Professional Documents
Culture Documents
CY 2022 PROJECT
DETAILED ENGINEERING DESIGN PLAN FOR
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PACKAGE 1A: STA.0+068 - 0+547.16, PACKAGE 4: STA.0+000.00 - 0+370.00, STA.0+000.00-0+282.13,
STA.0+000.00-310.00, STA.0+000.00-324.25, PACKAGE 5: STA.0+000-0+183.15
NET LENGTH = 1,948.69 L.M..
N
POLITICAL MAP
of the THIS SITE
E
A
PHILIPPINES
S
Calog
Cr
Creek
N
O
CAR
Z
REGION I REGION II
U
L
REPUBLIC OF THE PHILIPPINES
REGION IV
LUZON
THE SITE REGION III
Creek
NCR
Creek
Falls
REGION VIII
REGIONAL OFFICE VI
P H
REGION VI
I L
VISAYAS
E
P P
ILOILO
G
A
I N E
S
S
A
PANAY ISLAND
P
S E A
N
P
A
L
A
W REGION VI
REGION VII
REGION XIII
(CARAGA)
C.Y.2022 PROJECT
A
REGION X
U
L
S U
REGION IX
REGION XII
BORACAY DRAINAGE IMPROVEMENT PROJECT Mananipa Falls
MINDANAO
BORACAY ISLAND, MALAY, AKLAN
ARMM
VICINITY MAP
PACKAGE 1A: STA.0+068 - 0+547.16, PACKAGE 4: STA.0+000.00 - 0+370.00, STA.0+000.00-0+282.13,
A
E M I N S E A REGION XI
D A N A O
S
S
E
E B
C E L
PACKAGE 1A
KALAHI ROAD
KALAHI
PACKAGE 5
ROAD
WETLAND
04
PACKAGE 3
PUMPING STATION 04
WETLAND 06
1321200.00
TO YA
PAK
TO M
ANO
K MAN
OK PACKAGE 4
PACKAGE 4 LUGUTAN ROAD
BORACAY REGENCY ROAD
PACKAGE 4
SUNSET ROAD
PACKAGE 4
WHITE BEACH PCTV ROAD
1323900.00
0.0127
FORMED SEALANT GROOVE
ENGINEER OF DISCREPANCIES BETWEEN ACTUAL CONDITIONS AND INFORMATION SHOWN ON THE 4. SEE PROVISIONS FOR BACKFILLING AND COMPACTION, ENSURING COMPLIANCE TO MATERIAL AND
CL
SEE STANDARD DRAWING
DRAWINGS BEFORE PROCEEDING WITH THE WORK. THIS SHALL INCLUDE THE LOCATION AND DIMENSIONS COMPACTION SPECIFICATIONS.
0.0635
OF GROOVES, REGLETS, SLEEVES, CURBS, OPENINGS, EMBEDDED OR ATTACHED ITEMS ETC. REFER TO
CL
EQUAL
0.0508
ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING DRAWINGS. 2.4 MATERIALS
1.2 ALL INDICATED DIMENSIONS ARE IN METERS UNLESS OTHERWISE INDICATED AND SHALL TAKE 2.4.1 REINFORCING STEEL BARS
PRECEDENCE OVER SCALED DIMENSIONS FROM PLANS, SECTIONS AND DETAILS. NOTES AND DETAILS ON FOR DETAILS OF TOP REINFORCEMENT
COLD JOINT APPLY 2 COATS OF BOND
DRAWINGS SHALL TAKE PRECEDENCE OVER GENERAL NOTES AND TYPICAL DETAILS. 1. GRADE : REINFORCING STEEL DEFORMED BARS SHALL CONFORM TO ASTM 615 GRADE 40 (40 ksi) 276 BARS AT CONST. JOINT,
BREAKER. AVOID COATING WATERSTOP.
MPa -Ø12 & SMALLER AND FOR PRECAST WALL AND LEDGE REINFORCEMENT GRADE 60 (60 ksi) 414 MPa
SEE ROOF SLAB DETAILS
FOR BOND BREAKER, SEE SPECS. FOR REINFORCEMENT SEE
0.1143 0.1143
0.0635
1.3 THE CONTRACT STRUCTURAL DRAWINGS AND SPECIFICATIONS REPRESENT THE FINISHED STRUCTURE. - Ø16 & BIGGER SLAB TYP. DETAILS 0.3810 0.3810
CL
THEY DO NOT INDICATE THE METHODS OF CONSTRUCTION, UNLESS SO STATED, THE CONTRACTOR 2. DOWEL CONNECTIONS (REBARS & PIPE SLEEVES) AT THE BOTTOM OF THE PRECAST PANEL WALLS AT
SHALL PROVIDE ALL NECESSARY MEASURES TO PROTECT THE STUCTURES, ADJACENT PROPERTY,
LAP LAP
GROUND FLOOR SHALL BE GALVANIZED, IF APPLICABLE. DOWEL BARS: SAME SIZE
COLD JOINT APPLY 2 COATS OF BOND
EXISTING UTILITIES, WORKMEN AND OTHER PERSONS DURING ALL PHASES OF CONSTRUCTION. THE 3. IN GENERAL, THE LATEST EDITION OF ACI - 315, MANUAL OF STANDARD PRACTICE FOR DETAILING AS SLAB REINF. SPACE AT
0.610 O.C. BREAKER. AVOID COATING W.S. & SPECS.
CONTRACTOR SHALL IMMEDIATELY NOTIFY THE ENGINEER OF ANY CONDITION WHICH IN HIS OPINION REINFORCED CONCRETE STRUCTURES SHALL BE ADHERED TO, UNLESS OTHERWISE SHOWN OR GROOVE FOR BOND BREAKERS, SEE SPECS.
MIGHT ENDANGER THE STABILITY OF THE STRUCTURE OR CAUSE DISTRESS IN THE STRUCTURE. NOTED ON DRAWINGS. FOR REINF. SEE ROOF
SLAB DETAILS WATERSTOP AT CENTER OF SLAB FOR
4. MILL CERTIFICATE OF REINFORCEMENT SHALL BE SUBMITTED FOR REVIEW BY THE STRUCTURAL
W.S. TYPE REQUIRED. IN ROOF SLAB CONST.
1.4 CONSTRUCTION MATERIALS SHALL NOT BE STORED ON POURED SLABS. IT IS THE GENERAL ENGINEER. NOTES:
BOTTOM REINF. BARS TO BE JOINTS, SEE TYP. SECTION
CONTRACTORS RESPONSIBILITY TO ENSURE THAT SUBCONTRACTORS ARE INFORMED AND DO NOT 5. ALL BARS SHALL BE BENT COLD UNLESS OTHERWISE PERMITTED BY THE STRUCTURAL ENGINEER. AT ALL SLAB CONST. JOINTS CONCRETE
CONTINUOUS THRU CONST. JOINT
VIOLATE THIS IMPORTANT REQUIREMENT. 6. ALL REINFORCING BARS SHALL BE CLEANED THOROUGHLY OF ALL LOOSE RUST, SOIL OR OTHER SHALL BE WORKED UNDER W.S. BY HAND,
MATERIAL IMMEDIATELY PRIOR TO PLACING OF CONCRETE. MAKING SURE THAT AIR & ROCK POCKETS
1.5 THE CONTRACTOR SHALL PROVIDE TEMPORARY ERECTION BRACING AND SHORING FOR ALL STRUCTURE 7. A FULL BUTT WELDED SPLICE ALLOWED BY THE ENGINEER SHALL DEVELOP IN TENSION AT LEAST 125 ARE ELIMINATED.
MEMBERS AS REQUIRED FOR STRUCTURE STABILITY DURING ALL PHASES OF CONSTRUCTION. PERCENT OF THE SPECIFIED YIELD STRENGTH (fy) OF THE BAR.
8. ALL WELDING OF REINFORCEMENT ALLOWED BY THE ENGINEER SHALL CONFORM TO THE PROVISIONS ALL DIMENSIONS ARE IN METERS EXCEPT WHERE
1.6 THE CONTRACTOR SHALL TAKE ALL STEPS NECESSARY TO ENSURE PROPER ALIGNMENT OF THE OF THE STRUCTURAL WELDING CODE REINFORCING STEEL, AWS D 1.4. OTHERWISE SHOWN.
