Professional Documents
Culture Documents
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
WORKMANSHIP ..................................................................................................................... 47
HANDLING AND STORAGE OF MATERIALS ........................................................................ 47
CON1.W010.9 BAGGED CEMENT ......................................................................................... 47
CON1.W020.9 BULK CEMENT, PFA AND GGBS ................................................................ 47
CON1.W030.9 AGGREGATES ................................................................................................ 47
CON1.W040.9 ADMIXTURES AND CURING COMPOUNDS ............................................. 47
BATCHING AND MIXING CONCRETE..................................................................................... 48
CON1.W110.9 BATCHING PLANT ........................................................................................ 48
CON1.W120.9 ALLOWANCE FOR WATER CONTENT OF AGGREGATES..................... 48
CON1.W130.9 QUANTITY OF WATER ................................................................................. 48
CON1.W140.9 CONCRETE MIXING PLANT ........................................................................ 48
Specification Library 2022 Edition (Batch 1) CON /3
CONCRETE WORKS CON > TABLE OF CONTENTS
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING ................................................................................................................................... 64
TRIALS OF DESIGNED CONCRETE MIXES ........................................................................... 64
CON1.T010.9 REQUIREMENT FOR TRIAL MIXES ........................................................... 64
CON1.T020.9 TIMING OF TRIALS ....................................................................................... 64
CON1.T030.9 PLANT AND LABORATORY TRIALS ......................................................... 64
CON1.T040.A PROCEDURE OF PLANT TRIALS FOR CONCRETE FROM
SINGLE BATCHING PLANT ......................................................................... 64
CON1.T045.9 PROCEDURE OF PLANT TRIALS FOR MIXING CONCRETES
FROM TWO BATCHING PLANTS WITH DIFFERENT CEMENT
SOURCES ......................................................................................................... 65
CON1.T050.9 PROCEDURE OF LABORATORY MIX TRIALS ......................................... 65
CON1.T070.9 STANDARD FOR APPROVAL OF PLANT TRIALS FOR
CONCRETE FROM SINGLE BATCHING PLANT ....................................... 65
CON1.T075.9 STANDARD FOR APPROVAL OF PLANT TRIALS FOR MIXING
CONCRETE FROM TWO BATCHING PLANTS WITH
DIFFERENT CEMENT SOURCES ................................................................. 66
CON1.T080.9 STANDARD FOR APPROVAL OF LABORATORY MIX TRIALS ............ 67
CON1.T085.9 PROVISIONAL APPROVAL OF PLANT AND LABORATORY
MIX TRIALS .................................................................................................... 67
CON1.T090.9 NON-COMPLIANCE ....................................................................................... 67
CON1.T100.9 VARIATIONS TO APPROVED MIXES ......................................................... 68
CON1.T110.9 PRACTICAL TESTS FOR SUITABILITY OF THE MIX .............................. 68
CON1.T120.9 CERTIFIED EVIDENCE OF MIX SUITABILITY ......................................... 68
SAMPLING AND TESTING GENERALLY ................................................................................ 68
CON1.T205.9 GENERAL ........................................................................................................ 68
CON1.T210.9 DEFINITION OF "BATCH" ............................................................................ 68
CON1.T220.9 SAMPLES FOR TESTING BY DIRECT TESTING CONTRACTOR
(DTC) ................................................................................................................ 68
CON1.T230.9 TESTING PROGRAMME ............................................................................... 68
CON1.T240.9 SAMPLE SIZES ............................................................................................... 68
SAMPLING....................................................................................................................................... 69
CON1.T320.9 COARSE AND FINE AGGREGATES ............................................................ 69
CON1.T330.9 WATER FOR MAKING CONCRETE ............................................................ 69
CON1.T340.9 FRESH CONCRETE ........................................................................................ 70
CON1.T350.9 FACILITIES FOR SAMPLING FRESH CONCRETE .................................... 71
TESTS ON AGGREGATES ............................................................................................................ 71
CON1.T410.9 STANDARD ..................................................................................................... 71
CON1.T420.9 FURTHER ANALYSIS .................................................................................... 72
TESTS FOR WORKABILITY ....................................................................................................... 72
CON1.T510.9 STANDARD ..................................................................................................... 72
CON1.T520.9 ACCEPTANCE VALUES FOR APPROVED MIXES .................................... 73
TESTS ON COMPRESSIVE STRENGTH OF CONCRETE CUBES ....................................... 73
CON1.T610.9 STANDARD FOR CUBE TESTS .................................................................... 73
CON1.T620.9 SAMPLES FOR DESIGNED CONCRETE MIXES ........................................ 74
CON1.T630.9 RESULTS FOR DESIGNED CONCRETE MIXES......................................... 74
CON1.T640.9 COMPLIANCE CRITERIA FOR DESIGNED CONCRETE MIXES ............. 75
_____________________________________________________________________________________________
APPENDICES............................................................................................................................ 82
CON1.APPEND1.9 FORM A ........................................................................................................... 82
_____________________________________________________________________________________________
MATERIALS ............................................................................................................................. 89
DEFINITIONS .................................................................................................................................. 89
CON2.M010.9 FORMWORK OR FORM ................................................................................ 89
CON2.M020.9 FALSEWORK .................................................................................................. 89
CON2.M030.9 TRADITIONAL FORMWORK ....................................................................... 89
CON2.M040.9 PERMANENT OR LEFT IN FORMWORK .................................................... 89
CON2.M050.9 LARGE PANEL FORMWORK ....................................................................... 89
CON2.M060.9 SMALL PANEL METAL FORMWORK ........................................................ 89
CON2.M080.9 TIMBER FOR FORMWORK .......................................................................... 89
SHEATHING .................................................................................................................................... 89
CON2.M110.9 SUITABLE MATERIALS ................................................................................ 89
ANCILLARY MATERIALS ........................................................................................................... 89
CON2.M210.9 RELEASE AGENT ........................................................................................... 89
CON2.M220.9 SURFACE RETARDERS................................................................................. 89
CON2.M230.9 HOLLOW CONCRETE BLOCKS FOR SLABS ............................................. 89
CON2.M240.9 PRECAST KICKER BLOCKS ......................................................................... 90
MATERIAL FOR SEALING FORMWORK TIE HOLES ......................................................... 90
CON2.M250.9 MORTAR.......................................................................................................... 90
CON2.M260.9 POLYURETHANE FOAM .............................................................................. 90
WORKMANSHIP ..................................................................................................................... 91
Specification Library 2022 Edition (Batch 1) CON /8
CONCRETE WORKS CON > TABLE OF CONTENTS
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING ................................................................................................................................... 99
TESTING OF MORTAR FOR SEALING FORMWORK TIE HOLES.................................... 99
CON2.T110.9 LABORATORY TESTING .............................................................................. 99
CON2.T120.9 TESTING FOR CHARACTERISTICS OF MORTAR .................................... 99
CON2.T130.9 REQUIREMENT FOR FURTHER TEST ........................................................ 99
CON2.T140.9 WATERTIGHTNESS TEST ON SITE ............................................................ 99
CON2.T150.9 FAILURE OF WATERTIGHTNESS TEST................................................... 100
CON2.T160.9 ADDITIONAL TESTS UPON FAILURE OF WATERTIGHTNESS
TEST ............................................................................................................... 100
CON2.T170.9 MAKE GOOD FORMWORK TIE HOLES ................................................... 100
CON2.T180.9 BLOWHOLES ................................................................................................ 101
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
GENERAL
CON1.M010.9 STANDARD
Unless otherwise specified, comply with 'Code of Practice for Structural Use of
Concrete 2013' issued by the Buildings Department, BS8007:1987 and
BS5400:Part 4:1990 as appropriate.
_____________________________________________________________________________________________
CEMENTS
CON1.M110.9 SUBMISSIONS
Submit to the CM for Approval, a sample for each type of cement, PFA and GGBS
together with a certificate issued by an Approved laboratory within six months
before the submission, showing the following:
1. For each type of cement:
a. The manufacturer's name;
b. The date and place of manufacture;
c. With test results that the cement complies with the requirements of this
Specification.
2. For PFA:
a. The manufacturer's name (it must be stated explicitly if high lime PFA, as
defined in CON1.M150 (1)(b), is submitted);
b. The date and place of manufacture;
c. With test results that the PFA complies with the requirements of this
Specification and the tests required in Clause 14.1 of BS 3892:Part 1:1997.
3. For GGBS:
a. The manufacturer's name;
b. The date and place of manufacture;
c. With test results that the GGBS complies with the requirements of this
Specification and the tests required for factory production control as
stipulated in CON1.M180.
_____________________________________________________________________________________________
2. Comply with the limiting values given in Table NB.1 of National annex NB of
BS EN 197-1:2011 for acceptance inspection of cement at delivery.
_____________________________________________________________________________________________
2. At the discretion of the Contractor and where approved by the CM, incorporate
PFA to PC as a partial cement replacement in structural concrete not shown as
PFA concrete on the Drawings. PFA content to be 25% by mass of the
cementitious content of the concrete;
3. Prior to the use of PFA concrete in sub-clause (2) above:
a. Carry out necessary tests and trials to provide evidence to the satisfaction of
the CM that the use of PFA concrete shall not adversely affect the
construction cycle, curing of the concrete and the application of finishes; and
b. Submit details for sub-clause (3)(a) before carrying out the tests and trials
for the Approval of the CM.
4. PFAC may be used where PFA concrete with PFA content of 25% by mass of
the cementitious content of concrete is specified or permitted;
5. Use of PC in the works specified in sub-clauses (1)(a) to (1)(c) above may be
accepted provided that:
a. Satisfactory evidence can be furnished to the CM showing that supply of
PFA or PFAC from all available sources cannot be obtained;
b. The highest grade of PC concrete for caissons and bored piles shall not
exceed 35/20D. For pile caps or footings and transfer structures submit a
detailed method statement of the proposed temperature control and
monitoring strategy as stipulated in CON1.W470 to the CM for approval at
least 7 days before concreting;
c. Where necessary, submit re-design of the foundation works resulting from
such a change to the CM for approval at least 21 days before
commencement of affected works. Submit re-design according to
PIL1.D030 and any other requirement as detailed elsewhere in this
Specification;
d. Be liable for any additional cost or time as a result of any such change. The
Surveyor shall, if he considers that there is a saving in cost arising from any
such change determine the sum which in his opinion shall be deducted from
the contract sum as result of such saving and certify in accordance with the
General Conditions of Contract.
_____________________________________________________________________________________________
AGGREGATES
CON1.M210.9 SUBMISSIONS
Submit to the CM, for Approval, a sample of each type of aggregate together with a
certificate showing that the aggregate producer has a quality assurance system
certified to the ISO 9001, and a certificate for each nominal maximum aggregate size
showing:
1. The name of the quarry / locality of the aggregate and documentary evidence
from the supplier for subsequent verification;
2. Where available, evidence that the aggregates from the same source have been
used in other HA Contracts in the past 12 months;
3. That the aggregate complies with the requirements of this Specification;
4. Results of tests carried out by HOKLAS laboratories and presented in HOKLAS
endorsed test reports of all the typical properties listed in CS3:2013 Clause 6.2.2
with the following validity period on the test data:
a. Issued within three months before the submission:
i. Grading.
b. Issued within six months before the submission:
i. All other properties.
_____________________________________________________________________________________________
4. Clear overburden as far as practicable from the working area prior to rock
excavation. Overburden is defined as all unwanted material including vegetation,
top soil and material of varying degrees of decomposition from the parent rock.
The latter category may appear as intrusive bands between volumes of massive
rock;
5. Remove rock from igneous intrusions as far as practicable from the working area;
6. Incorporate sufficient scalping and screening facilities in the aggregate
production plant to remove all overburden from the aggregates;
7. Keep separate in clearly defined areas the materials both before and after
processing where the aggregate production plant is rock from more than one
quarry or rock source.
WATER
CON1.M310.9 WATER
1. In accordance with PRE.B10.1210 to PRE.B10.1260 or PRE.C11.090 as
appropriate, and;
2. Use only clean fresh water from Water Supplies Department mains supply for
making concrete. Unless otherwise specified, do not use recycled water;
3. If the water from Water Supplies Department mains supply is not available,
submit to the CM for Approval:
a. The source of water;
_____________________________________________________________________________________________
b. A certificate showing that the water complies with the requirement of this
Specification.
4. Where specified in the Contract, use recycled water to make concrete for minor
structures.
ADMIXTURES
CON1.M410.9 ADMIXTURES GENERALLY
Ensure that the chloride ion content of admixtures for concrete containing embedded
metal or for concrete made with SRPC does not exceed 2% by mass of the admixture
or 0.03% by mass of the cementitious content, whichever is the less.
CON1.M420.A SUBMISSIONS
Submit to the CM for Approval:
1. Manufacturer's information on admixtures;
2. Certificate issued within 6 months before the submission from the manufacturer
that the admixtures comply with the requirements of this Specification;
3. Details of toxicity, proposed dosage, detrimental effects, if any, of under-dosage
or over-dosage;
4. Details of chloride content and method of adding to the concrete mix;
5. One sample of each type of admixtures.
CURING COMPOUNDS
CON1.M510.9 GENERAL
1. Of an Approved type and:
a. Having an efficiency index of at least 85% when tested to BS 7542:1992;
b. Either wax or aluminised resin based and containing a fugitive dye.
2. Do not use curing compound containing organic solvents for public roads and
bus terminuses which are to be handed over to the Highways Department of the
HKSAR on completion.
_____________________________________________________________________________________________
CON1.M520.9 SUBMISSIONS
Submit to the CM for Approval:
1. Manufacturer's information on curing compounds showing that the curing
compounds comply with the requirements of this Specification;
2. Test certificates prepared by an Approved testing laboratory, to show that the
curing compounds will provide the required efficiency index;
3. A sample of each type of curing compound.
CON1.M530.9 PROPERTIES
The compound when applied according to the manufacturer's recommendations must:
1. Be stable and impervious to evaporation of water from the concrete surface
within 60 minutes after application;
2. Not react chemically with the concrete to be cured and not crack, peel or
disintegrate within 1 week after application;
3. Degrade completely within 3 weeks after application.
ANCILLARY MATERIALS
CON1.M610.9 UNDERLAYS TO CONCRETE PAVINGS AND SLABS ON HARDCORE
Either:
1. Subsoil grade reinforced waterproof building paper to BS 1521:1972, grade B1F;
or
2. 0.125 mm nominal thick impermeable polythene sheet.
_____________________________________________________________________________________________
Performance
Properties Testing method
characteristics
3. The repair mortar shall not release substances hazardous to health, hygiene and
environment;
4. Submit the following for CM's information:
a. The original or a certified true copy of the product conformity certificate to
PCCS-RM stipulated in sub-clause (1). Certified true copy shall be certified
true by the issuer of the original copy or by the QCM;
b. A summary of the results on tests stipulated in the 'initial type test' and 'audit
testing' of the PCCS-RM. The summary shall be prepared by the accredited
laboratory who carried out the testing or by the certified manufacturer. If so
directed by CM, submit a full set of the audit test reports to CM for
information.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
NO FINES CONCRETE
CON1.M910.9 COMPOSITION
1. Cement: Portland cement;
2. Aggregate: nominal maximum size 20 mm of which not more than 15% by
mass is retained on a 20 mm BS test sieve, and not more than 10% by mass
passes a 10 mm BS test sieve.
_____________________________________________________________________________________________
2. For concrete of grade strength 20 MPa with recycled coarse aggregates, mix to
give a slump value of 75 mm and in the following proportions:
Portland Cement 100 kg
Recycled Coarse aggregate
20 mm 180 kg
10 mm 90 kg
Fine aggregate 180 kg
a. Fine aggregates to be within the limits of grading M in Table 3.2 of
CS3:2013;
b. Do not derive fine aggregates from concrete rubble;
c. Conduct laboratory trial mix for concrete with recycled coarse aggregates in
accordance with CON1.T050 prior to Approval.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
WORKMANSHIP
CON1.W030.9 AGGREGATES
1. Do not handle or store aggregates in a manner which will result in the mixing of
different types and sizes or in the segregation or contamination of the aggregates;
2. Store different types and sizes of aggregates in separate hoppers or in separate
stockpiles. Provide the stockpiles with well drained concrete floors and dividing
walls of sufficient height to keep the different aggregates separate.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON1.W170.9 REMIXING
Do not remix partially hardened concrete with or without additional cement,
aggregate or water.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON1.W430.9 CLEANLINESS
1. Clean all areas where concrete is to be placed and, except for concrete placed
under water, remove all standing water immediately before placing the concrete;
2. Protect slab formwork surfaces from concrete droppings and spillage during
concreting.
CON1.W450.9 PROCEDURE
1. Place concrete continuously between construction joints as close as practicable
to its final position;
2. Do not allow concrete to free fall in excess of 2.7 m unless otherwise Approved;
3. Deposit concrete in horizontal layers to a compacted depth not exceeding
450 mm where internal vibrators are used or 150 mm in all other cases unless
otherwise Approved. Do not force concrete into place by vibrator;
4. Do not place fresh concrete against insitu concrete which has been in position for
more than 30 minutes unless the insitu concrete has been kept damp with a layer
of wet hessian and protected from the weather to the satisfaction of the CM;
5. When insitu concrete has been in place for 4 hours or in the opinion of the CM
the concrete has stiffened to such an extent that it no longer responds to the
action of an internal vibrator, do not place further concrete against it for a further
20 hours unless otherwise Approved and form a construction joint in accordance
with CON1.W510 to CON1.W570 as appropriate;
6. Compact concrete in its final position within 2½ hours of the introduction of
cement to the mix. Concrete, which in the opinion of the CM is no longer
sufficiently workable, will be rejected;
7. Place concrete by skip or such other Approved methods as specified by the
requirements of the Specifications;
8. Do not place concrete in flowing water.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
COMPACTION
CON1.W610.9 GENERAL
Compact concrete to produce a dense homogeneous mass with vibrators unless
otherwise Approved and:
_____________________________________________________________________________________________
PUMPING CONCRETE
CON1.W710.9 CM'S APPROVAL
Do not use concrete pumps without prior Approval.
CON1.W730.9 PIPELINES
Position concrete pumps such that pipelines are as short and straight as practicable
and require as little repositioning as practicable and arrange bends in such a manner
that the concrete, formwork, reinforcement or built-in components are not disturbed.
_____________________________________________________________________________________________
CON1.W820.9 STANDARD
Place underwater concrete in accordance with the recommendations given in Code of
Practice for Structural Use of Concrete 2013.
CON1.W830.9 TREMIES
Securely support tremies used to place concrete in position and ensure the joints are
watertight. Use a temporary seal of an Approved type to keep the water and the
concrete separate at the start of concreting.
CON1.W840.9 PROCEDURE
After the concrete is flowing, raise the tremie in a manner agreed by the CM and:
1. Keep the lower end of the tremie immersed in the concrete to a depth of a least
1 m;
2. Prevent water, mud and other deleterious material from entering the tremie after
concreting has started.
_____________________________________________________________________________________________
GROUND SLABS
CON1.W1210.9 LAYING UNDERLAYS TO SLABS LAID ON HARDCORE
Lap and tape underlays at least 300 mm at joints.
_____________________________________________________________________________________________
KICKERS
CON1.W1310.9 WALLS AND COLUMNS
See CON2.W410 to CON2.W440.
CURING
CON1.W1410.9 METHODS OF CURING - GENERAL
1. Immediately after compaction, protect finished concrete against the harmful
effects of weather, running water and drying out;
2. Close any cracks developed on the concrete surface immediately while the
concrete is still plastic with suitable methods such as trowelling and brushing
before curing;
3. Ensure proper protection by using one of the following methods which are
minimum requirements and apply them for the minimum periods stated in
CON1.W1490:
a. Method A (as CON1.W1420): For all concrete slabs in domestic floors and
transfer structures except for areas which in the opinion of the CM are of
such irregular shape which renders the method impractical;
b. Method F (as CON1.W1470): For caps or footings where the least
dimension exceeds 500 mm;
c. Methods B, C, D or E (as CON1.W1430 to CON1.W1460): At the
Contractor's option for all other concrete elements including domestic floor
slabs and transfer structures with irregular shapes.
4. Where concrete is to be kept moist by spraying water for curing methods
stipulated in sub-clause (3), or during temporary removal of the protection to
facilitate construction stipulated in CON1.W1500, take due consideration and
necessary measures to avoid thermal shock to the concrete;
5. Agree with the CM within 4 weeks from the notified date of commencement of
the Works on the format and size of site works photographic records. Submit
one set of photographic records to the CM on each working day showing the
concrete surfaces being cured at all locations.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CRACK REPAIR
CON1.W1910.9 GENERAL
All visual cracks to hardened structural and non-structural concrete in domestic and
non-domestic buildings discovered during the construction period and/or
Maintenance Period, whether they are less than, equal to or greater than the
calculated maximum crack width as stated in Code of Practice for Structural Use of
Concrete 2013, shall be regarded as defects, imperfections or faults for which the
Contractor is liable under GCC Clause 10.3(2), unless such cracks are proved by the
Contractor to be due to a design fault of the Authority. If any cracks prove to be due
to a design fault of the Authority, then the expense incurred in any investigation and
remedial work carried out by the Contractor, as hereunder specified, will be valued
in accordance with GCC Clause 10.3(3).
CON1.W1920.9 INVESTIGATION
Investigate all visual cracks as directed by the CM and repair in accordance with the
classification methods described in the Table contained in CON1.W1990.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
6. Inject epoxy resin under pressure into the crack until it exudes at weep holes
located so as to ensure that when this occurs the crack may reasonably be
expected to have been completely filled and all air to have been displaced by
resin; and
7. Apply the method in sub-clause (6), and a coat of heavy grade bitumastic paint
over the surface of the crack or other method as approved by CM.
_____________________________________________________________________________________________
b. Core tests of the concrete shall be assessed based on the grade strength of
concrete as specified in the Drawings in accordance with Clause
CON1.T760.
3. Bear all associated costs and the extra time for complying with the requirements
of this clause.
TOLERANCES
CON1.W2010.9 GENERAL
1. For tolerances other than civil engineering works and slopeworks, refer to:
a. Code of Practice for Structural Use of Concrete 2013 published by the BD;
b. Appendix H "Schedule of Tolerances" to this Specification;
c. Where any ambiguity, discrepancy or conflict arises between sub-clauses 1(a)
and 1(b) above, the provisions given in Appendix H shall prevail.
2. For any abrupt projections in excess of 5 mm at inner surfaces of liftwell walls:
a. Use Approved non-shrink cementitious material to form a hard smooth
surface to splay the abrupt projections, to an angle of not less than 75º from
the horizontal plane, and extend for a distance of not less than 20 mm;
b. Submit remedial details for the CM's approval.
3. For civil engineering works and slopeworks, tolerances given in this
Worksection should be read in conjunction with additional tolerances given in
Worksection FOR. Tolerances on joints:
a. The best fit straight line of straight joints shall be within 25 mm of a
specified line. The line of straight joints shall be within 10 mm of the best
fit straight line;
b. The best fit curved line of curved joints shall be as agreed by the CM and
shall be within 25 mm of the specified line. The line of curved joints shall
be within 10 mm of the best fit curved line;
c. Joints shall be continuous across intersections of joints to within 5 mm of the
best fit straight lines or best fit curved lines of each joint.
_____________________________________________________________________________________________
TESTING
_____________________________________________________________________________________________
4. For the GGBS concrete in the production of precast facade, precast staircase,
precast refuse chute, precast partition wall and precast concrete panel, make two
additional test cubes on each day for compressive strength test at the time of
demoulding.
_____________________________________________________________________________________________
i. The range of the three measured slump values for each of the three days
must not exceed the average of the three measured slump values by
±20%;
ii. The average of the nine measured slump values for the three days must
fall within ±20 mm or ±25% of the designed slump value, whichever is
the greater.
b. Flow table test:
i. The range of the three measured flow values for each of the three days
must not exceed the designed flow value by ±70 mm;
ii. The average of the nine measured flow values for the three days must
fall within ±50 mm of the designed flow value.
3. The results of tests on compressive strength of concrete in precast concrete
components at demoulding of the test cubes must comply with the following
requirement:
a. The compressive strength of each individual test cube attains a compressive
strength of at least 15 MPa.
_____________________________________________________________________________________________
CON1.T090.9 NON-COMPLIANCE
If the result of any test for workability or strength of trial mix concrete, whether the
trial mix concrete is as stated in CON1.T040 or as stated in CON1.T045, does not
comply with the specified requirements, particulars of proposed changes to details of
mix design under CON1.M1110 shall be submitted to the CM for Approval. Further
trial mixes are to be made until the results of every test complies with the specified
requirements of trial mix concrete.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
SAMPLING
CON1.T320.9 COARSE AND FINE AGGREGATES
1. Except for recycled coarse aggregates, the DTC shall sample coarse and fine
aggregates at each stockpile and carry out sieve analyses only when instructed
by the CM;
2. For recycled coarse aggregates from a particular source, the DTC shall carry out
tests stipulated in CON1.T410 once at the start of the Contract and at weekly
intervals thereafter.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTS ON AGGREGATES
CON1.T410.9 STANDARD
1. The DTC shall test recycled coarse aggregates for the following properties:
Requirements Limits Testing Method
Minimum dry particle density 2000 kg/m³ CS3:2013 Section 17
_____________________________________________________________________________________________
_____________________________________________________________________________________________
c. Be remixed and divided into two specimens. Each specimen shall be tested
by DTC to determine the workability of the concrete either by the slump test
or by the flow table test all in accordance with CS1:2010.
