construction, the blue sheet shall be prepared on site against rain. The
blue sheet shall be covered with sand bags especially slope area to prevent the soil wash out.
Page 10
Sampling: The test frequency of embankment material during construction will be in accordance
with Borrow Material (black sand).
Summary of the Test Result for Embankment Material
Source: Meghna River
S Date of Acceptable
Name of Test Test Result Frequency Remarks
N Test Limit
15-May- No limit
1 Sieve analysis, As per test result Acceptable
17 mentioned
15-May-
% passing No. No limit
2 17 7% Acceptable
200 sieve mentioned
California 17-May-
˃ 8% at
6 Bearing Ratio 17 23.9% Acceptable
95% MDD
(CBR)
16-May-
7 Organic Content 0.43% ˂5% Acceptable
17
Moisture 16-May- MDD = 1.618
No limit
8 Density 17 gm/cc, OMC = Per 1,000m³ Acceptable
mentioned
Relation 15.9%
17-May-
Bulk Sp. Gravity-
Specific Gravity 17 No limit
9 2.6 Absorption- Acceptable
and Absorption mentioned
1.5%
Page 11
Fig 9: Filling by Dump Truck Fig 10: Spreading and Grading by Motor Grader
Fig 11: Compaction by Roller Fig 12: Thickness Check after Compaction
Page 12
Compaction will be undertaken at moisture content close to the optimum moisture content determined for
the specific degree of compaction. Moisture will be controlled by spraying water. Each layer (not more
than 200mm thick after its compaction) of filling shall be graded and compacted to its required density
95% of the maximum dry density of AASHTO Standard Proctor, and shall be tested. Surface drain, if
necessary, will be provided near to the bed to maintain dry surface. In case rainy day, the compaction
work will be suspended and be covered with blue sheet on the surface. The condition of resuming the
compaction is that the moisture content on the surface to be 12.0% ~ 19.0%. And during sudden shower,
there will be provision for plastic sheets for covering the construction area to prevent washout of material.
Fig 15: Moisture Maintain by Spraying water Fig 16: Compaction by Vibratory Roller
Page 13
3.3 Field Test
Field density test and Checking of thickness need to be conducted during embankment construction.
List of Field Tests:
SN Test Acceptable limit
1 Field Density Test (FDT) Field density > 95% of MDD
2 Thickness (compacted) Maximum 200mm
3.3.2 Thickness
Layer thickness will be checked by level machine as well as will observed by digging hole in the bed
during and after compaction work. Thickness check will be continued for each layer.
Page 14
3.4 Capping Layer and Turfing (including slope protection by Geo-bag/Geo-jumbo bag)
Cohesive soil for slope protection will be provided in the areas shown in the section drawings. Grass
turfing consists of providing grass cover by planning prepared sods. The local name of the grass species
in Durva grass. Turfing work will be proceeded as per Engineer’s approval. Geo-bags (Size-
900mm*700mm*100mm) will be installed instead of capping layer & turfing up to high water level. geo-
bags (Size-900mm*700mm*100mm) will be filled up by equally distributed sand and placed on level
surface with maintaining proper alignment & level. at Sta. 0+060 to 0+120 (deep location) Geo-jumbo
bag (Size-1.0m dia & 1.0m height) will be placed for permanent slope protection during dry season.
Fig 20: Slope Protection During Dry Season (Sta. 0+021.1 to 0+220_GB Left Side)
Page 15
Fig 21: Slope Protection During Dry Season (Sta. 0+021.1 to 0+060 and 0+120 to 0+220_GB Right Side)
Fig 22: Slope Protection During Dry Season (Sta. 0+060 to 0+120_GB Right Side)
Page 16
3.4.1 Material for Capping Layer and Turfing
The properties of cohesive soil will meet the specification. Material is approximately 2400 cum.
Summary of the Test Result for Cohesive Soil:
Fig 23: Durva Grass (Bermuda Grass) Fig 24: Sod Blocks
3.4.2 Construction
The cohesive soil will be placed as specification. Details Construction Procedure will be followed as
described in the Approved Method Statement for Embankment Construction.
Page 17
4. EQUIPMENT LIST
5. MANPOWER LIST
Page 18
Check by
Subcontractor’s Engineer
Check by
Contractor’s Engineer
Inspection by
the Engineer
incident/accident.
Page 19
8. ENVIRONMENTAL CONTROL
With regards to the environmental aspects and impacts in embankment construction work, all works shall
be carried out in compliance with the requirements of the Project Environmental Control Plan.
9. RISK ASSESSMENT
Risk assessment for the works described by identifying anticipated hazards and impacts associated with
safety and environmental issues in order to take precautions and preventive measures against each hazard
identified.
Page 20