STRUCTURE AFTER THE INSTALLATION OF ALL STRUCTURAL AND FINISH MATERIALS. 9. A FULL MECHANICAL CONNECTION (REBAR SPLICER) SHALL BE DEVELOPED IN TENSION OR IN
COMPRESSION, AS REQUIRED, AT LEAST 125% OF THE SPECIFIED YIELD STRENGTH fy OF THE BAR. IF
1 ROOF SLAB CONSTRUCTION JOINT 2 FLOOR SLAB CONSTRUCTION JOINT
1.7 TYPICAL DETAILS AND GENERAL NOTES ON THIS SHEET SHALL APPLY TO ALL PARTS OF THE JOB UNLESS S-01 SCALE NTS. S-01 SCALE NTS.
USED, SAMPLES ARE SUBMITTED FOR APPROVAL OF THE DESIGNER.
OTHERWISE SHOWN ON THE DRAWINGS. 10. GENERALLY, NO SPLICES SHALL BE PERMITTED ON MEMBERS WHERE CRITICAL BENDING STRESSES
OCCUR. LOCATION AND LENGTHS OF LAP SPLICES ARE INDICATED IN THESE NOTES AND ON THE
2.0 STRUCTURAL DESIGN CRITERIA STRUCTURAL DRAWINGS.
WATERSTOP CONTINUOS IN ALL
2.1 STANDARD DESIGN CODES & REFERENCES 2.5 MINIMUM CONCRETE COVER FOR REINFORCEMENT BEND WATERSTOP ON 125mm ROOF SLAB CONSTRUCTION JOINTS.
(5") RADIUS, MINIMUM BOND WATERSTOPS AT ALL ROOF
2.1.1 NATIONAL STUCTURAL CODE OF THE PHILIPPINES (NSCP) 2.5.1 SLABS ........................................................................................................................................ 40mm JOINT INTERSECTIONS BY HEATING.
2.5.2 BEAMS, COLUMNS AND PEDESTAL ....................................................................................... 50mm
2.1.2 AMERICAN CONCRETE INSTITUTE (ACI) STANDARDS 2.5.3 WALLS ........................................................................................................................................ 50mm
2.5.4 FOOTING, TIE BEAMS AND BASE SLABS ............................................................................... 75mm NOTES:
1.2.1 ACI 350-CODE REQUIREMENTS FOR THE ENVIRONMETAL ENGINEERING CONCRETE STRUCTURES
1.2.2 ACI 315-DETAILS AND DETAILING CONCRETE REINFORCEMENT 2.6 CONSTRUCTION JOINTS WATERSTOP AT CENTER OF WALL WATERSTOPS SHALL BE CONTINUOS
1.2.3 ACI 318-BUILDING CODE REQUIREMENT FOR STRUCTURAL CONCRETE IN ALL VERTICAL CONSTRUCTION JOINT THROUGH FLOOR, WALLS & ROOF
OF RESERVOIR EXCEPT WHERE
CONSTRUCTION JOINTS SHALL BE PROVIDED IN ACCORDANCE WITH ACI 350R AND SHALL BE LOCATED SO AS
OTHERWISE SHOWN.
2.1.3 PHILIPPINE NATIONAL STANDARDS (PNS) TO LEAST IMPAIR THE STRENGTH OF THE STRUCTURE, TO PROVIDE LOGICAL SEPARATION BETWEEN BOND WATERSTOPS IN FLOOR AND SEALANT GROOVE. CONTINUOS AT
SEGMENTS OF THE STRUCTURE AND TO FACILITATE CONSTRUCTION. ALL REINFORCEMENT SHALL BE WALL CONSTRUCTION JOINTS WITH FLOOR SLAB CONSTRUCTION JOINTS. FOR WATERSTOPS TYPE REQUIRED
2.1.4 AMERICAN SOCIETY OR TESTING AND MATERIALS (ASTM) CONTINUED ACROSS OR THROUGH THE JOINT. ALL TYPES OF JOINTS SHALL BE PROVIDED WITH WATERSTOPS UNDER WALL BY HEATING CONTINUE GROOVE TO CENTER OF SEE DRAWINGS.
WATERSTOPS AND SEALANTS WHERE WATER TIGHTNESS IS REQUIRED. LOCATIONS OF ALL JOINTS SHALL WALL & FILL WITH SEALANT SO AS
0.75
2.1.5 AMERICAN SOCIETY OF CIVIL ENGINEERS MANUAL BE SHOWN ON THE DRAWINGS. TO BOND WITH WATERSTOP. SEALANT WATERSTOPS SAMPLES SHALL BE
UNDER WALL SHALL BE IN PLACE SUBMITTED FOR APPROVAL BY
2.1.6 AMERICAN INSTITUTE OF STEEL CONSTUCTION (AISC) 3.0 WORKS 3.1 EXCAVATION: PRIOR TO PLACEMENT OF CONCRETE THE ENGINEER.
FOR WALL
2.1.7 AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO) DIMENSION ARE IN METERS UNLESS
EXCAVATION FOR STRUCTURE SHALL BE TO THE NEAT LINE AS SHOWN IN THE PLANS. THE GROUND
OTHERWISE SHOWN.
UNDERNEATH THAT SERVE AS STRUCTURE FOUNDATION SHALL BE LEFT UNDISTURBED. IF THE REQUIRED
2.1.8 UNIFORM BUILDING CODE (UBC) BEARING CAPACITY OF SOIL UNDER FOOTING CANNOT BE ATTAINED, THE ENGINEER SHALL BE NOTIFIED
FOR REDESIGN OF FOOTING.
2.1.9 PORTLAND CEMENT ASSOCIATION (PCA) CONCRETE INFORMATION
3.2 FILLING AND BACKFILLING: WATERSTOP CONTINUOS IN ALL
BEND WATERSTOPS ON 125mm FLOOR CONSTRUCTION JOINTS.
2.2 DESIGN LOAD (5") RADIUS, MINIMUM BOND WATERSTOPS AT ALL FLOOR
FILL AND BACKFILL MATERIAL SHALL CONSIST OF SUITABLE MATERIALS FROM EXCAVATION OR FROM JOINTS INTERSECTIONS BY HEATING.
2.2.1 DEAD LOAD: APPROVED BORROW AREAS, AND SHALL BE FREE FROM ROOTS, WOOD SCRAPS, VEGETATIONS, AND OTHER
EXTRANEOUS MATERIALS AND FROM LARGE CLODS OF EARTH OR STONES GREATER THAN 100 MM. NO FILL
2.2.1 CONCRETE ...................................................... 24.00 kN/m MATERIAL SHALL BE PLACED UNTIL THE SURFACE TO BE FILLED HAS BEEN APPROVED.
2.2.2 STEEL ............................................................... 78.00 kN/m 3 TYPICAL WATERSTOP INSTALLATION
2.2.1 WATER .............................................................. 9.81 kN/m a. FILLING AND BACKFILLING FOR STRUCTURES AND TRENCHES BACKFILLING AROUND STRUCTURES SHALL SCALE NTS.
2.2.1 SOIL
S-01
BE PLACED AS THE CONSTRUCTION WORK PROGRESS, INSOFAR AS PRACTICABLE. BACKFILLING OF
BORACAY, DRY .................................................. 17.60 kN/m TRENCHES SHALL PROGRESS AS RAPIDLY AS CONSTRUCTION AND TESTING WILL PERMIT. IN BACKFILLING
BORACAY, SATURATE ...................................... 19.00 kN/m PIPE TRENCHES, APPROVED BACKFILL SHALL BE COMPACTED IN 200mm LAYERS TO A DEPTH OF 150mm
OVER THE PIPE AND THE REMAINDER OF THE TRENCH DEPTH SHALL BE BACKFILLED AND COMPACTED IN 152
2.2.2 LIVE LOAD: 300mm LAYERS. FOR TRENCHES UNDER ROAD PAVEMENTS AND CONCRETE FLOOR SLABS, THE BACKFILL
15.9mm BULB
SHALL BE PLACED AND COMPACTED IN 200mm LAYERS TO THE TOP OF THE TRENCH.
2.2.1 ROOF WITH SLOPE ......................................... 1.44 kN/m
(MIN.)
2.2.2 ROOF DECK ..................................................... 1.92 kN/m b. EMBANKMENT CONSTRUCTION BEFORE PLACING FILL MATERIAL, THE SURFACE UPON WHICH IT WILL BE
3.2mm
(MIN.)
2.2.3 PUMP FLOOR AREAS ..................................... 12.00 kN/m
9.5mm
PLACED SHALL BE SCARIFIED TO INSURE GOOD BONDING BETWEEN THE EXISTING SURFACE AND THE FILL
9.5mm
(MIN.)
(MIN.)