2. Unless otherwise specified by the CM, adopt the testing method for workability
as below:
Normal Workability High Workability
(designed slump value (designed flow value
from 20 mm to 200 mm) from 340 mm to 600 mm)
Slump Test Flow Table Test
(For designed slump value exceeding
175mm and ≤ 200mm, see the Note to
Clause 2.1.1 of CS1)
3. Notwithstanding the sampling requirement specified in sub-clause (1)(b) above,
the first 0.3 m³ discharged concrete may be used in the Works provided that:
a. The discharged concrete is properly protected from contamination to CM's
satisfaction; and
b. The measured workability of the concrete is in compliance with this
Specification.
4. For pre-batched concrete or concrete with volume less than 1 m3 as defined in
Clause 1.2 of CS1:2010, the requirement to disregard the first 0.3 m3 and the last
0.3m3 of concrete before sampling from a mixer for making concrete cube is
waived.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON1.T720.9 STANDARD
1. Comply with CS1:2010 in respect of the method of preparing, inspecting and
testing concrete cores to determine compressive strength;
2. Witness the sampling of cores by the DTC who shall avoid the following
concrete as far as practicable:
a. The top 50 mm or 20% layer of concrete in a lift, whichever is the greater,
where the depth of lift is less than 1.5 m;
b. The top 300 mm layer of concrete in a lift, where the depth of lift is 1.5 m or
more.
3. Agree with the CM on the section of the core samples to be selected as test
specimens, including those cores sampled from concrete in thin lift where such
layer stated in sub-clause (2) cannot be avoided.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
ADDITIONAL TESTS
CON1.T810.9 GENERAL
1. During the progress of the Works, the CM has the power to order tests other than
cube tests and core tests. Comply with CS1:2010 or with the relevant British
Standard and Code of Practice where CS1:2010 does not apply;
2. The method of sampling, preparing and testing of hardened concrete to
determine cement content is to be in accordance with CS1:2010.
_____________________________________________________________________________________________
TESTS ON GGBS
CON1.T1110.A PURCHASER TESTS
1. Employ an Approved testing laboratory as stipulated in CON7.W010 for
carrying out the tests to verify the physical and chemical properties of GGBS in
accordance with BS EN 15167-1:2006 before production of the precast facade,
precast staircase, precast refuse chute, precast partition wall and precast concrete
panel units;
2. Submit the test reports to the CM in accordance with CON7.T010.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
APPENDICES
CON1.APPEND1.9 FORM A
APPENDIX CON1/I - FORM A
NAME OF CONTRACT
CONTRACT NO. ………….
10 mm 20 mm
Please tick
Remarks:
_____________________________________________________________________________________________
CON2 FORMWORK
DESIGN
CON2.D020.9 STANDARD
Comply with the requirements of BS 5975:1982 regarding design, construction and
dismantling of falsework and formwork.
_____________________________________________________________________________________________
2. For domestic blocks without rotational symmetry and where the use of large
panel formwork at critical areas of a domestic floor would lead to an
unacceptable prolonged construction cycle, the Contractor may propose the use
of small panel metal formwork, together with justification in the submission
stipulated in CON2.D240, for CM's approval.
CON2.D130.9 APPROVALS
1. Take responsibility for obtaining all necessary approvals of any proposed
falsework design and construction, through the Authority, from the Highways
Department, the Commissioner of Police and the Commissioner for Transport;
2. Do not commence any temporary works, including falsework spanning a public
highway, unless the falsework design and construction method has been
approved by the Highways Department and Commissioner of Police and
Commissioner for Transport.
SUBMISSIONS
CON2.D210.9 TIMING
Submit details of formwork and falsework to the CM for information before
commencement of construction.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON2.D350.9 JUNCTIONS
At any wall junction, where it is not practicable to position the edge of the formwork
assembly at the junction, position the edge at a clear distance of not more than
300 mm from the junction line.
_____________________________________________________________________________________________
4. Provide toe boards to a minimum height of 200 mm on the platform side where a
person or object could fall for more than two metres;
5. Read this Specification in conjunction with drawing No. SES/LP/S/EG001 in
Appendix B which details the access walkway.
CON2.D520.9 JUNCTIONS
As CON2.D350.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
MATERIALS
DEFINITIONS
CON2.M010.9 FORMWORK OR FORM
That section of the temporary works used to give the required shape and support to
poured concrete, consisting of sheathing material in direct contact with the concrete
and joists or stringers that directly support the sheathing.
CON2.M020.9 FALSEWORK
Any temporary structure used to support a permanent structure while it is not self-
supporting.
SHEATHING
CON2.M110.9 SUITABLE MATERIALS
Material against which the concrete will be cast must be suitable for providing the
specified concrete finish, formed for example, in metal, timber, plywood, film faced
plywood or plastic.
ANCILLARY MATERIALS
CON2.M210.9 RELEASE AGENT
An Approved type which will not:
1. Stain or colour the concrete;
2. Affect the adhesion between the concrete and any subsequent finishings.
_____________________________________________________________________________________________
1. Concrete:
a. Mix comprising cement, granite fines and granite aggregate passing a
10 mm sieve but retained on a 5 mm sieve;
b. Grade: 20/10.
2. Dimensions:
a. Outer casing and web: 25 mm thick;
b. With a 25 mm x 5 mm groove formed along both sides for key.
_____________________________________________________________________________________________
WORKMANSHIP
ERECTING FORMWORK
CON2.W210.9 CHECKING AND INSPECTION
Check the alignment of all kickers and wallforms prior to concreting and:
1. Allow the CM to inspect the completed formwork before any work, including
fixing reinforcement adjacent to formwork, makes access for inspection difficult;
2. Inform the CM 24 hours, or sooner if agreed with the CM, before carrying out
such work.
CON2.W220.9 KICKERS
Fix wall and column forms tightly against kickers by an Approved method.
_____________________________________________________________________________________________
CON2.W230.9 JOINTS
Construct joints between formwork panels, stop ends and adjoining concrete to
prevent loss of grout. Cut formwork in such a manner that reinforcement and built-
in components passing through the formwork are maintained in position and grout
loss is prevented.
_____________________________________________________________________________________________
CON2.W320.9 ARRISES
Erect formwork to provide smooth arrises free from damage and cracks.
_____________________________________________________________________________________________
STRIKING FORMWORK
CON2.W610.9 GENERAL
Strike formwork and falsework without disturbing, damaging or overloading the
finished concrete work or the structure and without affecting other formwork and
falsework.
_____________________________________________________________________________________________
3. In the event that a request for relaxation of the minimum periods before striking,
if any, is not accepted by the CM, the design of the formwork system is deemed
to have been prepared on the basis of the minimum periods detailed in
CON2.W630 or this sub-clause, provided the conditions referred to are complied
with;
4. As evidence that concrete placed insitu or in combined precast and insitu slabs
has attained the minimum strengths specified, from test results obtained from the
laboratory established on site in accordance with the requirements for testing
contained in the Preliminaries PRE.B9 of this Specification.
TRIAL PANELS
CON2.W710.9 SAMPLES
Provide samples of any exposed formed or worked finishes as detailed in the Project
Specific Specification, and obtain Approval.
STANDARD PANEL
CON2.W810.9 INSITU STANDARD PANEL
As soon as is practical after commencement of superstructure work, select a sample
area from the insitu works as being representative of the minimum standard of the
specified finish for inspection by the CM. Upon agreement in writing by the CM the
finish to the sample area will become the minimum standard for that specified finish
for all subsequent concrete.
_____________________________________________________________________________________________
MAINTENANCE OF FORMWORK
CON2.W1010.9 PREPARATION FOR RE-USE
Clean and repair formwork which has been previously used before it is re-erected.
_____________________________________________________________________________________________
TOLERANCES
CON2.W1210.9 GENERAL
Refer to Appendix H "Schedule of Tolerances" to this Specification.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING
_____________________________________________________________________________________________
a. Construct working platforms where necessary for carrying out water test
safely;
b. A continuous jet of water is to be sprayed from a nozzle at water pressure of
210 to 240 KPa at the nozzle inlet to the joint and along the longitudinal axis
of the formwork tie hole for a minimum of 5 minutes. The nozzle shall be
stationary while an observer inspects carefully on the indoor side of the
formwork tie hole with the assistance of adequate lighting where necessary.
The nozzle used for the tests shall be to the requirements of Architectural
Aluminium Manufacturers' Association (AAMA) 501.2-83, unless otherwise
Approved.
2. Before sealing any formwork tie holes, carry out watertightness test on Site for
the following:
a. Watertightness test for mortar only: the CM to select 10 nos. of formwork
tie holes sealed with mortar at one end of hole only and without
polyurethane, prepared in accordance with CON2.W1120. Watertightness
test to be applied on the mortar side for a minimum of 5 minutes;
b. Watertightness test for polyurethane foam only: the CM to select 10 nos. of
formwork tie holes sealed with polyurethane foam only and without mortar,
prepared in accordance with CON2.W1120 (2)(a) to (2)(f). Watertightness
test to be applied on the cork side for a minimum of 5 minutes.
3. Carry out watertightness test for completely sealed formwork tie holes on Site
for 10% of formwork tie holes at each floor of every block sealed complete in
accordance with CON2.W1120 (1) or CON2.W1120 (2) and selected by the CM.
Watertightness test to be applied on one side of a wall only (external side if
applicable) for a minimum of 5 minutes.
_____________________________________________________________________________________________
CON2.T180.9 BLOWHOLES
All blowholes shall be filled with one-part prebagged non-shrink cementitious
mortar Approved in CON2.M250.
_____________________________________________________________________________________________
CON3 REINFORCEMENT
MATERIALS
REINFORCEMENT GENERALLY
CON3.M010.9 STOCKIST'S OR SUPPLIER'S CERTIFICATION
Submission requirements:
1. For bar reinforcement, submit certificates from quality assured stockist
and/or supplier to demonstrate that the bar reinforcement supplied complies
with the requirements of CS2: 2012 Section 4 to the CM for Approval.
2. For fabric reinforcement, submit a certificate from the manufacturer to the
CM for Approval, stating:
a. That the fabric reinforcement supplied has been tested and complies
with the requirements of BS 4449:2005, BS 4483:2005 and this
Specification;
b. Evidence that the cold reduced steel wire in fabric reinforcement has
complied with the bond classification as specified in BS 4449:2005.
_____________________________________________________________________________________________
REINFORCEMENT
CON3.M110.9 BAR REINFORCEMENT
Quality requirements:
1. Hot rolled steel bars: to CS2:2012;
2. Cold reduced steel wire used for fabric reinforcement: to BS 4449:2005.
ANCILLARY MATERIALS
CON3.M210.9 COVER SPACERS
Quality requirements:
1. Unless specified elsewhere, type as shown on Standard Drawing
STD/FD/S/EG001 or STD/FD/S/EG001/A as appropriate, and as small as
practicable, consistent with their purposes, capable of supporting the weight of
reinforcement and construction loads without breaking, deforming or
overturning;
2. Be one of the following types:
a. Plastic: Approved type(s);
Specification Library 2022 Edition (Batch 1) CON /103
REINFORCEMENT CON3 > MATERIALS
_____________________________________________________________________________________________
_____________________________________________________________________________________________
3. The bond classification of coated bars determined in bond performance tests not
less than that of uncoated bars.
MECHANICAL COUPLER
CON3.M310.9 TYPE OF MECHANICAL COUPLER
Quality Requirements of mechanical coupler: Type 1 and Type 2 mechanical
couplers as stipulated in the Code of Practice for Structural Use of Concrete 2013
published by the Buildings Department.
CON3.M320.9 SUBMISSION
1. Commencement of the mechanical coupler works is subject to CM's written
permission;
2. Submit the following details to the CM for approval at least 30 days prior to the
commencement of the mechanical coupler works:
a. The name and model number of the mechanical coupler;
b. The name of the manufacturer and the address of manufacturing factory;
c. The information / documents of the quality assurance scheme as set out in
CON3.M330;
d. A description of the sampling procedures including the arrangement from
collecting samples to delivery of samples to laboratory for testing the quality
of the mechanical splice assemblies;
e. For Type 2 mechanical coupler, the quality supervision plan as set out in
CON3.W310.
3. Upon completion of the mechanical splice works, submit the following
documents to the CM for record: -
a. The inspection log book as detailed in CON3.W320;
b. A copy of mill certificates of the constituent materials used to produce the
couplers.
_____________________________________________________________________________________________
WORKMANSHIP
GENERAL
CON3.W010.9 STORAGE OF REINFORCEMENT
1. Store:
a. All reinforcement clear of a levelled, well-drained and maintained hard-
standing ground in a manner that will avoid damage, deformation and
contamination of the reinforcement;
b. Fabric reinforcement horizontally;
c Different types and sizes of reinforcement separately.
2. Agree with the CM within 4 weeks from the notified date of commencement of
the Works on the format and size of site works photographic records. Submit
one set of photographic records to the CM on each working day showing the
reinforcement at all storage locations.
_____________________________________________________________________________________________
FIXING REINFORCEMENT
CON3.W110.9 CUTTING AND BENDING REINFORCEMENT
Reinforcement bars are to be cut and bent in accordance with the dimensional
requirements of BS 8666:2005 unless otherwise shown on Drawing.
CON3.W150.9 WELDING
1. Do not weld bars without Approval;
2. Where Approved, weld in accordance with BS EN ISO 17660-1:2006, and the
relevant parts of Code of Practice for Structural Use of Concrete 2013.
_____________________________________________________________________________________________
1. Bar conditions;
2. Size of bars;
3. Provision of trimming bars;
4. Number of bars;
5. Spacing;
6. Cover.
TOLERANCES
CON3.W210.9 GENERAL
Refer to Appendix H "Schedule of Tolerances" to this Specification.
_____________________________________________________________________________________________
MECHANICAL COUPLER
CON3.W310.9 QUALIFIED SUPERVISION
1. Assign a Mechanical Coupler Quality Control Coordinator (MCQCC), with a
minimum qualification and experience of a Grade T1 TCP for Type 1
mechanical coupler and a Grade T3 TCP for Type 2 mechanical coupler under
the Registered Contractor’s stream in the CoPSS, to:
a. Supervise mechanical splice works and ensure that these are all carried out
in accordance with approved plans and comply with the requirements on
quality and workmanship;
b. Devise inspection check list of the mechanical couplers works;
c. Provide full time continuous supervision of the manufacturing process of the
connecting ends of the steel reinforcing bars and the installation of steel
reinforcing bars to the mechanical couplers.
2. For Type 1 mechanical coupler, submit the details as specified in the Project
Specific Specification to the CM for approval;
3. For Type 2 mechanical coupler, submit a quality supervision plan as specified in
the Project Specific Specification to the CM for approval;
4. The duties of MCQCC can be taken up by SQCC as stipulated in PRE.B6.130.
_____________________________________________________________________________________________
TESTING
DEFINITIONS
CON3.T010.9 BATCH OF BAR REINFORCEMENT
1. Subject to the maximum tonnage in sub-clause (2) below, a batch of bar
reinforcement is the quantity of bar reinforcement delivered to Site within a
week under one delivery order, of one nominal diameter, and one steel grade and
produced by the same manufacturer;
2. The maximum tonnage of a batch shall not exceed:
a. For bars of diameter 20 mm and above : 200 tonnes;
b. For bars of diameter less than 20 mm : 100 tonnes..
PURCHASERS TESTING
CON3.T110.9 RATE OF SAMPLING
1. For bar reinforcement, provide adequate test specimens from each batch
delivered to the Site in accordance with CS2:2012. The number of test
specimens taken from each batch and the rate of sampling shall be in accordance
with Table 10 of CS2:2012;
2. For fabric reinforcement in factory/stockholder's yard, provide samples from
each batch as follows:
_____________________________________________________________________________________________
CON3.T120.9 PROCEDURE
Testing arrangement:
1. Under the supervision of the CM,
a. Cut and take test specimens selected at random from bar reinforcement on
Site or samples selected at random from fabric reinforcement in
factory/stockholder's yard;
b. Ensure size of specimens/samples to be:
i. Bar reinforcement: each specimen to be minimum 1 m long;
ii. Fabric reinforcement: each sample to be 1.2 m long x 1.2 m wide
containing at least four wires in each direction.
c. Appropriately mark and deliver the test specimens or samples to the DTC
for testing.
TESTING BY DTC
CON3.T210.9 SCOPE AND NUMBER OF TESTS
Testing samples:
1. Tests will be carried out on each specimen of bar reinforcement in accordance
with CS2:2012;
_____________________________________________________________________________________________
COMPLIANCE
CON3.T310.9 COMPLIANCE CRITERIA - BAR REINFORCEMENT
A batch of bar reinforcement is deemed to comply with the specification if the test
results meet the requirements of CS2:2012. Any non-complying batch of bar
reinforcement is to be removed from Site.
RE-TESTS
CON3.T410.9 REQUIREMENTS FOR BAR REINFORCEMENT
Non-compliance:
_____________________________________________________________________________________________
1. If the result of any test for bar reinforcement does not comply with the specified
requirements for the property, provide additional test specimens from the same
batch for additional tests for the property in accordance with CS2:2012. The
number of additional specimens must be as stated in CS2:2012.
_____________________________________________________________________________________________
a. Adhesion and continuity tests: to BS 7295:Part 1:1990 with 180° bend test
replaced by 90°;
b. Thickness test for bars of 12 mm diameter or below: to Method No. 6Aa of
BS 3900:Part C5:1992;
c. Thickness test for bars of 16 mm diameter or above to: Method No. 6Aa or
No. 6Ab of BS 3900:Part C5:1992.
2. Carry out tests on specimens within a temperature range of between 5 degree
Celsius and 30 degree Celsius;
3. Take 5 pairs of readings along two opposite sides of each specimen for thickness
test (a total of ten recorded measurements per bar). A single recorded thickness
measurement is the average of three individual reading obtained in between the
ribs of three consecutive deformations;
4. Perform two bend tests for adhesion at a uniform rate within 15 seconds.
MECHANICAL COUPLER
CON3.T510.9 RATE OF SAMPLING
Provide test specimens, each with two reinforcing bars of the relevant diameter
either threaded or grouted in sleeve in accordance with the manufacturer’s
recommended assembly method, from each batch for testing by DTC as follows;
1. For Type 1 mechanical coupler:
Specification Library 2022 Edition (Batch 1) CON /114
REINFORCEMENT CON3 > TESTING
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
DESIGN PARAMETERS
CON4.D010.9 PRECAST CONCRETE
1. Design in accordance with this Worksection and Worksection CON1;
2. Where any ambiguity, discrepancy or conflict arises between this Worksection
and any clauses in any other Worksections of this Specification, ensure that the
provisions of this Worksection prevail.
DESIGN SUBMISSIONS
CON4.D210.9 GENERAL
Where appropriate, submit all necessary design, calculation and drawings pertinent
to CON4.D010 to CON4.D110, CON4.D310 to CON4.D530 for Approval.
_____________________________________________________________________________________________
JOINTS
CON4.D310.9 JOINTS
For application of back-up materials, bond breakers and sealants, see Worksection
WAT5.
CON4.D320.9 GASKETS
Gasket may be used in weatherproofing joint provided that:
1. The joint is horizontal; and
2. The gasket is always under compression.
WEATHERPROOF JOINTS
CON4.D410.9 JOINT DESIGN
Design weatherproof external joints to ensure airtightness and watertightness and in
accordance with BS 6093:1993.
_____________________________________________________________________________________________
MATERIALS
GENERAL
CON4.M010.9 SUBSTITUTION OF NON-STRUCTURAL CONCRETE
Submission requirements:
1. Submit for Approval any proposal to substitute non-structural insitu concrete or
non-structural partitions, excluding panel wall partitions, with precast concrete.
SUBMISSIONS
CON4.M110.9 GENERAL
Submit the following details for Approval:
1. Drawings, calculations and any other information indicating the location and/or
element of precast concrete and any changes resulting from the use of precast
concrete;
2. Calculations which show all loading imposed on the precast concrete due to
lifting, handling, stacking, shock or any other reason, complies with the relevant
British Standards, unless specified otherwise;
3. A method for identifying and recording the daily production of precast concrete
units and their final position after installation;
4. The joints required between the proposed precast concrete and insitu concrete;
5. Drawings and calculations of lifting frames for precast units where specified.
CONCRETE GRADE
CON4.M210.9 CONCRETE FOR LINTELS
Cast precast lintels in concrete Grade 35/20, unless otherwise specified.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON4.M320.9 SEALANTS
As WAT5.M180.
_____________________________________________________________________________________________
WORKMANSHIP
CASTING LINTELS
CON4.W110.9 GENERAL
Except where unusual or exceptional loading conditions apply or specified elsewhere,
construct lintels as shown below:
Lintels
Clear Span Depth of Lintel No. and diameter of mild
(metres) (mm) steel bars per 105 mm (or part) in width
0-1 150 one 12 mm
1-2 225 one 16 mm
2-3 300 one 20 mm
CASTING STAIRS
CON4.W210.9 CONSTRUCTION
Construct stairs in accordance with details given on the Drawings specified in the
Project Specific Specification.
CON4.W220.9 FORMWORK
As CON2.W920, unless otherwise specified.
CURING
CON4.W310.9 GENERAL
Cure concrete in accordance with CON1.W1410 to CON1.W1490, unless otherwise
Approved.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
DEFECTS
CON4.W810.9 MINOR CHIPPING
Subject to Approval, carry out repairs to minor chipping only by patching up after
installation.
_____________________________________________________________________________________________
TESTING
_____________________________________________________________________________________________
TESTING FIXINGS
CON4.T110.9 TENSILE TESTING
Testing method:
1. When directed, test fixings and anchors to BS 5080:Part 1:1993.
_____________________________________________________________________________________________
GENERAL
CON5.D010.9 RELEVANCE OF OTHER SPECIFICATION WORKSECTIONS
1. Design and construct precast facades in accordance with this Worksection and
with the relevant provisions of the following Worksections:
a. CON1, Insitu Concrete;
b. CON2, Formwork;
c. CON3, Reinforcement;
d. CON4, Precast Concrete;
e. COM11, Radio Frequency Identification and Web-Based Database System
for Building Components.
2. Where any ambiguity, discrepancy or conflict arises between this Worksection,
and any clauses in any other Worksections of this Specification, ensure that the
provisions of this Worksection prevail.
CON5.D020.9 STANDARD
Comply particularly with CON1.M010.
_____________________________________________________________________________________________
DESIGN PARAMETERS
CON5.D210.9 GENERAL
Design the facade units generally as a one-piece design.
CON5.D250.9 LOADINGS
Design facade units to sustain all possible loadings acting upon the units. In
particular, take the following loading conditions into account:
1. Dead loads and superimposed loads;
2. Wind loads in accordance with the Code of Practice on Wind Effects in Hong
Kong 2004 issued by the Buildings Department except that the total pressure
coefficient (Cp) is 1.4;
_____________________________________________________________________________________________
3. Eccentric loads which arise either as a result of the centre of gravity of the
facade units being offset from the support or from random inaccuracies
occurring during construction. Allow a minimum of 25 mm eccentricity in the
design for such random inaccuracies;
4. Tensile loads if the facade units are designed to be hung from the top or from the
sides;
5. Buckling loads if the facade units are subject to vertical compression;
6. Temperature stresses;
7. Temporary loads which arise during demoulding, storage, lifting, transporting
and erection of the facade units. In particular, design for the complex stresses
arising out of lifting from stacked position into lifting position.
_____________________________________________________________________________________________
2. Do not use adjustment devices in the vertical plane for horizontal location
devices or horizontal restraint and do not design such devices to take any
permanent shear (horizontal) loads;
3. Do not design any adjustment devices in the horizontal plane to take permanent
vertical loads.
MECHANICAL CONNECTIONS
CON5.D510.9 GENERAL
Design the mechanical connections referred to in sub-clause (2) of CON5.D130 to
withstand the stresses transmitted by the facade units to the building structure,
described in CON5.D250 sub-clauses (1) to (6), in one of the following two groups:
1. Tying back fixing;
2. Location fixing.
_____________________________________________________________________________________________
WEATHERPROOF JOINTS
CON5.D610.9 GENERAL
Design weatherproof joints between the facade units and the structure or between
two adjacent facade units to ensure air and water tightness and in accordance with
BS 6093:1993 and include joint seals in accordance with CON5.M110 and
CON5.M120.
_____________________________________________________________________________________________
SUBMISSIONS
CON5.D810.9 TENDER DESIGN PROPOSAL
Submit for Approval, full details of tender design proposals including drawings,
layouts, details, calculations and any other information required by the CM.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON5.D910.9 PROGRAMMES
Within one month of the notified date for the commencement of the Works, submit,
for agreement:
1. When instructed by the CM, the programme for the design and the testing of the
trial samples of the facade units;
2. The programme for manufacture of the facade units showing the rate of
production for each month and the dates for clearing the area of casting yard and
associated plant upon completion of the manufacture of the facade units;
3. The programme for the erection of facade units in accordance with CON5.W610.
_____________________________________________________________________________________________
MATERIALS
WEATHERPROOFING
CON5.M110.9 GENERAL
Quality requirements:
1. Weatherproofing materials to comply with BS 6093:1993 and subject to
Approval.
