You are on page 1of 91

DAFTAR HARGA SATUAN UPAH DAN BAHAN

TAHUN ANGGARAN 2020

A. HARGA SATUAN UPAH


HARGA SATUAN
NO URAIAN SATUAN
(Rp.)
1 2 3 4
1 Pekerja 115,000.00 oh
2 Tukang 172,000.00 oh
3 Kepala Tukang 207,000.00 oh
4 Mandor 227,000.00 oh

B. HARGA SATUAN BAHAN


HARGA SATUAN
NO URAIAN SATUAN
(Rp.)
1 2 3 4
1 Aluminium foil/sisalation 11,700.00 m2
2 Amplas 13,800.00 lbr
3 Asbes 23,000.00 lbr
4 Atap bitumen 207,000.00 m2
5 Atap genteng keramik 22,400.00 bh
6 Atap genteng metal tbl. 0,25 mm 51,500.00 lbr
7 Atap genteng metal tbl. 0,30 mm 62,000.00 lbr
8 Atap genteng metal tbl. 0,35 mm 74,700.00 lbr
9 Atap genteng metal tbl. 0,40 mm 85,200.00 lbr
10 Atap zincalume (Spandeck), tbl. 0,25 mm 39,100.00 m1
11 Atap zincalume (Spandeck), tbl. 0,30 mm 46,000.00 m1
12 Atap zincalume (Spandeck), tbl. 0,35 mm 57,500.00 m1
13 Atap zincalume (Spandeck), tbl. 0,40 mm 72,400.00 m1
14 Bak cuci piring 1 lubang stainless steel 402,500.00 bh
15 Bak cuci piring 2 lubang stainless steel 690,000.00 bh
16 Balok kayu kls. I 20,125,000.00 m3
17 Balok kayu kls. II 10,350,000.00 m3
18 Balok kayu kls. III 6,900,000.00 m3
19 Balok kayu sembarang 6,325,000.00 m3
20 Bambu 23,000.00 btg
21 Batu Alam Andesit 287,500.00 m2
22 Batu Alam Andesit motif 287,500.00 m2
23 Batu alam andesit bintik bakar 287,500.00 m2
24 Batu alam candi 230,000.00 m2
25 Batu alam Palimanan 230,000.00 m2
26 Batu alam paras ukr. 30x60 cm 230,000.00 m2
27 Batu bata 630.00 bh
28 Batu bata ringan tebal 7,5 cm 1,063,700.00 m3
29 Batu bata ringan tebal 10 cm 1,063,700.00 m3
30 Batu kali 287,500.00 m3
31 Batu koral 287,500.00 m3
32 Batu terawang roster ukr. 18x18 cm 40,200.00 bh
33 Besi baja IWF 14,700.00 kg
34 Besi beton polos 10,800.00 kg
35 Besi beton ulir 13,200.00 kg
36 Besi profil 15,800.00 kg
37 Besi strip 9,700.00 kg
38 Besi plat 12,600.00 kg
39 Besi siku L 30 : 30 : 3 9,400.00 kg
40 Besi siku L 40 : 40 : 4 28,700.00 kg
41 Besi siku L 50 : 50 : 5 152,900.00 kg
42 Beton fabrikasi / ready mix concrete mutu f'c = 9,8 MPa (batu guli) 937,000.00 m3
43 Beton fabrikasi / ready mix concrete mutu f'c = 12,2 MPa (batu guli) 954,000.00 m3
44 Beton fabrikasi / ready mix concrete mutu f'c = 12,2 MPa (batu pecah) 966,000.00 m3
45 Beton fabrikasi / ready mix concrete mutu f'c = 14,5 MPa (batu pecah) 1,012,000.00 m3
46 Beton fabrikasi / ready mix concrete mutu f'c = 16,9 MPa (batu pecah) 1,035,000.00 m3
47 Beton fabrikasi / ready mix concrete mutu f'c = 19,3 MPa (batu pecah) 1,058,000.00 m3
48 Beton fabrikasi / ready mix concrete mutu f'c = 21,7 MPa (batu pecah) 1,092,000.00 m3
49 Beton fabrikasi / ready mix concrete mutu f'c = 24,0 MPa (batu pecah) 1,115,000.00 m3
50 Beton fabrikasi / ready mix concrete mutu f'c = 26,4 MPa (batu pecah) 1,173,000.00 m3
51 Beton fabrikasi / ready mix concrete mutu f'c = 28,8 MPa (batu pecah) 1,207,000.00 m3
52 Beton fabrikasi / ready mix concrete mutu f'c = 31,2 MPa (batu pecah) 1,242,000.00 m3
53 Bodem Φ 30 cm 28,700.00 bh
54 Broti kayu kls. I 20,125,000.00 m3
55 Broti kayu kls. II 10,350,000.00 m3
56 Broti kayu kls. III 6,900,000.00 m3
57 Broti kayu Sembarang 6,325,000.00 m3
58 Cat dasar/sealer 46,000.00 kg
59 Cat dinding/tembok 103,500.00 kg
60 Cat menie besi 43,700.00 kg
61 Cat menie kayu 37,900.00 kg
62 Cat minyak/kilat 77,000.00 kg
63 Cat vernis 78,200.00 kg
64 Dempul cat 34,500.00 kg
65 Engsel jendela 3" 23,000.00 bh
66 Engsel pintu 5" 46,000.00 bh
67 Engsel salon 28,700.00 bh
68 Folding door / pintu lipat bahan plastik / PVC 625,200.00 m2
69 Formika/HPL 184,000.00 lbr
70 Gerendel jendela 17,200.00 bh
71 Gerendel pintu 8" 34,500.00 bh
72 Gerendel pintu 10" 46,000.00 bh
73 Glass block 34,500.00 bh
74 GRC 80,500.00 lbr
75 Gypsum board 9 mm 60,900.00 lbr
76 Hak angin jendela 28,700.00 bh
77 Handle jendela 28,700.00 bh
78 Handle pintu stainless steel 345,000.00 bh
79 Ijuk 28,700.00 kg
80 Jaring kawat baja / wire mesh 29,400.00 kg
81 Jendela nako 18,800.00 bh
82 Jendela nako 207,000.00 m2
83 Kaca bening tbl. 5 mm 155,000.00 m2
84 Kaca reyben tbl 5 mm 21,000.00 m2
85 Kalsiboard 1,20 x 2,40 m 80,500.00 lbr
86 Kalsiplank +cat 60,300.00 m1
87 Kalsiplank +cat 241,200.00 kpg
88 Kanstin ukr. ± 15 x 30 x 60 cm 54,000.00 bh
89 Karpet 402,500.00 m2
90 Kaso-kaso (5x7) cm 10,350,000.00 m3
91 Kawat beton 28,700.00 kg
92 Kawat las 25,500.00 kg
93 Kawat / kasa nyamuk 32,200.00 m2
94 Kayu kelas I 20,125,000.00 m3
95 Kayu kelas II 10,350,000.00 m3
96 Kayu kelas III 6,900,000.00 m3
97 Kayu sembarang 6,325,000.00 m3
98 Keramik putih polos ukr. 30 x 30 cm 5,200.00 bh
99 Keramik putih polos ukr. 40 x 40 cm 10,500.00 bh
100 Keramik warna/motif ukr. 25 x 25 cm (lantai) 5,000.00 bh
101 Keramik warna/motif ukr. 20 x 20 cm (lantai) 2,700.00 bh
102 Keramik warna/motif ukr. 20 x 20 cm (dinding) 2,900.00 bh
103 Keramik warna/motif ukr. 20 x 25 cm (dinding) 4,300.00 bh
104 Keramik warna/motif ukr. 25 x 40 cm (dinding) 9,700.00 bh
105 Keramik warna/motif ukr. 25 x 45 cm (dinding) 12,900.00 bh
106 Keramik warna/motif ukr. 30 x 60 cm (dinding) 32,500.00 bh
107 Keramik warna/motif ukr. 30 x 30 cm 6,200.00 bh
108 Keramik warna/motif ukr. 33 x 33 cm 8,600.00 bh
109 Keramik warna/motif bertekstur kasar ukr. 30 x 30 cm 7,800.00 bh
110 Keramik warna/motif bertekstur kasar ukr. 33 x 33 cm 8,600.00 bh
111 Keramik warna/motif ukr. 40 x 40 cm 16,200.00 bh
112 Keramik warna/motif bertekstur kasar ukr. 40 x 40 cm 16,200.00 bh
113 Keramik warna/motif ukr. 60 x 60 cm (Homogeneous Tile) 74,700.00 bh
114 Kerikil beton 230,000.00 m3
115 Kloset duduk model duoblok 3,162,500.00 unit
116 Kloset duduk lengkap reservoir/duoblok 3,680,000.00 unit
117 Kloset duduk lengkap reservoir/duoblok + jet spray 3,680,000.00 unit
118 Kloset jongkok porselin 454,000.00 bh
119 Kran air stainless Φ 3/4" atau Φ 1/2" (single) 80,500.00 bh
120 Kran air stainless Φ 3/4" atau Φ 1/2" (double) 166,700.00 bh
121 Kuas cat 2,5" 28,700.00 bh
122 Kuas cat 3" 34,500.00 bh
123 Kuas cat 4" 40,200.00 bh
124 Kunci pintu 97,700.00 bh
125 Kunci tanam antik 172,500.00 bh
126 Kunci tanam stainless steel 230,000.00 bh
127 Kunci tanam kamar mandi 46,000.00 bh
128 Lantai parquet kayu 431,200.00 m2
129 Lem bitustic 11,500.00 tube
130 Lem kayu 51,700.00 kg
131 List profil gypsum ukr. 12 s/d 15 cm 23,000.00 btg
132 List profil gypsum ukr. 12 s/d 15 cm 11,500.00 m1
133 List profil gypsum ukr. 16 s/d 20 cm 28,600.00 btg
134 List profil gypsum ukr. 16 s/d 20 cm 14,300.00 m1
135 List kayu profil 34,500.00 m1
136 Marmer dinding ukr. 100x100 cm 287,500.00 bh
137 Marmer lantai ukr. 100x100 cm 287,500.00 bh
138 Minyak bekisting 17,200.00 ltr
139 Minyak pelumas 51,700.00 ltr
140 Minyak Solar 11,200.00 ltr
141 Mortar siap pakai 7,400.00 kg
142 Mozaik ukr. 30x30 cm 34,500.00 bh
143 Paku biasa 23,000.00 kg
144 Paku seng 40,200.00 kg
145 Paku skrup 69,000.00 kg
146 Paku untuk atap bitumen 82,600.00 dus
147 Papan kayu kelas I 20,125,000.00 m3
148 Papan kayu kelas II 10,350,000.00 m3
149 Papan kayu kelas III 6,900,000.00 m3
150 Papan kayu sembarang 6,325,000.00 m3
151 Pasir beton 172,500.00 m3
152 Pasir pasang 172,500.00 m3
153 Pasir urug 172,500.00 m3
154 Paving block tipe bata 1,900.00 bh
155 Paving block tebal 6 cm (natural) 100,900.00 m2
156 Paving block tebal 8 cm (natural) 126,200.00 m2
157 Paving block tipe segi enam 2,800.00 bh
158 Paving block tebal 6 cm (warna) 97,600.00 m2
159 Paving block tebal 8 cm (warna) 127,700.00 m2
160 Pengelasan 3,100.00 cm
161 Peranca kayu sembarang 6,325,000.00 m3
162 Pipa PVC tipe AW Φ 1/2" 7,300.00 m1
163 Pipa PVC tipe AW Φ 3/4" 10,000.00 m1
164 Pipa PVC tipe AW Φ 1" 13,600.00 m1
165 Pipa PVC tipe AW Φ 1 1/2" 23,600.00 m1
166 Pipa PVC tipe AW Φ 2" 32,600.00 m1
167 Pipa PVC tipe AW Φ 2 1/2" 45,700.00 m1
168 Pipa PVC tipe AW Φ 3" 66,900.00 m1
169 Pipa PVC tipe AW Φ 4" 103,200.00 m1
170 Pipa PVC tipe AW Φ 6" 138,000.00 m1
171 Pipa PVC tipe AW Φ 8" 384,100.00 m1
172 Pipa PVC tipe AW Φ 10" 594,500.00 m1
173 Plamir 9,200.00 kg
174 Profil aluminium 46,000.00 m1
175 Rabung genteng keramik 36,800.00 bh
176 Rabung genteng metal 29,900.00 lbr
177 Rabung seng 19,500.00 lbr
178 Rabung zincalume (spandek) 82,200.00 lbr
179 Rambuncis 60,400.00 bh
180 Rangka Besi 80,100.00 btg
181 Rangka metal hollo 40.40.2 mm 46,000.00 m1
182 Reng kayu kls. I 20,125,000.00 m3
183 Reng kayu kls. II 10,350,000.00 m3
184 Reng kayu kls. III 6,900,000.00 m3
185 Reng kayu sembarang 6,325,000.00 m3
186 Residu / colter 86,200.00 ltr
187 Riol ukr. 1/2 Φ 15 cm panjang 1 m 17,200.00 bh
188 Riol ukr. 1/2 Φ 20 cm panjang 1 m 19,500.00 bh
189 Riol ukr. Φ 15 cm panjang 1 m 28,700.00 bh
190 Riol ukr. Φ 20 cm panjang 1 m 31,000.00 bh
191 Riol ukr. Φ 30 cm panjang 1 m 46,000.00 bh
192 Riol ukr. Φ 40 cm panjang 1 m 86,200.00 bh
193 Riol ukr. Φ 50 cm panjang 1 m 103,500.00 bh
194 Riol ukr. Φ 60 cm panjang 1 m 126,500.00 bh
195 Riol ukr. Φ 80 cm panjang 1 m 130,500.00 bh
196 Riol ukr. Φ 100 cm panjang 1 m 143,700.00 bh
197 Rolling door / pintu gulung bahan aluminium komplit 1,150,000.00 m2
198 Rolling door besi 1,725,000.00 m2
199 Sabun 2,600.00 kg
200 Saringan air lantai / floor drain 63,200.00 bh
201 Sealant 14,900.00 tube
202 Seal tape 5,700.00 bh
203 Semen pengunci keramik / putih / warna 28,700.00 kg
204 Semen portland (40 kg) 68,000.00 zak
205 Semen portland (40 kg) 1,700.00 kg
206 Semen portland (50 kg) 85,000.00 zak
207 Semen rasin 99,800.00 kg
208 Seng gelombang 3' X 6' BJLS 35 62,100.00 lbr
209 Seng gelombang 3' X 6' BJLS 20 ukr. 7 ft 69,500.00 lbr
210 Seng plat 59,800.00 m1
211 Seng plat BJLS 22 104,500.00 kk
212 Sewa alat las 60,000.00 jam
213 Sirtu 201,000.00 m3
214 Skrap dinding uk. 1,5" 11,500.00 bh
215 Skrup fixer 19,500.00 bh
216 Soda api 20,100.00 kg
217 Sunscreen aluminium 586,500.00 m2
218 Tanah timbun 115,000.00 m3
219 Tepung gypsum 5,700.00 kg
220 Tinner cat 57,500.00 ltr
221 Triplek tebal 4 mm 92,000.00 lbr
222 Triplek tebal 6 mm 103,500.00 lbr
223 Triplek tebal 9 mm 138,000.00 lbr
224 Triplek tebal 12 mm 207,000.00 lbr
225 Underlayer 75,500.00 m2
226 Urinoir + flusher (dewasa) 6,900,000.00 unit
227 Urinoir + flusher (anak-anak) 4,600,000.00 unit
228 Venetion blind 753,200.00 m2
229 Vertical blind 402,500.00 m2
230 Wallpaper lebar 50 cm 86,200.00 m1
231 Wallpaper lebar 100 cm 166,700.00 m1
232 Washtafel 747,500.00 bh
233 Waterdrain 86,300.00 bh
234 Water proofing 63,200.00 kg
C. HARGA SATUAN BAHAN (LS)
HARGA SATUAN
NO URAIAN SATUAN
(Rp.)
1 2 3 4
1 AC Split 1/2 PK 4,365,400.00 unit
2 AC Split 1 PK 4,703,500.00 unit
3 AC Split 1,5 PK 5,750,000.00 unit
4 AC Split 2 PK 10,522,500.00 unit
5 Aluminium composite panel + rangka 1,121,000.00 m2
6 Angker Φ 16 mm, p = 80 cm 121,500.00 bh
7 Angker Φ 19 mm, p = 80 cm 145,400.00 bh
8 Atap genteng tylux 62,500.00 lbr
9 Atap polycarbonat 186,800.00 m2
10 Atap polycarbonat tipe solar flat 250,100.00 m2
11 Bak PVC model sudut 287,500.00 bh
12 Bak PVC persegi 230,000.00 bh
13 Bataco 2,800.00 bh
14 Batu bunga / transistor ukr. 15x30 cm 17,200.00 bh
15 Batu bunga / transistor ukr. 20x20 cm 17,200.00 bh
16 Batu bunga / transistor ukr. 20x40 cm 28,700.00 bh
17 Batu bunga / transistor ukr. 20x60 cm 34,500.00 bh
18 Batu kacang warna putih, hitam, maron, hijau murai 9,200.00 kg
19 Batu kacang warna kuning, multi color, hijau campur 4,600.00 kg
20 Batu pecah Φ 1/2 - 1 cm 310,500.00 m3
21 Batu pecah Φ 1 - 2 cm 310,500.00 m3
22 Batu pecah Φ 2 - 3 cm 299,000.00 m3
23 Batu pecah Φ 3 - 5 cm 299,000.00 m3
24 Batu pecah ukr. 5 - 7 cm 299,000.00 m3
25 Batu pecah ukr. 15 - 20 cm 299,000.00 m3
26 Baut anchor Φ 5/8" 13,800.00 bh
27 Besi plat ukr. 1,2x2,4m, tbl. 1,6 mm 627,900.00 m2
28 Besi plat ukr. 1,2x2,4m, tbl. 1,8 mm 739,400.00 m2
29 Besi plat ukr. 1,2x2,4m, tbl. 2 mm 971,700.00 m2
30 Bingkai naco 5 daun + Kaca 230,000.00 set
31 Bingkai naco 8 daun + Kaca 460,000.00 set
32 Bon-Bon keramik 11,500.00 m1
33 Cat coating batu alam 92,000.00 kg
34 Cat coating batu alam + Upah 36,200.00 m2
35 Cat wash 345,000.00 kg
36 Canai dingin C75 17,500.00 kg
37 Downlight outbow 4" 63,250.00 bh
38 Downlight outbow 5" 86,250.00 bh
39 Downlight Led 12 watt 97,750.00 bh
40 Downlight Led 15 watt 109,250.00 bh
41 Downlight Led 24 watt 155,250.00 bh
42 Dinding kaca tempered tbl 10 mm komplit 1,092,500.00 m2
43 Dinding kaca tempered tbl 12 mm komplit 1,207,500.00 m2
44 Dinding lemari lapis HPL - m1
45 Elbow pipa PVC Φ 1/2" 4,600.00 bh
46 Elbow pipa PVC Φ 3/4" 5,700.00 bh
47 Elbow pipa PVC Φ 1" 6,900.00 bh
48 Elbow pipa PVC Φ 1 1/2" 11,500.00 bh
49 Elbow pipa PVC Φ 2" 16,400.00 bh
50 Elbow pipa PVC Φ 2 1/2" 25,900.00 bh
51 Elbow pipa PVC Φ 3" 43,500.00 bh
52 Elbow pipa PVC Φ 4" 80,700.00 bh
53 Elbow pipa PVC Φ 6" 204,200.00 bh
54 Elbow pipa PVC Φ 8" 462,600.00 bh
55 Elbow pipa PVC Φ 10" 618,200.00 bh
56 Exhaust fan model hisap 398,500.00 unit
57 Exhaust fan 10" 364,400.00 unit
58 Filler cat 195,500.00 kg
59 Fitting lampu biasa 18,400.00 bh
60 Fitting lampu downlight 3" 58,900.00 bh
61 Fitting lampu downlight 4" 58,900.00 bh
62 Fitting lampu downlight 5" 80,500.00 bh
63 Flincote / menie besi 57,500.00 kg
64 Gembok pintu 51,700.00 bh
65 Granit 100x100 - bh
66 Granit 60 x p (Granit Star Galaxy) 1,305,400.00 bh
67 Granit 80 x p (Granit Star Galaxy) 1,366,200.00 bh
68 Granit 90 x p (Granit Star Galaxy) 1,366,200.00 bh
69 Slab Besar (Granit Star Galaxy) 2,201,100.00 bh
70 Slab Besar (Granit Blue In the Night) 2,216,200.00 bh
71 Hand dryer 2,760,000.00 unit
72 Handrail Besi Bulat Stainless Steel 345,000.00 m1
73 Huruf acrylic 11,500.00 cm
74 Huruf stainless steel 10,300.00 cm
75 Huruf Kombinasi acrylic/stainless steel dan Lampu 28,700.00 cm
76 Instalasi listrik dan perpipaan 172,500.00 titik
77 Jerjak jendela besi beton + Cat 460,000.00 m2
78 Jerjak jendela besi hollo + Cat 402,000.00 m2
79 Jerjak / teralis pagar besi beton + Cat 690,000.00 m2
80 Jerjak / teralis pagar besi hollo + Cat 575,000.00 m2
81 Jerjak / teralis pagar besi stainless steel 1,150,000.00 m2
82 Jerjak kerangkeng besi beton + Cat 402,000.00 m2
83 Jerjak kerangkeng besi hollo + Cat 322,000.00 m2
84 Jendela Aluminium - unit
85 Jendela Aluminium + Ventilasi (JA1) - unit
86 Kaca one way + rangka 1,003,000.00 m2
87 Kanopi atap genteng metal (rangka besi hollo/bulat) 632,000.00 m2
88 Kanopi atap polycarbonat (rangka besi hollo/bulat) 632,000.00 m2
89 Kanopi atap polycarbonat tipe solar flat (rangka besi hollo/bulat) 805,000.00 m2
90 Kanopi atap spandeck (rangka besi hollo/bulat) 517,000.00 m2
91 Kawat ayam 23,000.00 m2
92 Kawat penggantung 23,500.00 m1
93 Kipas Angin Besi18" + Remote 724,500.00 unit
94 Kipas angin dinding tipe besi 690,000.00 unit
95 Kipas angin langit - langit (ceiling fan) 820,800.00 unit
96 Kisi - kisi aluminium dan kaca tempered 6 mm 632,500.00 m2
97 Kolom GRC + rangka besi hollo 190,300.00 m2
98 Lambang Pemko Stainless Steel & Acrylic (inc. Lampu) ukr. 60 cm 1,725,000.00 set
99 Lambang Pemko Stainless Steel & Acrylic (inc. Lampu) ukr. 80 cm 2,300,000.00 set
100 Lampu mercuri 500 watt + Kap 8 Fitting 166,750.00 unit
101 Lampu mercuri 1000 watt + acc 13,061,700.00 unit
102 Lampu LED 8 watt 37,200.00 bh
103 Lampu LED 10 watt 47,300.00 bh
104 Lampu LED 12 watt 57,900.00 bh
105 Lampu LED 14,5 watt 62,700.00 bh
106 Lampu LED 16 watt 63,700.00 bh
107 Lampu LED 27 watt 132,250.00 bh
108 Lampu LED 33 watt 201,250.00 bh
109 Lampu SL 9 watt 34,700.00 bh
110 Lampu SL 14 watt 41,500.00 bh
111 Lampu SL 18 watt 43,400.00 bh
112 Lampu SL 23 watt 52,200.00 bh
113 Lampu SL 40 watt 71,800.00 bh
114 Lampu TL panjang, 18 watt 16,400.00 bh
115 Lampu TL panjang, 36 watt 18,600.00 bh
116 Lampu TL + kap. TBS + ballast TL electronic (2x18 watt komplit) 293,250.00 bh
117 Lampu TL + kap. TBS + ballast TL electronic (2x36 watt komplit) 493,800.00 bh
118 Lampu TL + kap. TBS + ballast TL electronic (4x18 watt komplit) 610,400.00 bh
119 Lampu PLC 1x18 watt 443,100.00 bh
120 Lisplank GRC 60,300.00 m1
121 Listello dinding keramik uk. 6x25 34,500.00 m1
122 Listello dinding keramik uk. 5x20 4,600.00 m1
123 Lubang angin keramik 50,600.00 bh
124 MCB 2A komplit 74,200.00 unit
125 MCB 4A komplit 74,200.00 unit
126 MCB 6A komplit 62,000.00 unit
127 MCB 10A komplit 62,000.00 unit
128 MCB 16A komplit 62,000.00 unit
129 MCB 3 phasa 40 A komplit 326,100.00 unit
130 MCCB 3 phasa 100 A komplit 631,800.00 unit
131 Mesin air automatis 1,115,500.00 unit
132 Mesin air automatis PS 230 BIT 1,092,500.00 unit
133 Minyak premium 8,700.00 ltr
134 Minyak tanah/kerosine 9,200.00 ltr
135 Pagar antik batu catur, t=45 cm 48,300.00 bh
136 Pagar antik batu catur, t=60 cm 59,800.00 bh
137 Pagar besi hollo komplit + cat (gerbang) 1,092,000.00 m2
138 Pagar besi strip komplit + cat (gerbang) 1,150,000.00 m2
139 Pagar stainless steel komplit (gerbang) 1,150,000.00 m2
140 Paku exagon 5,900.00 bh
141 Paku genteng 33,300.00 kg
142 Paku sumbat 1,175.00 bh
143 Panel distribution box (25x20x10) 215,600.00 unit
144 Panel distribution box (40x30x15) 352,100.00 unit
145 Panel distribution box (60x40x25) 589,300.00 unit
146 Penutup lubang kontrol grase strape + aksesories 431,200.00 unit
147 Pintu PVC 287,500.00 unit
148 Pintu plat besi 700,000.00 m2
149 Pintu Besi hollo komplit + cat 1,035,000.00 m2
150 Pintu kaca tempered tbl 12 mm komplit 4,025,000.00 m2
151 Pintu Aluminium 2,587,500.00 unit
152 Pintu Aluminium + Ventilasi Kaca Mati (PA2) - unit
153 Pintu Aluminium KM/WC (PAT) - unit
154 Pintu Aluminium KM/WC warna coklat - unit
155 Pipa besi stainless steel Φ 1,5" 81,800.00 m1
156 Pipa besi stainless steel Φ 2" 117,000.00 m1
157 Pipa instalasi listrik 17,200.00 btg
158 Plafond akustik ukr. 60 x 120 cm + rangka 210,000.00 m2
159 Plafond Gypsum + profil + cat +rangka 143,700.00 m2
160 Plafond PVC + Rangka 299,000.00 m2
161 Plafond PVC Shunda + rangka 523,200.00 m2
162 Plat Asbes 11,700.00 lbr
163 R. Socket PVC Φ 1/2" - 3/4" 4,600.00 bh
164 R. Socket PVC Φ 3/4" - 1" 5,700.00 bh
165 R. Socket PVC Φ 1" - 1 1/2" 9,200.00 bh
166 R. Socket PVC Φ 1 1/2" - 2" 15,500.00 bh
167 R. Socket PVC Φ 2" - 2 1/2" 26,400.00 bh
168 R. Socket PVC Φ 2 1/2" - 3" 33,300.00 bh
169 R. Socket PVC Φ 3" - 4" 69,000.00 bh
170 R. Socket PVC Φ 4" - 6" 112,800.00 bh
171 R. Socket PVC Φ 6" - 8" 231,400.00 bh
172 R. Socket PVC Φ 8" - 10" 404,800.00 bh
173 Railling selasar / tangga minimalis besi hollo + cat 1,035,000.00 m2
174 Railling selasar / tangga minimalis besi hollo + kayu + cat 1,725,000.00 m2
175 Railling selasar / tangga besi stainless steel 1,380,000.00 m2
176 Rangka kanopi besi hollo ukr. 30x60 mm + reng ukr. 30x30 mm 805,000.00 m2
177 Rangka kuda - kuda atap baja ringan 126,500.00 m2
178 Rangka metal furing plafond + upah 31,600.00 m2
179 Relief garis 115,000.00 m1
180 Relief minimalis 201,000.00 m2
181 Relief tangga 57,000.00 m1
182 Saklar lampu tunggal Komplit 29,000.00 bh
183 Saklar lampu ganda Komplit 36,000.00 bh
184 Saklar lampu triple Komplit 48,000.00 bh
185 Seng gelombang 3' X 6' BJLS 20 ukr. 6 ft 59,800.00 lbr
186 Seng gelombang 3' X 6' BJLS 20 ukr. 8 ft 81,600.00 lbr
187 Seng plat untuk talang 59,800.00 m1
188 Sekat Lapis HPL 1,092,500.00 m2
189 Septictank ukr. 1x3 m, kedalaman 1,5 m dengan plat beton bertulang 5,750,000.00 unit
190 Septictank ukr. 1,5x3 m, kedalaman 1,5 m dengan plat beton bertulang 7,475,000.00 unit
191 Sewa alat molen 230,000.00 hk
192 Sewa truck concrete pump 8,050,000.00 hk
193 Skring pas panel 12 group 137,700.00 unit
194 Skring pas panel 4 group 78,700.00 unit
195 Socket PVC Φ 1/2" 3,400.00 bh
196 Socket PVC Φ 3/4" 4,600.00 bh
197 Socket PVC Φ 1" 5,700.00 bh
198 Socket PVC Φ 1 1/2" 10,300.00 bh
199 Socket PVC Φ 2" 17,200.00 bh
200 Socket PVC Φ 2 1/2" 25,300.00 bh
201 Socket PVC Φ 3" 36,800.00 bh
202 Socket PVC Φ 4" 72,400.00 bh
203 Socket PVC Φ 6" 151,800.00 bh
204 Socket PVC Φ 8" 276,300.00 bh
205 Socket PVC Φ 10" 437,600.00 bh
206 Step nossing tangga ukr. 7x40 cm 34,500.00 m1
207 Step nossing tangga ukr. 7x60 cm 40,200.00 m1
208 Stop kontak komplit 12,700.00 bh
209 Stop kontak 16 A (3300 watt) 34,600.00 bh
210 Suling - suling PVC Φ 1 1/2 " 517,500.00 bh
211 Sumur bor (pipa 1/2") 3,162,000.00 unit
212 Talang PVC 72,400.00 btg
213 Tee PVC Φ 1/2" 5,700.00 bh
214 Tee PVC Φ 3/4" 6,900.00 bh
215 Tee PVC Φ 1" 9,200.00 bh
216 Tee PVC Φ 1 1/2" 14,900.00 bh
217 Tee PVC Φ 2" 34,500.00 bh
218 Tee PVC Φ 2 1/2" 49,400.00 bh
219 Tee PVC Φ 3" 69,000.00 bh
220 Tee PVC Φ 4" 138,000.00 bh
221 Tee PVC Φ 6" 345,000.00 bh
222 Tee PVC Φ 8" 678,500.00 bh
223 Tee PVC Φ 10" 1,207,500.00 bh
224 Tempat sabun keramik 63,200.00 bh
225 Tepung dempul 5,700.00 kg
226 Tiang bendera stainless steel komplit, t=6 m 4,485,000.00 unit
227 Tie rood Φ 12 mm, p = 60 cm 9,300.00 bh
228 Tutup bak air 11,500.00 bh
229 Ventilasi kaca mati aluminium - unit
230 Washtafel komplit 920,000.00 unit
231 Water tank stainless steel kap. 1000 liter 5,750,000.00 unit
232 Water tank stainless steel kap. 2000 liter 8,050,000.00 unit