FOR WALL REINF. SEE
2.2.4 STORAGE FLOOR AREAS .............................. 4.80 kN/m MATERIAL. WHERE EMBANKMENT ARE TO BE CONSTRUCTED ON SLOPING GROUND WITH SLOPES STEEPER TYP. DETAIL
2.2.5 PLATFORM FLOOR AREAS ............................ 4.80 kN/m WATERSTOP AT CENTER OF WALL FOR
THAN 1 VERTICAL TO 4 HORIZONTAL, THE NEW FILL SHALL BE CUT INTO OR BENCHED AS THE EMBANKMENT
W.S. TYPE REQ'D. IN WALL JOINTS,
2.2.6 HOUSING FLOOR AREAS ................................ 2.00 kN/m IS BROUGHT UP IN LAYERS IN SUCH A MANNER THAT THE EMBANKMENT MATERIAL WILL BOND WITH THE SEE TYPICAL SECTION
4.8mm
4.8mm
(MIN.)
(MIN.)
2.2.7 WORKSHOP FLOOR AREAS ........................... 7.20 kN/m EXISTING SURFACE. THE SIZE OF EACH BENCH SHALL BE SUBJECT TO APPROVAL AND SHALL DEPEND ON
EQUAL
THE EQUIPMENT TO BE USED.
2.2.3 EARTHQUAKE LOAD (EL)-SEISMIC EFFECT IN ACCORDANCE WITH UBC, ACI AND NSCP.
c. COMPACTION IN FILL AREAS, THE TOP 200mm SHALL BE COMPACTED TO A DENSITY OF AT LEAST 95
2.2.4 WIND LOAD (WL)-A MINIMUM OF 220 KPH BASIC WIND SPEED & EXPOSURE C OR D (AS APPROPRIATE) PERCENT OF MAXIMUM DENSITY AND THE REMAINING DEPTH OF FILL TO NOT LESS THAN 90 PERCENT OF
SHALL BE USED IN ACCORDANCE WITH THE UNIFORM BUILDING CODE (UBC). THE DESIGN SHALL MAXIMUM DENSITY; EXCEPT THAT UNDER RAMPS, PAVEMENTS, AND CONCRETE FLOOR SLABS, COMPACTION
BE GOVERNED BY MAXIMUM WIND OR MAXIMUM EARTHQUAKE LOAD, WHICHEVER IS GREATER . SHALL NOT BE LESS THAN 95 PERCENT OF MAXIMUM DENSITY FOR THE ENTIRE DEPTH OF FILL. UNLESS
OTHERWISE INDICATED, WHERE THE EXISTING SUB GRADE IN CUTS HAVE A DENSITY OF LESS THAN 95 4 0.152M CENTERBULB WATERSTOP 5 WALL VERTICAL CONSTRUCTION JOINT
2.2.5 HYDROSTATIC AND HYDRODYNAMIC LOADS: ALL HYDRAULIC STRUCTURES SHALL BE DESIGNED FOR PERCENT, ALL MATERIALS TO A DEPTH OF 150mm OR TO SUCH GREATER DEPTH AS MAYBE SPECIFIED, S-01 SCALE NTS. S-01 SCALE NTS.
HYDROSTATIC FORCES IMPOSED BY THE FLUID CONTAINED IN THESE STRUCTURES AND FOR SHALL BE COMPACTED TO NOT LESS THAN 95 PERCENT OF THE MAXIMUM MAYBE SPECIFIED, SHALL BE
HYDRODYNAMIC FORCES USING THE GROUND ACCELERATION AND THE RESPONSE SPECTRA PROVIDED COMPACTED TO NOT LESS THAN 95 PERCENT OF THE MAXIMUM DENSITY. SOIL MOISTURE DURING
BY THE GEOTECHNICAL REPORT. COMPACTION SHALL BE CONTROLLED BETWEEN 80 AND 110 PERCENT OF OPTIMUM MOISTURE CONTENT
DETERMINED IN ACCORDANCE WITH AASHTO METHOD T99-84.
2.2.6 LOADING CONDITION:
THE STRUCTURES SHALL BE DESIGNED FOR THE FOLLOWING CONDITION: 3.3 FALSE WORK:
2.6.1 TANK FULL: ALL FALSE WORK SHALL BE DESIGNED BY THE CONTRACTOR SUBJECT TO THE APPROVAL OF THE
HYDROSTATIC LOAD + DEAD LOAD; HYDRODYNAMIC + SEISMIC LOAD (DUE TO DEAD LOAD); ENGINEER.
HYDRODYNAMIC + SEISMIC LOAD (DUE TO DL) + DEAD LOAD
3.4 SURVEY WORK:
2.6.2 TANK EMPTY:
STATIC SOIL PRESSURE + DEAD LOAD; SEISMIC SOIL PRESSURE + SEISMIC LOAD (DUE TO DL) ALL ELEVATIONS SHALL BE CHECKED AND VERIFIED PRIOR TO EXECUTION OF ANY WORKS.
+SURCHARGE
2.6.3 UPLIFT:
ALL STRUCTURES SHALL BE CHECKED FOR UPLIFT WHEN SUBJECTED TO HIGH WATER TABLE.PROVIDE
WATER INSIDE TANK TO COUNTER BOUYANT FORCE DURING CONSTRUCTION IF NECESSARY
6 DETAIL OF STEEL LADDER RUNG
S-01 SCALE NTS.
2.3 FOUNDATION
1. ALLOWABLE SOIL BEARING CAPACITY WAS BASED ON THE GEOTECHNICAL INVESTIGATION REPORT.
THE VALUE SHALL BE VERIFIED DURING CONSTRUCTION.
2. THE CONTRACTOR SHALL UNDERTAKE THOROUGH INSPECTION DURING EXCAVATION AND SHALL
REPORT TO THE ENGINEER IF DIFFERENT MATERIAL CONDITION IS ENCOUNTERED.
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN STRUCTURAL NOTES 1 ADAPTED FROM TIEZA DRAWINGS G 02
02 08 33
TABLE 5
TABLE 1 - MINIMUM DEVELOPMENT LENGTH AND LAP LENGTH
SCHEDULE OF DIAGONAL CROSS BARS
MINIMUM DEVELOPMENT LENGTH MINIMUM LAP LENGTH
NO. OF BARS WALL THICKNESS
BAR DIAMETER
f'c=24MPa f'c=28MPa f'c=35MPa COMPRESSION TENSION
2 - Ø16 UP TO 175mm
SECOND LAYER
Ø10 350 330 300 400 500 2 - Ø20 200mm TO 500mm
1"CLEAR
1"CLEAR
Ø12 420 390 350 480 600 4 - Ø20 550mm TO 1000mm
H1
H2
A or G
HOOK
12db FOR 20mm LAP LENGTH
& 25mm
6db FOR 10mm,
12mm & 16mm PROVIDE CONSTRUCTION
db
JOINT BETWEEN (AS
DIMENSION SHOWN) SEE DETAIL
L/3
DETAILING
db
D
H
L2
b
D 4d L
DIMENSION
DETAILING
A or G db
D
db
FOR BEAMS WITH CONCENTRATED LOADS
6d
LAP LENGTH
b
NOMINAL (db) ACTUAL (da) DIAMETER (D) A or G A or G H FOR BEAMS WITHOUT CONCENTRATED LOADS
10 12 40 105.00 110 80
PLACE COLUMN HOOP
12 14 50 115.00 115 80
HOOKS OPPOSITE AT
16 19 65 155.00 140 95 EACH END ALTERNATELY
30db 75757575 30db
20 23 115 305.00 205 115 TYP. TYP. ADDITIONAL TIES (TYP.)
SUPPLEMENTARY CROSSTIES
25 29 155 410.00 270 155
MUST ENGAGE HOOPS AND
BEAM HEIGHT
H/3 H/3 H/3
COLUMN HOOPS BE WIRED TO COLUMN
COLUMN HOOPS
VERTICALS
DETAILING HOOK DETAILING
H
DIMENSION A or G DIMENSION
db
db
HOOKS OPPOSITE
A or G
J
b
30db
6°d
b
90
BAR SIZE *MINIMUM 90° BEND 135° BEND I.D = 4db
6db
50-100
°
NOMINAL (db) ACTUAL (da) DIAMETER (D) A or G A or G J 135
db
10 12 60 155 130 80
ALTERNATE 90° AND 135° ENDS
12 14 80 200 150 105
D
COLUMN HOOPS AT EACH END ON CONSECUTIVE CROSSTIES
16 19 95 250 180 130
1 PROVIDE
20 23 115 300 205 155 HOOP MAIN DETAIL SUPPLEMENTARY CROSSTIES DETAIL D 1 2-STIRRUPS
32 37 275 550 425 335 NOTE: AT THE LOCATION OF DEPRESSED SLABS, THE BOTTOM
OF BEAMS SHALL ALSO BE DEPRESSED.