_____________________________________________________________________________________________
CON5.M120.9 SEALANTS
As shown or scheduled on the Drawings as WAT5.M180.
CONDUIT SYSTEM
CON5.M210.9 STANDARDS
1. For rigid plain polyvinyl chloride (PVC) conduits, conduit fittings and PVC
boxes, comply with the following British Standards:
Conduits and Fittings British Standards
PVC conduits: BS 6099:Section 2.2:1982(1988)
PVC conduits fittings: BS 4607:Part 1:1984(1993)&
BS 4607:Part 5:1982(1988)
PVC circular conduit boxes: BS 4607:Part 5:1982(1988)
PVC boxes for electrical BS 4662:1970(1989)
accessories:
2. Ensure that all PVC conduits, fittings and boxes are of the same make.
CON5.M220.9 COLOUR
PVC conduits, fittings and boxes: white in colour.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
WORKMANSHIP
GENERAL
CON5.W010.9 CASTING YARD
Within one month from the notified date for commencement of the Works, submit
for Approval on the following:
1. For on-Site casting:
a. The location of casting yard for manufacture of precast concrete components;
b. Details of plant and equipment including the location, boom radii and lifting
capacities of cranes, gantry capacities, curing facilities, number of moulds
and means of transporting the concrete components within the Site.
2. For off-Site casting:
a. The name, casting yard address with street maps and job reference of the
manufacturer and the following:
i. Details of organisation structure and top management;
ii. Self-certified true copy of the business licence of the manufacturer;
iii. Annual production capacity of the casting yard in terms of concrete
volume, numbers of products and the current workload;
iv. Details of the Quality Assurance Scheme required in CON5.W030;
v. Details of the audit plan and previous audit report, if any, carried out by
the Precast Concrete Construction Auditing Consultant required in
CON5.W050;
vi. Details of compliance with requirements of this specification on
batching plant and concrete mixes in accordance with Worksection
CON1;
vii. Test results for quality tests being carried out for the precast concrete
components to demonstrate the compliance with requirements of this
specification;
viii. Other details of construction quality as required in CON5.W090 (1).
b. Scaled and dimensioned layout plan of the casting yard with fenced
boundaries showing the office, the production lines for the products
including hardstanding and covered casting yards, disposition of steel
moulds, vibration plant, handling and lifting plants, steam or hot air curing
room / facilities, storage areas for finished products, steel reinforcement
storage and bending yards, storage sheds for incoming materials, samples
room, batching plant if any, testing laboratory, concrete cubes curing
facilities, means of transporting the concrete components to the Site;
c. The laboratory for carrying out the tests and issuing test certificates shall be
approved by the Housing Department, or accredited either by Hong Kong
Accreditation Scheme (HKAS) under the Hong Kong Laboratory
Accreditation Scheme (HOKLAS), or an equivalent organization which has
signed a mutual recognition agreement with HOKLAS. All expenses / costs
related to the tests carried out by the laboratory shall be borne by the
Contractor.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON5.W060.9 EQUIPMENT
Ensure casting yards, erected on-Site or off-Site are equipped with all the necessary
facilities, including efficient vibration plant, necessary curing facilities, storage,
handling and lifting facilities to secure compliance with all the provisions of this
Specification.
Specification Library 2022 Edition (Batch 1) CON /141
PRECAST FACADE UNITS (CONTRACTOR'S...... CON5 > WORKMANSHIP
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
2. Carry out a site trial to demonstrate the adequacy of the proposed method to the
satisfaction of the CM.
_____________________________________________________________________________________________
SURFACE FINISHES
CON5.W310.9 EXTERNAL FACE
Finish outside faces except edges and overhang soffits to give an even textured
surface suitable for fixing glazed ceramic tiles by adhesive, or cast the tiles into the
mould as required by the Contract.
_____________________________________________________________________________________________
CON5.W530.9 INSPECTION
Inspect each facade unit before lifting to ensure that neither damage nor hazard
occurs during lifting.
CON5.W540.9 LIFTING
During lifting, keep the facade units vertical and:
1. Ensure that all connections between the lifting frame and lifting points remain
vertical as far as possible;
2. Lift the facade units only at appropriate lifting points as shown on the Approved
shop drawings;
3. Locate lifting points that the line of the resistant force passes through the centre
of gravity of the facade unit.
_____________________________________________________________________________________________
ERECTING UNITS
CON5.W610.9 PROGRAMME
Provide a programme for the erection of the facade units. showing the rate of
erection for each month. Make due allowance for all restrictions on the age of
concrete in the facade units for handling, storage, transportation and erection.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
DEFECTS
CON5.W710.9 MINOR CHIPPING
Carry out repairs only to minor chipping by patching up after installation subject to
Approval.
JOINTS
CON5.W810.9 GENERAL
1. Prepare and construct joints strictly in accordance with the Drawings and in
accordance with the relevant manufacturer's recommendations so as to provide
continuous weathertightness of buildings and give a neat, uniform and smooth
appearance;
2. For application of back-up materials, bond breakers and sealants, see
Worksection WAT5.
CON5.W820.9 GASKETS
Gasket may be used in weatherproofing joint provided that:
1. The joint is horizontal; and
2. The gasket is always under compression.
CONDUIT SYSTEM
CON5.W910.9 APPLICATION
Supply and install conceal rigid plain PVC conduit system complete with steel draw
wires for precast facade as indicated on the Drawings.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING
_____________________________________________________________________________________________
5. Before the tagged cubes are sent from the manufacturer’s factory to HDMTL or
are collected by the DTC, scan the tag again using the Bluetooth RFID reader
and ensure that information such as tag UID, EPC number and timestamp have
been uploaded to the PC and incorporated into the DTC’s database system
(through 3G or above internet service);
6. Deliver the tagged cubes to HDMTL or arrange the tagged cubes to be collected
by the DTC with due care at a time such that a minimum of 4 days is allowed for
curing the cubes in DTC or HDMTL before testing on compressive strength at
28 days by DTC or HDMTL;
7. In case any damaged RFID tags are discovered, report to the CM or his
representatives resident at manufacturer's factory immediately without any delay;
8. Maintain an inventory record of all RFID tags including those damaged and
submit the inventory record to the CM or his representatives resident at
manufacturer's factory.
TRIAL UNITS
CON5.T110.9 GENERAL
Prior to mass production of the facade units:
1. Produce a full size trial sample for the Type T1 facade unit or as specified in the
Project Specific Specification complete with joints, windows, glazing and the
electrical conduit system installation etc. and all finishing at ground level for
Approval;
2. Maintain the Approved sample facade unit as the yardstick for the standard and
quality necessary for all facade units unless otherwise required under the terms
of CON5.T120;
3. When construction of a trial panel is required in CON2.W720, structurally
connect the trial sample to surrounding structural frames and with interfacing
services as detailed on the Drawings.
TESTS ON WORKABILITY
CON5.T131.9 STANDARD
As CON1.T510.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON5.T222.9 STANDARD
Comply with CS1:2010 in respect of the method of preparing, inspecting and testing
concrete cores to determine the compressive strength except the measurement of
saturated density.
_____________________________________________________________________________________________
3. Make due allowance in the programme for the aforesaid arrangement and bear
all time and cost for compliance with this clause.
CON5.T231.9 STANDARD
As CON1.T720.
_____________________________________________________________________________________________
1. The mould for this test shall be formed from steel to provide an annular
specimen with an inner diameter of 115 0.1 mm, an outer diameter of
175 0.1 mm and a depth of 50 0.1 mm;
2. The grout shall be mixed in accordance with the manufacturer's specification and
placed within the mould. Materials, moulds and specimens shall be kept at a
temperature of 27C 2C and a relative humidity of 55% 5%;
3. After 72 hours the outer mould ring shall be removed from the hardened grout
specimen and the specimen with the inner ring still in place shall be returned to
the conditioning environment.
4. The grout specimen shall be examined at 7, 14, 21 and 28 days and any cracking
shall be reported.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING FIXINGS
CON5.T510.9 TENSILE TESTING
Testing method:
1. When directed test fixings and anchors to BS 5080:Part 1:1993.
SURVEILLANCE INSPECTION
CON5.T710.9 JOINT INSPECTION AT MANUFACTURER'S FACTORY AND
BREAKING UP INSPECTION
For off-site casting:
1. Arrange transportation for the CM and/or his representatives and carry out joint
inspections at the manufacturer's factory;
2. Carry out up to 4 breaking-up inspections which may be instructed by the CM,
each comprising the following:
_____________________________________________________________________________________________
LIFTING ANCHOR
CON5.T810.9 DEFINITION OF BATCH
In this Specification, a batch is defined as any quantity of lifting anchor of the same
type and same working load capacity, delivered to the casting yard as one
consignment and covered by the same test certificate issued by the lifting anchor
manufacturer.
CON5.T850.9 SUBMISSION
Prior to the production of precast concrete components, provide test certificates
issued by:
1. The lifting anchor manufacturer/agent supplier; and
2. An Approved testing laboratory employed by the manufacturer of precast
concrete component on the ultimate load capacity of lifting anchors for each
batch under the Quality Assurance System as stipulated in CON5.W030.
Specification Library 2022 Edition (Batch 1) CON /159
PRECAST FACADE UNITS (CONTRACTOR'S...... CON5 > TESTING
_____________________________________________________________________________________________
_____________________________________________________________________________________________
JOINT FILLERS
CON6.M010.9 COMPRESSIBLE JOINT FILLER
Quality requirements:
1. Firm, compressible, single thickness, non-rotting proprietary type approved by
the CM.
SEALANTS
CON6.M110.9 GENERAL
Refer to Worksection WAT5 for all sealants, primers, back-up materials and bond
breakers.
WATER STOPS
CON6.M210.9 WATER STOPS
Quality requirements:
1. Of an Approved type made with prefabricated angle and intersection pieces with
details on the type of materials required, its intended location and purpose of use
as specified in the Project Specific Specification and on the Drawings.
ANCILLARY MATERIALS
CON6.M410.9 ADHESIVE FOR JOINT FILLER
Quality requirements:
1. Bituminous type recommended by the joint filler manufacturer.
_____________________________________________________________________________________________
WORKMANSHIP
GENERAL
CON6.W010.9 JOINT CONSTRUCTION
1. Construct joints strictly in accordance with the drawings and in accordance with
the relevant manufacturer's recommendations;
2. Keep edges true, free from cracks, spalling or other imperfections. Ensure that
edges or joints are clean and free from dust or grease immediately before fixing
fillers or applying sealants.
MOVEMENT JOINTS
CON6.W110.9 FIXING JOINT FILLER
Fix joint filler to the concrete with bituminous adhesive before casting the adjoining
bay. Form a sealing slot by casting in a removable former.
WATER STOPS
CON6.W210.9 INSTALLATION
Adequately install waterstops to ensure their correct position is maintained during
concrete placement.
CON6.W220.9 JOINTING
Make all joints using hot or cold vulcanizing.
CON6.W230.9 CONCRETING
Compact concrete fully around waterstops to ensure that no voids or porous areas
remain.
_____________________________________________________________________________________________
GENERAL
CON7.D010.9 SCOPE OF THE WORK
Precast concrete components specified in this Worksection include:
1. Precast facades (including precast roof parapet);
2. Semi-precast slabs (including semi-precast roof slabs and semi-precast corridor
slabs);
3. Precast balconies;
4. Precast staircases (including precast roof staircases);
5. Precast structural walls; and
6. Precast partition walls.
Refer to the Drawings for the extent of fixtures, finishing, fittings and building
services installations associated with precast concrete components.
Refer to the Drawings and relevant Specification clauses for the scope of builders,
structural and building services works to be prefabricated in off-site yards.
SUBMISSIONS
CON7.D110.9 LOADING OF INSITU STRUCTURAL MEMBERS
Submit calculations to demonstrate that the insitu structural members are not subject
to excessive stresses arising from the erection method of the precast concrete
components and to demonstrate the adequacy of any temporary supports which may
be required.
_____________________________________________________________________________________________
2. Do not use adjustment devices in the vertical plane for horizontal location
devices or horizontal restraint and do not design such devices to take any
permanent shear (horizontal) loads;
3. Do not design any adjustment devices in the horizontal plane to take permanent
vertical loads.
_____________________________________________________________________________________________
MATERIALS
GENERAL
CON7.M010.9 RELEVANCE OF OTHER SPECIFICATION WORKSECTIONS
1. Construct precast concrete components for Standards Domestic in accordance
with this Worksection and with the relevant provisions of the following
Worksections:
a. CON1, Insitu Concrete;
b. CON2, Formwork;
c. CON3, Reinforcement;
d. CON4, Precast Concrete;
e. COM11, Radio Frequency Identification and Web-Based Database System
for Building Components.
2. Construct aluminium window or uPVC window frames in accordance with
Worksections COM2 or COM3 respectively;
3. Where any ambiguity, discrepancy or conflict arises between this Worksection
and any clauses in any other Worksections of this Specification, ensure that the
provisions of this Worksection prevail.
CON7.M120.9 COLOUR
PVC conduits, fittings and boxes: white in colour.
_____________________________________________________________________________________________
2. For PVC conduits, where the ambient temperature at the country of manufacture
is likely to be below -5ºC, the temperature classification is -25.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
WORKMANSHIP
GENERAL
CON7.W010.9 CASTING YARD
Within one month from the notified date for commencement of the Works, submit
for Approval on the following:
1. For on-Site casting:
a. The location of casting yard for manufacture of precast concrete components;
b. Details of plant and equipment including the location, boom radii and lifting
capacities of cranes, gantry capacities, curing facilities, number of moulds
and means of transporting the concrete components within the Site;
2. For off-Site casting:
a. The name, casting yard address with street maps and job reference of the
manufacturer and the following:
i. Details of organisation structure and top management;
ii. Self-certified true copy of the business licence of the manufacturer;
iii. Annual production capacity of the casting yard in terms of concrete
volume, numbers of products and the current workload;
iv. Details of the Quality Assurance Scheme required in CON7.W030;
v. Details of the audit plan and previous audit report, if any, carried out by
the Precast Concrete Construction Audit Consultant required in
CON7.W060;
vi. Details of compliance with requirements of this specification on
batching plant and concrete mixes in accordance with Worksection
CON1;
vii. Test results for quality tests being carried out for the precast concrete
components to demonstrate the compliance with requirements of this
specification;
viii. Other details of construction quality as required in CON7.W120 (1).
b. Scaled and dimensioned layout plan of the casting yard with fenced
boundaries showing the office, the production lines for the products
including hardstanding and covered casting yards, disposition of steel
moulds, vibration plant, handling and lifting plants, steam or hot air curing
room / facilities, storage areas for finished products, steel reinforcement
storage and bending yards, storage sheds for incoming materials, samples
room, batching plant if any, testing laboratory, concrete cubes curing
facilities, means of transporting the concrete components to the Site;
c. The laboratory for carrying out the tests and issuing test certificates shall be
approved by the Housing Department, or accredited either by Hong Kong
Accreditation Scheme (HKAS) under the Hong Kong Laboratory
Accreditation Scheme (HOKLAS), or an equivalent organization which has
signed a mutual recognition agreement with HOKLAS. All expenses / costs
related to the tests carried out by the laboratory shall be borne by the
Contractor.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON7.W080.9 PROGRAMME
Provide a programme for manufacture of the precast concrete components showing
the rate of production for each month. For on site precasting, the dates for clearing
the area of casting yard and associated plant upon completion of the manufacture of
the precast concrete components must also be shown.
CON7.W090.9 EQUIPMENT
Ensure casting yards, erected on-Site or off-Site are equipped with all the necessary
facilities, including efficient vibration plant, necessary curing facilities, storage,
handling and lifting facilities to secure compliance with all the provisions of this
Specification.
_____________________________________________________________________________________________
i. One sample with the reinforcement fixed in steel mould for the
inspection of workmanship including reinforcement fixing and provision
of bar spacers;
ii. One sample with concrete cast in steel mould for the inspection of
conditions of the steel mould, checking of the finished sample.
b. Carry out trial run to demonstrate the manufacturing process including
installation of windows, lifting operation, curing, storage, fixing of mosaic
tiles, quality tests at factory laboratory, applied finishes and quality controls
in accordance with the required drawings and specification;
c. Carry out verification check for engraved logo, casting date, identity number,
Schmidt hammer test certificate and covermeter tests record, dimensions,
size, spacing, position of starter bars and finishes.
4. The pilot production run may not be required, if the following documents are
submitted and are acceptable to the CM:
a. Track records on similar types of precast concrete components supplied by
the proposed manufacturer to other HA construction projects, within five
years prior to the notified date for commencement of the Works; or
b. In the absence of the track records, detailed records of the pilot production
run for similar types of precast concrete components carried out in other HA
construction projects, within five years prior to the notified date for
commencement of the Works.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON7.W520.9 INSPECTION
Inspect each precast concrete components before lifting to ensure that neither
damage nor hazard occurs during lifting.
CON7.W530.9 LIFTING
Lift the precast concrete components only at appropriate lifting points as shown on
the Drawings.
_____________________________________________________________________________________________
ERECTING UNITS
CON7.W610.9 PROGRAMME
Provide a programme for the erection of the precast concrete components showing
the rate of erection for each month. Make due allowance for all restrictions on the
age of concrete in the precast concrete components for handling, storage,
transportation and erection.
_____________________________________________________________________________________________
4. Submit detailed method statement including the design, drawing and installation
procedures with endorsement of the Contractor’s RSE demonstrating to the
satisfaction of the CM that the precast concrete component will not subject to
excessive stresses arising from their proposed erection method without the steel
lifting frame, exemption from using the steel lifting frame as stated in sub-clause
(1) above can be allowed only for the lifting of the following precast concrete
components.
a. Vertically lifting precast elements:
Precast façade, precast balcony, precast structural wall, precast partition wall,
precast refuse chute, lost form (semi-precast wall), precast roof parapet and
precast A/C hood with the maximum horizontal dimension less than or equal
to 1.8m;
b. Horizontally lifting precast elements:
Full precast slab, semi-precast slab, precast staircase and precast tie beam
with the maximum horizontal dimension less than or equal to 6m.
5. In connection with sub-clause (4) above, address the safety use of the proposed
lifting anchor system, including but not limited to the proprietary anchor bolt
with clutch. The proposed lifting anchor system shall be flexible enough to
allow for both vertical and slant lifting sling.
TRIAL UNIT
CON7.W710.9 GENERAL
Prior to mass production of the precast concrete component units:
1. Produce a full size trial sample for the precast façade / precast balcony unit and
semi-precast slabs (if any) complete with joints, windows and glazing and the
electrical conduit system installation and all finishing;
2. Maintain the Approved sample units as the yardstick for the standard and quality
necessary for all precast concrete components;
3. When construction of a trial panel is required in CON2.W720, structurally
connect the trial sample to surrounding structural frames and with interfacing
services as detailed on the Drawings.
_____________________________________________________________________________________________
CON7.W820.9 MOULDS
Construct moulds from steel or other materials to produce a standard in accordance
with the 'Surface finishes' specified in CON7.W850 to CON7.W900. Replace any
mould which fails to comply with the standard.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING
_____________________________________________________________________________________________
5. Before the tagged cubes are sent from the manufacturer’s factory to HDMTL or
are collected by the DTC, scan the tag again using the Bluetooth RFID reader
and ensure that information such as tag UID, EPC number and timestamp have
been uploaded to the PC and incorporated into the DTC’s database system
(through 3G or above internet service);
6. Deliver the tagged cubes to HDMTL or arrange the tagged cubes to be collected
by the DTC with due care at a time such that a minimum of 4 days is allowed for
curing the cubes in DTC or HDMTL before testing on compressive strength at
28 days by DTC or HDMTL;
7. In case any damaged RFID tags are discovered, report to the CM or his
representatives resident at manufacturer's factory immediately without any delay;
8. Maintain an inventory record of all RFID tags including those damaged and
submit the inventory record to the CM or his representatives resident at
manufacturer's factory for endorsement.
TESTS ON WORKABILITY
CON7.T050.9 STANDARD
As CON1.T510.
_____________________________________________________________________________________________
CON7.T122.9 STANDARD
Comply with CS1:2010 in respect of the method of preparing, inspecting and testing
concrete cores to determine the compressive strength except the measurement of
saturated density.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON7.T129.9 STANDARD
As CON1.T720.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
5. Repeat sub-clause (4) above until all testing precast facade / precast balcony
units and joints have complied with specified criteria of watertightness;
6. Bear all associated costs for the re-tests and additional tests as specified in the
above sub-clauses. No extension of time will be allowed.
SURVEILLANCE INSPECTION
CON7.T510.9 JOINT INSPECTION AT MANUFACTURER'S FACTORY AND
BREAKING UP INSPECTION
For off-site casting:
1. Arrange transportation for the CM and/or his representatives and carry out joint
inspections at the manufacturer's factory;
2. Carry out up to 4 breaking-up inspections which may be instructed by the CM,
each comprising the following:
a. Provide samples of precast concrete component randomly selected by the
CM or his representatives, break up the component for inspection and
remove the broken component after inspection;
b. Carry out the following inspection in the presence of the CM or his
representatives:
i. Reinforcement details including total number of bars and bar size in
accordance with standard design drawings;
ii. Bar pattern of the reinforcement used against the Mill Certificate and the
requirements of purchaser test in CS2:2012;
iii. The installation, markings and brand name of concealed electrical
conduits, fittings and conduit accessories etc. when pre-installed
electrical conduit system is installed.
3. In the event of samples of a type of components failing to meet any one of the
requirements in the breaking-up inspection above, take further precast concrete
components of that particular type according to the following formula until all
precast concrete components satisfy the requirements as above:
Nos. of further samples = (n² - 2n +3)
where n is equal to the total number of unsuccessful components;
4. Bear the costs of all further breaking-up inspections that may be required under
sub-clause (3) above and no extension of time will be allowed.
_____________________________________________________________________________________________
LIFTING ANCHOR
CON7.T610.9 DEFINITION OF BATCH
In this Specification, a batch is defined as any quantity of lifting anchor of the same
type and same working load capacity, delivered to the casting yard as one
consignment and covered by the same test certificate issued by the lifting anchor
manufacturer.
CON7.T650.9 SUBMISSION
Prior to the production of precast concrete components, provide test certificates
issued by:
1. The lifting anchor manufacturer/agent supplier; and
2. An Approved testing laboratory employed by the manufacturer of precast
concrete component on the ultimate load capacity of lifting anchors for each
batch under the Quality Assurance System as stipulated in CON7.W040.
_____________________________________________________________________________________________
GENERAL
CON8.D010.9 DEFINITION OF VOLUMETRIC PRECAST CONCRETE
CONSTRUCTION
Construction of three-dimensional precast concrete building components or units,
with fixtures, fittings and finishes, but excluding the following precast concrete
components:
1. Precast facades (including precast roof parapet) (refer to CON7);
2. Semi-precast slabs (including semi-precast roof slabs and semi-precast corridor
slabs) (refer to CON7);
3. Precast balconies (refer to CON7);
4. Precast staircases (including precast roof staircases) (refer to CON7);
5. Precast structural walls (refer to CON7);
6. Precast partition walls (refer to CON7);
7. Precast refuse chutes (refer to CON4).
_____________________________________________________________________________________________
SCOPE OF WORK
CON8.D110.9 GENERAL (ENGINEER'S DESIGN)
1. Refer to the Drawings for the extent of volumetric precast concrete components
including the identification of parts of the component that will function as
facades;
2. Refer to the Drawings for the extent of fixtures, finishing, fittings and building
services installations associated with volumetric precast concrete components;
3. Refer to the Drawings and relevant Specification clauses for the scope of
builders, structural and building services works to be prefabricated in off-site
yards.
_____________________________________________________________________________________________
CON8.D230.9 DEFORMATIONS
Design the volumetric precast concrete components to be located in the structure
without deforming excessively before all of the joints and permanent structural
connections are made. Include consideration of any temporary stiffening, support
jigs or frames in the design.
CON8.D260.9 LOADING
1. Design the volumetric precast concrete components to be either load bearing or
non load bearing to sustain all possible loading acting upon them;
2. If load bearing, then design the component to carry the loads placed on it in both
the temporary and permanent situations taking into consideration of any creep on
vertical shortening of walls which may be more highly stressed than outer
adjacent precast or in-situ vertical load bearing elements;
_____________________________________________________________________________________________
JOINTS
CON8.D410.9 JOINTS
Apply back-up materials, bond breakers and sealants in accordance with
Worksection WAT5.
CON8.D420.9 GASKETS
Gaskets may be used in weatherproofing joints provided that:
1. The joint is horizontal; and
2. The gasket is always under compression.
_____________________________________________________________________________________________
DESIGN TOLERANCES
CON8.D710.9 OVERALL TOLERANCES (CONTRACTOR'S DESIGN)
1. Design the volumetric precast concrete components and the associated
joints/connections to the in-situ structure, other volumetric precast concrete
components, precast concrete components, architectural and building services
installations, including all cast in elements, to conform with the relevant
tolerances given in Appendix H and the Code of Practice for Precast Concrete
Construction 2016;
2. Where any ambiguity, discrepancy or conflict arises between the tolerances
given in Appendix H and the CoP for Precast Concrete Construction, the
provisions given in Appendix H shall prevail.