NB : Harga belum termasuk PPn

Binjai, Maret 2020

KEPALA DINAS PEKERJAAN UMUM


DAN PENATAAN RUANG KOTA BINJAI/
PENGGUNA ANGGARAN
Ir. ELVI KRISTINA SRI ULINA, M.Sc
PEMBINA UTAMA MUDA
NIP. 19641001 199003 2 005
ANALISIS HARGA SATUAN PEKERJAAN (AHSP)
TAHUN ANGGARAN 2020

PEKERJAAN PERSIAPAN
A. 2.2.1.1 1 M2 Pembuatan Pagar Sementara dari Kayu Tinggi 2 Meter
A. 2.2.1.1.a Bahan
Semen portland 5.0000 kg x Rp. 1,700.00 = Rp. 8,500.00
Pasir beton 0.0050 m3 x Rp. 172,500.00 = Rp. 862.50
Koral beton 0.0090 m3 x Rp. 287,500.00 = Rp. 2,587.50
Kayu sembarang 0.0720 m3 x Rp. 6,325,000.00 = Rp. 455,400.00
Paku biasa 0.0600 kg x Rp. 23,000.00 = Rp. 1,380.00
Residu/colter 0.4000 ltr x Rp. 86,200.00 = Rp. 34,480.00
Jumlah (1) Rp. 503,210.00
A. 2.2.1.1.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 89,080.00
Jumlah (1) + (2) Rp. 592,290.00 Rp. 592,290.00

A. 2.2.1.2 1 M2 Pembuatan Pagar Sementara dari Seng Gelombang Tinggi 2 Meter


A. 2.2.1.2.a Bahan
Semen portland 2.5000 kg x Rp. 1,700.00 = Rp. 4,250.00
Seng gelombang 7 kaki BJLS 20 1.2000 lbr x Rp. 69,500.00 = Rp. 83,400.00
Pasir beton 0.0050 m3 x Rp. 172,500.00 = Rp. 862.50
Koral beton 0.0090 m3 x Rp. 287,500.00 = Rp. 2,587.50
Kayu sembarang 0.0240 m3 x Rp. 6,325,000.00 = Rp. 151,800.00
Paku biasa 0.0600 kg x Rp. 23,000.00 = Rp. 1,380.00
Cat meni besi 0.4500 ltr x Rp. 43,700.00 = Rp. 19,665.00
Jumlah (1) Rp. 263,945.00
A. 2.2.1.2.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.4000 oh x Rp. 172,000.00 = Rp. 68,800.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 100,480.00
Jumlah (1) + (2) Rp. 364,425.00 Rp. 364,420.00

A. 2.2.1.4 1 M1 Pengukuran dan Pemasangan Bowplank


A. 2.2.1.4.a Bahan
Balok kayu sembarang 0.0120 m3 x Rp. 6,325,000.00 = Rp. 75,900.00
Paku biasa 0.0200 kg x Rp. 23,000.00 = Rp. 460.00
Papan kayu sembarang 0.0070 m3 x Rp. 6,325,000.00 = Rp. 44,275.00
Jumlah (1) Rp. 120,635.00
A. 2.2.1.4.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 152,540.00 Rp. 152,540.00

A. 2.2.1.5 1 M Pembuatan Kantor Sementara/Direksi Keet, dengan Lantai Plesteran


2

A. 2.2.1.5.a Bahan
Kayu sembarang 0.0600 m3 x Rp. 6,325,000.00 = Rp. 379,500.00
Paku biasa 0.0800 kg x Rp. 23,000.00 = Rp. 1,840.00
Besi strip 1.1000 kg x Rp. 9,700.00 = Rp. 10,670.00
Semen portland 35.0000 kg x Rp. 1,700.00 = Rp. 59,500.00
Pasir pasang 0.1500 m3 x Rp. 172,500.00 = Rp. 25,875.00
Pasir beton 0.1000 m3 x Rp. 172,500.00 = Rp. 17,250.00
Koral beton 0.1500 m3 x Rp. 287,500.00 = Rp. 43,125.00
Bata merah 30.0000 bh x Rp. 630.00 = Rp. 18,900.00
Seng plat 0.2500 lbr x Rp. 59,800.00 = Rp. 14,950.00
Jendela nako 0.2000 bh x Rp. 18,800.00 = Rp. 3,760.00
Kaca polos 0.0800 m2 x Rp. 155,000.00 = Rp. 12,400.00
Kunci tanam 0.1500 bh x Rp. 230,000.00 = Rp. 34,500.00
Triplek 4 mm 0.0600 lbr x Rp. 92,000.00 = Rp. 5,520.00
Jumlah (1) Rp. 627,790.00
A. 2.2.1.5.b Tenaga
Pekerja 2.0000 oh x Rp. 115,000.00 = Rp. 230,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Tukang batu 1.0000 oh x Rp. 172,000.00 = Rp. 172,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 819,450.00
Jumlah (1) + (2) Rp. 1,447,240.00 Rp. 1,447,240.00

A. 2.2.1.6 1 M2 Pembuatan Rumah Jaga (Konstruksi Kayu)


A. 2.2.1.6.a Bahan
Kayu sembarang 0.2760 m3 x Rp. 6,325,000.00 = Rp. 1,745,700.00
Paku biasa 0.7000 kg x Rp. 23,000.00 = Rp. 16,100.00
Seng gelombang 7 kaki BJLS 20 1.5000 lbr x Rp. 69,500.00 = Rp. 104,250.00
Jumlah (1) Rp. 1,866,050.00

Analisis Harga Satuan Pekerjaan (AHSP)


11 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 2.2.1.6.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 1.5000 oh x Rp. 172,000.00 = Rp. 258,000.00
Kepala Tukang 0.1500 oh x Rp. 207,000.00 = Rp. 31,050.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 415,400.00
Jumlah (1) + (2) Rp. 2,281,450.00 Rp. 2,281,450.00

A. 2.2.1.7 1 M Pembuatan Gudang Semen dan Paralatan


2

A. 2.2.1.7.a Bahan
Kayu sembarang 0.0700 m3 x Rp. 6,325,000.00 = Rp. 442,750.00
Paku biasa 0.3000 kg x Rp. 23,000.00 = Rp. 6,900.00
Semen portland 10.5000 kg x Rp. 1,700.00 = Rp. 17,850.00
Pasir beton 0.0300 m3 x Rp. 172,500.00 = Rp. 5,175.00
Koral beton 0.0500 m3 x Rp. 287,500.00 = Rp. 14,375.00
Seng gelombang 7 kaki BJLS 20 1.5000 lbr x Rp. 69,500.00 = Rp. 104,250.00
Seng plat 0.2500 lbr x Rp. 59,800.00 = Rp. 14,950.00
Jumlah (1) Rp. 606,250.00
A. 2.2.1.7.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 511,750.00
Jumlah (1) + (2) Rp. 1,118,000.00 Rp. 1,118,000.00

A. 2.2.1.8 1 M2 Pembuatan Bedeng Pekerja


A. 2.2.1.8.a Bahan
Kayu sembarang 0.0620 m3 x Rp. 6,325,000.00 = Rp. 392,150.00
Paku biasa 0.3000 kg x Rp. 23,000.00 = Rp. 6,900.00
Semen portland 18.0000 kg x Rp. 1,700.00 = Rp. 30,600.00
Pasir beton 0.0300 m3 x Rp. 172,500.00 = Rp. 5,175.00
Koral beton 0.0500 m3 x Rp. 287,500.00 = Rp. 14,375.00
Seng gelombang 7 kaki BJLS 20 1.5000 lbr x Rp. 69,500.00 = Rp. 104,250.00
Tripleks tbl 4 mm 1.3500 lbr x Rp. 92,000.00 = Rp. 124,200.00
Jumlah (1) Rp. 677,650.00
A. 2.2.1.8.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 511,750.00
Jumlah (1) + (2) Rp. 1,189,400.00 Rp. 1,189,400.00

A. 2.2.1.9 1 M2 Pembersihan Lapangan dan Peralatan


A. 2.2.1.9.a Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah Rp. 22,850.00 Rp. 22,850.00

A. 2.2.1.10 1 M Pembuatan Steger / Perancah dari Bambu


2

A. 2.2.1.10.a Bahan
Bambu 1.2500 btg x Rp. 23,000.00 = Rp. 28,750.00
Ijuk 0.1860 kg x Rp. 28,700.00 = Rp. 5,338.20
Jumlah (1) Rp. 34,088.20
A. 2.2.1.10.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 511,750.00
Jumlah (1) + (2) Rp. 545,838.20 Rp. 545,830.00

A. 2.2.1.11 1 Bh Pembuatan Kotak Adukan uk. 40cm x 50cm x 25cm


A. 2.2.1.11.a Bahan
Papan kayu sembarang 0.0360 m3 x Rp. 6,325,000.00 = Rp. 227,700.00
Balok kayu sembarang 0.0140 m3 x Rp. 6,325,000.00 = Rp. 88,550.00
Paku biasa 0.0800 kg x Rp. 23,000.00 = Rp. 1,840.00
Jumlah (1) Rp. 318,090.00
A. 2.2.1.11.b Tenaga
Tukang kayu 0.3000 oh x Rp. 172,000.00 = Rp. 51,600.00
Kepala Tukang 0.0300 oh x Rp. 207,000.00 = Rp. 6,210.00
Jumlah (2) Rp. 57,810.00
Jumlah (1) + (2) Rp. 375,900.00 Rp. 375,900.00

Analisis Harga Satuan Pekerjaan (AHSP)


12 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 2.2.1.13 1 M3 Pembongkaran Beton Bertulang
A. 2.2.1.13.a Tenaga
Pekerja 13.3340 oh x Rp. 115,000.00 = Rp. 1,533,410.00
Mandor 0.6660 oh x Rp. 227,000.00 = Rp. 151,182.00
Jumlah Rp. 1,684,592.00 Rp. 1,684,590.00

A. 2.2.1.14 1 M3 Pembongkaran Dinding Tembok Bata


A. 2.2.1.14.a Tenaga
Pekerja 6.6670 oh x Rp. 115,000.00 = Rp. 766,705.00
Mandor 0.3330 oh x Rp. 227,000.00 = Rp. 75,591.00
Jumlah Rp. 842,296.00 Rp. 842,290.00

A. 2.2.1.17 1 M2 Pembongkaran Rangka dan Penutup Atap


A. 2.2.1.17.a Tenaga
Pekerja 0.0700 oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0035 oh x Rp. 227,000.00 = Rp. 794.50
Jumlah (2) Rp. 28,114.50 Rp. 28,110.00

A. 2.2.1.18 1 M Pembongkaran Rangka dan Penutup Plafond


2

A. 2.2.1.18.a Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0450 oh x Rp. 172,000.00 = Rp. 7,740.00
Kepala Tukang 0.0045 oh x Rp. 207,000.00 = Rp. 931.50
Mandor 0.0075 oh x Rp. 227,000.00 = Rp. 1,702.50
Jumlah (2) Rp. 27,624.00 Rp. 27,620.00

A. 2.2.1.19 1 M Pembongkaran Lantai


2

A. 2.2.1.19.a Tenaga
Pekerja 0.1600 oh x Rp. 115,000.00 = Rp. 18,400.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 20,216.00 Rp. 20,210.00

PEKERJAAN TANAH
A. 2.3.1.1 1 M3 Penggalian Tanah Biasa Sedalam 1 M
A. 2.3.1.1.a Tenaga
Pekerja 0.7500 oh x Rp. 115,000.00 = Rp. 86,250.00
Mandor 0.0250 oh x Rp. 227,000.00 = Rp. 5,675.00
Jumlah Rp. 91,925.00 Rp. 91,920.00

A. 2.3.1.2 1 M3 Penggalian Tanah Biasa Sedalam 2 M


A. 2.3.1.2.a Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah Rp. 113,715.00 Rp. 113,710.00

A. 2.3.1.3 1 M Penggalian Tanah Biasa Sedalam 3 M


3

A. 2.3.1.3.a Tenaga
Pekerja 1.0500 oh x Rp. 115,000.00 = Rp. 120,750.00
Mandor 0.0670 oh x Rp. 227,000.00 = Rp. 15,209.00
Jumlah Rp. 135,959.00 Rp. 135,950.00

A. 2.3.1.4 1 M3 Penggalian Tanah Keras Sedalam 1 M


A. 2.3.1.4.a Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Mandor 0.0320 oh x Rp. 227,000.00 = Rp. 7,264.00
Jumlah Rp. 122,264.00 Rp. 122,260.00

A. 2.3.1.5 1 M3 Penggalian Tanah Cadas Sedalam 1 M


A. 2.3.1.5.a Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Mandor 0.0600 oh x Rp. 227,000.00 = Rp. 13,620.00
Jumlah Rp. 186,120.00 Rp. 186,120.00

A. 2.3.1.6 1 M Penggalian Tanah Lumpur Sedalam 1 M


3

A. 2.3.1.6.a Tenaga
Pekerja 1.2000 oh x Rp. 115,000.00 = Rp. 138,000.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah Rp. 148,215.00 Rp. 148,210.00

A. 2.3.1.7 1 M2 Pekerjaan Stripping Tanah Tebing Setinggi 1 M


A. 2.3.1.7.a Tenaga
Pekerja 0.0500 oh x Rp. 115,000.00 = Rp. 5,750.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah Rp. 6,885.00 Rp. 6,880.00

A. 2.3.1.8 1 M Pembuangan Tanah Sejauh 30 M


3

A. 2.3.1.8.a Tenaga
Pekerja 0.3300 oh x Rp. 115,000.00 = Rp. 37,950.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah Rp. 40,220.00 Rp. 40,220.00

Analisis Harga Satuan Pekerjaan (AHSP)


13 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 2.3.1.9 1 M3 Pengurugan Kembali Galian Tanah
A. 2.3.1.9.a Tenaga
Pekerja 0.5000 oh x Rp. 115,000.00 = Rp. 57,500.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah Rp. 68,850.00 Rp. 68,850.00

A. 2.3.1.10 1 M3 Pemadatan Tanah


A. 2.3.1.10.a Tenaga
Pekerja 0.5000 oh x Rp. 115,000.00 = Rp. 57,500.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah Rp. 68,850.00 Rp. 68,850.00

A. 2.3.1.11 1 M3 Pengurugan Pasir


A. 2.3.1.11.a Bahan
Pasir urug 1.2000 m3 x Rp. 172,500.00 = Rp. 207,000.00
Jumlah (1) Rp. 207,000.00
A. 2.3.1.11.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 36,770.00
Jumlah (1) + (2) Rp. 243,770.00 Rp. 243,770.00

A. 2.3.1.13 1 M2 Pemasangan Lapisan ijuk tebal 10 cm untuk bidang resapan


A. 2.3.1.13.a Bahan
Ijuk 6.0000 kg x Rp. 28,700.00 = Rp. 172,200.00
Jumlah (1) Rp. 172,200.00
A. 2.3.1.13.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 20,655.00
Jumlah (1) + (2) Rp. 192,855.00 Rp. 192,850.00

A. 2.3.1.14 1 M3 Pengurugan Sirtu Padat


A. 2.3.1.14.a Bahan
Sirtu 1.2000 m3 x Rp. 201,000.00 = Rp. 241,200.00
Jumlah (1) Rp. 241,200.00
A. 2.3.1.14.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Mandor 0.0250 oh x Rp. 227,000.00 = Rp. 5,675.00
Jumlah (2) Rp. 34,425.00
Jumlah (1) + (2) Rp. 275,625.00 Rp. 275,620.00

A. 2.3.1.15 1 M3 Pengurugan Tanah


A. 2.3.1.15.a Bahan
Tanah timbun 1.2000 m3 x Rp. 115,000.00 = Rp. 138,000.00
Jumlah (1) Rp. 138,000.00
A. 2.3.1.15.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 36,770.00
Jumlah (1) + (2) Rp. 174,770.00 Rp. 174,770.00

PEKERJAAN PONDASI
A. 3.2.1.1 1 M3 Pemasangan Pondasi Batu Kali Camp. 1Pc : 3Pp
A. 3.2.1.1.a Bahan
Batu kali 1.2000 m3 x Rp. 287,500.00 = Rp. 345,000.00
Semen portland 202.0000 kg x Rp. 1,700.00 = Rp. 343,400.00
Pasir pasang 0.4850 m3 x Rp. 172,500.00 = Rp. 83,662.50
Jumlah (1) Rp. 772,062.50
A. 3.2.1.1.b Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Tukang batu 0.7500 oh x Rp. 172,000.00 = Rp. 129,000.00
Kepala Tukang 0.0750 oh x Rp. 207,000.00 = Rp. 15,525.00
Mandor 0.0750 oh x Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 334,050.00
Jumlah (1) + (2) Rp. 1,106,112.50 Rp. 1,106,110.00

A. 3.2.1.2 1 M Pemasangan Pondasi Batu Kali Camp. 1Pc : 4Pp


3

A. 3.2.1.2.a Bahan
Batu kali 1.2000 m3 x Rp. 287,500.00 = Rp. 345,000.00
Semen portland 163.0000 kg x Rp. 1,700.00 = Rp. 277,100.00
Pasir pasang 0.5200 m3 x Rp. 172,500.00 = Rp. 89,700.00
Jumlah (1) Rp. 711,800.00
A. 3.2.1.2.b Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Tukang batu 0.7500 oh x Rp. 172,000.00 = Rp. 129,000.00
Kepala Tukang 0.0750 oh x Rp. 207,000.00 = Rp. 15,525.00
Mandor 0.0750 oh x Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 334,050.00
Jumlah (1) + (2) Rp. 1,045,850.00 Rp. 1,045,850.00