36 42 305 600 475 375
42 49 465 775 675 550
FOR Ø10, Ø12 AND Ø16 TIES DEPRESSED BEAM ELEVATION
58 67 610 1050 925 725
B STANDARD HOOK & BEND D HOOPS & CROSS TIE BAR PLACEMENT DETAIL E CONCRETE BEAM & GIRDER CONSTRUCTION JOINT
S-02 SCALE NTS S-02 SCALE NTS S-02 SCALE NTS
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN STRUCTURAL NOTES 2 ADAPTED FROM TIEZA DRAWINGS G 03
03 08 33
COLUMN CONFINEMENT AS 500 500
SEE COLUMN
PER COLUMN SCHEDULE
SCHEDULE
(MINIMUM) (MINIMUM)
JOINT HOOP CONSTRUCTION JOINT Ldh BEAM REBARS
@100 TRANSVERSE
BEAM REBARS TERMINATION BEND
BEAM
(MINIMUM)
100
CONSTRUCTION JOINT CONSTRUCTION JOINT
(MINIMUM)
JOINT HOOPS
50
Xo Xo
500
Ldh
ROOF OR FLOOR
BEAMS
H\6
50 50
50 50
50
2 EXTRA TIES
50
50
50
50 50 50
CLEAR COLUMN HEIGHT : H
75mm O.C.
Ø16mm @
COLUMN CONFINEMENT TIES AS
h
6 PER COLUMN SCHEDULE
SEE SCHEDULE
HC
COLUMN TIES
COLUMN TIES
50
STAGGER SPLICE A MINIMUM
DISTANCE OF 600mm BETWEEN TWO
SEE COLUMN 50
ADJACENT BAR SPLICES. NOT MORE
THAN 33% OF THE BARS SHALL BE
INTERIOR COLUMN TERMINATION BEND
JOINT HOOPS
SPLICED IN ANY ONE LEVEL.
CONSTRUCTION JOINT
H\6
D D
GIRDER TOP BARS ARE LAID
SEE COLUMN
OVER OF BEAM TOP BARS
GIRDER TOP BARS
Xo > 1/6 (D) Xo <
SCHEDULE
Ld
50
NOTES: NOTES:
1. THE 90-DEGREE HOOK SHALL BE LOCATED WITHIN THE CONFINED
1. FOR Hc < 1000mm PROVIDE
CORE OF A COLUMN OR OF A BOUNDARY MEMBER
CONFINEMENT AS SHOWN
Xo = OFFSET DISTANCE
2. FOR TIES/HOOPS ARRANGEMENT
SEE COLUMN SCHEDULE 12d
BEAM
REINFORCED CONCRETE COLUMN DETAIL COLUMN DETAILS DUE TO DIFFERENT ELEVATIONS DETAILS DUE TO COLUMN OFFSETS 50 50 BEAM REINFORCEMENT
INTERIOR COLUMN
NOTE :
AT GIRDER SPAN CLEAR DISTANCE BETWEEN
CONSTRUCTION JOINT REBARS ARE TO BE
(TYPICAL) STRICTLY MAINTAINED
300
BEAM
SOFFIT TYPICAL PLAN OF BEAM/GIRDER COLUMN JOINT
COLUMN CLEAR HEIGHT (H)
CONSTRUCTION JOINT
(MINIMUM)
(MINIMUM)
ROUGHEN TO 6mm CONFINING REINF. ZONE MAXIMUM OF
AMPLITUDE (TYPICAL) 1. CLEAR HEIGHT/6
500
500
2. MAX. COL. DIMENSION
3. 450mm.
TOP OF FOOTING
50
50
REINF. ZONE TOP & BOT. BARS
@ MAT FTG.
1 BEAM STIRRUPS
ADD'L. 16mmØ CROSS JOINT-REINF. 50 50
TIES SPACED @ 400 CROSS-TIES
(Max) O.C. W/IN FOOTING BEAM BOTTOM BARS
SECTION COLUMN REBARS
2 EXTRA TIES
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN STRUCTURAL NOTES 3 ADAPTED FROM TIEZA DRAWINGS G 04
04 08 33
SEALANT
150x150mm - LINTEL BEAM
WITH 2-10mmØ
NON-EXTRUDING TYPE
JOINT FILLER Ø12 HORIZONTAL BARS
(LONGITUDINAL) AT EVERY 3 LAYERS OF CHB
600
12mmØ VERTICAL BAR
4. ALL CONCRETE HOLLOW BLOCKS MASONRY WALLS SHALL BE LAID IN RUNNING BOND ( INTERLOCKING COURSE ) WITH FULL
@600mm WITH 12mmØ 3-Ø10 LONGITUDINAL BARS
MORTAR BEDDING. STACK BOND SHALL BE USED ONLY WHEN SPECIFIED.
HORIZONTAL BAR @ 600
5. ALL CELLS SHALL SOLIDLY FILLED WITH CONCRETE-GROUT. 100mm THK. GRAVEL BED
200
WELL COMPACTED TO 95%%%
6. PROVIDE STIFFENER COLUMNS AT EVERY 3000mm O.C. WITH 4-Ø12 VERTICAL BARS & Ø10 TIES AT 200mm O.C. STIFFENER 10mmØ TIES @ 300mm MDD BASED ON ASTM D-698
COLUMN SIZE SHALL BE AT THE SAME THICKNESS AS CHBx300mm WIDE. (WHERE APPLICABLE)
7. PROVIDE STIFFENER BEAMS AT EVERY 3000mm O.C. WITH 4-Ø12 HORIZONTAL BARS & Ø10 TIES AT 200mm O.C.
STIFFENER BEAM SIZE WERE SAME THICKNESS AS CHBx300mm DEEP.
8. ALL MASONRY UNITS SHALL BE REINFORCED ACCORDING TO THE FOLLOWING SCHEDULE UNLESS OTHERWISE STATED IN THE PLANS. 450
9. BLOCK WALL REINFORCING BARS SHALL BE LAPPED A MINIMUM OF 30 BAR DIAMETERS WHERE SPLICED, HORIZONTAL / VERTICAL
WF1
DOWELS FROM FOOTINGS, COLUMNS/WALLS OR SLABS SHALL EXTEND INTO THE BLOCK WALL A MINIMUM OF 30 BAR DIAMETERS
OR A MINIMUM OF 400mm. WHICHEVER IS LONGER AND DOWELS TO MATCH VERTICAL REINFORCEMENTS OF WALL.
Ø10 HORIZONTAL BARS
AT EVERY 3 LAYERS OF CHB 100mm THK. CHB WALL
TABLE 7
S/2EQ.EQ.
0.152m CENTERBULB 10mm Ø BARS
LINTEL BEAM IN CMU WALL OPENING (100MM & 150MM THK.) @ EVERY 3 LAYERS
WATERSTOP
CLEAR TOTAL MIN. fc' HEIGHT OF
REINFORCEMENT
SPAN,L LENGTH MPa LINTEL (mm)
300
(mm) L + 400mm TOP BARS BOT. BARS TIES
"t" SLAB
(TYP)
50
150 "t" SLAB
1200 1600 13.80 200 1 -Ø12mm 1 -Ø12mm Ø10 @200 O.C.
100
2100 2500 13.80 250 2-Ø12mm 2-Ø12mm Ø10 @200 O.C.
ELASTIC SEALANT
2400 2800 13.80 250 2-Ø12mm 2-Ø12mm Ø10 @200 O.C.
3-10mmØ BARS
Ø10 @200 O.C.
400 50 (AS SHOWN)
2700 3100 13.80 250 2-Ø12mm 2-Ø12mm
3000 3400 13.80 300 2-Ø16mm 2-Ø12mm Ø10 @200 O.C. 100 WF3 12mmØ BOT. BARS
@300mm O.C.
6
2. SEE ARCHITECTURAL & MECHANICAL PLANS W > 400mm 2-Ø12 TOP OF BOTTOM BARS AT 600mm ON CENTER
FOR SLAB OPENING LOCATION. W < 150mm OR 0.10M (NO ADDITIONAL ø12 BACKER ROD
REINFORCEMENT REQ'D.)