_____________________________________________________________________________________________
SUBMISSIONS
CON8.D910.9 TENDER DESIGN PROPOSAL
Submit for Approval, full details of tender design proposals including drawings,
specifications, layouts, details, calculations and any other information required.
_____________________________________________________________________________________________
2. Agree with the CM a programme for all ICU submissions for building works
prior to the notified date for commencement of Works;
3. Within one month after the notified date for commencement of the Works,
submit to the CM for approval, a programme for the design, planning and
coordination with NSCs, ICU approval, manufacturing, erection and testing of a
study mock up of the volumetric precast concrete components;
4. No extension of time will be allowed for any delay related to ICU's approval.
_____________________________________________________________________________________________
STUDY MOCK-UP
CON8.D1110.9 GENERAL
1. Set up a study mock-up in order to demonstrate, prior to mass production, that
the use of the proposed volumetric precast concrete components is feasible and
that the volumetric precast concrete components are constructable, structurally
safe, architecturally and functionally satisfactory when gauging against the
following aspects:
a. Buildability - speed, safety, structural & building services connections &
interfaces, safe system of working;
b. Tolerances, accuracy;
c. Quality;
d. Manufacturing process;
e. Joint integrity;
f. Testing on watertightness, strength and, structural integrity.
Specification Library 2022 Edition (Batch 1) CON /200
VOLUMETRIC PRECAST CONCRETE...... CON8 > DESIGN
_____________________________________________________________________________________________
_____________________________________________________________________________________________
8. Submit a method statement, together with all necessary shop drawings, for the
study mock-up for review and comment by the CM prior to its execution. The
method statement shall contain details on the manufacturing and transportation
of the volumetric precast concrete components as well as their construction
methodology, construction cycle, labour force required, major machineries and
plants to be employed, and detailed work program;
9. Construct the study mock-up in strict accordance with the commented shop
drawings and all methods of the study mock-up joint assembly are to faithfully
represent actual job conditions. Do not use special measures or techniques that
are not representative of those to be used on the building;
10. After the completion of the erection of the study mock-up, submit a report
detailing the following:
a. Assessment of the performance of the study mock-up and identification of
any deficiencies or defects, conflicts or interface with building services;
b. Proposed improvement measures, covering the design, manufacture,
transportation and erection aspects of the study mock-up;
c. Dimensional checking results;
d. Test results;
e. RSE's appraisal of the jointing system;
f. Digital photographs and video records of the erection procedures, in
particular the fixing of the jointing system, and any in-situ testing.
11. Bear all costs for any required laboratory and field tests, including any additional
fees, penalties or retest costs, and no extension of time will be allowed for any
delay related to ICU's approval.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
2. Take 3 nos. 100 mm diameter cores from selected grouted joints or permanent
structural connections, as demonstrated on the study mock-up, to validate the
effectiveness of the proposed grouting procedure for the joints or permanent
structural connections;
3. In the event that any of the cores taken show any signs of irregularity or voids,
such core and grouting procedure are deemed to be unacceptable. Review and
revise the grouting procedures accordingly;
4. Replace and re-grout all such joints or permanent structural connections on the
study mock-up, at which the cores show signs of irregularity or voids, and repeat
the core test as described in sub-clause (2) above to the satisfaction of the CM;
5. Bear all costs of any further cores and no extension of time will be allowed.
_____________________________________________________________________________________________
MATERIALS
GENERAL
CON8.M010.9 RELEVANCE OF OTHER SPECIFICATION WORKSECTIONS
1. Construct volumetric precast concrete components in accordance with this
Worksection and the relevant provisions of the following Worksections:
a. CON1, In-situ Concrete;
b. CON2, Formwork;
c. CON3, Reinforcement;
d. CON4, Precast Concrete;
e. CON6, Movement Joints;
f. CON7, Precast Concrete Components;
g. COM11, Radio Frequency Identification and Web-based Database System
for Building Components.
2. Construct architectural, plumbing & drainage and structural works in accordance
with the Worksections listed in CON8.D030;
3. Construct building services installations in accordance with the Worksections
listed in CON8.D030;
4. Where any ambiguity, discrepancy or conflict arises between this Worksection
and any clauses in any other Worksections of this specification, the provisions of
this Worksection shall prevail.
SUBMISSIONS
CON8.M110.9 CONCRETE MIX
As CON1.
CONCRETE
CON8.M210.9 CONCRETE MIX
The concrete mix shall satisfy the requirements of CON1.M810 - CON1.M850,
CON1.M1010 - CON1.M1040, CON1.M1110 - CON1.M1200, the functional and
durability requirements of the volumetric precast concrete components, and comply
with the relevant provisions of CON1.M730.
_____________________________________________________________________________________________
CON8.M230.9 DURABILITY
Use the appropriate concrete mix for volumetric precast concrete components which
is compatible with the defined exposure conditions of the internal and external faces
of the components.
JOINTS
CON8.M310.9 WEATHERPROOF JOINTS
As CON4.M310 to CON4.M340.
CONDUIT SYSTEMS
CON8.M510.9 GENERAL
Conduit systems incorporated into volumetric precast concrete components shall
comply in general with the requirements of clauses CON7.M110 to CON7.M430
inclusive.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
b. Frequency:
Verification Items Sampling Representative
Frequency Consignment
Reinforcement details 1 no. per type of All volumetric precast
including total no. of volumetric precast concrete components
bars and bar size concrete delivered to Site
components per
domestic block
Bar pattern of 1 no. per type of All volumetric precast
reinforcement volumetric precast concrete components
concrete delivered to Site
components per
domestic block
Cover to reinforcement 1 no. per type of All volumetric precast
volumetric precast concrete components
concrete delivered to Site
components per
domestic block
Concrete strength 1 no. per type of All volumetric precast
volumetric precast concrete components
concrete delivered to Site
components per
domestic block
Embedded conduit 1 no. per type of All volumetric precast
cover and bends volumetric precast concrete components
concrete delivered to Site
components per
domestic block
Sizes and routing of 1 no. per type of All volumetric precast
embedded conduit volumetric precast concrete components
concrete delivered to Site
components per
domestic block
Embedded conduits, 1 no. per type of All volumetric precast
accessories and volumetric precast concrete components
adaptable boxes concrete delivered to Site
components per
domestic block
Embedded conduits and 1 no. per type of All volumetric precast
/ or connections with volumetric precast concrete components
accessories concrete delivered to Site
components per
domestic block
Conduits and 1 no. per type of All volumetric precast
accessories volumetric precast concrete components
concrete delivered to Site
components per
domestic block
2. Non-compliance:
a. In the event of samples failing to meet any of the requirements given above:
i. Remove the broken volumetric precast concrete components off site;
_____________________________________________________________________________________________
ii. Take further volumetric precast concrete components as sample for re-
test progressively according to the formula n² - 2n + 3 where n = total
number of unsuccessful volumetric precast concrete components and the
maximum value of n is limited to 3; until all samples satisfy the
requirements as above;
iii. In the event that n = 3 and not all samples satisfy the above requirements,
all volumetric precast concrete components of the same type cast on the
same date as per those samples that failed the breaking-up inspection
shall be condemned and removed off site.
b. Bear all associated costs of any further breaking-up inspections that are
instructed by the CM and no extension of time will be allowed.
_____________________________________________________________________________________________
WORKMANSHIP
GENERAL
CON8.W010.9 OFF SITE CASTING YARD
Unless otherwise specified in this Worksection, comply with the requirements of
CON7.W010 to CON7.W090 pertaining to off-site casting.
SUBMISSIONS
CON8.W110.9 MOULDS
1. Submit for CM's approval details of the mould for volumetric precast concrete
construction showing its support and design to fulfil the functional requirements.
Comply with the provisions given in CON7.W210;
2. Obtain CM's approval before casting any components.
_____________________________________________________________________________________________
4. Method to rectify starter bars which are out of position but within tolerances;
5. Details of the proposed means of support and storage of volumetric precast
concrete components in the casting yard;
6. A layout of the storage yard which allows any components to be removed
without disturbing other components on demand and minimises the need to
sequence stacking and removal;
7. Erection of volumetric precast concrete components at their final locations in the
structure;
8. The proposed Radio Frequency Identification tag and the associated fixing
method as stipulated in Worksection COM11.
CON8.W140.9 PROGRAMMES
Within one month after the notified date for commencement of the Works, submit,
for Approval, the following:
1. Programme for manufacturing volumetric precast concrete components showing
the rate of manufacture for each month and the dates for clearing the area of
casting yard and associated plant upon completion of the manufacture of the
components;
2. Programme for the erection of the volumetric precast concrete components
showing the rate of erection for each month. Make due allowance for all
restrictions on the age of concrete in the volumetric precast concrete components
for handling, storage, transportation and erection.
_____________________________________________________________________________________________
MOULD ASSEMBLY
CON8.W210.9 TOLERANCE
Ensure that the mould is capable of manufacturing a component that, after erection,
will be within the overall tolerances and manufacture tolerances for volumetric
precast concrete components.
CON8.W230.9 GAUGES
Provide details of gauges and fittings to check the correct set up of the mould before
casting.
CON8.W240.9 FITTINGS
Ensure that the means of securing fittings to the mould is robust, suitable for
repeated use, and will result in achieving the required tolerances without damage to
the component.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
CON8.W430.9 CLEANING
1. Ensure that all fittings that will be used to make connections in-situ are cleaned
and checked prior to delivery of the volumetric precast concrete components to
Site;
2. Ensure that all internal surfaces of the volumetric precast concrete components
are cleaned to the standard agreed with the CM before the components are
delivered to Site.
CON8.W440.9 PROTECTION
Protect volumetric precast concrete components to ensure that no damage is done
during and after storage, lifting, transportation or erection.
CON8.W450.9 LIFTING
1. Lift volumetric precast concrete components only when the concrete has
achieved the required lifting strength, measured on specimens kept with the
volumetric precast concrete components in accordance with the Approved
method statement required under CON8.D940 and CON8.W380;
2. Lift volumetric precast concrete components within the yard by means of a
lifting system designed in accordance with CON8.D810 to CON8.D830;
3. Ensure that lifting plant and equipment complies with the requirements of
CON7.W540.
_____________________________________________________________________________________________
CON8.W480.9 TRANSPORTATION
1. Provide a transportation system, complying with CON7.W510 to CON7.W560,
such that damage to the component is prevented preferably without reliance on
any protection cover;
2. Maintain lorries or wagons used for the transportation of the volumetric precast
concrete components in a good condition. Ensure wagons are equipped with
suspension systems to minimize shock loading;
3. Ensure all lifting of volumetric precast concrete components during
transportation, including loading and unloading from lorries or wagons, comply
with the lifting method as per CON8.W450.
_____________________________________________________________________________________________
CONDUIT SYSTEM
CON8.W710.9 APPLICATION
Supply and install concealed rigid plain PVC conduit system complete with steel
draw wires for volumetric precast concrete components as shown on Drawings.
_____________________________________________________________________________________________
PROTOTYPE MOCK-UP
CON8.W910.9 PROTOTYPE MOCK-UP
1. Erect a prototype mock-up on Site, in full accordance with the Approved as-built
drawings of the study mock-up;
2. If proposed by the Contractor and approved by the CM, the prototype mock-up
can be part of the permanent works;
3. Obtain Approval from the CM upon inspection of the completed prototype
mock-up to set the standard and quality of workmanship necessary for all
volumetric precast concrete components;
4. Do not alter, move, or destroy the Approved prototype mock-up unless permitted
by the CM.
_____________________________________________________________________________________________
TESTING
_____________________________________________________________________________________________
6. Deliver the tagged cubes to HDMTL or arrange the tagged cubes to be collected
by the DTC with due care at a time such that a minimum of 4 days is allowed for
curing the cubes in DTC or HDMTL before testing on compressive strength at
28 days by DTC or HDMTL;
7. In case any damaged RFID tags are discovered, report to the CM or his
representatives resident at manufacturer’s factory immediately without any delay;
8. Maintain an inventory record of all RFID tags including those damaged and
submit the inventory record to the CM or his representatives resident at
manufacturer’s factory for endorsement.
TESTS ON WORKABILITY
CON8.T045.9 STANDARD
As CON1.T510.
_____________________________________________________________________________________________
MIX TESTS
CON8.T110.9 GENERAL
Unless otherwise specified in this Worksection, comply with the requirements for
trial concrete mixes and associated tests of both concrete and grout as given in
Worksections CON1, CON4 and CON7.
_____________________________________________________________________________________________
CON8.T140.9 STANDARD
Comply with CS1:2010 in respect of the method of preparing, inspecting and testing
concrete cores to determine the compressive strength except the measurement of
saturated density.
_____________________________________________________________________________________________
2. For VPB, VPK, volumetric precast lift shaft and volumetric precast lift machine
room components of the same concreting day represented by the early cores that
the compressive strength of the early cores do not comply with CON8.T170:
a. if the concreting ages of the VPB, VPK, volumetric precast lift shaft and
volumetric precast lift machine room components are less than 28 days,
carry out further early core tests by DTC. If the result of the further early
core test does not comply with CON8.T170, the VPB, VPK, volumetric
precast lift shaft and volumetric precast lift machine room components are
not allowed to be lifted into place or installed on Site, and further early core
test may be carried out in accordance with this sub-clause;
b. if the concreting ages of the VPB, VPK, volumetric precast lift shaft and
volumetric precast lift machine room components are 28 days or over, carry
out further core test by DTC in accordance with CON1.T710 to CON1.T760.
If the result of this further core test does not comply with CON1.T760, the
VPB. VPK, volumetric precast lift shaft and volumetric precast lift machine
room components are not allowed to be lifted into place or installed on Site.
All relevant concrete of the VPB, VPK, volumetric precast lift shaft and
volumetric precast lift machine room components represented by this further
core test in the same concreting day is deemed not complying with this
Specification. Investigate the extent of non-compliance and re-execute the
works in accordance with CON1.T1210 to CON1.T1260.
3. Make due allowance in the programme for the aforesaid arrangement and bear
all time and cost for compliance with this clause.
TESTING FIXINGS
CON8.T210.9 TENSILE AND SHEAR TESTING
As CON4.T110 and CON4.T120.
_____________________________________________________________________________________________
2. Working from the exterior, wet the external face of the volumetric precast
concrete components selectively, starting from the lowest horizontal joint,
followed by the vertical joints and then the horizontal joint above;
3. Spray a continuous jet of water from a nozzle at a water pressure of 210 to
240 kPa at the nozzle inlet to the joint and perpendicular to the external face of
the volumetric precast concrete components. Move the nozzle slowly along the
joint, at a distance of 300 mm from it, for a period of 5 minutes in every 1.5
metre of joint length while an observer carefully inspects on the interior side of
the external face of the volumetric precast concrete components with the
assistance of adequate lighting where necessary;
4. Unless otherwise Approved, use a nozzle to the requirements of the
Architectural Aluminium Manufacturer's Association (AAMA) 501.2-83;
5. Repeat the process specified in sub-clause (3) above on all joints and joint
intersections using increments of exposed joint length not exceeding 1.5 metres
upward until all the joints are covered.
_____________________________________________________________________________________________
a. In the event that any test result on a weld does not comply with the
acceptance criteria, conduct further weld test in accordance with
STR1.T120 (5);
b. Cut out and repair all defective welds in accordance with STR1.T140 and re-
test the welds in accordance with STR1.T120;
c. Bear all costs of any further tests and no extension of time will be allowed.
LIFTING ANCHOR
CON8.T510.9 DEFINITION OF BATCH
In this Specification, a batch is defined as any quantity of lifting anchor of the same
type and same working load capacity, delivered to the casting yard as one
consignment and covered by the same test certificate issued by the lifting anchor
manufacturer.
CON8.T550.9 SUBMISSION
Prior to the production of precast concrete components, provide test certificates
issued by:
1. The lifting anchor manufacturer/agent supplier; and
2. An Approved testing laboratory employed by the manufacturer of precast
concrete component on the ultimate load capacity of lifting anchors for each
batch under the Quality Assurance System as stipulated in CON7.W040.
_____________________________________________________________________________________________
a. Seal all outlets and do not permit any debris to enter into the drainage
pipeworks;
b. Carefully flood the internal floor of the VPB component to levels agreed
with the CM or his representatives resident at manufacturer's factory,
generally no less than 50 mm, but in no case higher than the curb levels and
maintain for 24 hours;
c. Mark the top water level at clearly visible locations and regularly inspect for
leaks;
d. Carry out joint inspections with the CM or his representatives resident at
manufacturer's factory at the external side of the walls and at the underside
of the floor slab to check that there is no water leakage, water seepage or
visible damp patch within half an hour after the flooding has maintained for
24 hours;
e. If required by the CM, provide records in the form of photos or video clips
to prove that the inspected surfaces are free from water leakage, water
seepage or visible damp patch;
f. Subject to CM’s approval, in case the test results cannot be verified due to
wet weather, record such condition in the test report and the whole batch of
VPB components can be exempted from this test.
3. Non-compliance:
a. In the event that any VPB component fails to meet the requirement
stipulated in sub-clause (2)(d) above:
i. Carry out re-test to the non-complying VPB component, after repaired
according to the Approved remedial works, and until the criteria
stipulated in sub-clause (2)(d) above are complied with;
ii. Carry out further water flood tests to the batch of VPB components
represented by the non-complying VPB component according to the
following formula:
Nos. of further water flood tests = (n²-2n+3)
Where n is equal to the total number of the failed water flood tests
progressively until all the water flood tests complied with the criteria
specified;
iii. Bear all associated costs and expenses incurred for the re-tests and
further tests. No extension of time will be allowed.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
SUBMISSION
CON9.G110.9 GENERAL
1. For Type 1 Yard, submit the following within one month from the notified date
for commencement of the Works for CM’s information:
a. The name, address with street map of the OSRPY;
b. Details of the organisation structure of the OSRPY, including the
management and supervision teams;
c. Self-certified true copy of the valid registration document under the List as
stated in CON9.G020 (1);
d. Monthly production capacity of the OSRPY in terms of tonnage and the
current workload;
e. Where carrying out of the fabrication of reinforcement cage or threading for
steel reinforcing bar using reinforcement connector is involved, records
showing separate approval from the Government has been obtained for such
fabrication process to be carried out at this prefabrication yard; and
f. The storage and traceability system of steel reinforcing bar products within
the Site for identifying the steel reinforcing bar and the prefabricated steel
reinforcing bar products produced by this prefabrication yard and other steel
reinforcing bar for on-site cutting and bending or for fabrication of
reinforcement cage or threading for steel reinforcing bar using reinforcement
connector for on-site installation. Approval from the CM shall be obtained
for such storage and traceability system prior to the delivery of prefabricated
products to the Site.
2. For Type 2 Yard, submit the following within one month from the notified date
for commencement of the Works for CM’s approval:
a. The address with street map of the OSRPY and details of the quality
management system as stipulated in CON9.G120;
b. A scaled and dimensioned layout plan of the OSRPY with fenced
boundaries showing locations of entrances, exits, designated storage areas
for incoming steel reinforcing bar, and prefabricated steel reinforcing bar
products, and areas for prefabrication;
c. Details of the security and traceability requirements as stated in CON9.G310
and CON9.G320 respectively.
3. For. Type 3 Yard, submit the following within one month from the notified date
for commencement of the Works for CM’s approval:
_____________________________________________________________________________________________
a. The name, address with street maps, organisation structure, and job
reference of the OSRPY and details of the quality management system as
stipulated in CON9.G120;
b. A scaled and dimensioned layout plan of the OSRPY with fenced
boundaries showing locations of entrances, exits, designated storage areas
for incoming steel reinforcing bar and prefabricated steel reinforcing bar
products, and areas for prefabrication;
c. Details of the security and traceability requirement as stated in CON9.G310
and CON9.G320 respectively.
TYPE 1 YARD
CON9.G210.9 SURVEILLANCE AUDIT / INSPECTION
The CM or his representatives shall be allowed to enter the OSRPY to carry out
surveillance audit / inspection at any time without advance notice. They shall be
allowed to:
1. Check and make copy, if necessary, of all quality control records, test reports
and certificates associated with the prefabricated steel reinforcing bar products
of the Contract, which have been or will be delivered to the Site;
2. Inspect and take photo of, if necessary, all the steel reinforcing bars and
prefabrication steel reinforcing bar products of the Contract at the designated
storage area and the prefabrication lines.
CON9.G220.9 TRACEABILITY
When the prefabricated steel reinforcing bar products are delivered to Site, they shall
be affixed firmly with traceability tags which shall include, but not be limited to, the
information such as contract title, contract number, delivery note number / stockist
certificate number, test report number, bending schedule number, bar marks, shape,
bar size quantity and fabrication date.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
MATERIALS
REINFORCEMENT GENERALLY
CON9.M010.9 STOCKIST'S OR SUPPLIER'S CERTIFICATION
Submission requirements:
1. For bar reinforcement delivered to the OSRPY, submit certificates from quality
assured stockist and / or supplier to demonstrate that the bar reinforcement
supplied complies with the requirements of Section 4 of CS2: 2012;
2. For reinforcement delivered in the form of coil (coil reinforcement) to the
OSRPY, submit certificate from quality assured stockist and / or supplier to
demonstrate the coil reinforcement supplied complies with the requirements of
Section 4 of CS2: 2012 or alternatively compliance of the following
requirements:
a. The coil reinforcement has been manufactured and tested to comply with the
requirements of BS 4449:2005+A2:2009 Sections 7 and 8;
b. The coil reinforcement is produced by a manufacturer certified by a third
party certification body. The certification body shall be accredited by the
Hong Kong Accreditation Service or its ‘Multilateral Recognition
Agreements / Arrangements’(MLA) partner(s) to the requirements of ISO
9001 for its quality management system with a scope related to good
practices of reinforcing steel production to meet requirements of BS
4449:2005+A2:2009.
REINFORCEMENT
CON9.M110.9 BAR / COIL REINFORCEMENT
Quality requirement:
_____________________________________________________________________________________________
ANCILLARY MATERIALS
CON9.M210.9 COVER SPACERS
Cover spacers shall be in accordance with CON3.M210.
_____________________________________________________________________________________________
WORKMANSHIP
GENERAL
CON9.W010.9 STORAGE OF STEEL REINFORCING BAR DELIVERED TO OSRPY
BEFORE PREFABRICATION
Store:
1. All steel reinforcing bar in designated storage area(s);
2. All steel reinforcing bar on a levelled, well-drained and maintained hard-
standing ground in a manner that will avoid damage, deformation and
contamination of the steel reinforcing bar;
3. Different types and sizes of steel reinforcing bar separately.
FIXING REINFORCEMENT
CON9.W110.9 CUTTING AND BENDING STEEL REINFORCING BAR
1. Steel reinforcing bar shall be cut and bent in accordance with the dimensional
requirements of BS 8666:2005 unless otherwise shown on the Drawing;
2. For coil reinforcement, it shall be straightened before cutting and bending in
accordance with sub-clause (1) above. The straightening process shall be done
by Quality Assured (QA) Coil Processor with an automated machine made for
this purpose.
Specification Library 2022 Edition (Batch 1) CON /235
OFF-SITE STEEL REINFORCING BAR...... CON9 > WORKMANSHIP
_____________________________________________________________________________________________
CON9.W150.9 WELDING
Welding of reinforcement shall be in accordance with CON3.W150.
FIXING REINFORCEMENT
CON9.W190.9 QUALIFIED SUPERVISION
Assign an OSRPY Quality Control Coordinator (OSRPY-QCC), with a minimum
qualification and experience of a Grade T1 TCP under the Registered Contractor’s
stream in the CoPSS, to:
1. Supervise steel reinforcing bar prefabrication works and ensure that these are all
carried out in accordance with approved plans and comply with the requirements
on quality and workmanship;
2. Devise inspection check list of the off-site steel reinforcing bar prefabrication
works;
3. Provide full time continuous supervision of the off-site steel reinforcing bar
prefabrication works, including sampling of steel reinforcing bars.
_____________________________________________________________________________________________
TOLERANCES
CON9.W210.9 GENERAL
The tolerances shall comply with CON3.W210.
_____________________________________________________________________________________________
TESTING
GENERAL
CON9.T010.9 TESTING ARRANGEMENT
Unless otherwise stated, testing arrangement of steel reinforcing bar in the OSRPY
as defined in CON9.G020 shall be in accordance with this Worksection.
DEFINITIONS
CON9.T110.9 BATCH OF STEEL REINFORCING BAR
1. Subject to the maximum tonnage in sub-clause (2) below, a batch of steel
reinforcing bar is the quantity of steel reinforcing bar delivered to the OSRPY
within a week under one delivery order, of one nominal diameter, and one steel
grade and produced by the same manufacturer;
2. The maximum tonnage of a batch shall not exceed:
a. For steel reinforcing bars of diameter 20 mm and above : 200 tonnes;
b. For steel reinforcing bars of diameter less than 20 mm : 100 tonnes.