Analisis Harga Satuan Pekerjaan (AHSP)


14 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
3.2.1.2.1 1 M3 Pemasangan kembali Pondasi Batu Kali Camp. 1Pc : 4Pp
3.2.1.2.1.a Bahan
Semen portland 163.0000 kg x Rp. 1,700.00 = Rp. 277,100.00
Pasir pasang 0.5200 m3 x Rp. 172,500.00 = Rp. 89,700.00
Jumlah (1) Rp. 366,800.00
3.2.1.2.1.b Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Tukang batu 0.7500 oh x Rp. 172,000.00 = Rp. 129,000.00
Kepala Tukang 0.0750 oh x Rp. 207,000.00 = Rp. 15,525.00
Mandor 0.0750 oh x Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 334,050.00
Jumlah (1) + (2) Rp. 700,850.00 Rp. 700,850.00

A. 3.2.1.3 1 M3 Pemasangan Pondasi Batu Kali Camp. 1Pc : 5Pp


A. 3.2.1.3.a Bahan
Batu kali 1.2000 m3 x Rp. 287,500.00 = Rp. 345,000.00
Semen portland 136.0000 kg x Rp. 1,700.00 = Rp. 231,200.00
Pasir pasang 0.5440 m3 x Rp. 172,500.00 = Rp. 93,840.00
Jumlah (1) Rp. 670,040.00
A. 3.2.1.3.b Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Tukang batu 0.7500 oh x Rp. 172,000.00 = Rp. 129,000.00
Kepala Tukang 0.0750 oh x Rp. 207,000.00 = Rp. 15,525.00
Mandor 0.0750 oh x Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 334,050.00
Jumlah (1) + (2) Rp. 1,004,090.00 Rp. 1,004,090.00

A. 3.2.1.9 1 M3 Pemasangan Batu Kosong (Aanstamping)


A. 3.2.1.9.a Bahan
Batu kali 1.2000 m3 x Rp. 287,500.00 = Rp. 345,000.00
Pasir urug 0.4320 m3 x Rp. 172,500.00 = Rp. 74,520.00
Jumlah (1) Rp. 419,520.00
A. 3.2.1.9.b Tenaga
Pekerja 0.7800 oh x Rp. 115,000.00 = Rp. 89,700.00
Tukang batu 0.3900 oh x Rp. 172,000.00 = Rp. 67,080.00
Kepala Tukang 0.0390 oh x Rp. 207,000.00 = Rp. 8,073.00
Mandor 0.0390 oh x Rp. 227,000.00 = Rp. 8,853.00
Jumlah (2) Rp. 173,706.00
Jumlah (1) + (2) Rp. 593,226.00 Rp. 593,220.00

A. 3.2.1.10 1 M Pemasangan Pondasi Siklop, 60% Beton Camp. 1Pc : 2Pb : 3Kr dan 40% Batu Kali
3

A. 3.2.1.10.a Bahan
Batu kali 0.4800 m3 x Rp. 287,500.00 = Rp. 138,000.00
Semen portland 194.0000 kg x Rp. 1,700.00 = Rp. 329,800.00
Pasir beton 0.3120 m3 x Rp. 172,500.00 = Rp. 53,820.00
Kerikil beton 0.4680 m3 x Rp. 230,000.00 = Rp. 107,640.00
Besi beton 126.0000 kg x Rp. 10,800.00 = Rp. 1,360,800.00
Kawat beton 1.8000 kg x Rp. 28,700.00 = Rp. 51,660.00
Jumlah (1) Rp. 2,041,720.00
A. 3.2.1.10.b Tenaga
Pekerja 3.4000 oh x Rp. 115,000.00 = Rp. 391,000.00
Tukang batu 0.8500 oh x Rp. 172,000.00 = Rp. 146,200.00
Kepala Tukang 0.0850 oh x Rp. 207,000.00 = Rp. 17,595.00
Mandor 0.1700 oh x Rp. 227,000.00 = Rp. 38,590.00
Jumlah (2) Rp. 593,385.00
Jumlah (1) + (2) Rp. 2,635,105.00 Rp. 2,635,100.00

A. 3.2.1.11 1 M3 Pemasangan Pondasi Sumuran, Diameter 100 cm


A. 3.2.1.11.a Bahan
Batu kali 0.4500 m3 x Rp. 287,500.00 = Rp. 129,375.00
Semen portland 194.0000 kg x Rp. 1,700.00 = Rp. 329,800.00
Pasir beton 0.3120 m3 x Rp. 172,500.00 = Rp. 53,820.00
Kerikil beton 0.4680 m3 x Rp. 230,000.00 = Rp. 107,640.00
Jumlah (1) Rp. 620,635.00
A. 3.2.1.11.b Tenaga
Pekerja 2.4000 oh x Rp. 115,000.00 = Rp. 276,000.00
Tukang batu 0.8000 oh x Rp. 172,000.00 = Rp. 137,600.00
Kepala Tukang 0.0800 oh x Rp. 207,000.00 = Rp. 16,560.00
Mandor 0.1190 oh x Rp. 227,000.00 = Rp. 27,013.00
Jumlah (2) Rp. 457,173.00
Jumlah (1) + (2) Rp. 1,077,808.00 Rp. 1,077,800.00

A. 3.2.1.13 1 M3 Pemasangan Pondasi Batu Kali Camp. 1Pc : 4Pp (Upah)


A. 3.2.1.13.a Tenaga
Pekerja 1.5000 oh x Rp. 115,000.00 = Rp. 172,500.00
Tukang batu 0.7500 oh x Rp. 172,000.00 = Rp. 129,000.00
Kepala Tukang 0.0750 oh x Rp. 207,000.00 = Rp. 15,525.00
Mandor 0.0750 oh x Rp. 227,000.00 = Rp. 17,025.00
Jumlah Rp. 334,050.00 Rp. 334,050.00

Analisis Harga Satuan Pekerjaan (AHSP)


15 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN DINDING
A. 4.4.1.1 1 M2 Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 2Pp
A. 4.4.1.1.a Bahan
Batu bata 140.0000 bh x Rp. 630.00 = Rp. 88,200.00
Semen portland 43.5000 kg x Rp. 1,700.00 = Rp. 73,950.00
Pasir pasang 0.0800 m3 x Rp. 172,500.00 = Rp. 13,800.00
Jumlah (1) Rp. 175,950.00
A. 4.4.1.1.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 114,350.00
Jumlah (1) + (2) Rp. 290,300.00 Rp. 290,300.00

A. 4.4.1.2 1 M2 Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 3Pp
A. 4.4.1.2.a Bahan
Batu bata 140.0000 bh x Rp. 630.00 = Rp. 88,200.00
Semen portland 32.9500 kg x Rp. 1,700.00 = Rp. 56,015.00
Pasir pasang 0.0910 m3 x Rp. 172,500.00 = Rp. 15,697.50
Jumlah (1) Rp. 159,912.50
A. 4.4.1.2.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 114,350.00
Jumlah (1) + (2) Rp. 274,262.50 Rp. 274,260.00

A. 4.4.1.3 1 M Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 4Pp
2

A. 4.4.1.3.a Bahan
Batu bata 140.0000 bh x Rp. 630.00 = Rp. 88,200.00
Semen portland 26.5500 kg x Rp. 1,700.00 = Rp. 45,135.00
Pasir pasang 0.0930 m3 x Rp. 172,500.00 = Rp. 16,042.50
Jumlah (1) Rp. 149,377.50

Analisis Harga Satuan Pekerjaan (AHSP)


16 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.1.3.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 114,350.00
Jumlah (1) + (2) Rp. 263,727.50 Rp. 263,720.00

A. 4.4.1.4 1 M Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 5Pp
2

A. 4.4.1.4.a Bahan
Batu bata 140.0000 bh x Rp. 630.00 = Rp. 88,200.00
Semen portland 22.2000 kg x Rp. 1,700.00 = Rp. 37,740.00
Pasir pasang 0.1020 m3 x Rp. 172,500.00 = Rp. 17,595.00
Jumlah (1) Rp. 143,535.00
A. 4.4.1.4.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 114,350.00
Jumlah (1) + (2) Rp. 257,885.00 Rp. 257,880.00

A. 4.4.1.7 1 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 2Pp
A. 4.4.1.7.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 18.9500 kg x Rp. 1,700.00 = Rp. 32,215.00
Pasir pasang 0.0380 m3 x Rp. 172,500.00 = Rp. 6,555.00
Jumlah (1) Rp. 82,870.00
A. 4.4.1.7.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 140,045.00 Rp. 140,040.00

A. 4.4.1.8 1 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 3Pp
A. 4.4.1.8.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 14.3700 kg x Rp. 1,700.00 = Rp. 24,429.00
Pasir pasang 0.0400 m3 x Rp. 172,500.00 = Rp. 6,900.00
Jumlah (1) Rp. 75,429.00
A. 4.4.1.8.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 132,604.00 Rp. 132,600.00

A. 4.4.1.9 1 M Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 4Pp
2

A. 4.4.1.9.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 11.5000 kg x Rp. 1,700.00 = Rp. 19,550.00
Pasir pasang 0.0430 m3 x Rp. 172,500.00 = Rp. 7,417.50
Jumlah (1) Rp. 71,067.50
A. 4.4.1.9.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 128,242.50 Rp. 128,240.00

A. 4.4.1.10 1 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 5Pp
A. 4.4.1.10.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 9.6800 kg x Rp. 1,700.00 = Rp. 16,456.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Jumlah (1) Rp. 68,318.50
A. 4.4.1.10.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 125,493.50 Rp. 125,490.00

Analisis Harga Satuan Pekerjaan (AHSP)


17 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.1.22 1 M2 Pemasangan Dinding Terawang (Rooster) 12x11x24 Camp. Spesi 1Pc : 3Pp
A. 4.4.1.22.a Bahan
Batu terawang roster 30.0000 bh x Rp. 40,200.00 = Rp. 1,206,000.00
Semen portland 11.0000 kg x Rp. 1,700.00 = Rp. 18,700.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 1,230,737.50
A. 4.4.1.22.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 1,287,912.50 Rp. 1,287,910.00

A. 4.4.1.23 1 M2 Pemasangan Dinding Terawang (Rooster) 12x11x24 Camp. Spesi 1Pc : 4Pp
A. 4.4.1.23.a Bahan
Batu terawang roster 30.0000 bh x Rp. 40,200.00 = Rp. 1,206,000.00
Semen portland 11.0000 kg x Rp. 1,700.00 = Rp. 18,700.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 1,230,737.50
A. 4.4.1.23.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 1,287,912.50 Rp. 1,287,910.00

A. 4.4.1.25 1 M Pemasangan Dinding Bata Ringan tebal 7,5 cm dengan Mortar Siap Pakai
2

A. 4.4.1.25.a Bahan
Bata ringan tebal 7,5 cm 8.4000 m3 x Rp. 1,063,700.00 = Rp. 8,935,080.00
Mortar siap pakai 0.4730 kg x Rp. 7,400.00 = Rp. 3,500.20
Jumlah (1) Rp. 8,938,580.20
A. 4.4.1.25.b Tenaga
Pekerja 0.6700 oh x Rp. 115,000.00 = Rp. 77,050.00
Tukang batu 1.3000 oh x Rp. 172,000.00 = Rp. 223,600.00
Kepala Tukang 0.1300 oh x Rp. 207,000.00 = Rp. 26,910.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 328,241.00
A. 4.4.1.25.c Peralatan
Peralatan 10.0000 % x Rp. 1,063,700.00 = Rp. 106,370.00
106,370.00
Jumlah (1) + (2) + (3) Rp. 9,373,191.20 Rp. 9,373,190.00

A. 4.4.1.26 1 M2 Pemasangan Dinding Bata Ringan tebal 10 cm dengan Mortar Siap Pakai
A. 4.4.1.26.a Bahan
Bata ringan tebal 10 cm 8.4000 m3 x Rp. 1,063,700.00 = Rp. 8,935,080.00
Mortar siap pakai 0.0630 kg x Rp. 7,400.00 = Rp. 466.20
Jumlah (1) Rp. 8,935,546.20
A. 4.4.1.26.b Tenaga
Pekerja 0.6710 oh x Rp. 115,000.00 = Rp. 77,165.00
Tukang batu 1.3000 oh x Rp. 172,000.00 = Rp. 223,600.00
Kepala Tukang 0.1300 oh x Rp. 207,000.00 = Rp. 26,910.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 328,356.00
A. 4.4.1.26.c Peralatan
Peralatan 10.0000 % x Rp. 1,063,700.00 = Rp. 106,370.00
106,370.00
Jumlah (1) + (2) + (3) Rp. 9,370,272.20 Rp. 9,370,270.00

A. 4.4.1.27 1 M Pemasangan Glass Block


2

A. 4.4.1.27.a Bahan
Glass block 25.0000 bh x Rp. 34,500.00 = Rp. 862,500.00
Semen portland 11.5000 kg x Rp. 1,700.00 = Rp. 19,550.00
Pasir pasang 0.0430 m3 x Rp. 172,500.00 = Rp. 7,417.50
Jumlah (1) Rp. 889,467.50
A. 4.4.1.27.b Tenaga
Pekerja 0.0850 oh x Rp. 115,000.00 = Rp. 9,775.00
Tukang batu 0.1850 oh x Rp. 172,000.00 = Rp. 31,820.00
Kepala Tukang 0.0185 oh x Rp. 207,000.00 = Rp. 3,829.50
Mandor 0.0085 oh x Rp. 227,000.00 = Rp. 1,929.50
Jumlah (2) Rp. 47,354.00
Jumlah (1) + (2) Rp. 936,821.50 Rp. 936,820.00

PEKERJAAN PLESTERAN
A. 4.4.2.1 1 M2 Pemasangan Plesteran 1Pc : 1Pp, Tbl 15 mm
A. 4.4.2.1.a Bahan
Semen portland 15.5040 kg x Rp. 1,700.00 = Rp. 26,356.80
Pasir pasang 0.0160 m3 x Rp. 172,500.00 = Rp. 2,760.00
Jumlah (1) Rp. 29,116.80
A. 4.4.2.1.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 95,926.80 Rp. 95,920.00

A. 4.4.2.2 1 M Pemasangan Plesteran 1Pc : 2Pp, Tbl 15 mm


2

A. 4.4.2.2.a Bahan
Semen portland 10.2240 kg x Rp. 1,700.00 = Rp. 17,380.80
Pasir pasang 0.0200 m3 x Rp. 172,500.00 = Rp. 3,450.00
Jumlah (1) Rp. 20,830.80
A. 4.4.2.2.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 87,640.80 Rp. 87,640.00

Analisis Harga Satuan Pekerjaan (AHSP)


18 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.2.3 1 M2 Pemasangan Plesteran 1Pc : 3Pp, Tbl 15 mm
A. 4.4.2.3.a Bahan
Semen portland 7.7760 kg x Rp. 1,700.00 = Rp. 13,219.20
Pasir pasang 0.0230 m3 x Rp. 172,500.00 = Rp. 3,967.50
Jumlah (1) Rp. 17,186.70
A. 4.4.2.3.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 83,996.70 Rp. 83,990.00

A. 4.4.2.4 1 M2 Pemasangan Plesteran 1Pc : 4Pp, Tbl 15 mm


A. 4.4.2.4.a Bahan
Semen portland 6.2400 kg x Rp. 1,700.00 = Rp. 10,608.00
Pasir pasang 0.0240 m3 x Rp. 172,500.00 = Rp. 4,140.00
Jumlah (1) Rp. 14,748.00
A. 4.4.2.4.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 81,558.00 Rp. 81,550.00

A. 4.4.2.5 1 M2 Pemasangan Plesteran 1Pc : 5Pp, Tbl 15 mm


A. 4.4.2.5.a Bahan
Semen portland 5.1840 kg x Rp. 1,700.00 = Rp. 8,812.80
Pasir pasang 0.0260 m3 x Rp. 172,500.00 = Rp. 4,485.00
Jumlah (1) Rp. 13,297.80
A. 4.4.2.5.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 80,107.80 Rp. 80,100.00

A. 4.4.2.19 1 M Pemasangan Berapen 1SP : 5PP, Tbl. 15 mm


2

A. 4.4.2.19.a Bahan
Semen portland 5.1840 kg x Rp. 1,700.00 = Rp. 8,812.80
Pasir pasang 0.0260 m3 x Rp. 172,500.00 = Rp. 4,485.00
Jumlah (1) Rp. 13,297.80
A. 4.4.2.19.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang batu 0.0750 oh x Rp. 172,000.00 = Rp. 12,900.00
Kepala Tukang 0.0080 oh x Rp. 207,000.00 = Rp. 1,656.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 33,622.00
Jumlah (1) + (2) Rp. 46,919.80 Rp. 46,910.00

A. 4.4.2.23 1 M2 Pemasangan Plesteran Ciprat 1Pc : 2Pp


A. 4.4.2.23.a Bahan
Semen portland 4.3200 kg x Rp. 1,700.00 = Rp. 7,344.00
Pasir pasang 0.0060 m3 x Rp. 172,500.00 = Rp. 1,035.00
Jumlah (1) Rp. 8,379.00
A. 4.4.2.23.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 57,175.00
Jumlah (1) + (2) Rp. 65,554.00 Rp. 65,550.00

A. 4.4.2.24 1 M2 Pemasangan Finishing Siar Pasangan Bata Merah


A. 4.4.2.24.a Bahan
Semen portland 3.1080 kg x Rp. 1,700.00 = Rp. 5,283.60
Jumlah (1) Rp. 5,283.60
A. 4.4.2.24.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang batu 0.0750 oh x Rp. 172,000.00 = Rp. 12,900.00
Kepala Tukang 0.0080 oh x Rp. 207,000.00 = Rp. 1,656.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 33,622.00
Jumlah (1) + (2) Rp. 38,905.60 Rp. 38,900.00

Analisis Harga Satuan Pekerjaan (AHSP)


19 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.2.26 1 M2 Pemasangan Finishing Siar Pasangan Batu Kali Camp. 1Pc : 2 Pp
A. 4.4.2.26.a Bahan
Semen portland 6.3400 kg x Rp. 1,700.00 = Rp. 10,778.00
Pasir pasang 0.0120 m3 x Rp. 172,500.00 = Rp. 2,070.00
Jumlah (1) Rp. 12,848.00
A. 4.4.2.26.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 66,810.00
Jumlah (1) + (2) Rp. 79,658.00 Rp. 79,650.00

A. 4.4.2.27 1 M2 Pemasangan Acian


A. 4.4.2.27.a Bahan
Semen portland 3.2500 kg x Rp. 1,700.00 = Rp. 5,525.00
Jumlah (1) Rp. 5,525.00
A. 4.4.2.27.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 44,540.00
Jumlah (1) + (2) Rp. 50,065.00 Rp. 50,060.00

PEKERJAAN KAYU
A. 4.6.1.1 1 M3 Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. I
A. 4.6.1.1.a Bahan
Balok Kayu 1.1000 m3 x Rp. 20,125,000.00 = Rp. 22,137,500.00
Paku biasa 1.2500 kg x Rp. 23,000.00 = Rp. 28,750.00
Lem kayu 1.0000 kg x Rp. 51,700.00 = Rp. 51,700.00
Jumlah (1) Rp. 22,217,950.00
A. 4.6.1.1.b Tenaga
Pekerja 7.0000 oh x Rp. 115,000.00 = Rp. 805,000.00
Tukang kayu 21.0000 oh x Rp. 172,000.00 = Rp. 3,612,000.00
Kepala Tukang 2.1000 oh x Rp. 207,000.00 = Rp. 434,700.00
Mandor 0.3500 oh x Rp. 227,000.00 = Rp. 79,450.00
Jumlah (2) Rp. 4,931,150.00
Jumlah (1) + (2) Rp. 27,149,100.00 Rp. 27,149,100.00

A. 4.6.1.2 1 M Pembuatan dan Pemasangan Kusen Pintu dan Kusen Jendela Kayu kls. II
3

A. 4.6.1.2.a Bahan
Balok Kayu 1.2000 m3 x Rp. 10,350,000.00 = Rp. 12,420,000.00
Paku biasa 1.2500 kg x Rp. 23,000.00 = Rp. 28,750.00
Lem kayu 1.0000 kg x Rp. 51,700.00 = Rp. 51,700.00
Jumlah (1) Rp. 12,500,450.00
A. 4.6.1.2.b Tenaga
Pekerja 6.0000 oh x Rp. 115,000.00 = Rp. 690,000.00
Tukang kayu 18.0000 oh x Rp. 172,000.00 = Rp. 3,096,000.00
Kepala Tukang 1.8000 oh x Rp. 207,000.00 = Rp. 372,600.00
Mandor 0.3000 oh x Rp. 227,000.00 = Rp. 68,100.00
Jumlah (2) Rp. 4,226,700.00
Jumlah (1) + (2) Rp. 16,727,150.00 Rp. 16,727,150.00

4.6.1.2.1 1 M3 Pembuatan dan Pemasangan Kusen Pintu dan Kusen Jendela Kayu kls. III
4.6.1.2.1.a Bahan
Balok Kayu 1.2000 m3 x Rp. 6,900,000.00 = Rp. 8,280,000.00
Paku biasa 1.2500 kg x Rp. 23,000.00 = Rp. 28,750.00
Lem kayu 1.0000 kg x Rp. 51,700.00 = Rp. 51,700.00
Jumlah (1) Rp. 8,360,450.00
4.6.1.2.1.b Tenaga
Pekerja 6.0000 oh x Rp. 115,000.00 = Rp. 690,000.00
Tukang kayu 18.0000 oh x Rp. 172,000.00 = Rp. 3,096,000.00
Kepala Tukang 1.8000 oh x Rp. 207,000.00 = Rp. 372,600.00
Mandor 0.3000 oh x Rp. 227,000.00 = Rp. 68,100.00
Jumlah (2) Rp. 4,226,700.00
Jumlah (1) + (2) Rp. 12,587,150.00 Rp. 12,587,150.00

A. 4.6.1.3 1 M Pembuatan dan Pemasangan Pintu Klamp Standar, Kayu kls. II


2

A. 4.6.1.3.a Bahan
Papan Kayu 0.0400 m3 x Rp. 10,350,000.00 = Rp. 414,000.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00
Jumlah (1) Rp. 415,150.00
A. 4.6.1.3.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang kayu 1.0500 oh x Rp. 172,000.00 = Rp. 180,600.00
Kepala Tukang 0.1050 oh x Rp. 207,000.00 = Rp. 21,735.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 246,671.00
Jumlah (1) + (2) Rp. 661,821.00 Rp. 661,820.00

A. 4.6.1.4 1 M2 Pembuatan dan Pemasangan Pintu Klamp Sederhana, Kayu kls. III
A. 4.6.1.4.a Bahan
Papan Kayu 0.0400 m3 x Rp. 6,900,000.00 = Rp. 276,000.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00
Jumlah (1) Rp. 277,150.00
A. 4.6.1.4.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang kayu 1.0500 oh x Rp. 172,000.00 = Rp. 180,600.00
Kepala Tukang 0.1050 oh x Rp. 207,000.00 = Rp. 21,735.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 246,671.00
Jumlah (1) + (2) Rp. 523,821.00 Rp. 523,820.00

A. 4.6.1.5 1 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu kls. I


A. 4.6.1.5.a Bahan
Papan Kayu 0.0400 m3 x Rp. 20,125,000.00 = Rp. 805,000.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Jumlah (1) Rp. 830,850.00 ###
A. 4.6.1.5.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00

Analisis Harga Satuan Pekerjaan (AHSP)


20 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 1,535,300.00 Rp. 1,535,300.00

4.6.1.5.1 1 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu kls. II


4.6.1.5.1a Bahan
Papan Kayu 0.0400 m3 x Rp. 10,350,000.00 = Rp. 414,000.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Jumlah (1) Rp. 439,850.00
4.6.1.5.1.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 1,144,300.00 Rp. 1,144,300.00

A. 4.6.1.6 1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. I
A. 4.6.1.6.a Bahan
Papan Kayu 0.0240 m3 x Rp. 20,125,000.00 = Rp. 483,000.00
Lem kayu 0.3000 kg x Rp. 51,700.00 = Rp. 15,510.00
Jumlah (1) Rp. 498,510.00

Analisis Harga Satuan Pekerjaan (AHSP)


