S/N ITEM DESCRIPTION COST TOTAL
UNIT QTY (Kshs.) COST (Kshs.)
A ELEMENT 1: PRELIMINARIES
GATES
D Extra over ditto for struts struts 2600 mm long 68 No. 1,200.00 81,600
A. Clearing/excavation
1 Clear pipe route of bushes, shrubs and cart away
all arisings m 200.00 12,000.00
60.0
2 Excavate for 600mmx600mm channel and
stockpile soil
materials for reuse m 60.0 300.00 18,000.00
3 Prepare channel bed for pipe laying
m 60.0 120.00 7,200.00
Provide, transport to site, and install the pipes
(with sockets and / butt-fusion for assorted pipes(
HDPE pipes(63mm PN8, 2'' G.I
pipes),connectors and all necessary accompanying
B
fittings ,Piping start line connected from Existing
Valve chamber (rising main) at the the Pan to
Storage Tank
Item 1 350,000.00 350,000.00
C Valve chamber -
-
1 Source supply materials to site and Construct STD
ministry valve chambers 0.8 MX 0.8 MX 0.6 M
deep with 1:2:4 rc concrete manhole cover of
600mm x600mm size. The cover to be encased in
25mm angle framing . Chamber to be of well
dressed quarry stone and
plastered to finish.
No. 1 20,000.00 20,000.00
D Tanks
B
Allow a provisional sum of Kenya shillings Four
hundred thousand for construction of Livestocks 250,000
water trough 1no. For camels as per the drawings
750,000.00
D PC SUMS
4,309,800.00
SUB-TOTAL
689,568.00
Add vat 16%
TOTAL SUMMARY CARRIED TO FORM OF
4,999,368.00
TENDER