CHB WALL
Ø12 x 1000 LONG AT MID-DEPTH 0.08 mm THICK
OF SLAB AT EACH CORNER POLYETHYLENE
VAPOR BARRIER
600
RC COLUMN OR
WALL 100mm THK. GRAVEL BED WELL
CHB HOR. REINF. COMPACTEDTO 95% MDD BASED ON
COLUMN (SEE SCHED. OF REINF. TABLE II)
1-Ø12 TOP ASTM D-698(WHERE APPLICABLE)
& BOTTOM BARS ADDITIONAL TRIMMER BARS 1-Ø10 EXTRA
200
40 (SHOWN AS DOTTED LINES), AS VERT. REINF.
SIDE OF OPENING EQUAL TO THE
NUMBER OF BARS TERMINATED
BY THE OPENING
SEE NOTE NO.9 OF MASONRY
DIAGONAL BAR BLOCK WALLS ON DWG. NO. S001-5
1 DETAIL OF OPENING
S-04 SCALE 1:15
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN STRUCTURAL NOTES 4 ADAPTED FROM TIEZA DRAWINGS G 05
05 08 33
2-Ø10 POWDER ACTUATED
25 MIN.
STUD ANCHOR (OR EQUAL)
CHB WALL
200x300x6 PL. SUPPORT
CHB VERT. REINF. @ 1200 O.C.
(SEE SCHED. OF REINF. SLAB/BEAM
DWG. NO. S001-5) COMPRESSIBLE FILLER MATERIAL CHB INTERIOR UNITS HOR. MASONRY REINFORCEMENT
25 MIN.
COMPRESSIBLE FILLER MATERIAL
LINTEL BLOCK W/ 2-Ø16
BLOCK WALLS ON
CHB VERT. REINF. DOWELS CONT. HOR. REINF. (SEE SCHEDULE DWG. NO. S001-5)
DWG. NO. S001-5
SEE NOTE NO.9
OF MASONRY
SLAB,t
SLAB
DEP.
COLUMN
BRACE @ 1200 O.C. 6mm THK. PLATE ANCHORED TO
SEE NOTE NO.9 OF MASONRY
300
300
BRACE ANGLE 64x64x6mm
@ 1200 O.C. SEALANT W/BACKER ROD
ON BOTH SIDE
SEALANT W/BACKER ROD
TOP OF CHB WALL ON BOTH SIDE PELT PAPER ON
2-Ø16 EXTRA VERT. BARS
1-Ø16 BOLTS PELT PAPER ON PVC SLEEVE
CHB VERT. REINF. (SEE SCHED. ADDITIONAL Ø10 2-Ø16 EXTRA VERT. BARS
2-Ø10X150LG. ANCHOR BOLTS PVC SLEEVE
OF REINF. DWG. NO. S001-5) @ 400 O.C. WT6X13x4" LG. W/ 100
CHB VERT. REINF. (SEE SCHED. LG. FOR 1-Ø16mm BOLT
OF REINF. DWG. NO. S001-5) WT6x13x4" LG.
CHB HOR. REINF. (SEE SCHED. CEILING LINE
OF REINF. DWG. NO. S001-5) LINTEL BLOCK 2-Ø16
CHB VERT. REINF. (SEE SCHED.
CHB VERT. REINF. (SEE SCHEDULE CONT. HORIZONTAL BARS
OF REINF. DWG. NO. S001-5)
FOR REINF. DWG. NO. S001-5) 2-Ø10x150 LG. ANCHOR BOLTS EXTERIOR CHB WALL
EXTERIOR CHB WALL ON R.C. WALL
ON R.C. WALL
CONCRETE FILLER
(MAX.)
PIPE
3.00
25mm GAP
LINTEL BEAM W/ CHB WALL STIFF. BEAMS
A 1-Ø16 CON. CONCRETE
(MIN)
LINTEL BEAM W/ -
A 2 - Ø 12 HOR. REINF. FILLER
- CONTINUOUS
B
(MAX.)
HORIZONTAL WINDOW
H
3.00
REINFORCEMENTS - OPENING STIFF. COLUMNS
C
- (SEE SCHEDULE DWG. NO. S001-5) MASTIC SEALANT
DOOR EACH SIDE
H
B PIPE SLEEVE
600 MIN.
CHB WALL
100mm
THAN 200 MM VERT. & 400 MM. HOR.
100 THK. CHB WALL 150 THK. CHB WALL CONC. EXTENSION WHEN 2Ø12 VERT. BARS FOR H≤3.0m
REQUIRED W/ 2-Ø16 REINF. 3-ø12 VERT. BARS FOR 3.0m<H<4.0m
CHB. VERT. REINF. 3-ø16 VERT. BARS FOR H>4.0m
CHB WALL CONC. END
(SEE SCHED. OF REINF.)
BLOCK
2-Ø12 HOR. BARS Ø10 TIES SPACED@ 150 O.C TO C.L.
CHB. VERT. REINF. 2-Ø12 HOR. BARS ALTERNATELY PLACED (TYP.)
CHB. VERT. REINF. (SEE SCHED. (SEE SCHED. OF REINF. 400
150mm
CHB "t"
400
Ø10 SPACED
400
Ø10 SPACED
@ 150 O.C. (TYP.)
CHB. VERT. REINF. (SEE SCHED. @ 150 O.C. (TYP.)
ALTERNATELY PLACED
OF REINF. DWG. NO. S001-5)
1-Ø16mm
200 (MIN.)
200 (MIN.)
SECTION A SECTION B SECTION C TYPICAL CHB STIFFENER BEAM DETAIL TYPICAL CHB STIFFENER COLUMN DETAIL ON CHB WALLS
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN STRUCTURAL NOTES 5 ADAPTED FROM TIEZA DRAWINGS G 03
06 08 33
INDEX OF DRAWINGS
DRAFTED:
PROJECT NAME AND LOCATION: SHEET CONTENTS: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: CONCURRED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS JAY C. QUINTILLA
ENGINEER I
QUANTITIES ARE SUBJECT TO DECREASE OR INCREASE AS PER ACTUAL ACCOMPLISHMENT AND AS CERTIFIED BY THE ENGINEER.
DRAFTED:
PROJECT NAME AND LOCATION: SHEET CONTENTS: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: CONCURRED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS JAY C. QUINTILLA
ENGINEER I
KALAHI RO
AD
N
A PLAN
- SCALE 1:1000
AKN-36
N=1,323,764.652
E=382,244.721
EL.=2.339m
20cm x 20cm CONCRETE
MONUMENT W/ BOLT @ CENTER
END OF PROJECT
0+547.16 1
DS-05
B PROFILE
- SCALE 1:1000
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN AND PROFILE
(PACKAGE 1A - KALAHI ROAD)
ADAPTED FROM TIEZA DRAWINGS PP 09
01 07 33
0 30
. 0+
INE ET 2
STA
HE
MAT SEE S
CHL
A1 P L A N
- SCALE 1:500
N
A2 PROFILE
- SCALE 1:500
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN AND PROFILE
(PACKAGE 4 - LAGUTAN ROAD)
ADAPTED FROM TIEZA DRAWINGS PP 10
02 07 33
N
300
. 0+
STA
1
ET
SHE
NE
HLI
SEE
C
MAT
A1 P L A N
- SCALE 1:500
A2 PROFILE
- SCALE 1:500
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN AND PROFILE
(PACKAGE 4 - LAGUTAN ROAD)
ADAPTED FROM TIEZA DRAWINGS PP 11
03 07 33
LEGEND:
TO MANOC -
RESORT AY
DRAINAGE LINE
MANOC
HOLID
1+540
FLOW DIRECTION
BO CAY
BEGINNING OF PROJECT ROAD INTERSECTION A1 400X500mm BASE X HEIGHT OF U-DITCH
STA. 0+000.00 (SEE DETAIL)
A
DS-01
R
1000mm DIAMETER OF HDPE PIPE
H
HDPE HIGH-DENSITY POLYETHYLENE
FIESTA
STA. 0+020.00 END OF PROJECT
C
PROVIDE BAR SCREEN STA. 0+287.13
1+560
INSIDE THE MANHOLE LS LIFT STATION
TO TRAP DEBRIS
A
DIM DROP INLET MANHOLE
1-1200mm Ø HDPE
E
IE = 2.69m INSTALLED U-DITCH & MANHOLE
0+000
0+020
LS-01
0+040
B
0+060
R O A D
0+100
1+580
0+120
0+08
0+280
0+287.13
0+260
NOTES:
0+140
0+240
0+220
0+160
0+200
0+180
T E
1-1200mm Ø HDPE
1) PROVIDE INLET AS EVERY 20M INTERVAL.
IE = 2.70m
2) U-DITCH W/ COVER SHALL HAVE A
BORACAY REGENCY ROAD MINIMUM FREE BOARD OF 100mm.