PURCHASERS TESTING
CON9.T210.9 RATE OF SAMPLING
1. For bar reinforcement and coil reinforcement complying CS2:2012, provide
adequate test specimens from each batch delivered to the OSRPY in accordance
with CS2:2012. The number of test specimens taken from each batch and the
rate of sampling shall be in accordance with Table 10 of CS2:2012;
2. For coil reinforcement complying BS 4449:2005+A2:2009, provide samples
from each batch as follows:
_____________________________________________________________________________________________
CON9.T220.9 PROCEDURE
Testing arrangement:
1. Under the supervision of the CM or his representatives,
a. Cut and take test specimens selected at random from steel reinforcing bar in
the OSRPY as defined in CON9.G020;
b. Each steel reinforcing bar specimen shall be minimum 1 m long;
_____________________________________________________________________________________________
c. Test specimens taken from coil reinforcement shall have been straightened
according to BS EN ISO 15630-1:2010 Clause 4 or CS2:2012. The means
of straightening the test specimen (manual, machine) shall be indicated in
the test request form;
d. Appropriately mark and keep the test specimens or samples on yard for
collection and testing by the DTC and / or HDMTL;
e. The test specimens or samples shall be stored in a lockable steel box before
collection.
TESTING BY DTC
CON9.T310.9 SCOPE AND NUMBER OF TESTS
Testing samples:
1. Tests shall be carried out on each specimen in accordance with
a. CS2:2012 for bar reinforcement; and
b. CS2:2012 or BS 4449:2005+A2:2009 for coil reinforcement.
2. Number of tests on each specimen shall be in accordance with
a. Table 10 of CS2:2012 for bar reinforcement; and
b. CON9.T210 (2) for coil reinforcement.
COMPLIANCE
CON9.T410.9 COMPLIANCE CRITERIA – STEEL REINFORCING BAR
1. Bar reinforcement
A batch of bar reinforcement is deemed to comply with the Specification if the
test results meet the requirements of CS2:2012. Any non-complying batch of
bar reinforcement shall not be used and shall be removed from the designated
area in the OSRPY;
2. Coil reinforcement
_____________________________________________________________________________________________
RE-TESTS
CON9.T510.9 REQUIREMENTS FOR STEEL REINFORCING BAR
Non-compliance:
1. Bar reinforcement
If the result of any test for bar reinforcement does not comply with the specified
requirements for the property, provide additional test specimens from the same
batch for additional tests for the property in accordance with CS2:2012. The
number of additional specimens must be as stated in CS2:2012;
2. Coil reinforcement
For each test specimen taken in accordance with CON9.T210 and failing to meet
the requirement for the mass per meter, chemical composition, tensile properties
and bend performance or bond property, two additional test specimens shall be
taken from the remainder of the same batch and be subjected to the test or tests
which the original specimen failed.
_____________________________________________________________________________________________
EAR EARTHWORK
_____________________________________________________________________________________________
MATERIALS ............................................................................................................................. 16
DEFINITIONS .................................................................................................................................. 16
EAR1.M005.9 INERT CONSTRUCTION AND DEMOLITION MATERIAL ...................... 16
EAR1.M010.9 EARTHWORKS MATERIAL ......................................................................... 16
EAR1.M020.9 OWNERSHIP OF EARTHWORKS MATERIAL ........................................... 16
EAR1.M030.9 SUITABLE MATERIAL .................................................................................. 16
EAR1.M040.9 PUBLIC FILL ................................................................................................... 16
EAR1.M045.9 GRADE 200 RECYCLED ROCK FILL........................................................... 16
EAR1.M050.9 UNSUITABLE MATERIAL ............................................................................ 17
EAR1.M055.9 MARINE MUD ................................................................................................. 17
EAR1.M060.9 ROCK ............................................................................................................... 17
EAR1.M070.9 TOPSOIL .......................................................................................................... 17
EAR1.M080.9 EMBANKMENT .............................................................................................. 17
EAR1.M090.9 TRENCH EXCAVATION ................................................................................ 18
EAR1.M100.9 BULK EXCAVATION ..................................................................................... 18
EAR1.M110.N SELF-COMPACTING BACKFILL MATERIAL (SCM) ................................ 18
FILL MATERIALS .......................................................................................................................... 18
EAR1.M210.9 GENERAL ........................................................................................................ 18
EAR1.M220.9 PARTICLE SIZE DISTRIBUTION AND TYPES OF FILL
MATERIAL ...................................................................................................... 18
EAR1.M230.9 FILTER MATERIAL........................................................................................ 19
EAR1.M240.9 HARDCORE ..................................................................................................... 20
EAR1.M250.9 HYDROSEEDING ........................................................................................... 20
EAR1.M260.9 SOFT LANDSCAPING .................................................................................... 20
WORKMANSHIP ..................................................................................................................... 21
DEFINITIONS AND SUBMISSIONS ............................................................................................ 21
EAR1.W010.9 AREAS OF FILL .............................................................................................. 21
EAR1.W020.9 EARTHWORKS FINAL SURFACE ............................................................... 21
EAR1.W030.9 FORMATION ................................................................................................... 21
EAR1.W040.9 INTERMEDIATE AREAS OF FILL................................................................ 21
EAR1.W050.9 SUBMISSION OF PARTICULARS ................................................................ 21
EAR1.W060.N SUBMISSION OF PARTICULARS OF SELF-COMPACTING
BACKFILL MATERIAL (SCM) ...................................................................... 22
USE OF BLASTING ........................................................................................................................ 23
EAR1.W110.9 USE OF BLASTING METHOD ...................................................................... 23
Specification Library 2022 Edition| (Batch 1) EAR /2
EARTHWORK EAR > TABLE OF CONTENTS
_____________________________________________________________________________________________
SURVEYS.......................................................................................................................................... 23
EAR1.W210.9 DATUM ............................................................................................................ 23
EAR1.W220.9 COMMENCEMENT SURVEY ....................................................................... 23
EAR1.W230.9 INTERIM AND FINAL SURVEYS ................................................................. 23
EAR1.W240.9 SURVEY INFORMATION .............................................................................. 24
TEMPORARY WORKS, SLOPES AND GROUND DRAINAGE ............................................. 24
EAR1.W310.9 TEMPORARY DRAINAGE SYSTEM ............................................................ 24
EAR1.W320.9 TEMPORARY SUPPORTS TO EARTHWORKS........................................... 24
EAR1.W330.9 GENERAL SAFETY PRECAUTIONS ............................................................ 25
EAR1.W340.9 SAFETY PRECAUTIONS FOR OPEN EXCAVATION
EARTHWORKS ............................................................................................... 25
GENERAL ........................................................................................................................................ 25
EAR1.W410.9 EXCAVATION AND EARTHWORKS .......................................................... 25
EAR1.W420.9 PROTECTION FROM WATER AND WEATHER......................................... 26
EAR1.W430.9 WORK NEAR SLOPES ................................................................................... 26
EAR1.W440.9 UNSUITABLE EARTHWORKS MATERIAL................................................ 26
EAR1.W450.9 ADDITIONAL EXCAVATION AND STABILIZATION .............................. 27
EAR1.W460.9 HANDLING AND STORAGE OF EARTHWORKS MATERIAL................. 27
EAR1.W470.9 EXISTING DRAINS AND SERVICES ........................................................... 27
EAR1.W480.9 EXCAVATION ADJACENT EXISTING STRUCTURES ............................. 27
EAR1.W490.9 TRIMMING ...................................................................................................... 28
EAR1.W500.9 EXCAVATION OF TRENCHES FOR UTILITIES ........................................ 28
OBSTRUCTIONS ............................................................................................................................ 28
EAR1.W610.9 BURIED OBSTRUCTIONS ............................................................................. 28
EAR1.W620.9 DISUSED DRAINS AND MANHOLES ......................................................... 28
EAR1.W630.9 OLD UNDERGROUND STRUCTURES ........................................................ 28
EAR1.W640.9 BOULDERS...................................................................................................... 28
EAR1.W650.9 PILED FOUNDATIONS .................................................................................. 28
CUTTINGS ....................................................................................................................................... 28
EAR1.W710.9 SURFACES OF CUTTINGS ............................................................................ 28
EAR1.W720.9 DEPTH OF REMOVAL ................................................................................... 29
EAR1.W730.9 MAKING GOOD .............................................................................................. 29
DISPOSAL OF EXCAVATED MATERIAL................................................................................. 29
EAR1.W810.9 UNSUITABLE AND SURPLUS MATERIAL ................................................ 29
EAR1.W820.9 SUITABLE MATERIAL .................................................................................. 29
EAR1.W830.9 DUMPING OF UNSUITABLE AND SURPLUS MATERIALS .................... 29
EAR1.W835.9 DISPOSAL OR REUSE OF MARINE MUD................................................... 29
EAR1.W840.9 ON SITE SORTING OF CONSTRUCTION AND DEMOLITION
MATERIALS .................................................................................................... 30
EAR1.W845.9 TRIP-TICKET SYSTEM .................................................................................. 30
RETAINING WALLS, SHALLOW FOUNDATIONS AND OTHER STRUCTURES ............ 30
EAR1.W910.9 SIZE OF EXCAVATIONS ............................................................................... 30
EAR1.W920.9 APPROVAL OF EXCAVATION BOTTOMS................................................. 30
EAR1.W930.9 FOUNDING OF SHALLOW FOUNDATIONS .............................................. 30
EAR1.W940.9 PROVING BEDROCK FOR FOOTINGS (RAFTS AND PADS) ................... 31
REMEDIAL WORKS ...................................................................................................................... 32
EAR1.W1010.9 EXCAVATION BOTTOMS DAMAGED AFTER APPROVAL .................... 32
EAR1.W1020.9 OVER EXCAVATION ..................................................................................... 32
EAR1.W1030.9 DAMAGED SURFACES ................................................................................. 32
FILLING GENERALLY ................................................................................................................. 32
EAR1.W1110.9 USE OF ROCK CRUSHING PLANT .............................................................. 32
EAR1.W1115.9 USE OF GRADE 200 RECYCLED ROCK FILL ............................................ 32
Specification Library 2022 Edition| (Batch 1) EAR /3
EARTHWORK EAR > TABLE OF CONTENTS
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING ................................................................................................................................... 49
FILL MATERIAL - GENERAL REQUIREMENTS ................................................................... 49
EAR1.T020.9 BATCH ............................................................................................................. 49
EAR1.T030.9 SAMPLES ......................................................................................................... 49
EAR1.T040.9 SAMPLE SIZE ................................................................................................. 49
SITE TESTS FOR SOIL AND GROUNDWATER ...................................................................... 49
EAR1.T110.9 GENERAL ........................................................................................................ 49
EAR1.T115.9 COMPACTION TEST FOR FILL SLOPES .................................................... 49
FILL MATERIAL - PARTICLE SIZE DISTRIBUTION, LIQUID LIMIT, PLASTICITY
INDEX, COEFFICIENT OF UNIFORMITY AND SULPHATE CONTENT ........................... 50
EAR1.T210.9 GENERAL ........................................................................................................ 50
EAR1.T220.9 TESTING CRITERIA ....................................................................................... 50
EAR1.T230.9 TEST METHODS ............................................................................................. 51
EAR1.T240.9 NON-COMPLIANCE WITH TESTS ............................................................... 51
FILL MATERIAL - OPTIMUM MOISTURE CONTENT AND MAXIMUM DRY
DENSITY .......................................................................................................................................... 51
EAR1.T310.9 GENERAL ........................................................................................................ 51
EAR1.T320.9 LOCATION ...................................................................................................... 52
EAR1.T330.9 ADDITIONAL SAMPLES ............................................................................... 52
Specification Library 2022 Edition| (Batch 1) EAR /5
EARTHWORK EAR > TABLE OF CONTENTS
_____________________________________________________________________________________________
WORKMANSHIP ..................................................................................................................... 66
GENERALLY ................................................................................................................................... 66
EAR2.W010.9 STATUTORY REQUIREMENTS ................................................................... 66
Specification Library 2022 Edition| (Batch 1) EAR /6
EARTHWORK EAR > TABLE OF CONTENTS
_____________________________________________________________________________________________
_____________________________________________________________________________________________
GENERAL
EAR1.D010.9 DESIGN RESPONSIBILITY
1. Submit for Approval, within 7 days of the notified date for commencement of
the Works, the name and particulars of the Registered Structural Engineer (RSE)
and Registered Geotechnical Engineer (RGE) who will be employed on the
Project in accordance with the Preliminaries Worksection. The RSE and RGE
must have relevant experience to design, supervise and control all temporary
works, excavation, dewatering and any specified design and built items.
Comply with PNAP APP-141 for the division of responsibilities between RSE
and RGE in connection with the excavation and lateral support works;
2. Prior to the notified date for commencement of the Works, the CM has provided
reference design for the Excavation and Lateral Support Works (ELSW) for
permanent works construction as specified in sub-clause (2) of EAR1.D030.
The Contractor shall review and decide whether to dispense with, adopt in full or
modify the reference design provided by the CM;
3. Should the Contractor choose to adopt in full the reference design provided by
the CM, the procedures for submitting the Excavation and Lateral Support Plan
(ELSP) to the CM as stipulated in sub-clause (3) of EAR1.D030 shall be
followed;
4. Should the Contractor choose to dispense with or modify the reference design
provided by the CM, the procedures for obtaining the CM's approval of the
Contractor's design or the modified design as stipulated in sub-clause (4) of
EAR1.D030 shall be followed;
5. If the reference design provided by the CM is adopted in full by the Contractor,
the Contractor shall assume full design responsibility for the said ELSW in sub-
clause (2);
6. If the Contractor decides to dispense with or modify the reference design
provided by the CM, the Contractor shall be solely responsible for the design of
ELSW or the modified design (including submission of ELSP).
_____________________________________________________________________________________________
_____________________________________________________________________________________________
3. Where the Contractor chooses to adopt in full the said reference design of the
ELSW referred to in sub-clause (3) of EAR1.D010, submit ELSP based on the
said reference design of the ELSW duly signed by the RSE and / or RGE as
appropriate appointed in accordance with the Preliminaries Worksection and
allow at least the number of days as specified in the Project Specific
Specification to obtain CM’s approval for such submission before
commencement of the ELSW. Notwithstanding the approval of the ELSP, the
commencement of the ELSW shall be subject to the CM's written permission
referred to in PRE.B4.050;
4. Where the Contractor chooses to dispense with or modify the said reference
design of the ELSW referred to in sub-clause (4) of EAR1.D010, the Contractor
shall submit ELSP to CM and allow at least the number of days as specified in
the Project Specific Specification to obtain CM’s approval for the new or
modified design before commencement of the ELSW. The structural
calculations and drawings submitted are prepared and signed by the RSE
referred to in sub-clause (1) of EAR1.D010. The geotechnical report /
supporting documentation for the ELSP shall be prepared and signed by the
RGE appointed in accordance with the Preliminaries Worksection in case of
having excavation depth deeper than 4.5 m and / or involving significant
geotechnical elements. Allow for a further number of days as specified in the
Project Specific Specification for granting of approval by the CM for each ELSP
re-submission. ELSP submission is required where the excavation is one of the
following types:
a. Deeper than 2.5 m and greater than 5 m in length;
b. Liable to affect any road, building, structure, slope steeper than 30 degrees
or water main 75 mm in diameter or greater, the affected area being defined
as within the 45 degree line up from the base of the excavation to the ground
surface;
c. Of substantial depth, the collapse of which would cause serious
consequences to public safety as per PNAP APP-57;
d. Any other ELSW requiring ELSP submission as specified by CM.
Notwithstanding the approval of the ELSP, the commencement of the ELSW
shall be subject to the CM's written permission referred to in PRE.B4.050.
5. The ELSP submission shall include information as specified in the Project
Specific Specification;
6. For ELSW with pile walls and bulk excavation, comply with the following:
a. Refer to the Project Specific Specification on restrictions on commencement
for pile walls driving work;
b. Comply with the requirements of the Approved ELSP;
c. At the completion of pile walls driving works, submit record plans showing
the actual penetration depth of the pile walls to CM for approval. Allow at
least of 22 days for granting of approval by CM on:
i. Certification of completion of the works using Form ICU 14;
ii. Commencement of bulk excavation works.
d. Allow sufficient time in the programme of Works for obtaining the said
Approvals. Do not commence driving of pile walls and bulk excavations
without written Approval for commencement from the CM.
7. For ELSW with bulk excavation only, comply with the following:
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
Soil Parameters
Soil material
c (kPa) (deg.) (kN/m3) E (MPa)
Notes to table:
a. c = effective cohesion of soil;
b. = effective friction angle of soil;
c. = bulk unit weight of soil;
d. E= Young’s modulus (for drained loading); and
e. Poisson’s ratio (for drained loading)
3. The above information is given in good faith for reference only and is not meant
to be exhaustive or to be representative of the whole or any part of the Site or in
any way limiting the obligations and liabilities of the Contractor under the
Contract. No guarantee can be given nor responsibility be taken by the
Employer or the CM for their accuracy, consistency or sufficiency, and no claim
whatsoever will be entertained on account of any errors, discrepancies and
insufficiency in relation to the information given.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
MATERIALS
DEFINITIONS
EAR1.M005.9 INERT CONSTRUCTION AND DEMOLITION MATERIAL
Rock, rubble, earth, soil, concrete, asphalt, brick, tile and masonry generated from
construction and demolition works.
_____________________________________________________________________________________________
2. RR 200 shall be collected from the recycling facilities managed by the Fill
Management Division of Civil Engineering and Development Department as
specified in the Project Specific Specification;
3. In the event that RR200 is used in the Works, comply with the following:
a. Comply with the relevant ordering and collection procedures of RR 200 as
specified by the CEDD;
b. Complete and submit the order form to the CM at least 10 days before the
collection of RR 200 from the recycling facilities. The ordering and
collection procedures together with the order form can be obtained from the
CEDD web-site;
c. Make due allowance in the works programme for the time associated with
ordering and collection of RR200 and bear all associated costs, and no
extension of time will be allowed.
EAR1.M060.9 ROCK
1. Naturally occurring hard material which in the opinion of the CM can only be
removed by:
a. Blasting;
b. Pneumatic tools other than clay spades;
c. Wedges and sledge hammers;
d. Drilling and the use of mechanical bursting;
e. Drilling and the use of expanding agents.
2. Any isolated, solid boulder or detached piece of rock exceeding 0.2 m³.
EAR1.M070.9 TOPSOIL
Soil capable of supporting vegetable growth.
EAR1.M080.9 EMBANKMENT
An area on the Site, other than a foreshore or sea-bed, where the ground level is to be
raised by filling in layers as part of the Works.
Specification Library 2022 Edition| (Batch 1) EAR /17
EXCAVATION AND FILLING EAR1 > MATERIALS
_____________________________________________________________________________________________
FILL MATERIALS
EAR1.M210.9 GENERAL
1. Use only suitable material as previously defined;
2. Unless otherwise specified, form areas of fill by general fill material;
3. Obtain fill material from excavation within the Site. If there is insufficient fill
material of the required types within the Site, provide imported fill material from
sources outside the Site subject to approval by the CM.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR1.M240.9 HARDCORE
To comprise either:
1. Rock fill, or;
2. Broken stone, hard brick, concrete or other comparable hard, inert material, free
from dust, rubbish or deleterious foreign matter and capable of passing through a
150 mm diameter ring in every direction.
EAR1.M250.9 HYDROSEEDING
Refer to Project Specific Specification.
_____________________________________________________________________________________________
WORKMANSHIP
EAR1.W030.9 FORMATION
That part of the earthworks final surface on which a pavement, structure or utility, is
constructed, or on which the blinding or bedding for a pavement, structure or utility
is placed.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
a. Before SCM reaching its initial set and providing sufficient load bearing
capacity in the first several hours after placement, the Contractor shall
submit a plan to fence off the backfilled area properly before any subsequent
application of the surfacing materials above.
USE OF BLASTING
EAR1.W110.9 USE OF BLASTING METHOD
Refer to Project Specific Specification.
SURVEYS
EAR1.W210.9 DATUM
Spot levels and contours shown on the Drawings are, unless otherwise specified,
reduced to Hong Kong Principal Datum for levels and the latest edition of Hong
Kong Geodetic Datum for coordinate locations.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
GENERAL
EAR1.W410.9 EXCAVATION AND EARTHWORKS
1. Carry out excavations and earthworks in dry conditions unless otherwise
permitted by the CM, except where the excavations and earthworks are required
to be carried out in or with water or other fluids;
2. Suppress dust generation during excavation and earthworks operations by
spraying the work area of any excavation or earth moving equipment operation
with water or a dust suppression chemical immediately before, during and
immediately after the operation so as to maintain the entire surface wet. Dispose
cement, pulverized fuel ash or any other dusty materials collected by fabric
filters or other air pollution control system or equipment in totally enclosed
containers;
3. Control height from which excavated materials are dropped to a practical
minimum;
4. Carry out the formation of cuttings and filling in such a manner that the surfaces
have at all times a sufficient minimum crossfall and, where practicable a
sufficient longitudinal gradient to enable them to shed water and prevent
ponding;
5. Adopt a method of working which minimises the area of exposed soil across the
Site;
6. Carry out excavation to the lines, levels, dimensions and slopes specified;
Specification Library 2022 Edition| (Batch 1) EAR /25
EXCAVATION AND FILLING EAR1 > WORKMANSHIP
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR1.W490.9 TRIMMING
Neatly trim the face of excavations. Do not trim the side faces of excavation for at
least 24 hours after placing any blinding concrete.
OBSTRUCTIONS
EAR1.W610.9 BURIED OBSTRUCTIONS
Notify the CM without delay of the location and nature of any unforeseen
obstruction encountered during excavation.
EAR1.W640.9 BOULDERS
Treat boulders that intersect the earthworks final surface or formation as excavation
proceeds by methods agreed by the CM. Do not leave boulders protruding unless
permitted by the CM.
CUTTINGS
EAR1.W710.9 SURFACES OF CUTTINGS
Remove the following from surfaces as required by the CM:
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
3. Sink drillholes for carrying out Standard Penetration tests (SPT) in accordance
with BS EN ISO 22476-3:2005, modified by Geoguide 2 as necessary, to the
founding materials (except for foundations on rock). The SPT shall be carried
out by a contractor on the Housing Authority List of Ground Investigation
Contractors. The minimum number and depth of the drillholes shall be as
specified in Project Specific Specification. Unless otherwise Instructed,
commence the drillhole at existing ground level before excavation for the
foundations and carry out the SPT at intervals as specified in Project Specific
Specification. Submit to the CM the preliminary test reports within 2 days and
the final test reports within 2 weeks upon completion of the SPT;
4. If Instructed, carry out Plate Load Test for shallow foundations (except for
foundations on rock) in accordance with GIN.T190 and the Code of Practice for
Foundations issued by the Buildings Department;
5. If Instructed, take down the excavations for founding of shallow foundations
(except for foundations on rock) first to not less than 300 mm above the
designed founding level and carry out dynamic probe tests or other tests. The
dynamic probe tests shall be in accordance with Appendix 7.1 of the 'General
Specification for Civil Engineering Works', The Government of the Hong Kong
Special Administrative Region, 2006 Edition. Submit the test results within 2
days and a record plan showing all the locations and levels of the dynamic probe
tests within 1 week upon completion of the tests;
6. If considered necessary after examining the actual ground exposures and / or test
results, the CM may order further excavation to deepen the founding level of the
foundations and / or other measures to ensure a satisfactory foundation. The
bases shall be inspected and approved by the CM before concreting;
7. If considered necessary the CM may order compaction of the whole or parts of
the founding bases of shallow foundations by at least 12 passes of a vibratory
roller, or other accepted construction plant, with a minimum static load per
100 mm width of roll of 2kN or 4kN. In areas adjacent to structures and utilities,
which are existing or constructed as part of the permanent works, compaction
shall be carried out by hand-rammers or manually operated power equipment in
a manner that these structures and utilities are not disturbed or damaged.
_____________________________________________________________________________________________
REMEDIAL WORKS
EAR1.W1010.9 EXCAVATION BOTTOMS DAMAGED AFTER APPROVAL
If, due to water or other causes, the bottom of the excavation becomes unsuitable
after Approval, excavate further to a new Approved level, and backfill with Grade
15/20 concrete as specified in Worksection CON1.
FILLING GENERALLY
EAR1.W1110.9 USE OF ROCK CRUSHING PLANT
Do not use rock crushing plant on the Site unless permitted by the CM to do so.
_____________________________________________________________________________________________
EAR1.W1220.9 WATER-COURSES
Do not place fill material until watercourses have been diverted or under-drained.
EAR1.W1250.9 SCARIFYING
Scarify surfaces other than rock to a depth of 200 mm and compact to the same
standard as the fill material which is to be deposited.
FILLING OPERATIONS
EAR1.W1310.9 DISPOSAL OF WATER
1. Keep the fill area free of water;
2. Leave surfaces with no area that can retain water at the end of each day's work
and, if necessary, cut ditches to achieve this.
_____________________________________________________________________________________________
EAR1.W1320.9 APPROVAL
Obtain Approval before deposition of fill material starts and before any fill layer is
covered.
EAR1.W1390.9 SETTLEMENT
Make good, to the satisfaction of the CM, settlement in filling and backfilling and
any consequential damage that may occur up to the end of the Maintenance Period.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR1.W1520.9 FILLING
Filling materials and method of construction to be used are specified in Project
Specific Specification.
EAR1.W1620.9 FILLING
Unless otherwise specified place special filling material as backfilling and compact
by the Performance Specification method of compaction: EAR1.W1810 -
EAR1.W1860. Compaction plant is to be of such a size as to ensure that no undue
stress is placed on the wall during compaction.