21 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.6.1.6.b Tenaga
Pekerja 0.8000 oh x Rp. 115,000.00 = Rp. 92,000.00
Tukang kayu 2.4000 oh x Rp. 172,000.00 = Rp. 412,800.00
Kepala Tukang 0.2400 oh x Rp. 207,000.00 = Rp. 49,680.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 563,560.00
Jumlah (1) + (2) Rp. 1,062,070.00 Rp. 1,062,070.00

4.6.1.6.1 1 M Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. II
2

4.6.1.6.1.a Bahan
Papan Kayu 0.0240 m3 x Rp. 10,350,000.00 = Rp. 248,400.00
Lem kayu 0.3000 kg x Rp. 51,700.00 = Rp. 15,510.00
Jumlah (1) Rp. 263,910.00
4.6.1.6.1.b Tenaga
Pekerja 0.8000 oh x Rp. 115,000.00 = Rp. 92,000.00
Tukang kayu 2.4000 oh x Rp. 172,000.00 = Rp. 412,800.00
Kepala Tukang 0.2400 oh x Rp. 207,000.00 = Rp. 49,680.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 563,560.00
Jumlah (1) + (2) Rp. 827,470.00 Rp. 827,470.00

A. 4.6.1.7 1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. I
A. 4.6.1.7.a Bahan
Papan Kayu 0.0640 m3 x Rp. 20,125,000.00 = Rp. 1,288,000.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Jumlah (1) Rp. 1,313,850.00
A. 4.6.1.7.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 2,018,300.00 Rp. 2,018,300.00

4.6.1.7.1 1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. II
4.6.1.7.1.a Bahan
Papan Kayu 0.0640 m3 x Rp. 10,350,000.00 = Rp. 662,400.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Jumlah (1) Rp. 688,250.00
4.6.1.7.1.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 1,392,700.00 Rp. 1,392,700.00

A. 4.6.1.8 1 M2 Pembuatan Daun Pintu Tripleks Rangkap, Rangka Kayu kls. II tertutup
A. 4.6.1.8.a Bahan
Papan Kayu 0.0250 m3 x Rp. 10,350,000.00 = Rp. 258,750.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Jumlah (1) Rp. 377,290.00
A. 4.6.1.8.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang kayu 2.1000 oh x Rp. 172,000.00 = Rp. 361,200.00
Kepala Tukang 0.2100 oh x Rp. 207,000.00 = Rp. 43,470.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 493,115.00
Jumlah (1) + (2) Rp. 870,405.00 Rp. 870,400.00

A. 4.6.1.8.1 1 M2 Pembuatan dan Pemasangan Pintu Tripleks Rangkap, Rangka Tertutup Kayu Lapis Seng
A. 4.6.1.8.1.a Bahan
Papan Kayu sembarang 0.0256 m3 x Rp. 6,325,000.00 = Rp. 161,920.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Seng plat bjls 22 8.0000 kk x Rp. 104,500.00 = Rp. 836,000.00
Jumlah (1) Rp. 1,116,460.00
A. 4.6.1.8.1.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang kayu 2.1000 oh x Rp. 172,000.00 = Rp. 361,200.00
Kepala Tukang 0.2100 oh x Rp. 207,000.00 = Rp. 43,470.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 493,115.00
Jumlah (1) + (2) Rp. 1,609,575.00 Rp. 1,609,570.00

A. 4.6.1.9 1 M Pembuatan Pintu Tripleks Rangkap, Rangka Expose Kayu kls. I


2

A. 4.6.1.9.a Bahan
Papan Kayu 0.0256 m3 x Rp. 20,125,000.00 = Rp. 515,200.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Jumlah (1) Rp. 633,740.00

Analisis Harga Satuan Pekerjaan (AHSP)


22 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.6.1.9.b Tenaga
Pekerja 0.8000 oh x Rp. 115,000.00 = Rp. 92,000.00
Tukang kayu 2.4000 oh x Rp. 172,000.00 = Rp. 412,800.00
Kepala Tukang 0.2400 oh x Rp. 207,000.00 = Rp. 49,680.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 563,560.00
Jumlah (1) + (2) Rp. 1,197,300.00 Rp. 1,197,300.00

4.6.1.9.1 1 M Pembuatan Pintu Tripleks Rangkap, Rangka Expose Kayu kls. II


2

4.6.1.9.1.a Bahan
Papan Kayu 0.0256 m3 x Rp. 10,350,000.00 = Rp. 264,960.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Triplek tebal 4 mm 1.0000 lbr x Rp. 92,000.00 = Rp. 92,000.00
Jumlah (1) Rp. 383,500.00
4.6.1.9.1.b Tenaga
Pekerja 0.8000 oh x Rp. 115,000.00 = Rp. 92,000.00
Tukang kayu 2.4000 oh x Rp. 172,000.00 = Rp. 412,800.00
Kepala Tukang 0.2400 oh x Rp. 207,000.00 = Rp. 49,680.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 563,560.00
Jumlah (1) + (2) Rp. 947,060.00 Rp. 947,060.00

A. 4.6.1.10 1 M2 Pemasangan Jalusi Kusen Kayu kls. I


A. 4.6.1.10.a Bahan
Papan Kayu 0.0600 m3 x Rp. 20,125,000.00 = Rp. 1,207,500.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 1,210,950.00
A. 4.6.1.10.b Tenaga
Pekerja 0.6700 oh x Rp. 115,000.00 = Rp. 77,050.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.3350 oh x Rp. 227,000.00 = Rp. 76,045.00
Jumlah (2) Rp. 538,495.00
Jumlah (1) + (2) Rp. 1,749,445.00 Rp. 1,749,440.00

4.6.1.10.1 1 M2 Pemasangan Jalusi Kusen Kayu kls. II


4.6.1.10.1.a Bahan
Papan Kayu 0.0600 m3 x Rp. 10,350,000.00 = Rp. 621,000.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 624,450.00
4.6.1.10.1.b Tenaga
Pekerja 0.6700 oh x Rp. 115,000.00 = Rp. 77,050.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.3350 oh x Rp. 227,000.00 = Rp. 76,045.00
Jumlah (2) Rp. 538,495.00
Jumlah (1) + (2) Rp. 1,162,945.00 Rp. 1,162,940.00

A. 4.6.1.13 1 M Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. I Bentang 6m


3

A. 4.6.1.13.a Bahan
Balok Kayu 1.1000 m3 x Rp. 20,125,000.00 = Rp. 22,137,500.00
Besi plat strip 15.0000 kg x Rp. 9,700.00 = Rp. 145,500.00
Paku biasa 5.6000 kg x Rp. 23,000.00 = Rp. 128,800.00
Jumlah (1) Rp. 22,411,800.00
A. 4.6.1.13.b Tenaga
Pekerja 4.0000 oh x Rp. 115,000.00 = Rp. 460,000.00
Tukang kayu 12.0000 oh x Rp. 172,000.00 = Rp. 2,064,000.00
Kepala Tukang 1.2000 oh x Rp. 207,000.00 = Rp. 248,400.00
Mandor 0.2000 oh x Rp. 227,000.00 = Rp. 45,400.00
Jumlah (2) Rp. 2,817,800.00
Jumlah (1) + (2) Rp. 25,229,600.00 Rp. 25,229,600.00

4.6.1.13.1 1 M3 Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. II Bentang 6m


4.6.1.13.1.a Bahan
Balok Kayu 1.1000 m3 x Rp. 10,350,000.00 = Rp. 11,385,000.00
Besi plat strip 15.0000 kg x Rp. 9,700.00 = Rp. 145,500.00
Paku biasa 5.6000 kg x Rp. 23,000.00 = Rp. 128,800.00
Jumlah (1) Rp. 11,659,300.00
4.6.1.13.1.b Tenaga
Pekerja 4.0000 oh x Rp. 115,000.00 = Rp. 460,000.00
Tukang kayu 12.0000 oh x Rp. 172,000.00 = Rp. 2,064,000.00
Kepala Tukang 1.2000 oh x Rp. 207,000.00 = Rp. 248,400.00
Mandor 0.2000 oh x Rp. 227,000.00 = Rp. 45,400.00
Jumlah (2) Rp. 2,817,800.00
Jumlah (1) + (2) Rp. 14,477,100.00 Rp. 14,477,100.00

Analisis Harga Satuan Pekerjaan (AHSP)


23 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.6.1.13.2 1 M3 Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. III Bentang 6m
4.6.1.13.2.a Bahan
Balok Kayu 1.1000 m3 x Rp. 6,900,000.00 = Rp. 7,590,000.00
Besi plat strip 15.0000 kg x Rp. 9,700.00 = Rp. 145,500.00
Paku biasa 5.6000 kg x Rp. 23,000.00 = Rp. 128,800.00
Jumlah (1) Rp. 7,864,300.00
4.6.1.13.2.b Tenaga
Pekerja 4.0000 oh x Rp. 115,000.00 = Rp. 460,000.00
Tukang kayu 12.0000 oh x Rp. 172,000.00 = Rp. 2,064,000.00
Kepala Tukang 1.2000 oh x Rp. 207,000.00 = Rp. 248,400.00
Mandor 0.2000 oh x Rp. 227,000.00 = Rp. 45,400.00
Jumlah (2) Rp. 2,817,800.00
Jumlah (1) + (2) Rp. 10,682,100.00 Rp. 10,682,100.00

A. 4.6.1.14 1 M3 Pemasangan Kontruksi Kuda-kuda Ekspose, Kayu kls. I


A. 4.6.1.14.a Bahan
Balok Kayu 1.2000 m3 x Rp. 20,125,000.00 = Rp. 24,150,000.00
Besi plat strip 15.0000 kg x Rp. 9,700.00 = Rp. 145,500.00
Paku biasa 5.6000 kg x Rp. 23,000.00 = Rp. 128,800.00
Jumlah (1) Rp. 24,424,300.00
A. 4.6.1.14.b Tenaga
Pekerja 6.7000 oh x Rp. 115,000.00 = Rp. 770,500.00
Tukang kayu 20.1000 oh x Rp. 172,000.00 = Rp. 3,457,200.00
Kepala Tukang 2.0100 oh x Rp. 207,000.00 = Rp. 416,070.00
Mandor 0.3350 oh x Rp. 227,000.00 = Rp. 76,045.00
Jumlah (2) Rp. 4,719,815.00
Jumlah (1) + (2) Rp. 29,144,115.00 Rp. 29,144,110.00

A. 4.6.1.15 1 M Pemasangan Kontruksi Gording, Kayu kls. II


3

A. 4.6.1.15.a Bahan
Balok Kayu 1.1000 m3 x Rp. 10,350,000.00 = Rp. 11,385,000.00
Besi plat strip 15.0000 kg x Rp. 9,700.00 = Rp. 145,500.00
Paku biasa 3.0000 kg x Rp. 23,000.00 = Rp. 69,000.00
Jumlah (1) Rp. 11,599,500.00
A. 4.6.1.15.b Tenaga
Pekerja 6.7000 oh x Rp. 115,000.00 = Rp. 770,500.00
Tukang kayu 20.1000 oh x Rp. 172,000.00 = Rp. 3,457,200.00
Kepala Tukang 2.0100 oh x Rp. 207,000.00 = Rp. 416,070.00
Mandor 0.3350 oh x Rp. 227,000.00 = Rp. 76,045.00
Jumlah (2) Rp. 4,719,815.00
Jumlah (1) + (2) Rp. 16,319,315.00 Rp. 16,319,310.00

A. 4.6.1.16 1 M2 Pemasangan Rangka Atap Genteng Keramik, Kayu kls. II


A. 4.6.1.16.a Bahan
Kaso-kaso (5x7) cm 0.0140 m3 x Rp. 10,350,000.00 = Rp. 144,900.00
Reng (2x3) cm 0.0360 m3 x Rp. 10,350,000.00 = Rp. 372,600.00
Paku biasa 0.2500 kg x Rp. 23,000.00 = Rp. 5,750.00
Jumlah (1) Rp. 523,250.00
A. 4.6.1.16.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 555,155.00 Rp. 555,150.00

A. 4.6.1.17 1 M2 Pemasangan Rangka Atap Genteng Beton, Kayu kls. II


A. 4.6.1.17.a Bahan
Kaso-kaso (5x7) cm 0.0140 m3 x Rp. 10,350,000.00 = Rp. 144,900.00
Reng (3x4) cm 0.0570 m3 x Rp. 10,350,000.00 = Rp. 589,950.00
Paku biasa 0.2500 kg x Rp. 23,000.00 = Rp. 5,750.00
Jumlah (1) Rp. 740,600.00
A. 4.6.1.17.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 772,505.00 Rp. 772,500.00

A. 4.6.1.18 1 M² Pemasangan Rangka Atap Sirap, Kayu kls. II


A. 4.6.1.18.a Bahan
Kayu 0.0140 m ³ × Rp. 10,350,000.00 = Rp. 144,900.00
Paku biasa 0.0570 kg × Rp. 23,000.00 = Rp. 1,311.00
Jumlah (1) Rp. 146,211.00

Analisis Harga Satuan Pekerjaan (AHSP)


24 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.6.1.18.b Tenaga
Pekerja 0.1200 Oh × Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.1200 Oh × Rp. 172,000.00 = Rp. 20,640.00
Kepala tukang 0.0120 Oh × Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0060 Oh × Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 38,286.00
Jumlah (1) + (2) Rp. 184,497.00 Rp. 184,490.00

A. 4.6.1.19 1 M² Pemasangan Rangka Langit-langit (50×100 ) cm, Kayu kls. II


A. 4.6.1.19.a Bahan
Kayu 0.0154 m ³ × Rp. 10,350,000.00 = Rp. 159,390.00
Paku biasa 0.2000 kg × Rp. 23,000.00 = Rp. 4,600.00
Jumlah (1) Rp. 163,990.00
A. 4.6.1.19.b Tenaga
Pekerja 0.1500 Oh × Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.3000 Oh × Rp. 172,000.00 = Rp. 51,600.00
Kepala tukang 0.0300 Oh × Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0750 Oh × Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 92,085.00
Jumlah (1) + (2) Rp. 256,075.00 Rp. 256,070.00

4.6.1.19.1 1 M² Pemasangan Rangka Langit-langit (50×100 ) cm, Kayu kls. III


4.6.1.19.1.a Bahan
Kayu 0.0154 m ³ × Rp. 6,900,000.00 = Rp. 106,260.00
Paku biasa 0.2000 kg × Rp. 23,000.00 = Rp. 4,600.00
Jumlah (1) Rp. 110,860.00
4.6.1.19.1.b Tenaga
Pekerja 0.1500 Oh × Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.3000 Oh × Rp. 172,000.00 = Rp. 51,600.00
Kepala tukang 0.0300 Oh × Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0750 Oh × Rp. 227,000.00 = Rp. 17,025.00
Jumlah (2) Rp. 92,085.00
Jumlah (1) + (2) Rp. 202,945.00 Rp. 202,940.00

A. 4.6.1.20 1 M² Pemasangan Rangka Kayu Langit-langit (60×60 ) cm, Kayu kls. II


A. 4.6.1.20.a Bahan
Kayu 0.0163 m ³ × Rp. 10,350,000.00 = Rp. 168,705.00
Paku biasa 0.2500 kg × Rp. 23,000.00 = Rp. 5,750.00
Jumlah (1) Rp. 174,455.00
A. 4.6.1.20.b Tenaga
Pekerja 0.2000 Oh × Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.3000 Oh × Rp. 172,000.00 = Rp. 51,600.00
Kepala tukang 0.0300 Oh × Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0100 Oh × Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 83,080.00
Jumlah (1) + (2) Rp. 257,535.00 Rp. 257,530.00

4.6.1.20.1 1 M² Pemasangan Rangka Kayu Langit-langit (60×60 ) cm, Kayu kls. III
4.6.1.20.1.a Bahan
Kayu 0.0163 m ³ × Rp. 6,900,000.00 = Rp. 112,470.00
Paku biasa 0.2500 kg × Rp. 23,000.00 = Rp. 5,750.00
Jumlah (1) Rp. 118,220.00
4.6.1.20.1.b Tenaga
Pekerja 0.2000 Oh × Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.3000 Oh × Rp. 172,000.00 = Rp. 51,600.00
Kepala tukang 0.0300 Oh × Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0100 Oh × Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 83,080.00
Jumlah (1) + (2) Rp. 201,300.00 Rp. 201,300.00

A. 4.6.1.21 1 M Pemasangan Lisplank ukr. (3x20) cm, Kayu kls. I


1

A. 4.6.1.21.a Bahan
Papan Kayu 0.0108 m3 x Rp. 20,125,000.00 = Rp. 217,350.00
Paku biasa 0.1000 kg x Rp. 23,000.00 = Rp. 2,300.00
Jumlah (1) Rp. 219,650.00 ###
A. 4.6.1.21.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 51,175.00
Jumlah (1) + (2) Rp. 270,825.00 Rp. 270,820.00

4.6.1.21.1 1 M1 Pemasangan Lisplank ukr. (3x20) cm, Kayu kls. II


4.6.1.21.1.a Bahan
Papan Kayu 0.0108 m3 x Rp. 10,350,000.00 = Rp. 111,780.00
Paku biasa 0.1000 kg x Rp. 23,000.00 = Rp. 2,300.00
Jumlah (1) Rp. 114,080.00
4.6.1.21.1.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 51,175.00
Jumlah (1) + (2) Rp. 165,255.00 Rp. 165,250.00

A. 4.6.1.22 1 M1 Pemasangan Lisplank ukr. (3x30) cm, Kayu kls. I


A. 4.6.1.22.a Bahan
Papan Kayu 0.0110 m3 x Rp. 20,125,000.00 = Rp. 221,375.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00
Jumlah (1) Rp. 222,525.00
A. 4.6.1.22.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 51,175.00
Jumlah (1) + (2) Rp. 273,700.00 Rp. 273,700.00

4.6.1.22.1 1 M Pemasangan Lisplank ukr. (3x30) cm, Kayu kls. II


1

4.6.1.22.1.a Bahan
Papan Kayu 0.0110 m3 x Rp. 10,350,000.00 = Rp. 113,850.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00

Analisis Harga Satuan Pekerjaan (AHSP)


25 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
Jumlah (1) Rp. 115,000.00
4.6.1.22.1.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 51,175.00
Jumlah (1) + (2) Rp. 166,175.00 Rp. 166,170.00

A. 4.6.1.23 1 M Pemasangan Rangka Dinding Pemisah (60x120) cm, Kayu kls. II


2

A. 4.6.1.23.a Bahan
Balok Kayu 0.0280 m3 x Rp. 10,350,000.00 = Rp. 289,800.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 293,250.00

Analisis Harga Satuan Pekerjaan (AHSP)


26 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.6.1.23.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 105,781.00
Jumlah (1) + (2) Rp. 399,031.00 Rp. 399,030.00

4.6.1.23.1 1 M Pemasangan Rangka Dinding Pemisah (60x120) cm, Kayu kls. III
2

4.6.1.23.1.a Bahan
Balok Kayu 0.0280 m3 x Rp. 6,900,000.00 = Rp. 193,200.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 196,650.00
4.6.1.23.1.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 105,781.00
Jumlah (1) + (2) Rp. 302,431.00 Rp. 302,430.00

A. 4.6.1.24 1 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Lapis Seng
A. 4.6.1.24.a Bahan
Papan Kayu 0.0400 m3 x Rp. 6,900,000.00 = Rp. 276,000.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
Seng plat bjls 22 8.0000 kk x Rp. 104,500.00 = Rp. 836,000.00
Jumlah (1) Rp. 1,137,850.00
A. 4.6.1.24.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang kayu 3.0000 oh x Rp. 172,000.00 = Rp. 516,000.00
Kepala Tukang 0.3000 oh x Rp. 207,000.00 = Rp. 62,100.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 704,450.00
Jumlah (1) + (2) Rp. 1,842,300.00 Rp. 1,842,300.00

A. 4.6.1.25 1 M2 Pemasangan Dinding Pemisah Tripleks Rangkap, Rangka Kayu kls. II


A. 4.6.1.25.a Bahan
Balok Kayu 0.0280 m3 x Rp. 10,350,000.00 = Rp. 289,800.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Triplek tbl 4 mm 0.8600 lbr x Rp. 92,000.00 = Rp. 79,120.00
Lem kayu 0.5600 kg x Rp. 51,700.00 = Rp. 28,952.00
Jumlah (1) Rp. 401,322.00
A. 4.6.1.25.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.6000 oh x Rp. 172,000.00 = Rp. 103,200.00
Kepala Tukang 0.0600 oh x Rp. 207,000.00 = Rp. 12,420.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 140,890.00
Jumlah (1) + (2) Rp. 542,212.00 Rp. 542,210.00

A. 4.6.1.26 1 M Pemasangan Dinding Lambrisering dari Papan Kayu kls. I


2

A. 4.6.1.26.a Bahan
Papan Kayu 0.0070 m3 x Rp. 20,125,000.00 = Rp. 140,875.00
Paku biasa 0.1000 kg x Rp. 23,000.00 = Rp. 2,300.00
Paku skrup 0.1500 kg x Rp. 69,000.00 = Rp. 10,350.00
Jumlah (1) Rp. 153,525.00
A. 4.6.1.26.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang kayu 1.8000 oh x Rp. 172,000.00 = Rp. 309,600.00
Kepala Tukang 0.1800 oh x Rp. 207,000.00 = Rp. 37,260.00
Mandor 0.0300 oh x Rp. 227,000.00 = Rp. 6,810.00
Jumlah (2) Rp. 422,670.00
Jumlah (1) + (2) Rp. 576,195.00 Rp. 576,190.00

A. 4.6.1.27 1 M2 Pemasangan Dinding Lambrisering dari Triplek Ukr. (120 x 240) cm


A. 4.6.1.27.a Bahan
Triplek tbl 4 mm 0.4000 lbr x Rp. 92,000.00 = Rp. 36,800.00
Paku biasa 0.0500 kg x Rp. 23,000.00 = Rp. 1,150.00
Jumlah (1) Rp. 37,950.00
A. 4.6.1.27.b Tenaga
Pekerja 0.0250 oh x Rp. 115,000.00 = Rp. 2,875.00
Tukang kayu 0.0750 oh x Rp. 172,000.00 = Rp. 12,900.00
Kepala Tukang 0.0080 oh x Rp. 207,000.00 = Rp. 1,656.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 17,658.00
Jumlah (1) + (2) Rp. 55,608.00 Rp. 55,600.00

A. 4.6.1.28 1 M Pemasangan Daun Pintu Panel Double Tripleks 9 mm Lapis HPL Rangka Kayu
2

A. 4.6.1.28.a Bahan
Kayu sembarang 0.0250 m3 x Rp. 6,325,000.00 = Rp. 158,125.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Lem kayu 0.5000 kg x Rp. 51,700.00 = Rp. 25,850.00
HPL 2.0000 m2 x Rp. 184,000.00 = Rp. 368,000.00
Tripleks 9 mm 2.0000 m2 x Rp. 138,000.00 = Rp. 276,000.00
Jumlah (1) Rp. 828,665.00

Analisis Harga Satuan Pekerjaan (AHSP)


27 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.6.1.28.b Tenaga
Pekerja 0.6000 oh x Rp. 115,000.00 = Rp. 69,000.00
Tukang kayu 2.0000 oh x Rp. 172,000.00 = Rp. 344,000.00
Kepala Tukang 0.2000 oh x Rp. 207,000.00 = Rp. 41,400.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 463,480.00
Jumlah (1) + (2) Rp. 1,292,145.00 Rp. 1,292,140.00

A. 4.6.1.29 1 M Pemasangan Dinding Pemisah Kalsiboard Rangkap, Rangka Kayu


2

A. 4.6.1.29.a Bahan
Balok Kayu sembarang 0.0280 m3 x Rp. 6,325,000.00 = Rp. 177,100.00
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Kalsiboard 1,2x2,4 m 0.8600 lbr x Rp. 80,500.00 = Rp. 69,230.00
Lem kayu 0.5600 kg x Rp. 51,700.00 = Rp. 28,952.00
Jumlah (1) Rp. 278,732.00
A. 4.6.1.29.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.6000 oh x Rp. 172,000.00 = Rp. 103,200.00
Kepala Tukang 0.0600 oh x Rp. 207,000.00 = Rp. 12,420.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 140,890.00
Jumlah (1) + (2) Rp. 419,622.00 Rp. 419,620.00