I
3) PROVIDE MANHOLE AT EVERY CHANGE
M A I N
H
S
1+600
W
PROVIDE EXTRA STORAGE.
W
1+620
N
TO PLAN
SCALE: 1:700m
YAPAK
Cannot draw reference system - no coordinate system assigned
10
E L E V A T I O N
STA. 0+209.13
MANHOLE 01
MANHOLE 03
BEGINNING OF PROJECT
STA. 0+000.00
HDPE 1000mmØ
STA. 0+000.00
STA. 0+132.13
MANHOLE 02
I.E= +1.437
END OF PROJECT
STA. 0+287.13
LS-01
5
LS-01
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
DIM
IIE=2.694
1-1200mmØ
HDPE PIPE
PROFILE
PROVIDE VERTICAL SCALE: 1:70m
HORIZONTAL SCALE: 1:700m
BAR SCREEN
0
0+280 0+300 0+320 0+340
STATION 0+000 0+020 0+040 0+060 0+080 0+100 0+120 0+140 0+160 0+180 0+200 0+220 0+240 0+260
0+287.13
3.241
4.190
3.656
3.406
3.369
3.270
3.160
3.193
3.217
3.208
3.267
3.363
3.389
3.072
2.926
3.205
3.41
3.21
3.21
4.19
3.66
3.37
3.27
3.24
3.16
3.19
3.22
3.27
3.36
3.39
3.07
2.93
ORIGINAL GROUND
PIPE INVERT
0.911
0.933
1.233
1.246
1.246
1.269
1.469
1.50
ELEVATION
PIPE/U-DITCH 1500mmØ HDPE 1200mmØ HDPE 1200mmØ HDPE 1000mmØ HDPE
SIZE
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN AND PROFILE
(BORACAY REGENCY ROAD SECTION)
ADAPTED FROM TIEZA DRAWINGS PP 12
04 07 33
LEGEND:
TO BRGY.
SAN ROQUE DRAINAGE LINE
1+480
FLOW DIRECTION
SEAM WIRELESS
400X500mm BASE X HEIGHT OF U-DITCH
ACE
BEGINNING OF PROJECT
STA. 0+000.00
1000mm DIAMETER OF HDPE PIPE
H
BORACAY
END OF PROJECT
1+500
HDPE
DAUM
HIGH-DENSITY POLYETHYLENE
ROAD INTERSECTION A1
C
(SEE DETAIL) DS-02 STA. 0+310.00
LS LIFT STATION
A
DIM DROP INLET MANHOLE
STA. 0+020.00
E
0+200
0+220
0+180
LS-02 PROVIDE BAR SCREEN INSTALLED U-DITCH & MANHOLE
INSIDE THE MANHOLE
0+240
0+260
0+000
TO TRAP DEBRIS
0+160
1+520
B
0+280
0+020
0+140
0+040
SUNSET ROAD NOTES:
0+060
0
0+120
0+30
T E
10
0+100
0+3
S 1) PROVIDE INLET AS EVERY 20M INTERVAL.
R O A D
0+080
2) U-DITCH W/ COVER SHALL HAVE A
AY
I
HOLID
1+540
BORACAY RT
H
RESO
W
W PROVIDE EXTRA STORAGE.
M A I N
LED
N
INSTAL
FIESTA
1+560
TO BRGY.
0
PLAN
0+00
SCALE: 1:700m
SAN ROQUE
0
0+02
1+580
10
E L E V A T I O N
BEGINNING OF PROJECT
1-1200mmØ HDPE
STA. 0+000.00
END OF PROJECT
STA. 0+000
IE = 3.142
STA. 0+310.00
HDPE 1200mmØ
5
I.E = 1.143
INSTALLED
LS-02
PROVIDE
BAR SCREEN
1800mmØ HDPE
I.E=0.130
PROFILE
VERTICAL SCALE: 1:70m
HORIZONTAL SCALE: 1:700m
0
0+280 0+300 0+320 0+340
STATION 0+000 0+020 0+040 0+060
0+064
0+080
0+084
0+100 0+120 0+140 0+160 0+180 0+200 0+220 0+240 0+260
0+310
3.471
3.421
3.831
4.323
3.732
3.603
3.515
3.437
3.529
3.545
3.510
3.542
3.462
3.438
3.674
3.657
3.454
3.51
4.32
3.60
3.52
3.42
3.44
3.54
3.54
3.44
3.73
3.47
3.53
3.46
3.67
3.83
3.66
3.45
ORIGINAL GROUND
PIPE INVERT
0.111
0.731
0.130
2.135
2.335
2.524
0.743
1.727
ELEVATION
PIPE/U-DITCH 450x850mm 400x650mm
1500mmØ HDPE 1200mmØ HDPE
SIZE
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN AND PROFILE
(SUNSET ROAD SECTION)
ADAPTED FROM TIEZA DRAWINGS PP 13
05 07 33
TO BRGY.
BEGINNING OF PROJECT
SAN ROQUE
1+400
STA. 0+000.00
H
C
END OF PROJECT
STA. 0+324.25
A1 ROAD INTERSECTION
A
DS-03 (SEE DETAIL)
0+000
STA.0+255.08
1+380
0+ 020
STA.0+234.25
STA.0+269.08
STA.0+284.25
STA.0+214.25
E
STA.0+194.25
0+040
STA.0+304.25
0+060
STA.0+324.25
0+080
B
0+100
0+240
0+260
0+120
0+220
0+280
0+200
0+140
T E
0+180
0+160
5
0+300
0+324.2
0+320
1+360
PCT V ROAD
I
LEGEND:
R O A D
H
DRAINAGE LINE
PCT V ROAD
LS-03
W
1+340
FLOW DIRECTION STA. 0+309.00
PNB
M A I N
1) PROVIDE INLET AS EVERY 20M INTERVAL.
1+320
LS
S
LIFT STATION
TYARD
CY
3) PROVIDE MANHOLE AT EVERY CHANGE
N
CROW
REGEN
OF DIMENSIONS AND DIRECTIONS.
DIM DROP INLET MANHOLE
COUR
4) THE 1500mmØ HDPE PIPE IS USED TO TO BRGY.