_____________________________________________________________________________________________
EAR1.W1730.9 COMPACTION
1. Compact filling material, other than rock fill and material as stated in
EAR1.W1940 in accordance with the Compaction by Performance Specification:
EAR1.W1810 - EAR1.W1860 unless otherwise specified;
2. Compact rock fill material in accordance with the Compaction by Method
Specification: EAR1.W1910 - EAR1.W1930;
3. Compact general fill material with a large portion of coarse material in
accordance with EAR1.W1940.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
COMPACTION BY PERFORMANCE
SPECIFICATION
EAR1.W1810.9 PROCEDURE
1. Compact fill material in areas of fill in uniform layers to a stable condition as
soon as practicable after deposition and in a manner appropriate to the location
and to the material to be compacted;
2. Obtain the permission of the CM before the next layer is deposited on each layer
of compact fill material;
3. Agree with the CM the thickness of each layer which is to be compatible with
the compaction plant used. Carry out carefully controlled tests to determine the
optimum placing thickness for the particular fill and the number of passes to
achieve the required density with the compaction plant provided;
4. Do not place any permanent fill until such tests have been agreed with the CM.
Earthmoving plant will not be accepted as compaction equipment.
EAR1.W1820.9 TESTING
Test each class of material to be compacted in accordance with the compaction tests
specified in the Testing section of this Worksection.
_____________________________________________________________________________________________
EAR1.W1920.9 ROLLERS
Use vibratory rollers having a static load of at least 2 kN per 100 mm width of roll
for layers with a compacted thickness not exceeding 500 mm, and at least 4 kN for
layers with a compacted thickness exceeding 500 mm.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR1.W2020.9 COMPACTION
Except in areas of fill formed of rock fill material or fill material as stated in
EAR1.W1940, compact fill material in intermediate areas of fill to a degree which in
the opinion of the CM is practicable. Compact fill material above the level stated in
clause EAR1.W2010 to obtain a relative compaction of at least:
1. 90% throughout;
2. 95% within 1500 mm of earthworks final surfaces and formations; and
3. 98% within 200 mm of formations.
EAR1.W2120.9 COMPACTION
Compact formations to obtain a relative compaction of at least 98% to a depth of
200 mm below the formation.
_____________________________________________________________________________________________
EAR1.W2170.9 HYDROSEEDING
Refer to Project Specific Specification.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
8. Where there is reason to believe that the placed fill may be loose, or if the CM
from time to time directs, carry out field checks under the CM's direction,
initially by dynamic probe tests (supplemented by observations of fill materials
in trial pits if an appreciable cobble and boulder content in the fill is suspected).
Provide the necessary equipment, apparatus and labourers for the dynamic probe
tests and trial pit excavation. Carry out dynamic probe tests in accordance with
Appendix 7.1 of the 'General Specification for Civil Engineering Works', The
Government of the Hong Kong Special Administrative Region, 2006;
9. If loose fill is detected, arrange for the Approved Laboratory to carry out insitu
density tests of the loose layer in accordance with the Testing section of this
Worksection in the presence of the CM or his representatives. Carry out the
tests within seven days after the detection of the loose fill. If the test results fail
to comply with the Contract requirements, rectify the filling works to the
satisfaction of the CM as a matter of urgency. Where extensive loose fill is
found which could pose a significant threat if not rectified, the CM may issue an
order to suspend the progress of the Works in accordance with GCC Clause 9.2;
10. If the filling work has been done after compliance with the requirements of GCC
Clause 7.3, and is found to be executed in accordance with the Contract, the
expense of investigation, testing, reinstating and making good the same shall be
valued at the relevant Contract rates but in any other case the expense shall be
borne by the Contractor;
11. Upon completion of the filling work, submit to the CM:
a. "As-built" plans and sections of the work showing its relationship to existing
and proposed structures; and
b. Records of insitu density tests and laboratory compaction tests of the fill.
The costs of providing as-built records are deemed to be included in the Contract
rates of the filling works;
12. Bear all associated costs and make due allowance in the programme of the
Works for the provisions as stated in the above sub-clauses. No claim for
extension of time will be entertained in connection therewith.
TOLERANCES
EAR1.W2610.9 GENERAL
Refer to Appendix H 'Schedule of Tolerances' to this Specification.
_____________________________________________________________________________________________
TESTING
EAR1.T030.9 SAMPLES
Each sample of fill material must consist of at least four increments taken from
different parts of the batch. Combine the increments and thoroughly mix and divide
by quartering or by using a riffle box to obtain specimens of an appropriate size to
carry out the individual tests.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
3. Liquid limit: test all samples other than rock fill material (unless otherwise
agreed by the CM) as EAR1.T230 (3);
4. Plasticity index: as sub-clause (3) above and EAR1.T230 (4);
5. Soluble sulphate: test each sample of fill that will be deposited within 500 mm
of concrete, cement bound, or cementitious material, or metalwork as
EAR1.T230 (5).
_____________________________________________________________________________________________
EAR1.T320.9 LOCATION
Inform the CM of the exact location in which the fill material from which each
sample is taken is to be deposited.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR1.T530.9 METHODS
1. Adopt Method 1, or adopt Method 2 if agreed by the CM, to determine the
relative compaction of fill material as follows:
a. Method 1: Test Method 11.4, Geospec 3, GEO
Determine the relative compaction (RC) of fill material from the equation:
RC = IDD/MDD x 100%
where:
IDD is the in-situ dry density determined as EAR1.T540;
MDD is the maximum dry density determined as EAR1.T350 (1)(b);
b. Method 2: The relative compaction (RC) shall be calculated from the
equation:
RC = IBulkD/MCBulkD x 100%
where:
IBulkD is the in-situ bulk density determined as EAR1.T540;
MCBulkD is the maximum converted bulk density determined by Hilf
method as EAR1.T350 (2). If the amount of material retained on a 20 mm
BS test sieve is more than 5% of the mass of the sample, adjust the
maximum converted bulk density (MCBulkD) of fill material in accordance
with EAR1.T910 to EAR1.T950.
2. If in the opinion of the CM that there is any undue discrepancy between the
results of tests for relative compaction of fill using Method 1 stipulated in sub-
clause (1)(a) above and the results of tests using Method 2 stipulated in sub-
clause (1)(b), adopt only the results of tests using the Method 1.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR1.T820.9 APPARATUS
Use the following apparatus:
1. A microwave oven with a timer and an adjustable power setting;
2. An airtight container of microwave safe and non-reflective material;
3. A balance readable and accurate to 0.01 g;
4. A desiccator containing anhydrous silica gel.
EAR1.T830.9 PROCEDURE
Adopt the following procedure:
1. The container must be clean, dry and weighed to the nearest 0.01 g (m1);
2. Crumble a specimen and place loosely in the container and replace the lid.
Ensure each specimen of fine grained material is at least 30 g and each specimen
of medium grained material at least 300 g. Specimens of medium grained
material may be tested in several parts each less than 300 g and the results
aggregated;
3. Weigh the container and contents to the nearest 0.01 g (m2);
4. Remove the lid of the specimen container and place the container with its lid and
content in the microwave oven and dry. Consider the specimen to be dry when,
after an initial drying period, successive weighing at intervals of 1 minute
produce results which are the same to the nearest 0.01 g. Alternatively, the oven
may be set to an appropriate time and power setting to dry the specimen as
determined by calibration of the oven on soil of a similar type;
5. After drying, remove the container and contents from the microwave oven and
place in the desiccator to cool;
6. Replace the lid and weigh the container and contents to the nearest 0.01 g (m3).
EAR1.T840.9 CALCULATION
Calculate the moisture content of the material (w) as a percentage of the dry mass of
the material from the equation:
w = (m2 - m3)/(m3 - m1) x 100%
where:
- m1 is the mass of the container (g)
- m2 is the mass of the container and contents before drying (g)
- m3 is the mass of the container and contents after drying (g).
_____________________________________________________________________________________________
EAR1.T850.9 REPORTING
Report on the following:
1. Source and identification of the soil;
2. The moisture content of the material to the nearest 0.1%;
3. That the test method used was in accordance with this Specification.
EAR1.T870.9 APPARATUS
Use the following apparatus:
1. Apparatus in accordance with Geospec 3, Test Method 10.1 or 10.2, whichever
as Instructed by the CM;
2. Apparatus for determination of the moisture content in accordance with either
Geospec 3, Test Method 5.1 or 5.2 or EAR1.T820, whichever as Instructed by
the CM;
3. Apparatus to extract specimen from the mould;
4. Apparatus, such as a warm air blower, for rapid drying of the material.
EAR1.T880.9 PROCEDURE
Adopt the following procedures:
1. Take a sample of material immediately after completing the in-situ bulk density
test at the same location as the test. The sample shall be obtained by digging to
the same depth as that of the in-situ bulk density test, keeping the sides of the
excavation vertical and bottom lat and level. The size of the sample shall be
sufficient to yield a maximum of 10 kg after screening over a 20 mm BS test
sieve;
2. Weigh the sample to the nearest 0.01 g;
3. Screen the sample over a 20 mm BS test sieve, ensuring that moisture loss is
kept to a minimum and that any free moisture appearing in the container is
worked back into the sample;
4. Weigh the amount retained on the sieve to the nearest 0.01 g and express as a
percentage of the mass of the sample. If the percentage exceeds 5%, adjust for
coarse material in accordance with EAR1.T910 to EAR1.T950. If the
percentage does not exceed 5%, no adjustment is required;
_____________________________________________________________________________________________
_____________________________________________________________________________________________
b. If the plotted value of the CBulkD2 is less than the plotted value of CBulkD1,
dry and cool the third specimen until the amount of water removed is
approximately 2% of the specimen after cooling. Alternatively, if the
procedure of sub-clause (11) above has been followed, increase the moisture
content by adding an amount of water equal to 2% of the mass of the
specimen;
c. Mix the specimen thoroughly and compact in accordance with the method
stipulated in sub-clause (9) above. Determine the amount of water removed
if applicable;
d. Calculate the bulk density (BulkD3) as stated in EAR1.T890 (1), adjust to
converted bulk density (CBulkD3) as stated in EAR1.T890 (2) and plot on
the graph at a point corresponds to the amount of water added or removed.
13. If the centre point of the three points plotted is lower than one of the other two
points, or is higher than one point and equal to the other, obtain an additional
point or points by proceeding in 2% increments or decrements as appropriate;
14. If it is apparent that the moisture condition of the material is such that a total five
points will not result in the determination of the optimum moisture content,
adopt increments or decrements of 3% moisture content for the entire procedure;
15. Draw a smooth parabolic curve to the plotted points. Determine the peak of the
curve as the maximum converted bulk density (MCBulkD);
16. Determine the amount of water added of removed as a percentage of the mass of
the specimen at the in-situ moisture content corresponding to the maximum
converted bulk density (zm);
17. Determine the value of moisture correction curve passing through the peak value
of the plotted parabolic curve (zc). If there is no moisture correction curve
passing through the peak value of the curve, draw a moisture correction curve
through the peak by interpolating to the nearest 0.1%.
EAR1.T890.9 CALCULATION
1. Calculate the bulk density (BulkD) from the equation:
BulkD = (m2 – m1)/V Mg/m³
where:
m1 is the mass of the mould and base (g)
m2 is the mass of the mould and base and wet material (g)
V is the mass of the volume of the mould (mL).
2. Calculate the converted bulk density (CBulkD) from the equation:
CBulkD = BulkD/(1 + z/100) Mg/m³
where:
z is the amount of water added or removed as a percentage of mass of the
specimen at the in-situ moisture content (%)
z is negative for values below the in-situ moisture content.
3. Calculate the difference between the optimum moisture content (wo) and the in-
situ moisture content (wi) of the material from the equation:
wo – wi = zm + zc %
where:
_____________________________________________________________________________________________
EAR1.T900.9 REPORTING
Report on the following:
1. Source and identification of the soil;
2. The graph showing the plotted points and the parabolic curve passing through
them;
3. The maximum converted bulk density to the nearest 0.01 Mg/m³;
4. The optimum moisture content to the nearest 0.1%;
5. The maximum dry density to the nearest 0.01 Mg/m³;
6. The relative compaction to the nearest 0.1 %, if determined;
7. The percentage retained on the 20 mm BS test sieve and the percentage retained
on the 37.5 mm BS test sieve to the nearest 1%;
8. Whether the test was carried out using individual specimens or repeat testing of
a single specimen;
9. Whether a manual or an automatic compaction rammer was used;
10. That the test method used was in accordance with this Specification.
_____________________________________________________________________________________________
EAR1.T920.9 APPARATUS
Use the following apparatus:
1. Apparatus in accordance with EAR1.T870;
2. A 20 mm and a 37.5 mm BS test sieve;
3. A mould with collar as used for determination of the California Bearing Ratio
(CBR mould);
4. An extrusion device as used for determination of the California Bearing Ratio.
EAR1.T930.9 PROCEDURE
Adopt the following procedures:
1. If the amount of material retained on the 20 mm BS test sieve exceeds 5% and
does not exceeds 20%, compact the material passing the sieve in accordance
with EAR1.T860 to EAR1.T900. Determine and adjust the maximum converted
bulk density (MCBulkD) as stated in EAR1.T940;
2. If the amount of material retained on the 20 mm BS test sieve exceeds 20%,
screen the retained material over the 37.5 mm BS test sieve. Follow the
procedure stated in either sub-clause (3) or (4) below as appropriate;
3. If the amount of material retained on the 37.5 mm BS test sieve does not exceed
5%, follow the procedure stated in sub-clause (5);
4. If the amount of material retained on the 37.5 mm BS test sieve exceeds 5% and
does not exceed 20%, replace the retained material with an equal mass of
material which is of similar nature and which is retained on a 20 mm BS test
sieve but passes a 37.5 mm BS test sieve. Follow the procedure stated in sub-
clause (5) below;
5. Follow the procedure in EAR1.T860 to EAR1.T900 except that the material
shall be compacted into the CBR mould and each layer shall be subject to 62
blows of the rammer.
EAR1.T940.9 CALCULATION
Calculate the maximum converted bulk density (MCBulkD) from the equation:
MCBulkD = MCBulkD20[1 + m(1 – MCBulkD20/Gs)/(1 + z/100)] Mg/m³
where:
MCBulkD20 is the maximum converted bulk density of the material passing 20 mm
BS test sieve (Mg/m³)
m is the mass of material not passing the 20 mm BS test sieve expressed as a fraction
of the mass of the material at the in-situ moisture content
Specification Library 2022 Edition| (Batch 1) EAR /61
EXCAVATION AND FILLING EAR1 > TESTING
_____________________________________________________________________________________________
EAR1.T950.9 REPORTING
Report on the following:
1. Source and identification of the soil;
2. The results in accordance with EAR1.T900;
3. The mass of the original material not passing the 20 mm BS test sieve and
37.5 mm BS test sieve as a percentage of the mass of the material at the in-situ
moisture content to the nearest 0.1%;
4. The type of mould used;
5. The number of blows per layer;
6. Whether the specific gravity was measured or assumed and, if measured, the
method used;
7. That the test method used and the results adjusted were in accordance with this
Specification.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR2 BLASTING
MATERIALS
EXPLOSIVES
EAR2.M010.9 NITRO-GLYCERINE BASED EXPLOSIVES
Do not use.
_____________________________________________________________________________________________
WORKMANSHIP
GENERALLY
EAR2.W010.9 STATUTORY REQUIREMENTS
1. Comply with conditions and restrictions imposed by the Commissioner of Mines
for:
a. Blasting operations;
b. Supply, transportation, storage, use and disposal of explosives.
2. Make all arrangements with and obtain all licences and permits from the
Commissioner of Mines in connection with blasting operations;
3. Ensure that the Mines and Quarries Division, Civil Engineering Development
Department is given adequate notice to arrange visits to the site to consider
blasting conditions, and thereafter comply promptly and fully with any
instruction issued by the Commissioner of Mines, or his representative, in
connection with blasting;
4. Allow access to the Site by the staff of the Mines and Quarries Division at all
times;
5. Employ at least one registered shotfirer who holds a valid Hong Kong Mine
Blasting Certificate and is approved by the Mines and Quarries Division and the
CM.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
EAR2.W170.9 DETONATORS
Do not use electrical detonators within 60 m of overhead power lines unless
permitted by the Commissioner of Mines. When using electrical detonators in the
vicinity of static or mobile radios transmitters comply with BS 6657:1991.
_____________________________________________________________________________________________
PRE-SPLIT BLASTING
EAR2.W310.9 FORMING FINAL SURFACES
1. Form earthworks final surfaces and formations, which are to be formed by
blasting, and which slope at a gradient exceeding 2 vertical to 1 horizontal and
exceed 3 m in height by pre-splitting. Do not use other methods of controlled
blasting unless permitted by the CM;
2. Ensure that:
a. Other blast holes are located at a sufficient distance from the earthwork final
surface to avoid damaging the surface; and
b. The row of blast holes nearest to that surface is inclined parallel to the slope
face.
EAR2.W320.9 METHODOLOGY
1. Carry out pre-splitting and other methods of controlled blasting in such a manner
that the rock mass is cleanly split on the required plane and that rock outside the
earthworks final surface is not shattered or loosened;
2. Faces formed by pre-splitting or other methods of controlled blasting must not
exceed 15 m in height in any one blasting operation unless permitted by the CM.
_____________________________________________________________________________________________
TRIAL BLASTS
EAR2.W410.9 REASON FOR TRIAL BLASTS
Carry out trial blasts to demonstrate that:
1. The procedure is safe;
2. The resulting ground vibrations at locations stated in the Contract or instructed
by the CM can be satisfactorily predicted, recorded and are within acceptable
limits, do not adversely affect the safety and stability of adjoining structures,
installations, slopes and land.
_____________________________________________________________________________________________
2. Carry out blasting trials in accordance with the trial procedure submitted to and
agreed by the CM. The location and size of blasting trials shall be as agreed by
the CM.