A. 4.6.1.30 1 M2 Pemasangan Dinding Pemisah GRC Rangkap, Rangka Besi


A. 4.6.1.30.a Bahan
Rangka Besi / Baja Ringan 0.8700 btg x Rp. 80,100.00 = Rp. 69,687.00
Paku skrup 0.1500 kg x Rp. 69,000.00 = Rp. 10,350.00
GRC 0.8600 lbr x Rp. 80,500.00 = Rp. 69,230.00
Jumlah (1) Rp. 149,267.00
A. 4.6.1.30.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.6000 oh x Rp. 172,000.00 = Rp. 103,200.00
Kepala Tukang 0.0600 oh x Rp. 207,000.00 = Rp. 12,420.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 140,890.00
Jumlah (1) + (2) Rp. 290,157.00 Rp. 290,150.00

A. 4.6.1.31 1 M2 Pemasangan Dinding Pemisah GRC (1 Sisi), Rangka Besi


A. 4.6.1.31.a Bahan
Rangka Besi / Baja Ringan 0.8700 btg x Rp. 80,100.00 = Rp. 69,687.00
Paku skrup 0.0750 kg x Rp. 69,000.00 = Rp. 5,175.00
GRC 0.4300 lbr x Rp. 80,500.00 = Rp. 34,615.00
Jumlah (1) Rp. 109,477.00
A. 4.6.1.31.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.6000 oh x Rp. 172,000.00 = Rp. 103,200.00
Kepala Tukang 0.0600 oh x Rp. 207,000.00 = Rp. 12,420.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 140,890.00
Jumlah (1) + (2) Rp. 250,367.00 Rp. 250,360.00

A. 4.6.1.32 1 M2 Pemasangan Dinding Pemisah GRC Tanpa Rangka


A. 4.6.1.32.a Bahan
Paku skrup 0.0750 kg x Rp. 69,000.00 = Rp. 5,175.00
GRC 0.4300 lbr x Rp. 80,500.00 = Rp. 34,615.00
Jumlah (1) Rp. 39,790.00
A. 4.6.1.32.b Tenaga
Pekerja 0.1420 oh x Rp. 115,000.00 = Rp. 16,330.00
Tukang kayu 0.4260 oh x Rp. 172,000.00 = Rp. 73,272.00
Kepala Tukang 0.0426 oh x Rp. 207,000.00 = Rp. 8,818.20
Mandor 0.0071 oh x Rp. 227,000.00 = Rp. 1,611.70
Jumlah (2) Rp. 100,031.90
Jumlah (1) + (2) Rp. 139,821.90 Rp. 139,820.00

A. 4.6.1.33 1 M2 Pemasangan Dinding Kalsiplank (Dinding Susun Sirih) 1 Sisi


A. 4.6.1.33.a Bahan
Rangka Besi / Baja Ringan 1.4400 btg x Rp. 80,100.00 = Rp. 115,344.00
Paku skrup 0.1500 kg x Rp. 69,000.00 = Rp. 10,350.00
Kalsiplank 2.1000 kpg x Rp. 241,200.00 = Rp. 506,520.00
Jumlah (1) Rp. 632,214.00
A. 4.6.1.33.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.6000 oh x Rp. 172,000.00 = Rp. 103,200.00
Kepala Tukang 0.0600 oh x Rp. 207,000.00 = Rp. 12,420.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 140,890.00
Jumlah (1) + (2) Rp. 773,104.00 Rp. 773,100.00

Analisis Harga Satuan Pekerjaan (AHSP)


28 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN BETON
A. 4.1.1.1 1 M3 Pembuatan Beton Mutu f'c, = 7,4 MPa
A. 4.1.1.1.a Bahan
Semen portland 247.0000 kg x Rp. 1,700.00 = Rp. 419,900.00
Pasir beton 0.6210 m3 x Rp. 172,500.00 = Rp. 107,122.50
Kerikil beton 0.7400 m3 x Rp. 230,000.00 = Rp. 170,200.00
Jumlah (1) Rp. 697,222.50
A. 4.1.1.1.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 958,909.50 Rp. 958,900.00

A. 4.1.1.2 1 M3 Pembuatan Beton Mutu f'c = 9,8 MPa


A. 4.1.1.2.a Bahan
Semen portland 276.0000 kg x Rp. 1,700.00 = Rp. 469,200.00
Pasir beton 0.5910 m3 x Rp. 172,500.00 = Rp. 101,947.50
Kerikil beton 0.7500 m3 x Rp. 230,000.00 = Rp. 172,500.00
Jumlah (1) Rp. 743,647.50
A. 4.1.1.2.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,005,334.50 Rp. 1,005,330.00

A. 4.1.1.3 1 M Pembuatan Beton Mutu f'c = 12,2 MPa


3

A. 4.1.1.3.a Bahan
Semen portland 299.0000 kg x Rp. 1,700.00 = Rp. 508,300.00
Pasir beton 0.5710 m3 x Rp. 172,500.00 = Rp. 98,497.50
Kerikil beton 0.7530 m3 x Rp. 230,000.00 = Rp. 173,190.00
Jumlah (1) Rp. 779,987.50
A. 4.1.1.3.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,041,674.50 Rp. 1,041,670.00

A. 4.1.1.4 1 M3 Pembuatan Lantai Kerja Beton Mutu f'c = 7,4 MPa slump (3-6) cm, w/c = 0,87
A. 4.1.1.4.a Bahan
Semen portland 230.0000 kg x Rp. 1,700.00 = Rp. 391,000.00
Pasir beton 0.6380 m3 x Rp. 172,500.00 = Rp. 110,055.00
Kerikil beton 0.7610 m3 x Rp. 230,000.00 = Rp. 175,030.00
Jumlah (1) Rp. 676,085.00
A. 4.1.1.4.b Tenaga
Pekerja 1.2000 oh x Rp. 115,000.00 = Rp. 138,000.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0600 oh x Rp. 227,000.00 = Rp. 13,620.00
Jumlah (2) Rp. 190,160.00
Jumlah (1) + (2) Rp. 866,245.00 Rp. 866,240.00

A. 4.1.1.4.1 1 M2 Pembuatan Lantai Kerja Beton Camp. 1PC :3PB : 5KR


A. 4.1.1.4.1.a Bahan
Semen portland 10.0000 kg x Rp. 1,700.00 = Rp. 17,000.00
Pasir beton 0.0260 m3 x Rp. 172,500.00 = Rp. 4,485.00
Kerikil beton 0.0440 m3 x Rp. 230,000.00 = Rp. 10,120.00
Jumlah (1) Rp. 31,605.00
A. 4.1.1.4.1b Tenaga
Pekerja 1.1500 oh x Rp. 115,000.00 = Rp. 132,250.00
Tukang batu 0.0200 oh x Rp. 172,000.00 = Rp. 3,440.00
Kepala Tukang 0.0020 oh x Rp. 207,000.00 = Rp. 414.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 137,466.00
Jumlah (1) + (2) Rp. 169,071.00 Rp. 169,070.00

A. 4.1.1.5 1 M3 Pembuatan Beton Mutu f'c = 14,5 MPa, slump (120 ±20) mm
A. 4.1.1.5.a Bahan
Semen portland 326.0000 kg x Rp. 1,700.00 = Rp. 554,200.00
Pasir beton 0.5430 m3 x Rp. 172,500.00 = Rp. 93,667.50
Kerikil beton 0.7620 m3 x Rp. 230,000.00 = Rp. 175,260.00
Jumlah (1) Rp. 823,127.50
A. 4.1.1.5.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,084,814.50 Rp. 1,084,810.00

Analisis Harga Satuan Pekerjaan (AHSP)


29 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.1.1.5.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 14,5 MPa
4.1.1.5.1.a Bahan
Ready Mix Concrete Mutu f'c = 14,5 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,012,000.00 = Rp. 1,012,000.00
Jumlah (1) Rp. 1,012,000.00
4.1.1.5.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,142,843.50 Rp. 1,142,840.00
A. 4.1.1.6 1 M3 Pembuatan Beton Mutu f'c = 16,9 MPa
A. 4.1.1.6.a Bahan
Semen portland 352.0000 kg x Rp. 1,700.00 = Rp. 598,400.00
Pasir beton 0.5220 m3 x Rp. 172,500.00 = Rp. 90,045.00
Kerikil beton 0.7640 m3 x Rp. 230,000.00 = Rp. 175,720.00
Jumlah (1) Rp. 864,165.00
A. 4.1.1.6.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,125,852.00 Rp. 1,125,850.00

Analisis Harga Satuan Pekerjaan (AHSP)


30 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.1.1.6.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 16,9 MPa
4.1.1.6.1.a Bahan
Ready Mix Concrete Mutu f'c = 16,9 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,035,000.00 = Rp. 1,035,000.00
Jumlah (1) Rp. 1,035,000.00
4.1.1.6.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,165,843.50 Rp. 1,165,840.00

A. 4.1.1.7 1 M3 Pembuatan Beton Mutu f'c = 19,3 MPa


A. 4.1.1.7.a Bahan
Semen portland 371.0000 kg x Rp. 1,700.00 = Rp. 630,700.00
Pasir beton 0.4990 m3 x Rp. 172,500.00 = Rp. 86,077.50
Kerikil beton 0.7760 m3 x Rp. 230,000.00 = Rp. 178,480.00
Jumlah (1) Rp. 895,257.50
A. 4.1.1.7.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,156,944.50 Rp. 1,156,940.00

4.1.1.7.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 19,3MPa


4.1.1.7.1.a Bahan
Ready Mix Concrete Mutu f'c = 19,3MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,058,000.00 = Rp. 1,058,000.00
Jumlah (1) Rp. 1,058,000.00
4.1.1.7.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,188,843.50 Rp. 1,188,840.00

A. 4.1.1.8 1 M Pembuatan Beton Mutu f'c = 21,7 MPa


3

A. 4.1.1.8.a Bahan
Semen portland 384.0000 kg x Rp. 1,700.00 = Rp. 652,800.00
Pasir beton 0.4940 m3 x Rp. 172,500.00 = Rp. 85,215.00
Kerikil beton 0.7700 m3 x Rp. 230,000.00 = Rp. 177,100.00
Jumlah (1) Rp. 915,115.00
A. 4.1.1.8.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,176,802.00 Rp. 1,176,800.00

4.1.1.8.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 21,7 MPa
4.1.1.8.1.a Bahan
Ready Mix Concrete Mutu f'c = 21,7 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,092,000.00 = Rp. 1,092,000.00
Jumlah (1) Rp. 1,092,000.00
4.1.1.8.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,222,843.50 Rp. 1,222,840.00

A. 4.1.1.9 1 M3 Pembuatan Beton Mutu f'c = 24,0MPa


A. 4.1.1.9.a Bahan
Semen portland 406.0000 kg x Rp. 1,700.00 = Rp. 690,200.00
Pasir beton 0.4890 m3 x Rp. 172,500.00 = Rp. 84,352.50
Kerikil beton 0.7600 m3 x Rp. 230,000.00 = Rp. 174,800.00
Jumlah (1) Rp. 949,352.50
A. 4.1.1.9.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,211,039.50 Rp. 1,211,030.00

Analisis Harga Satuan Pekerjaan (AHSP)


31 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.1.1.9.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 24,0 MPa
4.1.1.9.1.a Bahan
Ready Mix Concrete Mutu f'c = 24,0 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,115,000.00 = Rp. 1,115,000.00
Jumlah (1) Rp. 1,115,000.00
4.1.1.9.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,245,843.50 Rp. 1,245,840.00

A. 4.1.1.10 1 M3 Pembuatan Beton Mutu f'c = 26,4 MPa


A. 4.1.1.10.a Bahan
Semen portland 413.0000 kg x Rp. 1,700.00 = Rp. 702,100.00
Pasir beton 0.4860 m3 x Rp. 172,500.00 = Rp. 83,835.00
Kerikil beton 0.7560 m3 x Rp. 230,000.00 = Rp. 173,880.00
Jumlah (1) Rp. 959,815.00
A. 4.1.1.10.b Tenaga
Pekerja 1.6500 oh x Rp. 115,000.00 = Rp. 189,750.00
Tukang batu 0.2750 oh x Rp. 172,000.00 = Rp. 47,300.00
Kepala Tukang 0.0280 oh x Rp. 207,000.00 = Rp. 5,796.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 261,687.00
Jumlah (1) + (2) Rp. 1,221,502.00 Rp. 1,221,500.00

4.1.1.10.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 26,4 MPa
4.1.1.10.1.a Bahan
Ready Mix Concrete Mutu f'c = 26,4 MPa(Agg. Batu Pecah) 1.0000 m3 x Rp. 1,173,000.00 = Rp. 1,173,000.00
Jumlah (1) Rp. 1,173,000.00
4.1.1.10.1.b Tenaga
Pekerja 0.8250 oh x Rp. 115,000.00 = Rp. 94,875.00
Tukang batu 0.1375 oh x Rp. 172,000.00 = Rp. 23,650.00
Kepala Tukang 0.0140 oh x Rp. 207,000.00 = Rp. 2,898.00
Mandor 0.0415 oh x Rp. 227,000.00 = Rp. 9,420.50
Jumlah (2) Rp. 130,843.50
Jumlah (1) + (2) Rp. 1,303,843.50 Rp. 1,303,840.00

A. 4.1.1.11 1 M Pembuatan Beton Mutu f'c = 28,8 MPa


3

A. 4.1.1.11.a Bahan
Semen portland 439.0000 kg x Rp. 1,700.00 = Rp. 746,300.00
Pasir beton 0.4790 m3 x Rp. 172,500.00 = Rp. 82,627.50
Kerikil beton 0.7450 m3 x Rp. 230,000.00 = Rp. 171,350.00
Jumlah (1) Rp. 1,000,277.50
A. 4.1.1.11.b Tenaga
Pekerja 2.1000 oh x Rp. 115,000.00 = Rp. 241,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.1050 oh x Rp. 227,000.00 = Rp. 23,835.00
Jumlah (2) Rp. 332,780.00
Jumlah (1) + (2) Rp. 1,333,057.50 Rp. 1,333,050.00

4.1.1.11.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 28,8 MPa
4.1.1.11.1.a Bahan
Ready Mix Concrete Mutu f'c = 28,8 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,207,000.00 = Rp. 1,207,000.00
Jumlah (1) Rp. 1,207,000.00
4.1.1.11.1.b Tenaga
Pekerja 1.0500 oh x Rp. 115,000.00 = Rp. 120,750.00
Tukang batu 0.1750 oh x Rp. 172,000.00 = Rp. 30,100.00
Kepala Tukang 0.0175 oh x Rp. 207,000.00 = Rp. 3,622.50
Mandor 0.0525 oh x Rp. 227,000.00 = Rp. 11,917.50
Jumlah (2) Rp. 166,390.00
Jumlah (1) + (2) Rp. 1,373,390.00 Rp. 1,373,390.00

A. 4.1.1.12 1 M3 Pembuatan Beton Mutu f'c = 31,2 MPa, slump (120 ± 20) mm
A. 4.1.1.12.a Bahan
Semen portland 448.0000 kg x Rp. 1,700.00 = Rp. 761,600.00
Pasir beton 0.4760 m3 x Rp. 172,500.00 = Rp. 82,110.00
Kerikil beton 0.7410 m3 x Rp. 230,000.00 = Rp. 170,430.00
Jumlah (1) Rp. 1,014,140.00
A. 4.1.1.12.b Tenaga
Pekerja 2.1000 oh x Rp. 115,000.00 = Rp. 241,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.1050 oh x Rp. 227,000.00 = Rp. 23,835.00
Jumlah (2) Rp. 332,780.00
Jumlah (1) + (2) Rp. 1,346,920.00 Rp. 1,346,920.00

Analisis Harga Satuan Pekerjaan (AHSP)


32 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.1.1.12.1 1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 31,2 MPa
4.1.1.12.1.a Bahan
Ready Mix Concrete Mutu f'c = 31,2 MPa (Agg. Batu Pecah) 1.0000 m3 x Rp. 1,242,000.00 = Rp. 1,242,000.00
Jumlah (1) Rp. 1,242,000.00
4.1.1.12.1.b Tenaga
Pekerja 1.0500 oh x Rp. 115,000.00 = Rp. 120,750.00
Tukang batu 0.1750 oh x Rp. 172,000.00 = Rp. 30,100.00
Kepala Tukang 0.0175 oh x Rp. 207,000.00 = Rp. 3,622.50
Mandor 0.0525 oh x Rp. 227,000.00 = Rp. 11,917.50
Jumlah (2) Rp. 166,390.00
Jumlah (1) + (2) Rp. 1,408,390.00 Rp. 1,408,390.00

A. 4.1.1.17 1 Kg Pembesian dengan Besi Polos


A. 4.1.1.17.a Bahan
Besi beton polos 1.0500 kg x Rp. 10,800.00 = Rp. 11,340.00
Kawat beton 0.0150 kg x Rp. 28,700.00 = Rp. 430.50
Jumlah (1) Rp. 11,770.50
A. 4.1.1.17.b Tenaga
Pekerja 0.0070 oh x Rp. 115,000.00 = Rp. 805.00
Tukang besi 0.0070 oh x Rp. 172,000.00 = Rp. 1,204.00
Kepala Tukang 0.0007 oh x Rp. 207,000.00 = Rp. 144.90
Mandor 0.0004 oh x Rp. 227,000.00 = Rp. 90.80
Jumlah (2) Rp. 2,244.70
Jumlah (1) + (2) Rp. 14,015.20 Rp. 14,010.00

A. 4.1.1.17.1 1 Kg Pembesian dengan Besi Ulir


A. 4.1.1.17.1.a Bahan
Besi beton ulir 1.0500 kg x Rp. 13,200.00 = Rp. 13,860.00
Kawat beton 0.0150 kg x Rp. 28,700.00 = Rp. 430.50
Jumlah (1) Rp. 14,290.50
A. 4.1.1.17.1.b Tenaga
Pekerja 0.0070 oh x Rp. 115,000.00 = Rp. 805.00
Tukang besi 0.0070 oh x Rp. 172,000.00 = Rp. 1,204.00
Kepala Tukang 0.0007 oh x Rp. 207,000.00 = Rp. 144.90
Mandor 0.0004 oh x Rp. 227,000.00 = Rp. 90.80
Jumlah (2) Rp. 2,244.70
Jumlah (1) + (2) Rp. 16,535.20 Rp. 16,530.00

A. 4.1.1.19 1 Kg Pemasangan Jaring Kawat Baja/Wire Mesh


A. 4.1.1.19.a Bahan
Jaring kawat baja dilas 1.0200 kg x Rp. 29,400.00 = Rp. 29,988.00
Kawat beton 0.0050 kg x Rp. 28,700.00 = Rp. 143.50
Jumlah (1) Rp. 30,131.50
A. 4.1.1.19.b Tenaga
Pekerja 0.0025 oh x Rp. 115,000.00 = Rp. 287.50
Tukang besi 0.0025 oh x Rp. 172,000.00 = Rp. 430.00
Kepala Tukang 0.0025 oh x Rp. 207,000.00 = Rp. 517.50
Mandor 0.0001 oh x Rp. 227,000.00 = Rp. 22.70
Jumlah (2) Rp. 1,257.70
Jumlah (1) + (2) Rp. 31,389.20 Rp. 31,380.00

A. 4.1.1.20 1 M2 Pemasangan Bekisting untuk Pondasi


A. 4.1.1.20.a Bahan
Kayu sembarang 0.0400 m3 x Rp. 6,325,000.00 = Rp. 253,000.00
Paku biasa 0.3000 kg x Rp. 23,000.00 = Rp. 6,900.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Jumlah (1) Rp. 261,620.00
A. 4.1.1.20.b Tenaga
Pekerja 0.5200 oh x Rp. 115,000.00 = Rp. 59,800.00
Tukang kayu 0.2600 oh x Rp. 172,000.00 = Rp. 44,720.00
Kepala Tukang 0.0260 oh x Rp. 207,000.00 = Rp. 5,382.00
Mandor 0.0260 oh x Rp. 227,000.00 = Rp. 5,902.00
Jumlah (2) Rp. 115,804.00
Jumlah (1) + (2) Rp. 377,424.00 Rp. 377,420.00

A. 4.1.1.21 1 M2 Pemasangan Bekisting untuk Sloof


A. 4.1.1.21.a Bahan
Kayu sembarang 0.0225 m3 x Rp. 6,325,000.00 = Rp. 142,312.50
Paku biasa 0.1500 kg x Rp. 23,000.00 = Rp. 3,450.00
Minyak bekisting 0.0500 ltr x Rp. 17,200.00 = Rp. 860.00
Jumlah (1) Rp. 146,622.50
A. 4.1.1.21.b Tenaga
Pekerja 0.5200 oh x Rp. 115,000.00 = Rp. 59,800.00
Tukang kayu 0.2600 oh x Rp. 172,000.00 = Rp. 44,720.00
Kepala Tukang 0.0260 oh x Rp. 207,000.00 = Rp. 5,382.00
Mandor 0.0260 oh x Rp. 227,000.00 = Rp. 5,902.00
Jumlah (2) Rp. 115,804.00
Jumlah (1) + (2) Rp. 262,426.50 Rp. 262,420.00

Analisis Harga Satuan Pekerjaan (AHSP)


33 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.1.1.21.1 1 M2 Pemasangan kembali Bekisting untuk Sloof
4.1.1.21.1.a Bahan
Paku biasa 0.3000 kg x Rp. 23,000.00 = Rp. 6,900.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Jumlah (1) Rp. 8,620.00
4.1.1.21.1.b Tenaga
Pekerja 0.5200 oh x Rp. 115,000.00 = Rp. 59,800.00
Tukang kayu 0.2600 oh x Rp. 172,000.00 = Rp. 44,720.00
Kepala Tukang 0.0260 oh x Rp. 207,000.00 = Rp. 5,382.00
Mandor 0.0260 oh x Rp. 227,000.00 = Rp. 5,902.00
Jumlah (2) Rp. 115,804.00
Jumlah (1) + (2) Rp. 124,424.00 Rp. 124,420.00

A. 4.1.1.22 1 M2 Pemasangan Bekisting untuk Kolom


A. 4.1.1.22.a Bahan
Kayu sembarang 0.0200 m3 x Rp. 6,325,000.00 = Rp. 126,500.00
Paku biasa 0.2000 kg x Rp. 23,000.00 = Rp. 4,600.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Balok kayu sembarang 0.0075 m3 x Rp. 6,325,000.00 = Rp. 47,437.50
Tripleks tebal 9 mm 0.1750 lbr x Rp. 138,000.00 = Rp. 24,150.00
Jumlah (1) Rp. 204,407.50
A. 4.1.1.22.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 351,389.50 Rp. 351,380.00

4.1.1.22.1 1 M Pemasangan kembali Bekisting untuk Kolom


2

4.1.1.22.1.a Bahan
Paku biasa 0.4000 kg x Rp. 23,000.00 = Rp. 9,200.00
Minyak bekisting 0.2000 ltr x Rp. 17,200.00 = Rp. 3,440.00
Jumlah (1) Rp. 12,640.00
A. 4.1.1.22.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 159,622.00 Rp. 159,620.00

A. 4.1.1.23 1 M2 Pemasangan Bekisting untuk Balok


A. 4.1.1.23.a Bahan
Kayu sembarang 0.0200 m3 x Rp. 6,325,000.00 = Rp. 126,500.00
Paku biasa 0.2000 kg x Rp. 23,000.00 = Rp. 4,600.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Balok kayu sembarang 0.0090 m3 x Rp. 6,325,000.00 = Rp. 56,925.00
Tripleks tebal 9 mm 0.1750 lbr x Rp. 138,000.00 = Rp. 24,150.00
Jumlah (1) Rp. 213,895.00
A. 4.1.1.23.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 360,877.00 Rp. 360,870.00

4.1.1.23.1 1 M Pemasangan kembali Bekisting untuk Balok


2

4.1.1.23.1.a Bahan
Paku biasa 0.4000 kg x Rp. 23,000.00 = Rp. 9,200.00
Minyak bekisting 0.2000 ltr x Rp. 17,200.00 = Rp. 3,440.00
Jumlah (1) Rp. 12,640.00
4.1.1.23.1.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 159,622.00 Rp. 159,620.00

A. 4.1.1.24 1 M2 Pemasangan Bekisting untuk Plat Lantai


A. 4.1.1.24.a Bahan
Kayu sembarang 0.0400 m3 x Rp. 6,325,000.00 = Rp. 253,000.00
Paku biasa 0.4000 kg x Rp. 23,000.00 = Rp. 9,200.00
Minyak bekisting 0.2000 ltr x Rp. 17,200.00 = Rp. 3,440.00
Balok kayu sembarang 0.0150 m3 x Rp. 6,325,000.00 = Rp. 94,875.00
Tripleks tebal 9 mm 0.3500 lbr x Rp. 138,000.00 = Rp. 48,300.00
Jumlah (1) Rp. 408,815.00