INSTALLED U-DITCH & MANHOLE PROVIDE EXTRA STORAGE. PLAN
SCALE: 1:700m
SAN ROQUE
BDO
Cannot draw reference system - no coordinate system assigned
E L E V A T I O N
BEGINNING OF PROJECT
STA. 0+000.00
END OF PROJECT
STA. 0+324.25
STA.0+309
STA. 0+309
5
STA. 0+150
STA. 0+250
LS-03
PROVIDE
BAR SCREEN
0
PROFILE
VERTICAL SCALE: 1:70m
HORIZONTAL SCALE: 1:700m
-2
0+280 0+300
STATION 0+000 0+020 0+040 0+060 0+080 0+100 0+120 0+140 0+150 0+160 0+170 0+180 0+200 0+220 0+240 0+260
4.161
4.161
4.161
4.586
4.164
3.897
3.727
3.599
3.578
3.457
3.455
3.567
3.526
3.660
3.538
3.575
3.509
3.720
3.51
3.90
4.59
4.16
3.60
3.54
3.72
4.16
3.73
3.58
3.46
3.46
3.57
3.53
3.66
3.58
ORIGINAL GROUND
PIPE INVERT
1.781
1.031
3.017
2.567
2.067
2.017
2.467
1.027
ELEVATION
PIPE/U-DITCH 500x600mm 550x700mm 600x750mm 1500mmØ HDPE
SIZE
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN AND PROFILE
(PCTV ROAD SECTION)
ADAPTED FROM TIEZA DRAWINGS PP 14
06 07 33
N
PS-04
A1 P L A N
- SCALE 1:500
A2 PROFILE
- SCALE 1:500
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN AND PROFILE
(PACKAGE 5 - END OF LUGUTAN ROAD TO PS4) ADAPTED FROM TIEZA DRAWINGS PP 15
BLOOMFIELD ROAD STA.0+000 - 0+183.15 07 07 33
A B C D E F
3 4
S-07 S-07
1'
A B C D E F
2 3 4
S-07 S-07 S-07
1
S-07
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PLAN
PUMPING STATION 4
ADAPTED FROM TIEZA DRAWINGS S 16
01 08 33
A B C D E F
1 SECTION
S-07 SCALE 1:50
4 3 2 1' 1 1 2 3 4
4 3 1' 1
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
SECTION
PUMPING STATION 4
ADAPTED FROM TIEZA DRAWINGS S 17
02 08 33
3
A B C D E S-08 F
2
S-08
4
S-08
A B C D E F 4 3 2 1
4
-
2 SECTION 3 SECTION
S-08 SCALE 1:40 S-08 SCALE 1:40
4 TYPICAL DETAIL
S-08 SCALE 1:40
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
PILE CAP PLAN AND SECTIONS
PUMPING STATION 4
ADAPTED FROM TIEZA DRAWINGS S 18
03 08 33
1 COLUMN SCHEDULE
S-09 SCALE NTS
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
COLUMN SCHEDULE AND WALL REINFORCEMENT
DETAIL
ADAPTED FROM TIEZA DRAWINGS S 19
PUMPING STATION 4 04 08 33
GRID GRID GRID GRID
1 RC GIRDER/BEAM SCHEDULE
S-10 SCALE NTS
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
RC GIRDER BEAM / BEAM SCHEDULE
PUMPING STATION 4
ADAPTED FROM TIEZA DRAWINGS S 20
05 08 33
1 TYPICAL SLAB ELEVATION
S-11 SCALE 1:20
R. C. S L A B S C H E D U L E
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
TYPICAL REINFORCEMENT DETAIL OF ONE &
TWO WAY SLAB ADAPTED FROM TIEZA DRAWINGS S 21
PUMPING STATION 06 08 33
A
S-12
A SECTION
S-12 SCALE 1:5
B SECTION
S-12 SCALE 1:5
CONFINEMENT RING
1 PILE REINFORCEMENT ELEVATION 2 PILE REINFORCEMENT LAYOUT C AND SPACER DETAIL F SPLICE DETAIL G SPACER DETAIL
S-12 SCALE 1:50 S-12 SCALE 1:50 S-12 SCALE 1:10 S-12 SCALE 1:10 S-12 SCALE 1:10
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
BORED PILE DETAILS
PUMPING STATION 4
ADAPTED FROM TIEZA DRAWINGS S
07 08
22
33
2 ELEVATION OF CYCLONE WIRE FENCE
S-13 SCALE 1:30
B
-
A PLAN
S-13 SCALE 1:30
4
S-13 5
6 S-13
S-13
3 DETAIL
S-13 SCALE 1:10 5 DETAIL
S-13 SCALE 1:10
3
S-13
B SECTION ELEVATION
S-13 SCALE 1:30 6 DETAIL
S-13 SCALE 1:10
4 DETAIL
S-13 SCALE 1:10
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
ENTRANCE GATE DETAIL AND CYCLONE WIRE
FENCE DETAIL ADAPTED FROM TIEZA DRAWINGS S 23
PUMPING STATION 4 08 08 30
A B C D E F
GENERAL NOTES
THE PUMPS SHALL BE SELF-PRIMING CENTRIFUGAL TYPE PUMP.
FOR MAINTENANCE PURPOSES, THE PUMPING SYSTEM SHALL BE PROVIDED WITH PROGRAM SEQUENCER
SUCH THAT LEAD PUMP SHALL BE IDENTIFIED AND OPERATED EVERY WEEK.
4 5 6
- - -
PUMP OPERATOR TRAINING SHALL BE PROVIDED IN THE OPERATION AND MAINTENANCE OF THE PUMPING SYSTEM.
3
-
1 GENERAL NOTES
M-01 SCALE NTS 3
4
A B C D E F
3 SECTION
M-01 SCALE 1:75
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
MECHANICAL PLAN, SECTION
AND GENERAL NOTES
PUMPING STATION 4
ADAPTED FROM TIEZA DRAWINGS M 24
01 02 33
4 3 2 1
1 2 3 4
4 SECTION
M-01 SCALE 1:50
4 3 2 1
6 SECTION
M-01 SCALE 1:50
7A ELEVATION 7B ISOMETRIC
M-02 SCALE NTS. M-02 SCALE NTS.
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
SECTION 4, 5, 6 AND
MOBILE LADDER
PUMPING STATION 4
ADAPTED FROM TIEZA DRAWINGS M 25
02 02 33
F2
-
C2
-
N
C3
F1 P L A N
- SCALE 1:100
-
C3 SECTION
SCALE 1:15
A MAIN ROAD - KALAHI ROAD INTERSECTION -
- SCALE NTS
DETAIL OF ANGLE
E FRAME SUPPORT
B3 - SCALE 1:10
-
B2 SECTION
- SCALE 1:50
B2
-
B3 SECTION B4 SECTION
- SCALE 1:50
B1 P L A N - SCALE 1:50
- SCALE 1:50
F3 SECTION
B DETAIL OF JUNCTION BOX - SCALE 1:30
- SCALE AS SHOWN
F TYPICAL DETAIL OF MANHOLE
- SCALE AS SHOWN
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
MAIN ROAD-KALAHI ROAD
TYPICAL DETAILS OF JUNCTION BOX MANHOLE
ADAPTED FROM TIEZA DRAWINGS SD 26
CATCHBASIN 01 08 33
A3
-
A1 A2
- -
DETAIL OF ANGLE
B SECTION B1 D FRAME SUPPORT
SCALE 1:10 SCALE 1:10
- -
A PLAN
SCALE 1:15
-
C SECTION B2
A2 DETAIL OF U-DITCH (WIDTH=1300mm-1600mm) - SCALE 1:10
SCALE 1:15
-
D
-
C
-
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN DETAIL OF U-DITCH WITH COVER ADAPTED FROM TIEZA DRAWINGS SD 27
02 08 33
250 2500 250 2000 250
800 900 800 650 1100 EXISTING DPWH MANHOLE EXISTING DPWH MANHOLE
16mmØ @100
16mmØ @100 MAIN ROAD
PCTV ROAD
B3
EXISTING DPWH
1200
1200
MANHOLE 1200mmØ HDPE (EXISTING)
1200mmø
1788
HDPE
3134
300
250
92
3000
B4
250
3000
250
200
250
B2 SECTION
100 150 250 2500 250
DS - 01 SCALE 1:50
12mmØ @100
16mmØ @100
BLOCKOUT FOR 12mmØ @100
1500mmØ HDPE
50 200mm PVC PIPE 16mmØ @100
Q=0.684cms
OPENING 16mmØ @100
25
25 25 250
2976
3476
100
50
BUTT WELD
1200mmø 1200mmø
12mmØx200mm HDPE HDPE
ANCHOR BAR
1500mmø
25
2038
1538
250
250
1500
92 92
150 100
12mmØ @100 3000 12mmØ @100
1238
B1 PLAN B4 SECTION
2-Ø12mm
DS - 01 SCALE 1:50
200
DS - 01 SCALE 1:50
Ø10mm
400
200
3000
200
1.06x0.95m RCBC
C3 TO YAPAK MAIN ROAD TO MANOC-MANOC
(EXISTING)
900
Ø16mm TOP & BOTTOM
BAR HANDLE BARS @ 100mm O.C. 900
STEEL FRAME
Ø10mm TOP & 425 STEEL FRAME
75x75mmx6 W/
BOTTOM BARS 75x75mmx6 W/
10mmØx150mm BAR HANDLE
@ 150mm O.C. 10mmØx150mm 1200mmØ HDPE
425
C2 ANCHOR BAR @
ANCHOR BAR @ (EXISTING)
150 O.C.
150 O.C.
TO PCTV
850
200
200
PNB
HENANN LAGOON RESORT
Ø10mm TOP & BOTT
BARS @ 150mm O.C.
Ø10mm TOP & Ø16mm TOP &
425
C2 SECTION C3 SECTION
DS - 01 SCALE 1:15 DS - 01 SCALE 1:15
C1 SECTION
DS - 01 SCALE 1:15
C MANHOLE COVER DETAIL A MAIN ROAD - PCTV ROAD INTERSECTION
DS - 01 SCALE AS SHOWN DS - 01 SCALE 1:150
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
MAIN ROAD - PCTV ROAD INTERSECTION AND
TYPICAL DETAILS OF JUNCTION BOX MANHOLE
ADAPTED FROM TIEZA DRAWINGS SD 28
03 08 33
250 2500 250 2000 250
800 900 800 650 1100 EXISTING DPWH MANHOLE EXISTING DPWH MANHOLE
16mmØ @100
16mmØ @100 MAIN ROAD
BORACAY REGENCY ROAD
B3
EXISTING DPWH
1200
1496
MANHOLE 1200mmØ HDPE (EXISTING)
1200mmø
1796
HDPE
3279
300
3621
242
92
460V, 3-PHASE
1500mmØ HDPE
92
3000
3000
3000
250
250
250
50
1500mmØ HDPE
25
Q=0.896 cms
25 25 1200mmø 1200mmø
HDPE HDPE 12mmØ @100
2038
1538
100
12mmØ @100
50
BUTT WELD
16mmØ @100
12mmØx200mm
ANCHOR BAR
25
3029
W.I. ANGLE
3621
E ANGLE FRAME SUPPORT DETAIL 12mmØ @100
DS - 02 SCALE 250 1:10 B2
12mmØ @100 1500mmø
1583
1158 157
92 1500 92
2-Ø12mm
200
3000
250
12mmØ @100
Ø10mm 3000
B1
400
900
425
75x75mmx6 W/ Ø10mm TOP & C2
BAR HANDLE 75x75mmx6 W/
10mmØx150mm BOTTOM BARS
10mmØx150mm
ANCHOR BAR @ @ 150mm O.C.
