3rd July 2014

D.M.W. Dissanayake,
Water & Sanitation Engineer,
Water Supply & Drainage Board.
Dear Sir,
FINAL QUOTATION FOR PRESSURE GROUTING UNDER ROCK BASE AT KOLONNA
With reference to your inquiry, please find below our quotation for the above area.
We shall be glad to receive an advance of 50% of the total amount with your confirmation.

Item Description Unit Qty Rate Amount


1.0 Mobilization
General transport mobilization of equipment
and personal to the site including sky drill, angle
Sum _ 1,000,000.00 1,000,000.00
drill & grouting machines, Grout Mixers for base
foundation area.
2.0 Insurance
Insurance & Other Safety devices Sum _ 90,000.00 90,000.00
3.0 Moving and Setting up
3.1 Preparation of Platform/Scafolding. Moving &
establishing for drilling machines at each Nos 18 20,000.00 360,000.00
locations.
4.0 Drilling
4.1 Drilling horizontal, angle or verticle holes in 75
mm (or more) diameter grout holes, through
m 36 31,000.00 1,116,000.00
concrete, Highly Weathered Rock, Moderately
Weathered Rock or Hard Rock
4.2 Supply & Installation of temporary casing for
m _ 8,000.00 Rate Only
protection the hole (only if is necessary)
5.0 Water pressure testing
Testing with clean water under continuous
pressure at each stage different pressure will Nos 18 54,200.00 975,600.00
apply for different stages of holes
6.0 Pressure grouting
Design of grout pattern & pressure, installation
grout casing, fixing and tighten the grout nipples
and grouting in stage from bottom to top with Nos 18 160,000.00 2,880,000.00
suitable grouting materials.(Rate include
Bentonite, CaCl2, Sand etc. )
7.0 Supplying of ordinary portland cement for
bags 240 940.00 225,600.00
grouting(50kg Bag)
7.1 Supplying of shrinkage compensating admixture
bags 240 375.00 90,000.00
for grouting(250g Bag)
Total 6,737,200.00
+ 12% VAT

Thanking You,
Yours Faithfully,

C.J. Gamage,
Managing Director.