Analisis Harga Satuan Pekerjaan (AHSP)


34 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.1.1.24.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 555,797.00 Rp. 555,790.00

A. 4.1.1.24.1 1 M Pemasangan Bekisting untuk Plat Duiker


2

A. 4.1.1.24.1.a Bahan
Papan Kayu sembarang 0.0200 m3 x Rp. 6,325,000.00 = Rp. 126,500.00
Paku biasa 0.2000 kg x Rp. 23,000.00 = Rp. 4,600.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Balok kayu sembarang 0.0075 m3 x Rp. 6,325,000.00 = Rp. 47,437.50
Tripleks tebal 6 mm 0.1750 lbr x Rp. 103,500.00 = Rp. 18,112.50
Jumlah (1) Rp. 198,370.00
A. 4.1.1.24.1.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 345,352.00 Rp. 345,350.00

A. 4.1.1.25 1 M2 Pemasangan Bekisting untuk Dinding


A. 4.1.1.25.a Bahan
Kayu sembarang 0.0150 m3 x Rp. 6,325,000.00 = Rp. 94,875.00
Paku biasa 0.2000 kg x Rp. 23,000.00 = Rp. 4,600.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Balok kayu sembarang 0.0100 m3 x Rp. 6,325,000.00 = Rp. 63,250.00
Tripleks tebal 9 mm 0.1750 lbr x Rp. 138,000.00 = Rp. 24,150.00
Jumlah (1) Rp. 188,595.00
A. 4.1.1.25.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 335,577.00 Rp. 335,570.00

Analisis Harga Satuan Pekerjaan (AHSP)


35 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.1.1.25.1 1 M2 Pemasangan kembali Bekisting untuk Dinding
4.1.1.25.1.a Bahan
Paku biasa 0.4000 kg x Rp. 23,000.00 = Rp. 9,200.00
Minyak bekisting 0.2000 ltr x Rp. 17,200.00 = Rp. 3,440.00
Jumlah (1) Rp. 12,640.00
4.1.1.25.1.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 159,622.00 Rp. 159,620.00

A. 4.1.1.26 1 M2 Pemasangan Bekisting untuk Tangga


A. 4.1.1.26.a Bahan
Kayu sembarang 0.0300 m3 x Rp. 6,325,000.00 = Rp. 189,750.00
Paku biasa 0.4000 kg x Rp. 23,000.00 = Rp. 9,200.00
Minyak bekisting 0.1500 ltr x Rp. 17,200.00 = Rp. 2,580.00
Balok kayu sembarang 0.0150 m3 x Rp. 6,325,000.00 = Rp. 94,875.00
Tripleks tebal 9 mm 0.3500 lbr x Rp. 138,000.00 = Rp. 48,300.00
Jumlah (1) Rp. 344,705.00
A. 4.1.1.26.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 491,687.00 Rp. 491,680.00

A. 4.1.1.27 1 M Pemasangan Jembatan untuk Pengecoran Beton


2

A. 4.1.1.27.a Bahan
Papan Kayu sembarang 0.0264 m3 x Rp. 6,325,000.00 = Rp. 166,980.00
Paku biasa 0.6000 kg x Rp. 23,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 180,780.00
A. 4.1.1.27.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0500 oh x Rp. 172,000.00 = Rp. 8,600.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 28,701.00
Jumlah (1) + (2) Rp. 209,481.00 Rp. 209,480.00

A. 4.1.1.35 1 M1 Pembuatan Kolom Praktis Beton Bertulang (11x11) cm


A. 4.1.1.35.a Bahan
Kayu sembarang 0.0020 m3 x Rp. 6,325,000.00 = Rp. 12,650.00
Paku biasa 0.0100 kg x Rp. 23,000.00 = Rp. 230.00
Besi beton polos 3.0000 kg x Rp. 10,800.00 = Rp. 32,400.00
Kawat beton 0.4500 kg x Rp. 28,700.00 = Rp. 12,915.00
Semen portland 4.0000 kg x Rp. 1,700.00 = Rp. 6,800.00
Pasir beton 0.0060 m3 x Rp. 172,500.00 = Rp. 1,035.00
Kerikil beton 0.0090 m3 x Rp. 230,000.00 = Rp. 2,070.00
Jumlah (1) Rp. 68,100.00
A. 4.1.1.35.b Tenaga
Pekerja 0.1800 oh x Rp. 115,000.00 = Rp. 20,700.00
Tukang batu 0.0200 oh x Rp. 172,000.00 = Rp. 3,440.00
Tukang kayu 0.0200 oh x Rp. 172,000.00 = Rp. 3,440.00
Tukang besi 0.0200 oh x Rp. 172,000.00 = Rp. 3,440.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0090 oh x Rp. 227,000.00 = Rp. 2,043.00
Jumlah (2) Rp. 34,305.00
Jumlah (1) + (2) Rp. 102,405.00 Rp. 102,400.00

A. 4.1.1.36 1 M1 Pembuatan Ring Balok Beton Bertulang (10x15) cm


A. 4.1.1.36.a Bahan
Kayu sembarang 0.0030 m3 x Rp. 6,325,000.00 = Rp. 18,975.00
Paku biasa 0.0200 kg x Rp. 23,000.00 = Rp. 460.00
Besi beton polos 3.6000 kg x Rp. 10,800.00 = Rp. 38,880.00
Kawat beton 0.0500 kg x Rp. 28,700.00 = Rp. 1,435.00
Semen portland 5.5000 kg x Rp. 1,700.00 = Rp. 9,350.00
Pasir beton 0.0090 m3 x Rp. 172,500.00 = Rp. 1,552.50
Kerikil beton 0.0150 m3 x Rp. 230,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 74,102.50
A. 4.1.1.36.b Tenaga
Pekerja 0.2970 oh x Rp. 115,000.00 = Rp. 34,155.00
Tukang batu 0.0330 oh x Rp. 172,000.00 = Rp. 5,676.00
Tukang kayu 0.0330 oh x Rp. 172,000.00 = Rp. 5,676.00
Tukang besi 0.0330 oh x Rp. 172,000.00 = Rp. 5,676.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 56,658.00
Jumlah (1) + (2) Rp. 130,760.50 Rp. 130,760.00

Analisis Harga Satuan Pekerjaan (AHSP)


36 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.1.1.37 1 M2 Pemasangan Bekisting untuk Dinding Drainase
A. 4.1.1.37.a Bahan
Kayu sembarang 0.0150 m3 x Rp. 6,325,000.00 = Rp. 94,875.00
Paku biasa 0.2000 kg x Rp. 23,000.00 = Rp. 4,600.00
Minyak bekisting 0.1000 ltr x Rp. 17,200.00 = Rp. 1,720.00
Balok kayu sembarang 0.0100 m3 x Rp. 6,325,000.00 = Rp. 63,250.00
Tripleks tebal 6 mm 0.1750 lbr x Rp. 103,500.00 = Rp. 18,112.50
Jumlah (1) Rp. 182,557.50
A. 4.1.1.37.b Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah (2) Rp. 146,982.00
Jumlah (1) + (2) Rp. 329,539.50 Rp. 329,530.00

4.1.1.37.1 1 M2 Pemasangan Bekisting untuk Dinding Drainase (Upah)


4.1.1.37.1.a Tenaga
Pekerja 0.6600 oh x Rp. 115,000.00 = Rp. 75,900.00
Tukang kayu 0.3300 oh x Rp. 172,000.00 = Rp. 56,760.00
Kepala Tukang 0.0330 oh x Rp. 207,000.00 = Rp. 6,831.00
Mandor 0.0330 oh x Rp. 227,000.00 = Rp. 7,491.00
Jumlah Rp. 146,982.00 Rp. 146,980.00

PEKERJAAN PENUTUP ATAP


A. 4.5.2.32 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,25 mm
A. 4.5.2.32.a Bahan
Atap genteng metal 1.3000 lbr x Rp. 51,500.00 = Rp. 66,950.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 80,750.00
A. 4.5.2.32.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 123,247.00 Rp. 123,240.00

A. 4.5.2.32.1 1 M Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,30 mm
2

A. 4.5.2.32.1.a Bahan
Atap genteng metal tebal 0,30 mm 1.3000 lbr x Rp. 62,000.00 = Rp. 80,600.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 94,400.00
A. 4.5.2.32.1.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 136,897.00 Rp. 136,890.00

A. 4.5.2.32.2 1 M2 Pemasangan Genteng Metal ukr. 800x100 Atap Pelana Tebal 0,35 mm
A. 4.5.2.32.2.a Bahan
Atap genteng metal tebal 0,35 mm 1.3000 lbr x Rp. 74,700.00 = Rp. 97,110.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 110,910.00
A. 4.5.2.32.2.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 153,407.00 Rp. 153,400.00

A. 4.5.2.32.3 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,40 mm
A. 4.5.2.32.3.a Bahan
Atap genteng metal tebal 0,40 mm 1.3000 lbr x Rp. 85,200.00 = Rp. 110,760.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 124,560.00
A. 4.5.2.32.3.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 167,057.00 Rp. 167,050.00

Analisis Harga Satuan Pekerjaan (AHSP)


37 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.5.2.33 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,25 mm
A. 4.5.2.33.a Bahan
Atap genteng metal 2.0000 lbr x Rp. 51,500.00 = Rp. 103,000.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 116,800.00
A. 4.5.2.33.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 159,297.00 Rp. 159,290.00

A. 4.5.2.33.1 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,30 mm
A. 4.5.2.33.1.a Bahan
Atap genteng metal 2.0000 lbr x Rp. 62,000.00 = Rp. 124,000.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 137,800.00
A. 4.5.2.33.1.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 180,297.00 Rp. 180,290.00

A. 4.5.2.33.2 1 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,35 mm
A. 4.5.2.33.2.a Bahan
Atap genteng metal 2.0000 lbr x Rp. 74,700.00 = Rp. 149,400.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 163,200.00
A. 4.5.2.33.2.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 205,697.00 Rp. 205,690.00

A. 4.5.2.33.3 1 M Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,40 mm
2

A. 4.5.2.33.3.a Bahan
Atap genteng metal 2.0000 lbr x Rp. 85,200.00 = Rp. 170,400.00
Paku skrup 0.2000 kg x Rp. 69,000.00 = Rp. 13,800.00
Jumlah (1) Rp. 184,200.00
A. 4.5.2.33.3.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 42,497.00
Jumlah (1) + (2) Rp. 226,697.00 Rp. 226,690.00

A. 4.5.2.37 1 M1 Pemasangan Nok/Rabung Genteng Metal


A. 4.5.2.37.a Bahan
Nok/rabung genteng metal 1.1000 lbr x Rp. 29,900.00 = Rp. 32,890.00
Paku skrup 0.0500 kg x Rp. 69,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 36,340.00
A. 4.5.2.37.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang kayu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0130 oh x Rp. 227,000.00 = Rp. 2,951.00
Jumlah (2) Rp. 60,606.00
Jumlah (1) + (2) Rp. 96,946.00 Rp. 96,940.00

A. 4.5.2.39 1 M2 Pemasangan Atap Seng Gelombang


A. 4.5.2.39.a Bahan
Seng gelombang 3'x6' BJLS 35 0.7000 lbr x Rp. 62,100.00 = Rp. 43,470.00
Paku seng 0.0200 kg x Rp. 40,200.00 = Rp. 804.00
Jumlah (1) Rp. 44,274.00
A. 4.5.2.39.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 26,724.00
Jumlah (1) + (2) Rp. 70,998.00 Rp. 70,990.00

A. 4.5.2.40 1 M Pemasangan Nok/Rabung Seng


1

A. 4.5.2.40.a Bahan
Nok/rabung seng 0.3000 lbr x Rp. 19,500.00 = Rp. 5,850.00
Paku seng 0.0400 kg x Rp. 40,200.00 = Rp. 1,608.00
Jumlah (1) Rp. 7,458.00
A. 4.5.2.40.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0700 oh x Rp. 172,000.00 = Rp. 12,040.00
Kepala Tukang 0.0070 oh x Rp. 207,000.00 = Rp. 1,449.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 32,101.00
Jumlah (1) + (2) Rp. 39,559.00 Rp. 39,550.00

Analisis Harga Satuan Pekerjaan (AHSP)


38 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.5.2.43 1 M2 Pemasangan Aluminium Foil / Sisalation
A. 4.5.2.43.a Bahan
Aluminium foil / sisalation 1.0500 m2 x Rp. 11,700.00 = Rp. 12,285.00
Jumlah (1) Rp. 12,285.00
A. 4.5.2.43.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0500 oh x Rp. 172,000.00 = Rp. 8,600.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 28,701.00
Jumlah (1) + (2) Rp. 40,986.00 Rp. 40,980.00

A. 4.5.2.45 1 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,25 mm


A. 4.5.2.45.a Bahan
Atap zincalume tebal 0,25 mm 1.2820 m1 x Rp. 39,100.00 = Rp. 50,126.20
Paku skrup 0.0200 kg x Rp. 69,000.00 = Rp. 1,380.00
Jumlah (1) Rp. 51,506.20
A. 4.5.2.45.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 26,724.00
Jumlah (1) + (2) Rp. 78,230.20 Rp. 78,230.00

Analisis Harga Satuan Pekerjaan (AHSP)


39 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.5.2.45.1 1 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,30 mm
A. 4.5.2.45.1.a Bahan
Atap zincalume tebal 0,30 mm 1.2820 m1 x Rp. 46,000.00 = Rp. 58,972.00
Paku skrup 0.0200 kg x Rp. 69,000.00 = Rp. 1,380.00
Jumlah (1) Rp. 60,352.00
A. 4.5.2.45.1.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 26,724.00
Jumlah (1) + (2) Rp. 87,076.00 Rp. 87,070.00

A. 4.5.2.45.2 1 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,35 mm


A. 4.5.2.45.2.a Bahan
Atap zincalume tebal 0,35 mm 1.2820 m1 x Rp. 57,500.00 = Rp. 73,715.00
Paku skrup 0.0200 kg x Rp. 69,000.00 = Rp. 1,380.00
Jumlah (1) Rp. 75,095.00
A. 4.5.2.45.2.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 26,724.00
Jumlah (1) + (2) Rp. 101,819.00 Rp. 101,810.00

A. 4.5.2.45.3 1 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,40 mm


A. 4.5.2.45.3.a Bahan
Atap zincalume tebal 0,40 mm 1.2820 m1 x Rp. 72,400.00 = Rp. 92,816.80
Paku skrup 0.0200 kg x Rp. 69,000.00 = Rp. 1,380.00
Jumlah (1) Rp. 94,196.80
A. 4.5.2.45.3.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 26,724.00
Jumlah (1) + (2) Rp. 120,920.80 Rp. 120,920.00

A. 4.5.2.46 1 M Pemasangan Nok/Rabung Zincalume (Spandeck)


1

A. 4.5.2.46.a Bahan
Nok/Rabung zincalume 1.1000 lbr x Rp. 82,200.00 = Rp. 90,420.00
Paku skrup 0.0200 kg x Rp. 69,000.00 = Rp. 1,380.00
Jumlah (1) Rp. 91,800.00
A. 4.5.2.46.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang kayu 0.0700 oh x Rp. 172,000.00 = Rp. 12,040.00
Kepala Tukang 0.0080 oh x Rp. 207,000.00 = Rp. 1,656.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 32,308.00
Jumlah (1) + (2) Rp. 124,108.00 Rp. 124,100.00

A. 4.5.2.47 1 M2 Pemasangan Atap Genteng Keramik


A. 4.5.2.47.a Bahan
Genteng keramik 14.5000 bh x Rp. 22,400.00 = Rp. 324,800.00
Jumlah (1) Rp. 324,800.00
A. 4.5.2.47.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 44,540.00
Jumlah (1) + (2) Rp. 369,340.00 Rp. 369,340.00

A. 4.5.2.48 1 M1 Pemasangan Rabung Genteng Keramik


A. 4.5.2.48.a Bahan
Rabung genteng keramik 3.5000 bh x Rp. 36,800.00 = Rp. 128,800.00
Semen portland 18.1500 kg x Rp. 1,700.00 = Rp. 30,855.00
Pasir pasang 0.0320 m3 x Rp. 172,500.00 = Rp. 5,520.00
Jumlah (1) Rp. 165,175.00
A. 4.5.2.48.b Tenaga
Pekerja 0.0400 oh x Rp. 115,000.00 = Rp. 4,600.00
Tukang 0.0200 oh x Rp. 172,000.00 = Rp. 3,440.00
Kepala Tukang 0.0020 oh x Rp. 207,000.00 = Rp. 414.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 8,908.00
Jumlah (1) + (2) Rp. 174,083.00 Rp. 174,080.00

Analisis Harga Satuan Pekerjaan (AHSP)


40 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.5.2.49 1 M2 Pemasangan Atap Single Bituminius
A. 4.5.2.49.a Bahan
Atap Bitumen 1.0000 m2 x Rp. 207,000.00 = Rp. 207,000.00
Paku untuk atap bitumen 0.0400 dus x Rp. 82,600.00 = Rp. 3,304.00
Lem Bitustic 0.0100 tube x Rp. 11,500.00 = Rp. 115.00
Underlayer 1.0000 m2 x Rp. 75,500.00 = Rp. 75,500.00
Triplek tbl 9 mm 0.3472 lbr x Rp. 138,000.00 = Rp. 47,913.60
Jumlah (1) Rp. 333,832.60
A. 4.5.2.49.b Tenaga
Pekerja 0.4500 oh x Rp. 115,000.00 = Rp. 51,750.00
Tukang kayu 0.2250 oh x Rp. 172,000.00 = Rp. 38,700.00
Kepala Tukang 0.0225 oh x Rp. 207,000.00 = Rp. 4,657.50
Mandor 0.0225 oh x Rp. 227,000.00 = Rp. 5,107.50
Jumlah (2) Rp. 100,215.00
Jumlah (1) + (2) Rp. 434,047.60 Rp. 434,040.00

PEKERJAAN KUNCI DAN KACA


A. 4.6.2.1 1 Buah Pemasangan Kunci Tanam Antik
A. 4.6.2.1.a Bahan
Kunci tanam antik 1.0000 bh x Rp. 172,500.00 = Rp. 172,500.00
Jumlah (1) Rp. 172,500.00
A. 4.6.2.1.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang kayu 0.6000 oh x Rp. 172,000.00 = Rp. 103,200.00
Kepala Tukang 0.0600 oh x Rp. 207,000.00 = Rp. 12,420.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 123,201.00
Jumlah (1) + (2) Rp. 295,701.00 Rp. 295,700.00

A. 4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa


A. 4.6.2.2.a Bahan
Kunci tanam 1.0000 bh x Rp. 230,000.00 = Rp. 230,000.00
Jumlah (1) Rp. 230,000.00
A. 4.6.2.2.b Tenaga
Pekerja 0.0100 oh x Rp. 115,000.00 = Rp. 1,150.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 98,635.00
Jumlah (1) + (2) Rp. 328,635.00 Rp. 328,630.00

A. 4.6.2.3 1 Buah Pemasangan Kunci Tanam Kamar Mandi


A. 4.6.2.3.a Bahan
Kunci tanam kamar mandi 1.0000 bh x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 46,000.00
A. 4.6.2.3.b Tenaga
Pekerja 0.0050 oh x Rp. 115,000.00 = Rp. 575.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 97,606.00
Jumlah (1) + (2) Rp. 143,606.00 Rp. 143,600.00

A. 4.6.2.5 1 Buah Pemasangan Engsel Pintu


A. 4.6.2.5.a Bahan
Engsel pintu 5" 1.0000 bh x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 46,000.00
A. 4.6.2.5.b Tenaga
Pekerja 0.0150 oh x Rp. 115,000.00 = Rp. 1,725.00
Tukang kayu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0008 oh x Rp. 227,000.00 = Rp. 170.25
Jumlah (2) Rp. 30,800.25
Jumlah (1) + (2) Rp. 76,800.25 Rp. 76,800.00

A. 4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu


A. 4.6.2.6.a Bahan
Engsel (kupu-kupu) jendela 3" 1.0000 bh x Rp. 23,000.00 = Rp. 23,000.00
Jumlah (1) Rp. 23,000.00
A. 4.6.2.6.b Tenaga
Pekerja 0.0100 oh x Rp. 115,000.00 = Rp. 1,150.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0005 oh x Rp. 227,000.00 = Rp. 113.50
Jumlah (2) Rp. 20,533.50
Jumlah (1) + (2) Rp. 43,533.50 Rp. 43,530.00

Analisis Harga Satuan Pekerjaan (AHSP)


41 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.6.2.9 1 Buah Pemasangan Kait Angin
A. 4.6.2.9.a Bahan
Kait angin/hak angin 1.0000 bh x Rp. 28,700.00 = Rp. 28,700.00
Jumlah (1) Rp. 28,700.00
A. 4.6.2.9.b Tenaga
Pekerja 0.0150 oh x Rp. 115,000.00 = Rp. 1,725.00
Tukang kayu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.00800 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 32,446.00
Jumlah (1) + (2) Rp. 61,146.00 Rp. 61,140.00

A. 4.6.2.12 1 Buah Pemasangan Pegangan Pintu/Door Holder Stainless


A. 4.6.2.12.a Bahan
Handle pintu/door holder stainless 1.0000 bh x Rp. 345,000.00 = Rp. 345,000.00
Jumlah (1) Rp. 345,000.00
A. 4.6.2.12.b Tenaga
Pekerja 0.0500 oh x Rp. 115,000.00 = Rp. 5,750.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 102,781.00
Jumlah (1) + (2) Rp. 447,781.00 Rp. 447,780.00

A. 4.6.2.17 1 M2 Pemasangan Kaca Bening, Tbl. 5 mm


A. 4.6.2.17.a Bahan
Kaca bening tbl. 5mm 1.1000 m2 x Rp. 155,000.00 = Rp. 170,500.00
Sealant 0.0500 kg x Rp. 14,900.00 = Rp. 745.00
Jumlah (1) Rp. 170,500.00
A. 4.6.2.17.b Tenaga
Pekerja 0.0150 oh x Rp. 115,000.00 = Rp. 1,725.00
Tukang kayu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0008 oh x Rp. 227,000.00 = Rp. 170.25
Jumlah (2) Rp. 30,800.25
Jumlah (1) + (2) Rp. 201,300.25 Rp. 201,300.00

A. 4.6.2.24 1 M2 Pemasangan Kaca Reben, Tbl. 5 mm


A. 4.6.2.24.a Bahan
Kaca reben tbl. 5 mm 1.1000 m2 x Rp. 21,000.00 = Rp. 23,100.00
Jumlah (1) Rp. 23,100.00
A. 4.6.2.24.b Tenaga
Pekerja 0.0150 oh x Rp. 115,000.00 = Rp. 1,725.00
Tukang kayu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0008 oh x Rp. 227,000.00 = Rp. 170.25
Jumlah (2) Rp. 30,800.25
Jumlah (1) + (2) Rp. 53,900.25 Rp. 53,900.00

A. 4.6.2.25 1 Buah Pemasangan Engsel Salon


A. 4.6.2.25.a Bahan
Engsel salon 1.0000 bh x Rp. 28,700.00 = Rp. 28,700.00
Jumlah (1) Rp. 28,700.00
A. 4.6.2.25.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0005 oh x Rp. 227,000.00 = Rp. 113.50
Jumlah (2) Rp. 50,153.50
Jumlah (1) + (2) Rp. 78,853.50 Rp. 78,850.00

A. 4.6.2.26 1 Buah Pemasangan Gerendel Pintu


A. 4.6.2.26.a Bahan
Gerendel pintu 8" 1.0000 bh x Rp. 34,500.00 = Rp. 34,500.00
Jumlah (1) Rp. 34,500.00
A. 4.6.2.26.b Tenaga
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Jumlah (2) Rp. 19,270.00
Jumlah (1) + (2) Rp. 53,770.00 Rp. 53,770.00

A. 4.6.2.27 1 Buah Pemasangan Gerendel Kodok / Jendela


A. 4.6.2.27.a Bahan
Gerendel kodok / jendela 1.0000 bh x Rp. 17,200.00 = Rp. 17,200.00
Jumlah (1) Rp. 17,200.00
A. 4.6.2.27.b Tenaga
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Jumlah (2) Rp. 19,270.00
Jumlah (1) + (2) Rp. 36,470.00 Rp. 36,470.00

Analisis Harga Satuan Pekerjaan (AHSP)