TOLERANCES
EAR2.W510.9 GENERAL
Refer to Appendix H 'Schedule of Tolerances' to this Specification.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
DESIGN ........................................................................................................................................ 9
GENERAL .......................................................................................................................................... 9
STR1.D010.9 STRUCTURAL STEEL DESIGN ...................................................................... 9
STR1.D020.9 DESIGN STANDARDS ..................................................................................... 9
STR1.D030.9 WIND LOADING ............................................................................................... 9
STR1.D040.9 SEISMIC LOADING .......................................................................................... 9
STR1.D050.9 ALTERNATIVE DESIGN ................................................................................. 9
STR1.D060.9 DESIGN SUBMISSION FOR MINOR STEEL STRUCTURE ......................... 9
FABRICATION AND ERECTION DOCUMENTS ....................................................................... 9
STR1.D110.9 FABRICATION DOCUMENTS ........................................................................ 9
STR1.D120.9 ERECTION DOCUMENTS ............................................................................. 10
STR1.D150.9 WELDING SYMBOLS .................................................................................... 10
STR1.D160.9 DRAWINGS RESPONSIBILITY .................................................................... 10
STR1.D170.9 RECORD DRAWINGS .................................................................................... 10
DESIGN OF SPACE FRAMES ...................................................................................................... 10
STR1.D210.9 GENERAL ........................................................................................................ 10
STR1.D220.9 DESIGN RESPONSIBILITY ........................................................................... 10
STR1.D230.9 SCOPE OF WORKS ......................................................................................... 11
STR1.D240.9 DESCRIPTION OF WORKS ........................................................................... 11
STR1.D250.9 SPACE FRAME SYSTEM ............................................................................... 11
STR1.D260.9 TENDER INFORMATION .............................................................................. 11
STR1.D270.9 DESIGN ............................................................................................................ 11
STR1.D280.9 ERECTION INFORMATION .......................................................................... 11
MATERIALS FOR AND FABRICATION OF SPACE FRAMES ............................................. 12
STR1.D310.9 MATERIALS STANDARDS ........................................................................... 12
STR1.D320.9 ROOF FALLS ................................................................................................... 12
STR1.D330.9 SIZE OF MEMBERS ........................................................................................ 12
STR1.D340.9 FABRICATION ................................................................................................ 12
STR1.D350.9 CUTTING AND FITTING ............................................................................... 12
STR1.D360.9 FASTENERS .................................................................................................... 12
STR1.D370.9 LIGHT FITTINGS ............................................................................................ 13
STR1.D380.9 ACCESS CATWALKS .................................................................................... 13
STR1.D390.9 SECURITY GATE............................................................................................ 13
STR1.D400.9 ELECTRICAL CONNECTIONS ..................................................................... 13
TREATMENTS AND FINISHES TO SPACE FRAMES ............................................................ 13
STR1.D510.9 ELECTROPLATING ........................................................................................ 13
STR1.D520.9 HOT DIP GALVANIZING .............................................................................. 13
STR1.D530.9 POWDER COATINGS ..................................................................................... 13
ERECTION OF SPACE FRAMES ................................................................................................ 14
STR1.D610.9 ERECTION SUBMISSION .............................................................................. 14
STR1.D620.9 TEMPORARY SUPPORTS ............................................................................. 14
STR1.D630.9 FIXINGS ........................................................................................................... 14
STR1.D640.9 PROTECTION .................................................................................................. 14
Specification Library 2022 Edition (Batch 1) STR /2
STRUCTURAL STEELWORK STR > TABLE OF CONTENTS
_____________________________________________________________________________________________
MATERIALS ............................................................................................................................. 17
GENERAL ........................................................................................................................................ 17
STR1.M020.9 MATERIALS AND WORKMANSHIP ........................................................... 17
STR1.M030.9 APPROVALS ................................................................................................... 17
STR1.M040.9 SAFETY............................................................................................................ 17
STR1.M050.9 METHOD OF MANUFACTURE .................................................................... 17
STR1.M060.9 STEEL GRADES .............................................................................................. 17
STR1.M070.9 HOT ROLLED SECTIONS .............................................................................. 17
STR1.M080.9 COLD ROLLED SECTIONS ........................................................................... 18
STR1.M090.9 COLD ROLLED HOLLOW SECTIONS ......................................................... 18
STR1.M100.9 PLATES, FLATS AND BARS ......................................................................... 18
STR1.M110.9 SURFACE QUALITY ...................................................................................... 18
STR1.M120.9 SURFACE DEFECTS AND REPAIR .............................................................. 18
STR1.M130.9 SURFACE RUSTING ...................................................................................... 18
STR1.M140.9 MAXIMUM CARBON EQUIVALENT .......................................................... 18
STR1.M150.9 MARKING STEELWORK............................................................................... 19
STR1.M160.9 NON-AVAILABLE MATERIALS .................................................................. 19
STR1.M170.9 MANUFACTURERS CERTIFICATES ........................................................... 19
STR1.M180.9 CLASS OF STEEL ........................................................................................... 19
BOLTS, ACCESSORIES, CONNECTIONS AND FITTINGS ................................................... 19
STR1.M210.9 STEEL GRADE FOR CONNECTIONS AND FITTINGS .............................. 19
STR1.M220.9 HIGH STRENGTH BOLTS AND NUTS ........................................................ 19
STR1.M230.9 BS 4190 HOLDING DOWN BOLTS AND NUTS .......................................... 20
STR1.M240.9 BS 3692 HOLDING DOWN BOLTS AND NUTS .......................................... 20
STR1.M250.9 BLACK BOLTS AND NUTS........................................................................... 20
STR1.M260.9 DRIVE SCREWS.............................................................................................. 20
STR1.M270.9 PLAIN WASHERS FOR BLACK BOLTS ...................................................... 20
STR1.M280.9 SPRING WASHERS FOR BLACK BOLTS .................................................... 20
STR1.M290.9 TAPERED WASHERS ..................................................................................... 20
STR1.M300.9 BOLT LENGTHS ............................................................................................. 20
STR1.M310.9 HIGH STRENGTH FRICTION GRIP BOLTS ................................................ 20
STR1.M320.9 RIVETS............................................................................................................. 20
STR1.M330.9 TURNBUCKLES OR SIMILAR ...................................................................... 20
STR1.M340.9 MARKING BOLTS AND ACCESSORIES ..................................................... 21
WELDING CONSUMABLES ......................................................................................................... 21
STR1.M410.9 QUALITY OF ELECTRODES, RODS AND WIRES ..................................... 21
STR1.M420.9 CONSUMABLES FOR WELDING STEELS TO BS EN 10025 .................... 21
STR1.M430.9 ELECTRODES FOR WELDING GRADE S355 AND S450 STEELS ........... 21
STR1.M440.9 COVERED ELECTRODES FOR MANUAL METAL ARC
WELDING ........................................................................................................ 21
STR1.M450.9 FILLER WIRES FOR GAS-SHIELDED WELDING ...................................... 21
STR1.M460.9 CORED ELECTRODES ................................................................................... 21
_____________________________________________________________________________________________
WORKMANSHIP ..................................................................................................................... 22
TRANSPORTATION AND STORAGE ........................................................................................ 22
STR1.W010.9 GENERAL ........................................................................................................ 22
STR1.W020.9 HANDLING...................................................................................................... 22
STR1.W030.9 SPECIAL HANDLING .................................................................................... 22
STR1.W040.9 BOLTS, NUTS, WASHERS, AND SCREWS ................................................. 22
STR1.W050.9 EXPOSURE TO POLLUTANTS ..................................................................... 22
STR1.W060.9 ROAD TRANSPORT ....................................................................................... 23
STR1.W070.9 SEA TRANSPORT ........................................................................................... 23
STR1.W080.9 REPAIR OF DAMAGE INCURRED IN TRANSPORT ................................. 23
FABRICATION ................................................................................................................................ 24
STR1.W110.9 ACCESS............................................................................................................ 24
STR1.W120.9 GEOMETRIC FORM ....................................................................................... 24
STR1.W130.9 IDENTIFICATION ........................................................................................... 24
STR1.W140.9 SURFACE PREPARATION ............................................................................ 24
STR1.W150.9 POST CLEANING............................................................................................ 24
STR1.W160.9 EXECUTION .................................................................................................... 24
STR1.W170.9 SETTING OUT ................................................................................................. 24
STR1.W180.9 TEMPORARY ATTACHMENTS.................................................................... 25
STR1.W190.9 END PLATES ................................................................................................... 25
STR1.W200.9 JIGS................................................................................................................... 25
STR1.W210.9 MEASUREMENT AND SETTING OUT MARKS ......................................... 25
STR1.W220.9 CONTINUOUS STRUCTURES ...................................................................... 25
STR1.W230.9 STRAIGHTENING BENDING AND CAMBERING OF STEEL
SECTIONS........................................................................................................ 25
STR1.W240.9 POST FABRICATION MAKING GOOD ....................................................... 25
STR1.W250.9 CUTTING STEEL ............................................................................................ 25
STR1.W260.9 CUT EDGES ..................................................................................................... 26
STR1.W270.9 MACHINING GENERALLY ........................................................................... 26
STR1.W280.9 FLAME CUTTING ........................................................................................... 26
STR1.W290.9 FORMING HOLES FOR BOLTS AND RIVETS ............................................ 26
STR1.W300.9 BUILT-UP SECTIONS .................................................................................... 27
STR1.W310.9 REMOVING BURRS ....................................................................................... 27
STR1.W320.9 HOLES FOR BLACK BOLTS ......................................................................... 27
STR1.W330.9 HOLES FOR HIGH STRENGTH FRICTION GRIP BOLTS.......................... 27
STR1.W340.9 FITTED BOLTS, PINS OR RIVETS ............................................................... 27
STR1.W350.9 SLOTTED HOLES ........................................................................................... 28
STR1.W360.9 PREVENT MOISTURE INGRESS .................................................................. 28
MECHANICAL JOINTING ........................................................................................................... 28
STR1.W410.9 SURFACE PREPARATION ............................................................................ 28
STR1.W420.9 USE OF HIGH STRENGTH FRICTION GRIP BOLTS ................................. 28
STR1.W430.9 WRENCH CALIBRATION ............................................................................. 28
STR1.W440.9 CALIBRATION OF BOLT LOAD METER .................................................... 29
STR1.W450.9 BLACK OR PRECISION BOLTED CONNECTIONS ................................... 29
STR1.W460.9 ALIGNMENT, TEMPORARY CONNECTIONS AND PERMANENT
FIXINGS ........................................................................................................... 29
STR1.W470.9 BOLTED CONNECTIONS WITH PROVISION FOR SLIDING ................... 29
_____________________________________________________________________________________________
WELDING ........................................................................................................................................ 30
STR1.W510.9 GENERAL ........................................................................................................ 30
STR1.W520.9 USE OF WELDING EQUIPMENT AND ACCESSORIES ............................ 30
STR1.W530.9 PREPARATION FOR WELDING ................................................................... 30
STR1.W540.9 ADDITIONAL REQUIREMENTS FOR SITE WELDING ............................. 30
STR1.W550.9 METHOD OF WELDING ................................................................................ 31
STR1.W560.9 REMOVAL OF SLAG ..................................................................................... 31
STR1.W570.9 TACK WELDS ................................................................................................. 31
STR1.W580.9 WELD DEFECTS ............................................................................................. 31
STR1.W590.9 FILLET WELDS ............................................................................................... 32
STR1.W600.9 BUTT WELDS.................................................................................................. 32
STR1.W610.9 STUD SHEAR CONNECTORS ....................................................................... 32
ERECTION OF STEELWORK ..................................................................................................... 32
STR1.W710.9 ERECTION ....................................................................................................... 32
STR1.W720.9 ERECTORS ...................................................................................................... 32
STR1.W730.9 SAFETY............................................................................................................ 32
STR1.W740.9 STABILITY ...................................................................................................... 32
STR1.W750.9 SEQUENCE OF OPERATIONS ...................................................................... 33
STR1.W760.9 PLANT AND EQUIPMENT ............................................................................ 33
STR1.W770.9 PREVENTION OF DISTORTION ................................................................... 33
STR1.W780.9 APPROVED SEQUENCE ................................................................................ 33
STR1.W790.9 FALSEWORK .................................................................................................. 33
STR1.W800.9 SETTING OUT, LEVELLING AND LOCATION .......................................... 33
STR1.W810.9 ERECTION OF STEELWORK ........................................................................ 33
STR1.W820.9 STEELWORK BY SUB-CONTRACTOR ....................................................... 34
CLEANING, SURFACE PREPARATION AND PROTECTION (POST FABRICATION) ... 34
STR1.W910.9 CLEANING AND COATING IN THE SUPPLIERS WORKSHOP ............... 34
STR1.W920.9 CLEANING SURFACES OF BARE METAL ................................................. 34
STR1.W930.9 CONTAMINATED SURFACES...................................................................... 34
STR1.W940.9 PAINTED AND OTHER COATED SURFACES............................................ 34
STR1.W950.9 ATMOSPHERIC CORROSION....................................................................... 35
STR1.W960.9 BLAST CLEANING ......................................................................................... 35
STR1.W970.9 MECHANICAL CLEANING ........................................................................... 35
STR1.W980.9 PICKLING ........................................................................................................ 35
STR1.W990.9 FLAME CLEANING ........................................................................................ 35
STR1.W1000.9 NEW GALVANIZED SURFACES .................................................................. 35
STR1.W1010.9 PREVIOUSLY PAINTED GALVANIZED SURFACES ................................ 36
STR1.W1020.9 CLEANED OR COATED MEMBERS ............................................................ 36
APPLICATION OF METAL COATINGS .................................................................................... 36
STR1.W1110.9 HOT DIP GALVANIZING .............................................................................. 36
STR1.W1120.9 SPRAYED METAL COATING ....................................................................... 37
STR1.W1130.9 ELECTROPLATING ........................................................................................ 37
STR1.W1140.9 CHROMIUM PLATING .................................................................................. 37
STR1.W1150.9 METAL COATING ON PART ONLY OF ASSEMBLED SECTION ............ 37
STR1.W1160.9 PROTECTION OF HSFG BOLTED JOINTS .................................................. 37
STR1.W1170.9 PROTECTION OF OTHER BOLTED JOINTS ............................................... 37
STR1.W1180.9 PROTECTION OF NON-BOLTED JOINTS ................................................... 38
STR1.W1190.9 SURFACES ADJACENT TO TREATED JOINTS ......................................... 38
STR1.W1200.9 PAINTING AND SEALING OF JOINTS ........................................................ 38
STR1.W1210.9 APPLICATION OF PAINT .............................................................................. 38
STR1.W1220.9 PAINTING STEELWORK ............................................................................... 39
STR1.W1230.9 PAINT FOR STEELWORK PROTECTION SYSTEMS................................. 40
_____________________________________________________________________________________________
TESTING ................................................................................................................................... 42
GENERAL REQUIREMENTS ....................................................................................................... 42
STR1.T010.9 GENERAL ........................................................................................................ 42
STR1.T020.9 TESTING BY MANUFACTURER .................................................................. 42
STR1.T030.9 TESTING OF BOLTS, NUTS AND WASHERS ............................................ 42
STR1.T040.9 TEST CERTIFICATES .................................................................................... 42
STR1.T050.9 TESTING OF SECTIONS ................................................................................ 42
STR1.T060.9 FAILURE OF TESTS ....................................................................................... 43
STR1.T070.9 ULTRASONIC TESTING ................................................................................ 43
STR1.T080.9 ABILITY OF WELDERS ................................................................................. 43
STR1.T090.9 PARTICULARS OF INSPECTING AUTHORITY ......................................... 43
STR1.T093.9 BATCH OF WELDING CONSUMABLE ....................................................... 43
STR1.T094.9 TESTING OF WELDING CONSUMABLES .................................................. 44
STR1.T095.9 ACCEPTANCE CRITERIA - WELDING CONSUMABLES ......................... 44
STR1.T096.9 FAILURE OF TESTS ....................................................................................... 44
STR1.T097.9 STANDARD FOR REJECTION ...................................................................... 45
STR1.T100.9 STANDARD OF WELD PROCEDURE TESTING ........................................ 45
STR1.T110.9 ADDITIONAL DESTRUCTIVE WELD TESTS AS SELECTED BY
THE CM............................................................................................................ 45
STR1.T120.9 ADDITIONAL NON-DESTRUCTIVE TESTING OF STEEL,
STAINLESS STEEL AND ALUMINIUM....................................................... 45
STR1.T130.9 ACCEPTANCE CRITERIA ............................................................................. 46
STR1.T140.9 WELD REPAIR ................................................................................................ 46
STR1.T150.9 ENGAGEMENT OF SPECIALIST TESTING CONTRACTOR (FOR
FABRICATION ON SITE) .............................................................................. 46
TESTING OF PAINTS .................................................................................................................... 46
STR1.T210.9 SAMPLING AND TESTING ........................................................................... 46
STR1.T220.9 PAINT SAMPLES ............................................................................................ 47
STR1.T230.9 TESTING PAINTS ........................................................................................... 47
STR1.T240.9 TESTING LABORATORY .............................................................................. 47
STR1.T250.9 GLOSS FINISH ................................................................................................ 47
SPACE FRAMES - WARRANTIES AND TESTING .................................................................. 47
STR1.T310.9 SUITABILITY WARRANTY .......................................................................... 47
STR1.T340.9 TESTING OF SECTIONS ................................................................................ 47
STR1.T350.9 WELDING TESTS ........................................................................................... 48
STR1.T360.9 PROOF LOAD TESTING ................................................................................ 48
STR1.T370.9 NODAL JOINTS OF SPACE FRAMES .......................................................... 48
STR1.T380.9 ACCEPTANCE CRITERIA FOR NODAL JOINT TESTS ............................. 48
STR1.T390.9 FAILURE AND RE-TESTING OF NODAL JOINTS ..................................... 48
STR1.T400.9 LOADING TESTS ............................................................................................ 49
OFF-SITE FABRICATION ............................................................................................................ 49
STR1.T510.9 TESTING AND SURVEILLANCE VISITS AT FABRICATION
YARD ............................................................................................................... 49
_____________________________________________________________________________________________
_____________________________________________________________________________________________
STANDARDS
STR1.G010.9 CODE OF PRACTICE AND STANDARDS
1. Comply with the Code of Practice for the Structural Use of Steel 2011 issued by
the Buildings Department;
2. Unless otherwise approved, comply with the British Standards stated in this
Specification. Where the Contractor proposes to substitute any other standard or
code of practice either in its entirety or in part, for any of those specified, submit
details of such together with two complete copies for Approval. Generally,
Approval will only be given where the CM considers the proposals to give at
least an equivalent standard of the finished work;
3. In the case of any conflict, ambiguity or contradiction between the Code of
Practice for the Structural Use of Steel 2011 and the British Standards or other
Approved Standards, unless expressly stated otherwise in this Specification, the
conditions of the Code of Practice for the Structural Use of Steel 2011 shall
prevail.
_____________________________________________________________________________________________
DESIGN
GENERAL
STR1.D010.9 STRUCTURAL STEEL DESIGN
Comply with the information given on the Drawings and the following information.
In general member sizes on the Drawings will be given as serial sizes and loads will
be indicated under dead and superimposed live loads only. Wind loading, seismic
loading and thermal loading will not generally be shown.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
STR1.D270.9 DESIGN
Design proprietary space frame system:
1. To comply with the Code of Practice for the Structural Use of Steel 2011 for
steel or BS 8118 for aluminium, as appropriate;
2. To be capable of withstanding thermal movement and induced stresses under a
temperature variation ranging from 0ºC to 40ºC and other loads as shown on
Drawings.
_____________________________________________________________________________________________
e. A quality control & assurance system for the verification of the compliance
of specification in all materials and workmanship;
f. A copy of full set of design calculations including those for the erection
stage, certified by the Responsible Engineer;
g. Four copies of a full set of shop drawings of the space frame structure and
the supporting parts complete with bearings, required for the proper
execution of works, certified by the same Responsible Engineer; and
h. Manufacturer's certificates of origin and chemical composition of, and
certificates of results of physical tests for, structural elements showing
compliance with the specification.
2. The CM undertakes to reply to the Contractor's submissions and re-submissions
within 42 days.
STR1.D340.9 FABRICATION
Ensure all members are free from twist, true to profile and dead straight or truly
curved as shown on the Drawings. Materials damaged whilst being straightened or
curved to be rectified or rejected as the CM directs.
STR1.D360.9 FASTENERS
1. Provide and fit all bolts with washers, splayed if necessary, to give a level and
even bearing on the nuts;
_____________________________________________________________________________________________
_____________________________________________________________________________________________
STR1.D630.9 FIXINGS
Provide installation details of all anchorages/anchor bolts, that must avoid conflicting
with the reinforcement of supporting elements.
STR1.D640.9 PROTECTION
Allow for taking necessary precautions to prevent damage to the existing structure
and finishes thereof if applicable, during erection. Protect floors when cranes or
other plant are to be used internally for erection.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
2. Assemble, fit and temporarily bolt or tack weld members to Approval prior to
final riveting or welding;
3. Submit records of inspection of the completed formwork and falsework to the
CM for information before carrying out any further works that may affect the
stability of the formwork and falsework. Such records are to be certified by a
contractor's superintendent holding qualification equivalent to TCP Grade T4 in
civil or structural engineering discipline;
4. Monitor falsework levels and make any necessary adjustments for settlement, or
other deflection or movements.
_____________________________________________________________________________________________
MATERIALS
GENERAL
STR1.M020.9 MATERIALS AND WORKMANSHIP
Ensure that all structural steelwork is in accordance with the Code of Practice for the
Structural Use of Steel 2011 for building and general work and in accordance with
BS 5400 and the Structure Design Manual for Highways and Railways issued by the
Highways Department for bridge works except where specified otherwise.
STR1.M030.9 APPROVALS
Prior to commencing construction, submit for Approval any details required of the
welding plant, techniques and procedures, jigs, workshop facilities and construction
devices e.g. cranes, scaffolding etc, which the Contractor proposes using for the
fabrication and erection of the steelwork. The information must be in sufficient
detail to enable the CM to approve or otherwise.
STR1.M040.9 SAFETY
Comply with safety recommendation contained in BS EN 1011-1:2009 and with the
Factories and Industrial Undertakings Ordinance throughout the fabrication,
transport, handling and erection of structural steelwork.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
STR1.M320.9 RIVETS
Use mild steel rivets for general engineering purposes to BS 4620:1970 (1988).
_____________________________________________________________________________________________
WELDING CONSUMABLES
STR1.M410.9 QUALITY OF ELECTRODES, RODS AND WIRES
Select to give weld metal properties not less than the minimum specified for the
grade of steel being welded.
_____________________________________________________________________________________________
WORKMANSHIP
STR1.W020.9 HANDLING
Carefully load, stack, and unload to avoid damage of any description. Replace
damaged items at Contractor's own expense unless the CM permits rectification of
damage.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
FABRICATION
STR1.W110.9 ACCESS
Provide access for the CM at all reasonable times to all places where work is being
carried out, with all necessary facilities for inspection during fabrication and off-site
assembly.
STR1.W130.9 IDENTIFICATION
Identify at all stages of fabrication, structural steel as described in STR1.M150.
STR1.W160.9 EXECUTION
1. Carry out all fabrication to:
a. The Code of Practice for the Structural Use of Steel 2011 for hot rolled
sections and cold formed sections in building;
b. BS 5400:Part 6:1980 for plates and sections in bridgework.
2. Conform with the requirements for accuracy of construction with respect to
levels, dimensions, alignment and fabrication tolerances of members and joints
given in the above Code of Practice and British Standard.
_____________________________________________________________________________________________
STR1.W200.9 JIGS
Use jigs for repetitive, interchangeable or complicated work.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
d. Holes must not to be punched full size in any of the following conditions:
i. In tension flanges at locations where plastic hinges have been assumed
in the design analysis;
ii. In elements of rigid connections in which local yield lines have been
assumed;
iii. Where repetition of loading makes fatigue critical in the member design.
2. Comply with clause 14.2.5 of the Code of Practice for the Structural Use of Steel
2011.
_____________________________________________________________________________________________
c. All holes not drilled through a thicknesses at one operation are to be drilled
to a smaller size and reamed out after assembly. Where this is not
practicable, drill and ream the parts separately through hard bushed steel jigs.
MECHANICAL JOINTING
STR1.W410.9 SURFACE PREPARATION
Prepare and prime the contact surfaces at riveted, bolted and screwed joints. If the
contact surfaces are specified to be coated or otherwise treated, e.g. machined
surface finish, obtain Approval to the joint before assembly.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
WELDING
STR1.W510.9 GENERAL
1. Prior to fabrication of bridgework carry out welding and flame cutting trials
using representative samples of materials to be used in the work in accordance
with BS 5400:Part 6:1980;
2. Provide an experienced and competent operative to supervise welding. Submit
evidence that all welders are capable in accordance with STR1.T080;
3. When directed by the CM, keep a site record that identifies the welders
responsible for major welds.
_____________________________________________________________________________________________
3. Electrodes: bake on site at a temperature between 100°C and 150°C and where
necessary store in heated quivers for use at the welders convenience;
4. Power supply: may be from a transformer or generator to provide a three phase
power supply of the required voltage. Locate the generator or transformer as
close as possible to the welder to prevent a drop in voltage along the cables
length. Ensure all the cables are as short as possible, routed away from the path
of construction vehicles, and adequately protected;
5. Earth run: adequately earth all electrical plant. Ensure the welding return from
the weldment is adequate in cross section and correctly connected and earthed;
6. Weld detail: ensure the welded joint is of the correct profile and fit up. As a
general guide do not carry out welding where the gap is less than 1 mm or more
than 3 mm unless a backing strip is provided. Where a backing strip is provided
the weld gap is not to exceed the greater of 5 mm or the thickness of the material
being welded. Adequately support all welded joints with props or restraints that
ensure relative movement of the fusion faces is prevented;
7. Work in confined spaces: provide adequate ventilation and formulate plans of
evacuation and escape before the work commences.
_____________________________________________________________________________________________
ERECTION OF STEELWORK
STR1.W710.9 ERECTION
1. Carry out all erection to:
a. The Code of Practice for the Structural Use of Steel 2011 for hot rolled
sections and cold formed sections in building;
b. BS 5400:Part 6:1980 for plates and sections in bridgework.
2. Conform with the requirements for accuracy of construction in respect of levels,
dimensions and alignment given in the above Code of Practice and British
Standard and those contained in the "Schedule of Tolerances" in Appendix H to
this Specification.
STR1.W720.9 ERECTORS
Carry out all work employing trained and experienced erectors. Provide evidence of
the erector's competence when directed by the CM.
STR1.W730.9 SAFETY
Comply with the relevant regulations on safety including the 'Factories and Industrial
Undertakings Ordinance', the recommendations of BS 5531:1988 as applicable and:
1. Use only recently tested equipment for lifting and remove from site any
damaged equipment;
2. Do not carry out complex operations at a height except from safe platforms large
enough to take operators and equipment. Maintain platforms and safe access
until work has been accepted and any added protection completed.
STR1.W740.9 STABILITY
Ensure stability of structure at all stages of construction.
_____________________________________________________________________________________________
STR1.W790.9 FALSEWORK
When specified, design, construct and dismantle falsework to BS 5975:1982.
Supply all staging and all labour, tools, erection plant, lifts, services, nuts and
washers and other necessary materials. Provide temporary bracings and guys to
ensure adequate resistance to wind and stability against collapse during construction.
1. Submit records of inspection of the completed formwork and falsework to the
CM for information before carrying cut any further works that may affect the
stability of the formwork and falsework. Such records are to be certified by a
contractor's superintendent holding qualification equivalent to TCP Grade T4 in
civil or structural engineering discipline;
2. Monitor falsework levels and make any necessary adjustments for settlement, or
other deflection or movements.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
STR1.W980.9 PICKLING
Carry out pickling of steel by the "Footner" process as specified in BS 5493:1977.
Apply the first priming coat of paint as soon as the steel has dried and is still warm.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
STR1.W1130.9 ELECTROPLATING
1. To BS 3382:Parts 1 and 2:1961;
2. Coating thickness: 5 microns minimum.
_____________________________________________________________________________________________
2. Site joints: apply to all surfaces, excepting those of fasteners, the same painting
system in the shop as is to be applied to the parent metal surfaces, unless
otherwise specified.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
OFF-SITE FABRICATION
STR1.W1410.9 SUBMISSIONS
Where structural steelwork is to be fabricated off-site, submit the following items for
Approval within a period from the notified date for commencement of Works as
specified in the Project Specific Specification:
1. The name, fabrication yard address with street maps and job reference of the
fabricator and the following:
a. A quality assurance (QA) scheme and testing regime on fabrication of the
structural steelwork with the items as stipulated in STR1.W1420; and
b. A fabrication and delivery schedule.
2. An RSE appointed by the Contractor/fabrication yard who shall carry out the
duties as stipulated in STR1.W1430;
3. A laboratory for carrying out the tests and issuing test certificates in the QA
scheme (except for those tests specified in STR1.T520 (2)), which shall be
accredited either by Hong Kong Accreditation Scheme (HKAS) under the Hong
Kong Laboratory Accreditation Scheme (HOKLAS), or an equivalent
organization which has signed a mutual recognition agreement with HOKLAS.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING
GENERAL REQUIREMENTS
STR1.T010.9 GENERAL
Allow sufficient time in the Works programme for the testing specified below. Do
not incorporate materials until relevant tests have been carried out and Approval
obtained.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TESTING OF PAINTS
STR1.T210.9 SAMPLING AND TESTING
Permit authorized sampling of materials on site. Set aside unopened sealed
containers of materials for testing when directed by the CM.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
3. If the result of any of these additional tests fail to fulfil the test requirements, the
part of the particular consignment represented by these nodal joints must be
removed from Site forthwith.
OFF-SITE FABRICATION
STR1.T510.9 TESTING AND SURVEILLANCE VISITS AT FABRICATION YARD
For off-site fabrication in Guangdong province of China, comply with the following:
1. Provide all necessary facilities and attendance required by the CM and
Consultant employed for inspection and surveillance visits and the Direct
Testing Contractors for carrying out the tests as stated in STR1.T520 (2) at the
fabrication yard;
2. Make all necessary arrangement including providing transportation to the CM
and Consultant employed for inspection and surveillance visits to the fabrication
yards. Take the staff of each of the Direct Testing Contractors to the locations of
the testing and / or parallel testing works for the first visit to the fabrication yards,
and the Direct Testing Contractors shall arrange their own transportation for
subsequent visits to the same locations of the fabrication yard.
_____________________________________________________________________________________________
c. Welds for testing shall be selected and tested by the Direct Testing
Contractors in the fabrication yard.
_____________________________________________________________________________________________
APPENDIX STR1/I
STR1.APPEND1.9 CALCULATION OF NUMBER OF FURTHER INSPECTIONS / TESTS
2. The Contractor can either remove the standard lot of the particular batch of welding consumables
from the Site and / or the fabrication yard for off-site fabrication or at his own expense, carry out
further test(s) in accordance with the formula of:
n 2
2n 3 = 2² - 2 x 2 + 3
= 3 further tests
3. If one of the above 3 further tests fails, the Contractor may order further tests to be carried out at the
Contractor's own expense by re-applying the formula and taking into account the total number of
failed samples. Altogether and based on the formula, the number of total retesting required:
= 3² - 2 x 3 + 3
=6
As 3 tests have already been carried out by the Contractor, the Contractor shall carry out:
6 - 3 = 3 further tests
4. If the next 3 further tests show further failed samples, the formula will be re-applied as before until all
the tests results are satisfactory.
.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
SCOPE OF MODIFICATIONS
APE2.A020.9 LIMITATIONS
1. Only modifications to design and/or Specification for domestic blocks arising as
a result of complying with Items APE2.A030 to APE2.A070 inclusive are
permitted in tender stage.
2. Permitted modifications proposed and submitted by the Contractor with the
tender shall be in accordance with the Special Conditions of Tender and shall
comply with all the requirements as specified in Worksections APE2 and APE4
of this Appendix.
_____________________________________________________________________________________________
SUBMISSIONS
APE2.A110.9 SUBMISSIONS - GENERALLY
Submit a schedule listing any permitted modifications to the design and/or
Specification for domestic blocks proposed by the Contractor in a letter attached to
the Form of Tender.
DESIGN RESPONSIBILITY
APE2.A210.9 DESIGN RESPONSIBILITY
Notwithstanding Clause 5.15 of the General Conditions of Contract, the Contractor
shall, with respect to the Contractor’s proposed modification to the design and / or
Specification, be responsible for the satisfactory performance of the Works as
modified by the Contractor’s proposed modifications to the design and / or
Specification and shall guarantee the same to the Employer. The Contractor shall
indemnify and keep indemnified the Employer, his agents and employees against
any liability, claims, demands, proceedings, damage, costs, charges and expenses
whatsoever in respect thereof or in relation thereto, and shall compensate the
Employer for any loss or expense arising therefrom.