ANCHOR BAR @
150 O.C. 150 O.C.
850
Ø10mm TOP & BOTT
200
200
TO REGENCY
425
CT
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
MAIN ROAD - BORACAY REGENCY ROAD
INTERSECTION AND TYPICAL DETAILS OF JUNCTION ADAPTED FROM TIEZA DRAWINGS SD 29
BOX MANHOLE 04 08 33
250 2500 250 2000 250
800 900 800 900 1100
EXISTING DPWH MANHOLE EXISTING DPWH MANHOLE
16mmØ @100
16mmØ @100 MAIN ROAD
SUNSET ROAD
EXISTING DPWH B3
1200
MANHOLE
1200mmø 1200mmØ HDPE (EXISTING)
1788
HDPE
300
250
4212
B4
3000
92
3000
2500 250
1500
5
250 2500 250
1500mmØ HDPE 650 250 1600
16mmØ @100
92
BLOCKOUT FOR
200mm PVC PIPE 16mmØ @100
OPENING
SUBMERSIBLE SEWERAGE PUMP
250
250
250
460V, 3-PHASE
250 B2 SECTION
1500mmØ HDPE
12mmØ @100 HDPE HDPE
Q=1.165cms
DS - 03 SCALE 1:50
100 150
2038
1538
50
16mmØ @100
25
25 25 16mmØ @100
250
4054
4554
100
50
2516
W.I. ANGLE
1500mmø
HDPE
E ANGLE FRAME SUPPORT DETAIL 1158 158
DS - 03 SCALE 1:10
92 1500 92
250
250
150 100 3001
B1 PLAN
12mmØ @100
DS - 03 SCALE 1:50
200
12mmØ @100 3000
2-Ø12mm
200
B3 SECTION B4 SECTION
DS - 03 SCALE 1:50 DS - 03 SCALE 1:50 1200mmØ HDPE
Ø10mm (EXISTING)
400
DS - 03 SCALE AS SHOWN
900
1200mmØ HDPE
TO YAPAK MAIN ROAD TO MANOC-MANOC
(PROPOSED)
900 Ø16mm TOP & BOTTOM
BAR HANDLE BARS @ 100mm O.C.
D DETAIL 4-Ø12mm STEEL FRAME
DS - 03 SCALE 1:10 75x75mmx6 W/ Ø10mm TOP &
Ø12mm BOTTOM BARS
10mmØx150mm
@ 150mm O.C.
ANCHOR BAR @
425
425 STEEL FRAME 150 O.C. C2
75x75mmx6 W/
BAR HANDLE
10mmØx150mm
ANCHOR BAR @
200
850
150 O.C.
TO BORACAY SUNSET
Ø10mm TOP & BOTT
200
425
BOTTOM BARS
@ 100mm O.C. BAR HANDLE
Ø10mm TOP & Ø16mm TOP &
BOTTOM BARS BOTTOM BARS C2 SECTION
@ 150mm O.C. @ 100mm O.C. DS - 03 SCALE 1:15
BORACAY HOLIDAY RESORT
C3 SECTION C1 SECTION
DS - 03 SCALE 1:15 DS - 03 SCALE 1:15
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
MAIN ROAD - SUNSET ROAD INTERSECTION AND
DETAIL OF JUNCTION BOX MANHOLE
ADAPTED FROM TIEZA DRAWINGS SD 30
05 08 33
EXISTING STRUCTURES
EXISTING STRUCTURES
150
CONCRETE CURB
150
CONCRETE CURB 2% SLOPE
200mm PCCP
200
1800
200
TYPICAL CROSS SECTION - RCBC
SCALE NTS
EXISTING STRUCTURES
EXISTING STRUCTURES
150
CONCRETE CURB
150
200mm PCCP
200
MANHOLE
1800
HDPE
200
DRAFTED:
PROJECT NAME AND LOCATION: SHEET CONTENTS: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: CONCURRED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS JAY C. QUINTILLA
ENGINEER I
W W W
mm
6mmØ m 10mmØ
25
25m
P P P P
.
D
D
I.
I.
I.
)
)
(d
(d
(d
I.D.
I.D.
W
NOTE :
BLUE PAINT - STANDARD STRENGTH RCPC
RED PAINT - EXTRA STRENGTH RCPC
Ø
FOR SMALL PIPES OR bc + 75cm EMBANKMENT
WHICHEVER IS GREATER, FROM THE DESIGN DIAMETER.
12
FOR 700-INCH OR LARGER PIPES (COMPACTED BASE COURSE MATERIAL)
200
2 0
2. WALL THICKNESS - THE WALL THICKNESS SHALL NOT BE LESS bc = outside diameter of pipe
THAN THAT SHOWN IN THE DESIGN BY MORE THAN 5%
bc + 15 cm
OR 4.8Om WHICHEVER IS GREATER.
DS-7
100
EXISTING RCP NEW RCP
14MPa CONC. OR BETTER
MIN = bc
4 bc ACCURATELY SHAPED
bc + 10 CM
TO FILL PIPE
THOROUGHLY MIN = bc/10
dc
D
100
TAMPED EARTH
100
t
pbc
150 150
I.D.
6-10mmØ BARS
t
100
EARTH OR ROCK ACCURATELY SHAPED EARTH OR ROCK
TO FILL PIPE 4cm PER METER
MIN= 41 INSIDE DIAMETER OF H WHEN H=5m
D
B
* THE DISTANCE FROM CENTERLINE OF THE REINFORCEMENT TO THE NEAREST SURFACE OF THE CONCRETE HAS BEEN ASSUMED AS 32mm FOR PIPES WITH A SHELL THICKNESS OF 64mm OR MORE
* TEST LOADS FOR SAND-BEARING TEST SHALL BE ONE-HALF TIMES THOSE SPECIFIED IN THIS TABLE FOR THE THREE - EDGE BEARING TEST.
PROJECT NAME AND LOCATION: SHEET CONTENTS: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VI
FORT SAN PEDRO, ILOILO CITY
BORACAY DRAINAGE IMPROVEMENT PROJECT
BORACAY ISLAND, MALAY, AKLAN
STANDARD DETAILS OF REINFORCED CONCRETE
PIPE CULVERT (RCPC)
ADAPTED FROM DPWH STANDARDS SD 32
07 08 33
2400 (8ft.)
ON NO
SI
S
UA
I
COMMISSION ON AUDIT
MM
TI D
CO
NOTE : THE EXPENSES INCURRED IN THE INSTALLATION OF BILLBOARD IS (PROVINCE AND CITY)
UE R
E S
BP
I N
IL
P
C
INCLUDED IN THE OCM PER DO. 12, SERIES 2011
P
F
I
O
T L
EH I
P H
Project: Cost:
2438mm (8ft.) Fund Source:
Location:
WHITE BACKGROUND Implementing Agency:
Development Partner:
2400 (8ft.)
Contractor/Supplier:
Brief Description of Project:
1219mm (4ft.)
BLACK TEXT
Project Details:
Project Date Project Status
Target Date Cost
Duration Percentage of As of Date Remarks
Started of Incurred to
Completion (Date) Completed
Completion Date
2400 (8ft.)
EDGE OF ROAD
45°
TRAFFIC DIRECTION
DISPLAY AREA
DISPLAY AREA ROAD (TARPAULIN ON 2400 X 2400 X 5 MARINE PLYWOOD)
2400
2400
50 x 50 HORIZONTAL ORIENTATION 50 X 50 HORIZONTAL 50 x 50 HORIZONTAL
COCO LUMBER COCO LUMBER COCO LUMBER
DISPLAY AREA
1200
1200
(1200 X 2400 X 12 MARINE FLYWOOD)
1000
50 x 75 HORIZONTAL
50 x 50 COCO LUMBER 50 x 50
1000
1000
1000
WOODEN STAKE WOODEN STAKE
500
500
500
1000 2400 1000 2400