42 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.6.2.28 1 Buah Pemasangan Rambuncis
A. 4.6.2.28.a Bahan
Rambuncis 1.0000 bh x Rp. 60,400.00 = Rp. 60,400.00
Jumlah (1) Rp. 60,400.00
A. 4.6.2.28.b Tenaga
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Jumlah (2) Rp. 19,270.00
Jumlah (1) + (2) Rp. 79,670.00 Rp. 79,670.00

PEKERJAAN PENUTUP LANTAI DAN DINDING


A. 4.4.3.4 1 M2 Pemasangan Lantai Keramik Ukr. 40x40 cm Warna/Motif
A. 4.4.3.4.a Bahan
Keramik lantai ukr. 40x40 cm warna/motif 6.6300 bh x Rp. 16,200.00 = Rp. 107,406.00
Semen portland 9.8000 kg x Rp. 1,700.00 = Rp. 16,660.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.6000 kg x Rp. 28,700.00 = Rp. 17,220.00
Jumlah (1) Rp. 149,048.50
A. 4.4.3.4.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang batu 0.1250 oh x Rp. 172,000.00 = Rp. 21,500.00
Kepala Tukang 0.0130 oh x Rp. 207,000.00 = Rp. 2,691.00
Mandor 0.0130 oh x Rp. 227,000.00 = Rp. 2,951.00
Jumlah (2) Rp. 55,892.00
Jumlah (1) + (2) Rp. 204,940.50 Rp. 204,940.00

A. 4.4.3.4.1 1 M2 Pemasangan Lantai Keramik Ukr. 40x40 cm Warna/Motif Bertekstur Kasar


A. 4.4.3.4.1.a Bahan
Keramik lantai ukr. 40x40 cm warna/motif bertekstur kasar 6.6300 bh x Rp. 16,200.00 = Rp. 107,406.00
Semen portland 9.8000 kg x Rp. 1,700.00 = Rp. 16,660.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.6000 kg x Rp. 28,700.00 = Rp. 17,220.00
Jumlah (1) Rp. 149,048.50
A. 4.4.3.4.1.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang batu 0.1250 oh x Rp. 172,000.00 = Rp. 21,500.00
Kepala Tukang 0.0130 oh x Rp. 207,000.00 = Rp. 2,691.00
Mandor 0.0130 oh x Rp. 227,000.00 = Rp. 2,951.00
Jumlah (2) Rp. 55,892.00
Jumlah (1) + (2) Rp. 204,940.50 Rp. 204,940.00

A. 4.4.3.4.2 1 M2 Pemasangan Lantai Keramik Ukr. 40x40 cm Putih Polos


A. 4.4.3.4.2.a Bahan
Keramik lantai ukr. 40x40 cm putih polos 6.6300 bh x Rp. 10,500.00 = Rp. 69,615.00
Semen portland 9.8000 kg x Rp. 1,700.00 = Rp. 16,660.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.6000 kg x Rp. 28,700.00 = Rp. 17,220.00
Jumlah (1) Rp. 111,257.50
A. 4.4.3.4.2.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang batu 0.1250 oh x Rp. 172,000.00 = Rp. 21,500.00
Kepala Tukang 0.0130 oh x Rp. 207,000.00 = Rp. 2,691.00
Mandor 0.0130 oh x Rp. 227,000.00 = Rp. 2,951.00
Jumlah (2) Rp. 55,892.00
Jumlah (1) + (2) Rp. 167,149.50 Rp. 167,140.00

A. 4.4.3.13 1 M2 Pemasangan Lantai Keramik Ukr. 60x60 cm Warna/Motif (Homogeneous Tile)


A. 4.4.3.13.a Bahan
Keramik warna/motif ukr. 60x60 cm (Homogeneous Tile) 3.1000 bh x Rp. 74,700.00 = Rp. 231,570.00
Semen portland 9.6000 kg x Rp. 1,700.00 = Rp. 16,320.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.5000 kg x Rp. 28,700.00 = Rp. 43,050.00
Jumlah (1) Rp. 298,702.50
A. 4.4.3.13.b Tenaga
Pekerja 0.2400 oh x Rp. 115,000.00 = Rp. 27,600.00
Tukang batu 0.1200 oh x Rp. 172,000.00 = Rp. 20,640.00
Kepala Tukang 0.0120 oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0120 oh x Rp. 227,000.00 = Rp. 2,724.00
Jumlah (2) Rp. 53,448.00
Jumlah (1) + (2) Rp. 352,150.50 Rp. 352,150.00

A. 4.4.3.35 1 M2 Pemasangan Lantai Keramik Ukr. 30x30 cm Warna/Motif


A. 4.4.3.35.a Bahan
Keramik lantai ukr. 30x30 cm 11.870 bh x Rp. 6,200.00 = Rp. 73,594.00
Semen portland 10.0000 kg x Rp. 1,700.00 = Rp. 17,000.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.5000 kg x Rp. 28,700.00 = Rp. 14,350.00
Jumlah (1) Rp. 112,706.50
A. 4.4.3.35.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 268,596.50 Rp. 268,590.00

Analisis Harga Satuan Pekerjaan (AHSP)


43 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.3.35.1 1 M2 Pemasangan Lantai Keramik Ukr. 30x30 cm Warna/Motif Bertekstur Kasar
A. 4.4.3.35.1.a Bahan
Keramik lantai ukr. 30x30 cm warna/motif 11.8700 bh x Rp. 7,800.00 = Rp. 92,586.00
Semen portland 10.0000 kg x Rp. 1,700.00 = Rp. 17,000.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.5000 kg x Rp. 28,700.00 = Rp. 14,350.00
Jumlah (1) Rp. 131,698.50
A. 4.4.3.35.1.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 287,588.50 Rp. 287,580.00

A. 4.4.3.35.2 1 M2 Pemasangan Lantai Keramik Ukr. 30x30 cm Putih Polos


A. 4.4.3.35.2.a Bahan
Keramik lantai ukr. 30x30 cm Putih Polos 11.8700 bh x Rp. 5,200.00 = Rp. 61,724.00
Semen portland 10.0000 kg x Rp. 1,700.00 = Rp. 17,000.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.5000 kg x Rp. 28,700.00 = Rp. 14,350.00
Jumlah (1) Rp. 100,836.50
A. 4.4.3.35.2.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 256,726.50 Rp. 256,720.00

Analisis Harga Satuan Pekerjaan (AHSP)


44 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.3.36 1 M2 Pemasangan Lantai Keramik Ukr. 20x20 cm Warna/Motif
A. 4.4.3.36.a Bahan
Keramik lantai ukr. 20x20 cm warna/motif 26.500 bh x Rp. 2,700.00 = Rp. 71,550.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.5000 kg x Rp. 28,700.00 = Rp. 14,350.00
Jumlah (1) Rp. 111,342.50
A. 4.4.3.36.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 267,232.50 Rp. 267,230.00

A. 4.4.3.38 1 M2 Pemasangan Lantai Mosaik Ukr. 30x30 cm


A. 4.4.3.38.a Bahan
Mosaik ukr. 30x30 cm 11.8700 bh x Rp. 34,500.00 = Rp. 409,515.00
Semen portland 14.1500 kg x Rp. 1,700.00 = Rp. 24,055.00
Pasir pasang 0.0390 m3 x Rp. 172,500.00 = Rp. 6,727.50
Semen warna 2.0000 kg x Rp. 28,700.00 = Rp. 57,400.00
Jumlah (1) Rp. 497,697.50
A. 4.4.3.38.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 653,587.50 Rp. 653,580.00

A. 4.4.3.43 1 M2 Pemasangan Lantai Marmer Ukr. 100x100 cm


A. 4.4.3.43.a Bahan
Marmer ukr. 100x100 cm 1.0600 bh x Rp. 287,500.00 = Rp. 304,750.00
Semen portland 8.1900 kg x Rp. 1,700.00 = Rp. 13,923.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 0.1340 kg x Rp. 28,700.00 = Rp. 3,845.80
Jumlah (1) Rp. 330,281.30
A. 4.4.3.43.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 486,171.30 Rp. 486,170.00

A. 4.4.3.44 1 M2 Pemasangan Lantai Karpet


A. 4.4.3.44.a Bahan
Karpet 1.0500 m2 x Rp. 402,500.00 = Rp. 422,625.00
Lem 0.3500 kg x Rp. 51,700.00 = Rp. 18,095.00
Jumlah (1) Rp. 440,720.00
A. 4.4.3.44.b Tenaga
Pekerja 0.1700 oh x Rp. 115,000.00 = Rp. 19,550.00
Tukang kayu 0.1700 oh x Rp. 172,000.00 = Rp. 29,240.00
Kepala Tukang 0.0170 oh x Rp. 207,000.00 = Rp. 3,519.00
Mandor 0.0090 oh x Rp. 227,000.00 = Rp. 2,043.00
Jumlah (2) Rp. 54,352.00
Jumlah (1) + (2) Rp. 495,072.00 Rp. 495,070.00

A. 4.4.3.45 1 M Pemasangan Underlayer (Pelapis Bawah Karpet)


2

A. 4.4.3.45.a Bahan
Underlayer 1.0500 m2 x Rp. 75,500.00 = Rp. 79,275.00
Lem 0.3500 kg x Rp. 51,700.00 = Rp. 18,095.00
Jumlah (1) Rp. 97,370.00
A. 4.4.3.45.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.1200 oh x Rp. 172,000.00 = Rp. 20,640.00
Kepala Tukang 0.0120 oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 38,286.00
Jumlah (1) + (2) Rp. 135,656.00 Rp. 135,650.00

A. 4.4.3.46 1 M2 Pemasangan Lantai Parquet Kayu


A. 4.4.3.46.a Bahan
Lantai Parquet kayu 1.0500 m2 x Rp. 431,200.00 = Rp. 452,760.00
Lem 0.6000 kg x Rp. 51,700.00 = Rp. 31,020.00
Jumlah (1) Rp. 483,780.00
A. 4.4.3.46.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang kayu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 639,670.00 Rp. 639,670.00

Analisis Harga Satuan Pekerjaan (AHSP)


45 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.3.54 1 M2 Pemasangan Dinding Keramik Ukr. 20x20 cm Warna/Motif
A. 4.4.3.54.a Bahan
Keramik dinding ukr. 20x20 cm warna/motif 26.5000 bh x Rp. 2,900.00 = Rp. 76,850.00
Semen portland 9.3000 kg x Rp. 1,700.00 = Rp. 15,810.00
Pasir pasang 0.0180 m3 x Rp. 172,500.00 = Rp. 3,105.00
Semen warna 1.9400 kg x Rp. 28,700.00 = Rp. 55,678.00
Jumlah (1) Rp. 151,443.00
A. 4.4.3.54.b Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Tukang batu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah (2) Rp. 200,430.00
Jumlah (1) + (2) Rp. 351,873.00 Rp. 351,870.00

A. 4.4.3.55 1 M2 Pemasangan Dinding Marmer Ukr. 100x100 cm


A. 4.4.3.55.a Bahan
Marmer ukr. 100x100 cm 1.0600 bh x Rp. 287,500.00 = Rp. 304,750.00
Semen portland 12.4400 kg x Rp. 1,700.00 = Rp. 21,148.00
Pasir pasang 0.0250 m3 x Rp. 172,500.00 = Rp. 4,312.50
Semen warna 0.6500 kg x Rp. 28,700.00 = Rp. 18,655.00
Jumlah (1) Rp. 348,865.50
A. 4.4.3.55.b Tenaga
Pekerja 1.3000 oh x Rp. 115,000.00 = Rp. 149,500.00
Tukang batu 0.6500 oh x Rp. 172,000.00 = Rp. 111,800.00
Kepala Tukang 0.0650 oh x Rp. 207,000.00 = Rp. 13,455.00
Mandor 0.0650 oh x Rp. 227,000.00 = Rp. 14,755.00
Jumlah (2) Rp. 289,510.00
Jumlah (1) + (2) Rp. 638,375.50 Rp. 638,370.00

A. 4.4.3.57 1 M Pemasangan Dinding Batu Alam Paras


2

A. 4.4.3.57.a Bahan
Batu alam paras 1.1000 m2 x Rp. 230,000.00 = Rp. 253,000.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 279,012.50
A. 4.4.3.57.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 434,902.50 Rp. 434,900.00

A. 4.4.3.58 1 M2 Pemasangan Dinding Batu Alam Candi


A. 4.4.3.58.a Bahan
Batu alam candi 1.1000 m2 x Rp. 230,000.00 = Rp. 253,000.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 279,012.50
A. 4.4.3.58.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 434,902.50 Rp. 434,900.00

A. 4.4.3.60 1 M Pemasangan Wallpaper, Lebar 50 cm


2

A. 4.4.3.60.a Bahan
Wallpaper 2.2000 m1 x Rp. 86,200.00 = Rp. 189,640.00
Lem 0.2500 kg x Rp. 51,700.00 = Rp. 12,925.00
Jumlah (1) Rp. 202,565.00
A. 4.4.3.60.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang 0.1750 oh x Rp. 172,000.00 = Rp. 30,100.00
Kepala Tukang 0.0170 oh x Rp. 207,000.00 = Rp. 3,519.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 74,323.00
Jumlah (1) + (2) Rp. 276,888.00 Rp. 276,880.00

A. 4.4.3.63 1 M1 Pemasangan Plint Kayu Tbl 2 cm, Lebar 10 cm


A. 4.4.3.63.a Bahan
Papan kayu 0.0030 m3 x Rp. 6,900,000.00 = Rp. 20,700.00
Paku skrup 0.0500 kg x Rp. 69,000.00 = Rp. 3,450.00
Jumlah (1) Rp. 24,150.00
A. 4.4.3.63.b Tenaga
Pekerja 0.1200 oh x Rp. 115,000.00 = Rp. 13,800.00
Tukang kayu 0.1200 oh x Rp. 172,000.00 = Rp. 20,640.00
Kepala Tukang 0.0120 oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 38,286.00
Jumlah (1) + (2) Rp. 62,436.00 Rp. 62,430.00

Analisis Harga Satuan Pekerjaan (AHSP)


46 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.3.64 1 M2 Pemasangan Paving Blok Natural, Tbl. 6 cm
A. 4.4.3.64.a Bahan
Paving blok tbl. 6 cm 1.0100 m2 x Rp. 100,900.00 = Rp. 101,909.00
Pasir beton 0.0500 m3 x Rp. 172,500.00 = Rp. 8,625.00
Jumlah (1) Rp. 110,534.00
A. 4.4.3.64.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0013 oh x Rp. 227,000.00 = Rp. 295.10
Jumlah (2) Rp. 125,395.10
A. 4.4.3.64.c Peralatan
Peralatan 10.0000 % x Rp. 100,900.00 = Rp. 10,090.00
Rp. 10,090.00
Jumlah (1) + (2) + (3) Rp. 246,019.10 Rp. 246,010.00

A. 4.4.3.65 1 M2 Pemasangan Paving Blok Natural, Tbl. 8 cm


A. 4.4.3.65.a Bahan
Paving blok tbl. 8 cm 1.0100 m2 x Rp. 126,200.00 = Rp. 127,462.00
Pasir beton 2.0700 m3 x Rp. 172,500.00 = Rp. 357,075.00
Jumlah (1) Rp. 484,537.00
A. 4.4.3.65.b Tenaga
Pekerja 0.5000 oh x Rp. 115,000.00 = Rp. 57,500.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0013 oh x Rp. 227,000.00 = Rp. 295.10
Jumlah (2) Rp. 154,145.10
A. 4.4.3.65.c Peralatan
Peralatan 10.0000 % x Rp. 126,200.00 = Rp. 12,620.00
Rp. 12,620.00
Jumlah (1) + (2) + (3) Rp. 651,302.10 Rp. 651,300.00

A. 4.4.3.66 1 M2 Pemasangan Paving Blok Berwarna, Tbl. 6 cm


A. 4.4.3.66.a Bahan
Paving blok tbl. 6 cm berwarna 1.0100 m2 x Rp. 97,600.00 = Rp. 98,576.00
Pasir beton 0.0500 m3 x Rp. 172,500.00 = Rp. 8,625.00
Jumlah (1) Rp. 107,201.00
A. 4.4.3.66.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0013 oh x Rp. 227,000.00 = Rp. 295.10
Jumlah (2) Rp. 125,395.10
A. 4.4.3.66.c Peralatan
Peralatan 10.0000 % x Rp. 97,600.00 = Rp. 9,760.00
Rp. 9,760.00
Jumlah (1) + (2) + (3) Rp. 242,356.10 Rp. 242,350.00

A. 4.4.3.67 1 M Pemasangan Paving Blok Berwarna, Tbl. 8 cm


2

A. 4.4.3.67.a Bahan
Paving blok tbl. 8 cm berwarna 1.0100 m2 x Rp. 127,700.00 = Rp. 128,977.00
Pasir beton 2.0700 m3 x Rp. 172,500.00 = Rp. 357,075.00
Jumlah (1) Rp. 486,052.00
A. 4.4.3.67.b Tenaga
Pekerja 0.5000 oh x Rp. 115,000.00 = Rp. 57,500.00
Tukang kayu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0013 oh x Rp. 227,000.00 = Rp. 295.10
Jumlah (2) Rp. 154,145.10
A. 4.4.3.67.c Peralatan
Peralatan 10.0000 % x Rp. 127,700.00 = Rp. 12,770.00
Rp. 12,770.00
Jumlah (1) + (2) + (3) Rp. 652,967.10 Rp. 652,960.00

A. 4.4.3.69 1 M2 Pemasangan Dinding Keramik Ukr. 30x60 cm Warna/Motif


A. 4.4.3.69.a Bahan
Keramik dinding ukr. 30x60 cm warna/motif 5.5600 bh x Rp. 32,500.00 = Rp. 180,700.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.6200 kg x Rp. 28,700.00 = Rp. 46,494.00
Jumlah (1) Rp. 252,636.50
A. 4.4.3.69.b Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Tukang batu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah (2) Rp. 200,430.00
Jumlah (1) + (2) Rp. 453,066.50 Rp. 453,060.00

Analisis Harga Satuan Pekerjaan (AHSP)


47 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.3.71 1 M1 Pemasangan Kanstin Beton Ukr. ± 15x30x60 cm
A. 4.4.3.71.a Bahan
Kanstin ukr. ± 15 x 30 x 60 cm 1.6700 bh x Rp. 54,000.00 = Rp. 90,180.00
Semen portland 0.1500 kg x Rp. 1,700.00 = Rp. 255.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Jumlah (1) Rp. 90,607.50
A. 4.4.3.71.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 73,240.00
Jumlah (1) + (2) Rp. 163,847.50 Rp. 163,840.00

A. 4.4.3.72 1 M2 Pemasangan Lantai Keramik Ukr. 25x25 cm Warna/Motif


A. 4.4.3.72.a Bahan
Keramik lantai ukr. 25x25 cm warna/motif 16.0000 bh x Rp. 5,000.00 = Rp. 80,000.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.6200 kg x Rp. 28,700.00 = Rp. 46,494.00
Jumlah (1) Rp. 151,936.50
A. 4.4.3.72.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 307,826.50 Rp. 307,820.00

A. 4.4.3.73 1 M Pemasangan Dinding Keramik Ukr. 25x45 cm Warna/Motif


2

A. 4.4.3.73.a Bahan
Keramik dinding ukr. 25x45 cm warna/motif 8.8900 bh x Rp. 12,900.00 = Rp. 114,681.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.6200 kg x Rp. 28,700.00 = Rp. 46,494.00
Jumlah (1) Rp. 186,617.50
A. 4.4.3.73.b Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Tukang batu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah (2) Rp. 200,430.00
Jumlah (1) + (2) Rp. 387,047.50 Rp. 387,040.00

A. 4.4.3.74 1 M2 Pemasangan Dinding Keramik Ukr. 25x40 cm Warna/Motif


A. 4.4.3.74.a Bahan
Keramik dinding ukr. 25x40 cm warna/motif 10.0000 bh x Rp. 9,700.00 = Rp. 97,000.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.6200 kg x Rp. 28,700.00 = Rp. 46,494.00
Jumlah (1) Rp. 168,936.50
A. 4.4.3.74.b Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Tukang batu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah (2) Rp. 200,430.00
Jumlah (1) + (2) Rp. 369,366.50 Rp. 369,360.00

A. 4.4.3.75 1 M Pemasangan Dinding Keramik Ukr. 20x25 cm Warna/Motif


2

A. 4.4.3.75.a Bahan
Keramik dinding ukr. 20x25 cm warna/motif 20.0000 bh x Rp. 4,300.00 = Rp. 86,000.00
Semen portland 10.4000 kg x Rp. 1,700.00 = Rp. 17,680.00
Pasir pasang 0.0450 m3 x Rp. 172,500.00 = Rp. 7,762.50
Semen warna 1.6200 kg x Rp. 28,700.00 = Rp. 46,494.00
Jumlah (1) Rp. 157,936.50
A. 4.4.3.75.b Tenaga
Pekerja 0.9000 oh x Rp. 115,000.00 = Rp. 103,500.00
Tukang batu 0.4500 oh x Rp. 172,000.00 = Rp. 77,400.00
Kepala Tukang 0.0450 oh x Rp. 207,000.00 = Rp. 9,315.00
Mandor 0.0450 oh x Rp. 227,000.00 = Rp. 10,215.00
Jumlah (2) Rp. 200,430.00
Jumlah (1) + (2) Rp. 358,366.50 Rp. 358,360.00

A. 4.4.3.76 1 M2 Pemasangan Dinding Batu Alam Palimanan


A. 4.4.3.76.a Bahan
Batu alam palimanan 1.1000 m2 x Rp. 230,000.00 = Rp. 253,000.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 279,012.50

Analisis Harga Satuan Pekerjaan (AHSP)


48 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.4.3.76.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 434,902.50 Rp. 434,900.00

A. 4.4.3.77 1 M Pemasangan Dinding Batu Alam Andesit


2

A. 4.4.3.77.a Bahan
Batu alam andesit 1.1000 m2 x Rp. 287,500.00 = Rp. 316,250.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 342,262.50
A. 4.4.3.77.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 498,152.50 Rp. 498,150.00

A. 4.4.3.78 1 M2 Pemasangan Dinding Batu Alam Andesit Motif


A. 4.4.3.78.a Bahan
Batu alam andesit motif 1.1000 m2 x Rp. 287,500.00 = Rp. 316,250.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 342,262.50
A. 4.4.3.78.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 498,152.50 Rp. 498,150.00

A. 4.4.3.79 1 M2 Pemasangan Dinding Batu Alam Andesit Bintik Bakar


A. 4.4.3.79.a Bahan
Batu alam andesit bintik bakar 1.1000 m2 x Rp. 287,500.00 = Rp. 316,250.00
Semen portland 11.7500 kg x Rp. 1,700.00 = Rp. 19,975.00
Pasir pasang 0.0350 m3 x Rp. 172,500.00 = Rp. 6,037.50
Jumlah (1) Rp. 342,262.50
A. 4.4.3.79.b Tenaga
Pekerja 0.7000 oh x Rp. 115,000.00 = Rp. 80,500.00
Tukang batu 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0350 oh x Rp. 227,000.00 = Rp. 7,945.00
Jumlah (2) Rp. 155,890.00
Jumlah (1) + (2) Rp. 498,152.50 Rp. 498,150.00

A. 4.4.3.80 1 M Pemasangan Paving Block Tipe Segi Enam (Merah)


2

A. 4.4.3.80.a Bahan
Paving block tipe segi enam (merah) 44.0000 bh x Rp. 2,800.00 = Rp. 123,200.00
Pasir pasang 0.0550 m3 x Rp. 172,500.00 = Rp. 9,487.50
Jumlah (1) Rp. 132,687.50
A. 4.4.3.80.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 73,240.00
Jumlah (1) + (2) Rp. 205,927.50 Rp. 205,920.00

A. 4.4.3.81 1 M2 Pemasangan Paving Block Tipe Bata


A. 4.4.3.81.a Bahan
Paving block tipe bata 46.0000 bh x Rp. 1,900.00 = Rp. 87,400.00
Pasir pasang 0.0550 m3 x Rp. 172,500.00 = Rp. 9,487.50
Jumlah (1) Rp. 96,887.50
A. 4.4.3.81.b Tenaga
Pekerja 0.3000 oh x Rp. 115,000.00 = Rp. 34,500.00
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0100 oh x Rp. 227,000.00 = Rp. 2,270.00
Jumlah (2) Rp. 73,240.00
Jumlah (1) + (2) Rp. 170,127.50 Rp. 170,120.00

Analisis Harga Satuan Pekerjaan (AHSP)