_____________________________________________________________________________________________
BILLS OF QUANTITIES
APE2.A310.9 AMENDMENTS
1. Subject to compliance with sub-clause (2) of this clause, the Contractor may, at
time of tender, insert, delete or revise the description and / or quantity of the
measured items within the Bills of Quantities to suit any modifications to design
and / or Specification for domestic blocks proposed by him. Such insertion,
deletion or revision shall be made in accordance with the Method of
Measurement stated in the Preliminaries to the Bills of Quantities. The
Contractor shall include a schedule in his tender showing all such revisions to
the Bills of Quantities;
2.
a. No insertion, deletion or revision shall be made to the Preliminaries to the
Bills of Quantities;
b. No insertion, deletion or revision to any provisional quantities contained in
the Bills of Quantities shall be allowed to be made, although the work or
works to which the provisional quantities refer may be modified by the
Contractor in accordance with Worksection APE2 of this Appendix.
PRELIMINARIES ITEMS
APE2.A410.9 ON-SITE PLANT AND EQUIPMENT
1. For domestic blocks, where the precast concrete facade system involves early
capital cost of major and necessary items of on-Site plant and equipment which
are used intimately in association with the precast facade construction, the
Contractor may make a request for special terms of payment in respect of these
items and is advised to make known to the Employer at time of tender, by
submitting proposals in a separate letter with his tender.
2. In this connection, the Contractor is to note that any special terms of payment
proposal must be restricted to only the on-Site items of plant and equipment as
described in Clause SCT10 of the Special Conditions of Tender and the amounts
of these items must have been tendered in Bill No 1 - Preliminaries. The
acceptance of any special terms of payment proposals shall be at the discretion
of the Employer.
3. All other Preliminaries items not related to the special terms of payment
proposal shall be paid in accordance with the provisions set out in Bill No 1
Preliminaries.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
SUBMISSIONS
APE3.A110.9 SUBMISSIONS - GENERALLY
Any modifications proposed by the Contractor shall be submitted in accordance with
Clause 11.8(2) of the General Conditions of Contract. Submit with the proposal a
report identifying the principles of any proposed structural modifications which shall
be prepared by a Registered Structural Engineer registered with the Buildings
Department.
_____________________________________________________________________________________________
CONSTRUCTION
APE4.A110.9 INSPECTION OF WORK
Any proposal that may require the CM or his representative to carry out inspection of
any work outside normal office hours will not be considered.
_____________________________________________________________________________________________
ACCEPTABILITY OF STRUCTURAL
MODIFICATIONS
APE4.A210.9 CONDITIONS OF ACCEPTABILITY
The following clauses in this sub-section are subject to all the conditions stated
elsewhere in the Appendix.
ACCEPTABILITY OF ARCHITECTURAL
MODIFICATIONS
APE4.A310.9 CONDITIONS OF ACCEPTABILITY
The following clauses in this sub-section are subject to all the conditions stated
elsewhere in this Appendix.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.FIN2 - PLASTERBOARD............................................................................................... 59
TOL.FIN2.010.9 BRITISH STANDARD .................................................................................... 59
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.COM1.020.9 VERTICALITY
PD of frame from plumb in any 1.2 m length .......... ±3 mm
_____________________________________________________________________________________________
TOL.COM2.010.9 DIMENSION
1. PD for peripheral dimensions:
a. Length 2 m: ±1.0 mm
b. Ditto 2 m 3.5 m: ±1.5 mm
c. Ditto 3.5 m 5 m: ±2.0 mm
d. Ditto 5 m: ±3.0 mm
2. PD for step joint: +0.5 mm : 0 mm
3. PD for diagonal dimensions:
a. Length 2 m: ±1.5 mm
b. Ditto 2 m 3.5 m: ±2.5 mm
c. Ditto 3.5 m: ±3.5 mm
4. Aluminum wall thickness:
a. Structural members: +0.16 mm : 0 mm
b. Non-structural members: +0.16 mm : 0 mm
c. Glazing bead ±0.1 mm
TOL.COM2.020.9 VERTICALITY
PD from plumb in any 1.2 m length ......................... ±3 mm
_____________________________________________________________________________________________
DOORSETS
TOLERANCE
TOL.COM5.010.9 WORKSIZES
PD from doorset worksizes specified in
BS 4787:Part 1:1980:
1. Height (A2 and G2) ............................................... +2.5 mm : -2.5 mm
2. Width (B2) ............................................................. +2.5 mm : -2.5 mm
DOOR LEAVES
TOLERANCE
TOL.COM5.110.9 HEIGHT
PD for leaves in all doorsets (d3) ............................... +2.5 mm : -2.5 mm
TOL.COM5.120.9 WIDTH
PD for leaves in single or double equal leaf doorsets
(e3) .............................................................................. +2.5 mm : -2.5 mm
TOL.COM5.130.9 THICKNESS
PD for all leaf thicknesses (f3):
1. Internal doorsets .................................................... +1.0 mm : -2.0 mm
2. External doorsets ................................................... +1.5 mm : -1.5 mm
TOL.COM5.160.9 CLEARANCES
PD from clearances specified in
BS 4787:Part 1:1980 or shown on drawings for:
1. Non fire resisting doors ......................................... +2.0 mm : -1.0 mm
2. Fire resisting doors without smoke seals .............. +1.0 mm : -0.5 mm
3. Fire resisting door with smoke seals ..................... See Note 2 Above
Specification Library 2022 Edition (Batch 1) APH /15
APPENDIX H - SCHEDULE OF TOLERANCES APH > TOL.COM5 - TIMBER......
_____________________________________________________________________________________________
TOL.COM5.170.9 SQUARENESS
PD when measured in accordance with
BS 5278:1976 at a point 500 mm from any
corner .......................................................................... 2.0 mm
TOL.COM5.180.9 FLATNESS
PD when measured in accordance with
BS 5278:1976, due to:
1. Bending:
a. Measured horizontally ..................................... 2.0 mm
b. Measured vertically .......................................... 4.0 mm
2. Twisting of any corner in relation to the other
three:
a. Doors of type '2' construction .......................... 6.0 mm
b. Doors of types '1' and '3' construction ............. 3.0 mm
TOL.COM5.190.9 SMOOTHNESS
For any door type:
1. PD in any position:
a. When measured with a 50 mm bridge ............ 0.2 mm
b. When measured with a 200 mm bridge .......... 1.0 mm
2. PD for doors of type '2' construction, when
measured with a 200 mm bridge, at not more
than 3 points along the 4 horizontal lines and 3
points along the 2 vertical lines of each face ........ 0.5 mm
3. PD for doors of type '1' and '3' construction,
when measured with a 200 mm bridge, at not
more than 4 points along the 2 vertical lines and
4 points along the 4 horizontal lines of each face
................................................................................. 0.5 mm
DOOR FRAMES
TOLERANCE
TOL.COM5.210.9 BOW
PD in the thickness of hardwood framing members
in any 2 m length:
1. Member thickness 50 mm ................................... 2.0 mm
2. Member thickness >50 mm .................................. 6.0 mm
TOL.COM5.220.9 SPRING
PD in the width of hardwood framing members in
any 2 m length:
1. Member thickness 100 mm ................................. 4.0 mm
2. Member thickness >100 mm ................................ 6.0 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.COM6.020.9 VERTICALITY
PD of frame from plumb in any 1.2 m length ........... ±3 mm
_____________________________________________________________________________________________
TOL.COM7 - GATESETS
_____________________________________________________________________________________________
PRODUCT ACCURACY
TOLERANCE
TOL.COM9.030.9 TWIST
PD in the distance of any one corner from the plane
containing the other three corners .............................. ±3 mm
TOL.COM9.050.9 FLATNESS
PD of a nominally plane surface when measured
with a 1.5 m straight edge .......................................... ±3 mm
ERECTION ACCURACY
TOLERANCE
_____________________________________________________________________________________________
UNREINFORCED/REINFORCED CONCRETE
FOUNDATION (INCLUDING RAFTS, GROUND
BEAMS, COLUMN BASES, PILE CAPS AND STRIP
FOUNDATIONS)
TOLERANCE
_____________________________________________________________________________________________
TOL.CON1.170.9 TWIST
The distance of any one corner from the plane
containing the other three corners, i.e. a variation
from the target plane:
1. For diagonal 3000 mm:
a. Formwork type A: ..................................... 10 mm
b. Formwork type B: ..................................... 5 mm
2. For diagonal 3000 mm 15 m:
a. Formwork type A: ..................................... 20 mm
b. Formwork type B: ..................................... 10 mm
3. For each further 10 m of diagonal:
a. Formwork type A: ..................................... 10 mm
b. Formwork type B: ..................................... 5 mm
_____________________________________________________________________________________________
TOL.CON1.200.9 LEVEL
PD from designed level with reference to the
nearest TBM of the upper or lower surface, as
may be specified of any slab or other element
or component:
1. Length 8 m: .................................................. ±10 mm
2. Length 8 m 15 m: ....................................... ±15 mm
3. Length 15 m 30 m: ..................................... ±20 mm
LIFTWELLS
TOLERANCE
_____________________________________________________________________________________________
4. 90 65 0
Read Table 1 in conjunction with figure 1 of Section 3 of BS 5655.
TOL.CON1.420.9 LENGTH
Length on plan of clear span (excluding
landings): ............................................................. ±15 mm
TOL.CON1.440.9 HEIGHT
Vertical height measured between either top
surfaces or soffit surfaces of any flight of
stairs: .................................................................... ±15 mm
TOL.CON1.460.9 RISE
Difference in the rise of two consecutive steps:
............................................................................... ±5 mm
_____________________________________________________________________________________________
TOL.CON1.470.9 GOING
Difference in width of tread of two consecutive
steps: .................................................................... ±10 mm
_____________________________________________________________________________________________
TOL.CON1.820.9 HEIGHT
To structural roof level with reference to the
TBM:
1. 30 m: ............................................................. ±40 mm
2. Each subsequent 30 m: ................................... ±15 mm
_____________________________________________________________________________________________
TOL.CON2 - FORMWORK
Note: Tolerances given in this section should be read in conjunction with those given in TOL.CON1.
_____________________________________________________________________________________________
TOL.CON2.130.9 TWIST
The distance of any one corner from the plane
containing the other three corners, i.e. a variation
from the target plane:
1. For diagonal 3000 mm:
a. Formwork type A: ..................................... 10 mm
b. Formwork type B: ..................................... 5 mm
2. For diagonal 3000 m 15 m:
a. Formwork type A: ..................................... 20 mm
b. Formwork type B: ..................................... 10 mm
3. For each further 10 m of diagonal:
a. Formwork type A: ..................................... 10 mm
b. Formwork type B: ..................................... 5 mm
_____________________________________________________________________________________________
TOL.CON3 - REINFORCEMENT
TOLERANCE
TOL.CON3.040.9 SPACING
The lesser of: ....................................................... +50 mm or 20% of specified
spacing
_____________________________________________________________________________________________
TOL.CON4.120.9 LENGTH
Length on plan of clear span (excluding
landings): ............................................................. ±12 mm
TOL.CON4.140.9 HEIGHT
Vertical height measured between either top
surfaces or soffit surfaces of any flight of stairs:
............................................................................... ±10 mm
TOL.CON4.160.9 RISE
Difference in the rise of two consecutive steps:
............................................................................... ±5 mm
TOL.CON4.170.9 GOING
Difference in width of tread of two consecutive
steps: .................................................................... ±8 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.CON5.020.9 SQUARENESS
When assessing the squareness of a corner:
1. Take the longer of the two adjacent sides
being checked as the base-line;
2. Ensure that the shorter side does not vary in
its distance from a perpendicular so that the
difference between the greatest and shortest
dimensions exceeds:
Length of shorter sides:
a. Up to and including 1000 mm: ................. 3 mm
b. Over 1000 mm to 2000 mm: .................... 5 mm
c. Over 2000 mm: ......................................... 6 mm
TOL.CON5.030.9 TWIST
Ensure that no corner is more than the dimension
stated from the plane containing the other three
corners:
1. Up to and including 3 m: ................................ 6 mm
2. Over 3 m to 6 m: ............................................. 9 mm
3. Over 6 m to 12 m: .......................................... 12 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.CON7.020.9 SQUARENESS
When assessing the squareness of a corner:
1. Take the longer of the two adjacent sides
being checked as the base-line;
2. Ensure that the shorter side does not vary in
its distance from a perpendicular so that the
difference between the greatest and shortest
dimensions exceeds:
Length of shorter sides:
a. Up to and including 1000 mm: ................. 3 mm
b. Over 1000 mm to 2000 mm: .................... 5 mm
c. Over 200 mm: ........................................... 6 mm
_____________________________________________________________________________________________
TOL.CON7.030.9 TWIST
Ensure that no corner is more than the dimension
stated from the plane containing the other three
corners:
1. Up to and including 3: .................................... 6 mm
2. Over 3 to 6: ..................................................... 9 mm
3. Over 6 to 12: ................................................... 12 mm
TOL.CON7.220.9 LENGTH
Length on plan of clear span (excluding
landings): ............................................................. ±12 mm
_____________________________________________________________________________________________
TOL.CON7.240.9 HEIGHT
Vertical height measured between either top
surfaces or soffit surfaces of any flight of
stairs: .................................................................... ±10 mm
TOL.CON7.260.9 RISE
Difference in the rise of two consecutive
steps: .................................................................... ±5 mm
TOL.CON7.270.9 GOING
Difference in width of tread of two consecutive
steps: .................................................................... ±8 mm
_____________________________________________________________________________________________
TOL.CON8.030.9 HEIGHT
To structural roof level with reference to the
Transferred Bench Mark (TBM):
1. 30 m: ........................................................... 40 mm
2. Each subsequent 30 m: ................................. 15 mm
_____________________________________________________________________________________________
TOL.CON8.060.9 TWIST
The distance of any one corner from the plane
containing the other three corners, i.e., a
variation from the target plane:
1. For diagonal 15 m: ...................................... 20 mm
2. For each further 10 m of
diagonal: ........................................................ 10 mm
TOL.CON8.080.9 LEVEL
Permissible Deviation (PD) from designed level
with reference to the nearest Transferred Bench
Mark (TBM) of the upper or lower surface, as
may be specified of any slab or other element or
component:
Length 8 m: ...................................................... 10 mm
Length 8 m 15 m: .......................................... 15 mm
Length 15 m 30 m: ........................................ 20 mm
_____________________________________________________________________________________________
3. 60 90 50 0
4. 90 65 0
Read Table 1 in conjunction with figure 1 of Section 3 of BS 5655.
_____________________________________________________________________________________________
TOL.DRA1.010.9 VERTICALITY
PD of pipes from plumb when measured with a
1.2 m straight edge ..................................................... 3 mm
_____________________________________________________________________________________________
TERMINATION PIPES
TOLERANCE
MANHOLES
TOLERANCE
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.EAR2 - BLASTING
PRE-SPLIT BLASTING
TOL.EAR2.010.9 FINAL SURFACE TOLERANCES
A tolerance of + 100 - 200 mm from the design profile.
Notes:
1. Redrill any pre-split hole which, before firing, is found to be outside this
tolerance;
2. A positive (+) tolerance refers to insufficient blasted material and a negative (-)
tolerance refers to excess blasted material.
_____________________________________________________________________________________________
TOL.EXT1.010.9 ALIGNMENT
PD of edgelines from the dimensions indicated on
the Drawings:
1. Generally ............................................................... +25 mm : -25 mm
2. Adjacent edges of structure ................................... +6 mm : -6 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.EXT2.050.9 FORMWORK
1. PD of line of formwork from that shown on
Drawings ................................................................ +10 mm : -10 mm
2. PD of level of formwork from that shown on
Drawings ................................................................ +3 mm : -3 mm
3. PD of abrupt irregularities in line and level of
formwork ............................................................... 3 mm
_____________________________________________________________________________________________
TOL.EXT2.090.9 LEVELS
When the levels of the concrete carriageway are
determined 200 mm from the edges of each bay, at
10 m centres in the longitudinal direction and 2 m
centres in the transverse direction:
1. PD of surface fall from that shown on
Drawings .......................... (Providing that falls +6 mm : -6 mm
shall always be in the specified direction without
backfall).
3 mm
2. Maximum difference in level across joint ............
_____________________________________________________________________________________________
MATERIALS
TOLERANCE
WORKMANSHIP
TOLERANCE
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.EXT5.010.9 LINE
PD from line specified ............................................... +3 mm : -3 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
MATERIALS
TOLERANCE
TOL.EXT7.030.9 CAMBER
PD from camber shown on the Drawings ................. +8 mm : -8 mm
TOL.EXT7.040.9 DISTORTION
PD within a 1.5 m length ........................................... 1.5 mm
WORKMANSHIP
TOLERANCE
TOL.EXT7.110.9 INSTALLATION
PD from specified position and height ...................... +10 mm : -10 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
FENCING
TOLERANCE
TOL.EXT9.010.9 MATERIALS
PDs for components as defined in Section 2 of
BS 1722 : Part 1 : 1986 -:-
TOL.EXT9.020.9 WORKMANSHIP
1. Position of posts: PD from specified position ....
................................................................................ 75 mm
2. Level of top of posts: PD from specified level ...
................................................................................ +25 mm : -25 mm
3. Verticality of posts: PD in the height of the post
rom plumb ............................................................ 5 mm
TOL.EXT9.110.9 ALIGNMENT
PD of line, position and height from that indicated
on Drawings ............................................................... +10 mm : -10 mm
_____________________________________________________________________________________________
TOL.FEN - FENCING
TOL.FEN.010.9 GENERAL
Fencing shall comply with the following requirements:
1. The position of posts shall be within 75 mm of the position shown on the
Drawings;
2. The level of the top of the posts shall be within 25 mm of the level shown on the
Drawings;
3. Posts shall be vertical to within 5 mm in the height of the post.
_____________________________________________________________________________________________
CEILING FINISHES
TOLERANCE
_____________________________________________________________________________________________
TOL.FIN2 - PLASTERBOARD
TOLERANCE
_____________________________________________________________________________________________
TOL.FIN3 - SCREEDS
TOLERANCE
TOL.FIN3.010.9 LEVEL
PD when measured with a 1.2 m straight edge:
1. From specified level measured in any direction ...
................................................................................. 3 mm
2. From specified fall measured in the direction of
fall provided that, in any situation, there is no
backfall .................................................................. 3 mm
_____________________________________________________________________________________________
TOL.FIN4.010.9 LEVEL
PD when measured with an 1.2 m straight edge:
1. From specified level measured in any direction ..
................................................................................ 3 mm
2. From specified fall measured along the fall
provided that in any situation there is no backfall
................................................................................ 3 mm
_____________________________________________________________________________________________
TOL.FIN5.010.9 LEVEL
PD from specified fall when measured with a 1.2 m
straight edge in the direction of fall provided that, in
any situation, there is no backfall .............................. 3 mm
WALL TILES
TOLERANCE
TOL.FIN5.110.9 PLANE
PD when measured with a 1.2 m straight edge in
any direction ............................................................... 3 mm
MOSAIC TILES
TOLERANCE
TOL.FIN5.210.9 PLANE
PD when measured with a 1.2 m straight edge in
any direction ............................................................... 3 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.FIN6.010.9 LEVEL
PD when measured with a 1.2 m straight edge .........
..................................................................................... 3 mm
_____________________________________________________________________________________________
CEILING COMPONENTS
TOLERANCE
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
c. The height, length and width of rubber fenders shall be within +4% and -2%
of the dimensions shown on the Drawings;
d. The thickness of fender sections shall be within +8% and -5% of the
thickness shown on the Drawings;
2. The positions of rubber fenders shall comply with the following requirements:
a. The centrelines shall be within 25 mm of the positions on the face of the
supporting structures shown on the Drawings;
b. The inclination shall not deviate by more than 1 in 50 from the inclination
shown on the Drawings.
_____________________________________________________________________________________________
BRICKWORK
TOL.MAS1.010.9 GENERALLY
Comply with Table 2 Section 3 of BS 8000:Part 3:1989.
TOL.MAS1.120.9 LENGTH
PD for:
1. Up to 5 m ............................................................... ±15 mm
2. 5 m to 10 m ............................................................ ±20 mm
3. 10 m to 20 m .......................................................... ±25 mm
4. Over 20 m .............................................................. ±30 mm
TOL.MAS1.130.9 HEIGHT
PD for:
1. Up to 3 m ............................................................... ±15 mm
2. 3 m to 6 m .............................................................. ±20 mm
3. Over 6 m ................................................................. ±25 mm
TOL.MAS1.160.9 STRAIGHTNESS
1. PD in any 1.2 m ..................................................... ±6 mm
TOL.MAS1.170.9 VERTICALITY
1. PD in any 1.2 m ..................................................... ±6 mm
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.MAS2 - STONEWORK
TOL.MAS2.020.9 LENGTH
PD ............................................................................... ±25 mm
TOL.MAS2.030.9 HEIGHT
PD ............................................................................... ±25 mm
TOL.MAS2.050.9 STRAIGHTNESS
PD in any horizontal 5 m ........................................... ±25 mm
TOL.MAS2.060.9 VERTICALITY
PD up to 3 m ............................................................... ±20 mm
TOL.MAS2.120.9 LENGTH
PD in any 6 m ............................................................. ±15 mm
TOL.MAS2.150.9 STRAIGHTNESS
PD in any horizontal 5 m ........................................... ±15 mm
TOL.MAS2.160.9 VERTICALITY
1. PD up to 3 m .......................................................... ±15 mm
2. PD up to 7 m .......................................................... ±20 mm
Specification Library 2022 Edition (Batch 1) APH /72
APPENDIX H - SCHEDULE OF TOLERANCES APH > TOL.MAS2 - STONEWORK
_____________________________________________________________________________________________
TOL.MAS2.220.9 THICKNESSES
PD from specified thickness (minimum 19 mm) ......
..................................................................................... ±3 mm
TOL.MAS2.320.9 LENGTH
PD in any 6 m ............................................................. ±10 mm
TOL.MAS2.350.9 STRAIGHTNESS
PD in any horizontal 2 m ........................................... ±3 mm
TOL.MAS2.360.9 VERTICALITY
PD in any 1.2 m .......................................................... ±3 mm
Note: The tolerance on the verticality is measured
in relation to the true vertical from the base of
the wall and is not cumulative.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.MEW - METALWORK
TOL.MEW.010.9 GENERAL
Handrailing, ladders, stairs and flooring shall comply with the following
requirements:
1. The position and height of handrailing shall be within 10 mm of the specified
position and height;
2. The level of the top rung of ladders and the top tread of stairs shall be within
75 mm of the specified level;
3. The level of flooring and curbs shall be within 3 mm of the specified level.
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.PIL1.020.9 VERTICALITY
Except Type 5 Piles, PD from the vertical axis of the
pile through the centroid of the cross-sections at the 1 in 75
cut-off level to any level of the finished pile:
TOL.PIL1.130.9 STRAIGHTNESS
PD: ............................................................................. 1 in 500
_____________________________________________________________________________________________
PILE TYPE 3
TOLERANCE
PILE TYPE 4
TOLERANCE
PILE TYPE 5
TOLERANCE
TOL.PIL1.310.9 BORING
Do not drill holes oversize by more than: ................. 20 mm
TOL.PIL1.330.9 VERTICALITY
PD from the vertical axis of the pile through the
centroid of the cross-section at the cut-off level to 1 in 100
any level of the finished pile:
_____________________________________________________________________________________________
_____________________________________________________________________________________________
_____________________________________________________________________________________________
SOIL-CEMENT FILLING
TOL.SLO.010.9 COMPACTION
1. The tolerance on the optimum moisture content percentage shall be ±3.
SOIL NAILING
TOL.SLO.110.9 GENERAL
The installation of soil nails shall comply with the following dimensional tolerances:
1. The permitted deviation of drillholes shall be within ±2º to the specified vertical
and horizontal alignments;
2. The nominal diameter of the centralizers shall not differ from the specified
diameter of the drillhole by more than 10mm.
_____________________________________________________________________________________________
FABRICATION OF STEELWORK
TOL.STR1.010.9 CRITICAL DIMENSIONS AFFECTING REPETITION OR
INTERCHANGEABILITY OF UNITS
Carry out fabrication so that the critical dimensions, when measured by a tape
calibrated at 20°C, comply with the tolerances given in the Table below:
Tolerance on overall
Dimension Measured Tolerance for Single dimension of assembled
Element system of more than
one
Not exceeding 5 m ±3 mm ±3 mm
Exceeding 5 m but not ±5 mm ±6 mm
exceeding 10 m
Exceeding 10 m but not ±5 mm ±10 mm
exceeding 15 m
Exceeding 15 m ±10 mm ±10 mm
ERECTION OF STEELWORK
TOLERANCE
_____________________________________________________________________________________________
_____________________________________________________________________________________________
TOL.STW - STEELWORK
TOL.STW.010.9 FABRICATION TOLERANCES GENERALLY
Fabrication tolerances for steelwork shall comply with BS 5950:Part 2:1992, Sub-
section 7.2 as appropriate.
_____________________________________________________________________________________________