You are on page 1of 5

BILLS OF QUANTITIES FOR THE PROPOSED QONQOMA WATER PAN FENCING,WATER

RETICULATION,STORAGE AND SUPPLY.

SITE LOCATION: QONQOMA,GOLBO WARD-MOYALE SUB COUNTY,MARSABIT


COUNTY

UNIT
S/N ITEM DESCRIPTION COST TOTAL
UNIT QTY (Kshs.) COST (Kshs.)
A ELEMENT 1: PRELIMINARIES

Project sign board as follows; Allow for 4ft x 8ft


project signboard (metallic) Main frame 50 x 50 x
4mm SHS tubes and plain sheet G16 engraved
with provided wordings and logos-see the
1 drawings LS 1 50,000.00 50,000.00

2 Allow for Mobilization and demobilization ITEM 1.00 120,000.00 120,000.00

Allow provisional sum of Kshs 150,000 to be


3 expended as Engineer's Supervision fee ITEM 1.00 150,000.00 150,000.00

Allow provisional sum of Kshs 200,000 for Water


4 Users Committee Training ITEM 1.00 200,000.00 200,000.00

Total for Preliminaries to Grand Summary page


520,000
ELEMENT NO.2 GATES AND FENCING
B

GATES

Vibrated reinforced concrete(1:2:4)


Class 20/20 in -:

Concrete base (1:2:4) in base size 1000 x 1000


x250mm thick, 200 mm x 200 mm x 2500 mm
A high column (1:2:4); Complete with specified
reinforcement,excavations and formwork
2 No. 30,000.00 60,000

B Mild steel hollow section gate , double leaf overall


size 5000 x 2000mm high constructed of
50x50x4mm thick frame and 50x25x3mm at
200mm centers.
1 No. 70,000.00 70,000
FENCING

2.4m high x 14 gauge chainlink complete with of


6 strand galvanised barbed wired fencing with
C 50x50x4mm Angle Iron posts at 3.0m centres
mortised in mass concrete surround
700 LM 1,800.00 1,260,000

D Extra over ditto for struts struts 2600 mm long 68 No. 1,200.00 81,600

Carried to Grand Summary


1,471,600
C ELEMENT NO.3 SUPPLY LINES AND
STORAGE TANK
No. Description Amount
Unit Qty Rate (Kshs) (Kshs)

A. Clearing/excavation
1 Clear pipe route of bushes, shrubs and cart away
all arisings m 200.00 12,000.00
60.0
2 Excavate for 600mmx600mm channel and
stockpile soil
materials for reuse m 60.0 300.00 18,000.00
3 Prepare channel bed for pipe laying
m 60.0 120.00 7,200.00
Provide, transport to site, and install the pipes
(with sockets and / butt-fusion for assorted pipes(
HDPE pipes(63mm PN8, 2'' G.I
pipes),connectors and all necessary accompanying
B
fittings ,Piping start line connected from Existing
Valve chamber (rising main) at the the Pan to
Storage Tank
Item 1 350,000.00 350,000.00
C Valve chamber -
-
1 Source supply materials to site and Construct STD
ministry valve chambers 0.8 MX 0.8 MX 0.6 M
deep with 1:2:4 rc concrete manhole cover of
600mm x600mm size. The cover to be encased in
25mm angle framing . Chamber to be of well
dressed quarry stone and
plastered to finish.
No. 1 20,000.00 20,000.00
D Tanks

1 Source and Supply to site 2no. 10,000 Ltrs water


tank Double Layer KenTank-Client's
requirement
No. 2 135,000.00 270,000.00
E Elevated Steel tank platform-6mtrs High

1 Source, supply and Install Steel water tank tower


by Sytech Fabrication (plaform size 6m x 3m) to
Support 2no.10,00 Ltrs plastic tank as per
structural Engineer's drawings.
No. 1 840,000.00 840,000.00
F Finishes
1 Back filling (A2) above leaving joints Protected
and Marked m 60 100.00 6,000.00
2 Final backfilling of item (A2), making good of site
Item 1 5,000.00 5,000.00
3 Pipe Anchor block 400mmx400mmx400mm,
Mass concrete(1:2:4)
No. 8 5,000.00 40,000.00
Total Carried to Grand summary page
1,568,200.00
PC AND PROVISIONAL SUMS
D

Allow a provisional sum of kenya shillings three


hundred thousand for supply and installation of
Surface Solar pump-Max. head
80Mtrs,1300w,150V,80mtrs,1.25'' outlet to include
A 300,000
solar panel 4x450w.,pump to have max flow of
7000ltrs/Hr with all accessories and solar panel
support module as shall be approved by the
engineer

B
Allow a provisional sum of Kenya shillings Four
hundred thousand for construction of Livestocks 250,000
water trough 1no. For camels as per the drawings

Allow a provisional sum of Kenya shillings One


C hundred and Fifty thousand shillings only
contigencies 150,000

Allow a provisional sum of Kenya shillings Fifty


D thousand only for fabrication and installation
water filtration screens unit at pipe inlet section 50,000

Carried to Grand Summary 750,000


GRAND SUMMARY PAGE
PROPOSED QONQOMA WATER PAN TOTAL AMOUNT
FENCING,WATER RETICULATION,STORAGE
ITEM
AND SUPPLY.
KSHS CTS

A. Element No . 01: PRELIMINARIES 520,000.00

B Element No. 02: FENCING 1,471,600.00

C Element No: 03 SUPPLY LINE AND STORAGE TANK 1,568,200.00

750,000.00
D PC SUMS

4,309,800.00
SUB-TOTAL

689,568.00
Add vat 16%
TOTAL SUMMARY CARRIED TO FORM OF
4,999,368.00
TENDER

You might also like