49 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN PENGECATAN
A. 4.7.1.1 1 M2 Pengikisan / Pengerokan Permukaan Cat Tembok Lama
A. 4.7.1.1.a Bahan
Soda api 0.0500 kg x Rp. 25,000.00 = Rp. 1,250.00
Jumlah (1) Rp. 1,250.00
A. 4.7.1.1.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 17,931.00
Jumlah (1) + (2) Rp. 19,181.00 Rp. 19,180.00

A. 4.7.1.2 1 M2 Pencucian Bidang Permukaan Tembok yang Pernah Dicat


A. 4.7.1.2.a Bahan
Sabun 0.0500 kg x Rp. 2,600.00 = Rp. 130.00
Jumlah (1) Rp. 130.00
A. 4.7.1.2.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 17,931.00
Jumlah (1) + (2) Rp. 18,061.00 Rp. 18,060.00

A. 4.7.1.3 1 M2 Pengerokan Karat pada Permukaan Baja / Besi Cara Manual


A. 4.7.1.3.a Bahan
Sabun 0.0500 kg x Rp. 2,600.00 = Rp. 130.00
Jumlah (1) Rp. 130.00
A. 4.7.1.3.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 19,066.00
Jumlah (1) + (2) Rp. 19,196.00 Rp. 19,190.00

Analisis Harga Satuan Pekerjaan (AHSP)


50 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.7.1.4 1 M2 Pengecatan Bidang Kayu Lama (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
A. 4.7.1.4.a Bahan
Cat menie 0.2000 kg x Rp. 37,900.00 Rp. 7,580.00
Plamir 0.1500 kg x Rp. 9,200.00 = Rp. 1,380.00
Cat dasar 0.1700 kg x Rp. 46,000.00 Rp. 7,820.00
Cat minyak / kilat 0.2600 kg x Rp. 77,000.00 Rp. 20,020.00
Kuas 0.0100 bh x Rp. 28,700.00 Rp. 287.00
Tinner 0.0300 ltr x Rp. 57,500.00 = Rp. 1,725.00
Amplas 0.2000 lbr x Rp. 13,800.00 = Rp. 2,760.00
Jumlah (1) Rp. 41,572.00
A. 4.7.1.4.b Tenaga
Pekerja 0.0700 oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.0750 oh x Rp. 172,000.00 = Rp. 12,900.00
Kepala Tukang 0.0075 oh x Rp. 207,000.00 = Rp. 1,552.50
Mandor 0.0025 oh x Rp. 227,000.00 = Rp. 567.50
Jumlah (2) Rp. 23,070.00
Jumlah (1) + (2) Rp. 64,642.00 Rp. 64,640.00

A. 4.7.1.5 1 M Pengecatan Bidang Kayu Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 3 Lapis Cat Minyak)
2

A. 4.7.1.5.a Bahan
Cat menie kayu 0.2000 kg x Rp. 37,900.00 = Rp. 7,580.00
Plamir 0.1500 kg x Rp. 9,200.00 = Rp. 1,380.00
Cat dasar 0.1700 kg x Rp. 46,000.00 = Rp. 7,820.00
Cat minyak / kilat 0.3500 kg x Rp. 77,000.00 = Rp. 26,950.00
Kuas 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Tinner 0.0300 ltr x Rp. 57,500.00 = Rp. 1,725.00
Amplas 0.2000 lbr x Rp. 13,800.00 = Rp. 2,760.00
Jumlah (1) Rp. 48,502.00
A. 4.7.1.5.b Tenaga
Pekerja 0.0700 Oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.1050 Oh x Rp. 172,000.00 = Rp. 18,060.00
Kepala tukang 0.0040 Oh x Rp. 207,000.00 = Rp. 828.00
Mandor 0.0030 Oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 27,619.00
Jumlah (1) + (2) Rp. 76,121.00 Rp. 76,120.00

A. 4.7.1.8 1 M2 Pelaburan Bidang Kayu dengan Residu


A. 4.7.1.8.a Bahan
Residu 0.3500 ltr x Rp. 86,200.00 = Rp. 30,170.00
Jumlah (1) Rp. 30,170.00
A. 4.7.1.8.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 12,862.00
Jumlah (1) + (2) Rp. 43,032.00 Rp. 43,030.00

A. 4.7.1.9 1 M2 Pelaburan Bidang Kayu dengan Vernis


A. 4.7.1.9.a Bahan
Vernis 0.1500 kg x Rp. 78,200.00 = Rp. 11,730.00
Dempul 0.0500 kg x Rp. 34,500.00 = Rp. 1,725.00
Amplas 0.1000 lbr x Rp. 13,800.00 = Rp. 1,380.00
Jumlah (1) Rp. 14,835.00
A. 4.7.1.9.b Tenaga
Pekerja 0.0700 Oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.1050 Oh x Rp. 172,000.00 = Rp. 18,060.00
Kepala tukang 0.0040 Oh x Rp. 207,000.00 = Rp. 828.00
Mandor 0.0030 Oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 27,619.00
Jumlah (1) + (2) Rp. 42,454.00 Rp. 42,450.00

A. 4.7.1.10 1 M Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 3 Lapis Cat Penutup)
2

A. 4.7.1.10.a Bahan
Plamir 0.1200 kg x Rp. 9,200.00 = Rp. 1,104.00
Cat dasar / sealer 0.1200 kg x Rp. 46,000.00 = Rp. 5,520.00
Cat dinding / tembok 0.2600 kg x Rp. 103,500.00 = Rp. 26,910.00
Jumlah (1) Rp. 33,534.00
A. 4.7.1.10.b Tenaga
Pekerja 0.0400 Oh x Rp. 115,000.00 = Rp. 4,600.00
Tukang cat 0.1200 Oh x Rp. 172,000.00 = Rp. 20,640.00
Kepala tukang 0.0120 Oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0020 Oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 28,178.00
Jumlah (1) + (2) Rp. 61,712.00 Rp. 61,710.00

Analisis Harga Satuan Pekerjaan (AHSP)


51 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.7.1.11 1 M2 Pengecatan Tembok Lama (1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
A. 4.7.1.11.a Bahan
Cat dasar / sealer 0.1200 kg x Rp. 46,000.00 = Rp. 5,520.00
Cat dinding / tembok 0.1800 kg x Rp. 103,500.00 = Rp. 18,630.00
Jumlah (1) Rp. 24,150.00
A. 4.7.1.11.b Tenaga
Pekerja 0.0280 Oh x Rp. 115,000.00 = Rp. 3,220.00
Tukang cat 0.0420 Oh x Rp. 172,000.00 = Rp. 7,224.00
Kepala tukang 0.0042 Oh x Rp. 207,000.00 = Rp. 869.40
Mandor 0.0030 Oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 11,994.40
Jumlah (1) + (2) Rp. 36,144.40 Rp. 36,140.00

A. 4.7.1.16 1 M2 Pengecatan Permukaan Baja / Besi dengan Menie Besi


A. 4.7.1.16.a Bahan
Cat menie besi 0.1000 kg x Rp. 43,700.00 = Rp. 4,370.00
Kuas 2,5" 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Jumlah (1) Rp. 4,657.00
A. 4.7.1.16.b Tenaga
Pekerja 0.0200 oh x Rp. 115,000.00 = Rp. 2,300.00
Tukang cat 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0025 oh x Rp. 227,000.00 = Rp. 567.50
Jumlah (2) Rp. 41,407.50
Jumlah (1) + (2) Rp. 46,064.50 Rp. 46,060.00

A. 4.7.1.17 1 M2 Pengecatan Permukaan Baja / Besi dengan Menie Besi dan Perancah Kayu
A. 4.7.1.17.a Bahan
Cat menie besi 0.1000 kg x Rp. 43,700.00 = Rp. 4,370.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Kuas 2,5" 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Peranca kayu sembarang 0.0020 m3 x Rp. 6,325,000.00 = Rp. 12,650.00
Jumlah (1) Rp. 17,882.00
A. 4.7.1.17.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang cat 0.2250 oh x Rp. 172,000.00 = Rp. 38,700.00
Kepala Tukang 0.0225 oh x Rp. 207,000.00 = Rp. 4,657.50
Mandor 0.0075 oh x Rp. 227,000.00 = Rp. 1,702.50
Jumlah (2) Rp. 73,810.00
Jumlah (1) + (2) Rp. 91,692.00 Rp. 91,690.00

A. 4.7.1.18 1 M2 Pengecatan Permukaan Baja Galvanis secara Manual 4 Lapis


A. 4.7.1.18.a Bahan
Cat menie besi (A) 0.1000 kg x Rp. 43,700.00 = Rp. 4,370.00
Cat menie besi (B) 0.1000 kg x Rp. 43,700.00 = Rp. 4,370.00
Cat 0.0800 kg x Rp. 77,000.00 = Rp. 6,160.00
Kuas 2,5" 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Jumlah (1) Rp. 15,762.00
A. 4.7.1.18.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang cat 0.2500 oh x Rp. 172,000.00 = Rp. 43,000.00
Kepala Tukang 0.0250 oh x Rp. 207,000.00 = Rp. 5,175.00
Mandor 0.0013 oh x Rp. 227,000.00 = Rp. 295.10
Jumlah (2) Rp. 77,220.10
Jumlah (1) + (2) Rp. 92,982.10 Rp. 92,980.00

A. 4.7.1.19 1 M2 Pengecatan Permukaan Baja Galvanis secara Manual 1 Lapis Cat Mutakhir
A. 4.7.1.19.a Bahan
Cat 0.3000 kg x Rp. 77,000.00 = Rp. 23,100.00
Kuas 2,5" 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Jumlah (1) Rp. 23,962.00
A. 4.7.1.19.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang cat 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0120 oh x Rp. 207,000.00 = Rp. 2,484.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 20,385.00
Jumlah (1) + (2) Rp. 44,347.00 Rp. 44,340.00

Analisis Harga Satuan Pekerjaan (AHSP)


52 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.7.1.20 1 M2 Pengecatan Permukaan Baja Galvanis secara Manual Sistem 3 Lapis
A. 4.7.1.20.a Bahan
Cat dasar 0.1000 kg x Rp. 46,000.00 = Rp. 4,600.00
Cat antara 0.1000 kg x Rp. 46,000.00 Rp. 4,600.00
Cat penutup 0.0800 kg x Rp. 46,000.00 = Rp. 3,680.00
Kuas 2,5" 0.0100 bh x Rp. 28,700.00 = Rp. 287.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Jumlah (1) Rp. 13,742.00
A. 4.7.1.20.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang cat 0.8000 oh x Rp. 172,000.00 = Rp. 137,600.00
Kepala Tukang 0.0800 oh x Rp. 207,000.00 = Rp. 16,560.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 204,700.00
Jumlah (1) + (2) Rp. 218,442.00 Rp. 218,440.00

A. 4.7.1.21 1 M2 Pengecatan Permukaan Baja Galvanis secara Semprot Sistem 3 Lapis Cat Mutakhir
A. 4.7.1.21.a Bahan
Cat dasar 0.3000 kg x Rp. 46,000.00 = Rp. 13,800.00
Tinner 0.0100 ltr x Rp. 57,500.00 = Rp. 575.00
Jumlah (1) Rp. 14,375.00
A. 4.7.1.21.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang cat 0.7000 oh x Rp. 172,000.00 = Rp. 120,400.00
Kepala Tukang 0.0700 oh x Rp. 207,000.00 = Rp. 14,490.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 185,430.00
Jumlah (1) + (2) Rp. 199,805.00 Rp. 199,800.00

A. 4.7.1.23 1 M Waterproof (1 Lapis Dasar, 1 Lapis Penutup)


2

A. 4.7.1.23.a Bahan
Waterproof dasar 0.1000 kg x Rp. 63,200.00 = Rp. 6,320.00
Waterproof penutup 0.2600 kg x Rp. 63,200.00 = Rp. 16,432.00
Jumlah (1) Rp. 22,752.00
A. 4.7.1.23.b Tenaga
Pekerja 0.0200 oh x Rp. 115,000.00 = Rp. 2,300.00
Tukang cat 0.0630 oh x Rp. 172,000.00 = Rp. 10,836.00
Kepala Tukang 0.0063 oh x Rp. 207,000.00 = Rp. 1,304.10
Mandor 0.0025 oh x Rp. 227,000.00 = Rp. 567.50
Jumlah (2) Rp. 15,007.60
Jumlah (1) + (2) Rp. 37,759.60 Rp. 37,750.00

A. 4.7.1.24 1 M2 Pendempulan dan Penggosokan Kayu


A. 4.7.1.24.a Bahan
Dempul 0.0800 kg x Rp. 34,500.00 = Rp. 2,760.00
Tinner 0.0200 ltr x Rp. 57,500.00 = Rp. 1,150.00
Amplas 0.1000 lbr x Rp. 13,800.00 = Rp. 1,380.00
Jumlah (1) Rp. 5,290.00
A. 4.7.1.24.b Tenaga
Pekerja 0.0400 oh x Rp. 115,000.00 = Rp. 4,600.00
Tukang cat 0.0400 oh x Rp. 172,000.00 = Rp. 6,880.00
Kepala Tukang 0.0400 oh x Rp. 207,000.00 = Rp. 8,280.00
Mandor 0.0025 oh x Rp. 227,000.00 = Rp. 567.50
Jumlah (2) Rp. 20,327.50
Jumlah (1) + (2) Rp. 25,617.50 Rp. 25,610.00

A. 4.7.1.25 1 M2 Pengecatan Bidang Baja / Besi dengan Cat Minyak


A. 4.7.1.25.a Bahan
Cat menie besi 0.2000 kg x Rp. 43,700.00 = Rp. 8,740.00
Cat minyak / kilat 0.2600 kg x Rp. 77,000.00 = Rp. 20,020.00
Jumlah (1) Rp. 28,760.00

A. 4.7.1.25.b Tenaga
Pekerja 0.0700 oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.0090 oh x Rp. 172,000.00 = Rp. 1,548.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 11,087.00
Jumlah (1) + (2) Rp. 39,847.00 Rp. 39,840.00

A. 4.7.1.26 1 M Pengecatan Bidang Baja / Besi dengan Cat Minyak dan Perancah Kayu
2

A. 4.7.1.26.a Bahan
Cat menie besi 0.2000 kg x Rp. 43,700.00 = Rp. 8,740.00
Cat minyak / kilat 0.2600 kg x Rp. 77,000.00 = Rp. 20,020.00
Peranca kayu sembarang 0.0020 m3 x Rp. 6,325,000.00 = Rp. 12,650.00
Jumlah (1) Rp. 41,410.00
A. 4.7.1.26.b Tenaga
Pekerja 0.0700 oh x Rp. 115,000.00 = Rp. 8,050.00
Tukang cat 0.0090 oh x Rp. 172,000.00 = Rp. 1,548.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 11,087.00
Jumlah (1) + (2) Rp. 52,497.00 Rp. 52,490.00

Analisis Harga Satuan Pekerjaan (AHSP)


53 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN SANITASI
A. 5.1.1.1 1 Bh Pemasangan Klozet Duduk / duoblock + Jet Spray
A. 5.1.1.1.a Bahan
Kloset duduk model duoblok + Jet Spray 1.0000 bh x Rp. 3,680,000.00 = Rp. 3,680,000.00
Perlengkapan (dari harga kloset duduk) 6% Ls x Rp. 3,680,000.00 = Rp. 220,800.00
Jumlah (1) Rp. 3,900,800.00
A. 5.1.1.1.b Tenaga
Pekerja 3.3000 oh x Rp. 115,000.00 = Rp. 379,500.00
Tukang batu 1.1000 oh x Rp. 172,000.00 = Rp. 189,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.1600 oh x Rp. 227,000.00 = Rp. 36,320.00
Jumlah (2) Rp. 607,090.00
Jumlah (1) + (2) Rp. 4,507,890.00 Rp. 4,507,890.00

A. 5.1.1.2 1 Bh Pemasangan Kloset Jongkok Porselin


A. 5.1.1.2.a Bahan
Kloset jongkok porselin 1.0000 bh x Rp. 454,000.00 = Rp. 454,000.00
Semen portland 6.0000 kg x Rp. 1,700.00 = Rp. 10,200.00
Pasir pasang 0.0100 m3 x Rp. 172,500.00 = Rp. 1,725.00
Jumlah (1) Rp. 465,925.00
A. 5.1.1.2.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang batu 1.5000 oh x Rp. 172,000.00 = Rp. 258,000.00
Kepala Tukang 0.1500 oh x Rp. 207,000.00 = Rp. 31,050.00
Mandor 0.1600 oh x Rp. 227,000.00 = Rp. 36,320.00
Jumlah (2) Rp. 440,370.00
Jumlah (1) + (2) Rp. 906,295.00 Rp. 906,290.00

A. 5.1.1.4 1 Bh Pemasangan Urinoir + Flusher (dewasa)


A. 5.1.1.4.a Bahan
Urinoir + flusher (dewasa) 1.0000 bh x Rp. 6,900,000.00 = Rp. 6,900,000.00
Perlengkapan (dari harga urinoir) 30% x Rp. 6,900,000.00 = Rp. 2,070,000.00
Semen portland 6.0000 kg x Rp. 1,700.00 = Rp. 10,200.00
Pasir pasang 0.0100 m3 x Rp. 172,500.00 = Rp. 1,725.00
Jumlah (1) Rp. 8,981,925.00

Analisis Harga Satuan Pekerjaan (AHSP)


54 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 5.1.1.4.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang batu 1.0000 oh x Rp. 172,000.00 = Rp. 172,000.00
Kepala Tukang 0.1000 oh x Rp. 207,000.00 = Rp. 20,700.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 319,050.00
Jumlah (1) + (2) Rp. 9,300,975.00 Rp. 9,300,970.00

A. 5.1.1.4.1 1 Bh Pemasangan Urinoir + Flusher (anak-anak)


A. 5.1.1.4.1.a Bahan
Urinoir + flusher (anak-anak) 1.0000 bh x Rp. 4,600,000.00 = Rp. 4,600,000.00
Perlengkapan (dari harga urinoir) 30% x Rp. 4,600,000.00 = Rp. 1,380,000.00
Semen portland 6.0000 kg x Rp. 1,700.00 = Rp. 10,200.00
Pasir pasang 0.0100 m3 x Rp. 172,500.00 = Rp. 1,725.00
Jumlah (1) Rp. 5,991,925.00
A. 5.1.1.4.1.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang batu 1.0000 oh x Rp. 172,000.00 = Rp. 172,000.00
Kepala Tukang 0.1000 oh x Rp. 207,000.00 = Rp. 20,700.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 319,050.00
Jumlah (1) + (2) Rp. 6,310,975.00 Rp. 6,310,970.00

A. 5.1.1.5 1 Bh Pemasangan Washtafel


A. 5.1.1.5.a Bahan
Washtafel 1.2000 bh x Rp. 747,500.00 = Rp. 897,000.00
Perlengkapan (dari harga washtafel) 12% x Rp. 747,500.00 = Rp. 89,700.00
Semen portland 6.0000 kg x Rp. 1,700.00 = Rp. 10,200.00
Pasir pasang 0.0100 m3 x Rp. 172,500.00 = Rp. 1,725.00
Jumlah (1) Rp. 998,625.00
A. 5.1.1.5.b Tenaga
Pekerja 1.2000 oh x Rp. 115,000.00 = Rp. 138,000.00
Tukang batu 1.4500 oh x Rp. 172,000.00 = Rp. 249,400.00
Kepala Tukang 0.1500 oh x Rp. 207,000.00 = Rp. 31,050.00
Mandor 0.0600 oh x Rp. 227,000.00 = Rp. 13,620.00
Jumlah (2) Rp. 432,070.00
Jumlah (1) + (2) Rp. 1,430,695.00 Rp. 1,430,690.00

A. 5.1.1.12 1 Bh Pemasangan Bak Cuci Piring Stainless Steel 1 Lobang


A. 5.1.1.12.a Bahan
Bak cuci piring stainless steel 1 Lobang 1.0000 unit x Rp. 402,500.00 = Rp. 402,500.00
Waterdrain 1.0000 bh x Rp. 86,300.00 = Rp. 86,300.00
Jumlah (1) Rp. 488,800.00
A. 5.1.1.12.b Tenaga
Pekerja 0.0300 oh x Rp. 115,000.00 = Rp. 3,450.00
Tukang batu 0.3000 oh x Rp. 172,000.00 = Rp. 51,600.00
Kepala Tukang 0.0300 oh x Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0150 oh x Rp. 227,000.00 = Rp. 3,405.00
Jumlah (2) Rp. 64,665.00
Jumlah (1) + (2) Rp. 553,465.00 Rp. 553,460.00

A. 5.1.1.12.1 1 Bh Pemasangan Bak Cuci Piring Stainless Steel 2 Lobang


A. 5.1.1.12.1.a Bahan
Bak cuci piring stainless steel 2 Lobang 1.0000 unit x Rp. 690,000.00 = Rp. 690,000.00
Waterdrain 1.0000 bh x Rp. 86,300.00 = Rp. 86,300.00
Jumlah (1) Rp. 776,300.00
A. 5.1.1.12.1.b Tenaga
Pekerja 0.0300 oh x Rp. 115,000.00 = Rp. 3,450.00
Tukang batu 0.3000 oh x Rp. 172,000.00 = Rp. 51,600.00
Kepala Tukang 0.0300 oh x Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 61,714.00
Jumlah (1) + (2) Rp. 838,014.00 Rp. 838,010.00

A. 5.1.1.14 1 Bh Pemasangan Floor Drain / Saringan Air Lantai


A. 5.1.1.14.a Bahan
Floor Drain / Saringan air lantai 1.0000 bh x Rp. 63,200.00 = Rp. 63,200.00
Jumlah (1) Rp. 63,200.00
A. 5.1.1.14.b Tenaga
Pekerja 0.0100 oh x Rp. 115,000.00 = Rp. 1,150.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 21,555.00
Jumlah (1) + (2) Rp. 84,755.00 Rp. 84,750.00

A. 5.1.1.15 1 Bh Pemasangan Bak Kontrol Pasangan Bata 30x30 Tinggi 35 cm


A. 5.1.1.15.a Bahan
Batu bata 40.0000 bh x Rp. 630.00 = Rp. 25,200.00
Semen portland 44.0000 kg x Rp. 1,700.00 = Rp. 74,800.00
Pasir pasang 0.0700 m3 x Rp. 172,500.00 = Rp. 12,075.00
Pasir beton 0.0600 m3 x Rp. 172,500.00 = Rp. 10,350.00
Kerikil beton 0.0700 m3 x Rp. 230,000.00 = Rp. 16,100.00
Besi beton polos 1.6000 kg x Rp. 10,800.00 = Rp. 17,280.00
Jumlah (1) Rp. 155,805.00

Analisis Harga Satuan Pekerjaan (AHSP)


55 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 5.1.1.15.b Tenaga
Pekerja 2.1600 oh x Rp. 115,000.00 = Rp. 248,400.00
Tukang batu 0.7200 oh x Rp. 172,000.00 = Rp. 123,840.00
Kepala Tukang 0.0720 oh x Rp. 207,000.00 = Rp. 14,904.00
Mandor 0.0110 oh x Rp. 227,000.00 = Rp. 2,497.00
Jumlah (2) Rp. 389,641.00
Jumlah (1) + (2) Rp. 545,446.00 Rp. 545,440.00

A. 5.1.1.16 1 Bh Pemasangan Bak Kontrol Pasangan Bata 45x45 Tinggi 50 cm


A. 5.1.1.16.a Bahan
Batu bata 70.0000 bh x Rp. 630.00 = Rp. 44,100.00
Semen portland 77.0000 kg x Rp. 1,700.00 = Rp. 130,900.00
Pasir pasang 0.1300 m3 x Rp. 172,500.00 = Rp. 22,425.00
Pasir beton 0.0900 m3 x Rp. 172,500.00 = Rp. 15,525.00
Kerikil beton 0.0200 m3 x Rp. 230,000.00 = Rp. 4,600.00
Besi beton polos 2.6000 kg x Rp. 10,800.00 = Rp. 28,080.00
Jumlah (1) Rp. 245,630.00
A. 5.1.1.16.b Tenaga
Pekerja 3.2000 oh x Rp. 115,000.00 = Rp. 368,000.00
Tukang batu 1.1500 oh x Rp. 172,000.00 = Rp. 197,800.00
Kepala Tukang 0.0110 oh x Rp. 207,000.00 = Rp. 2,277.00
Mandor 0.0160 oh x Rp. 227,000.00 = Rp. 3,632.00
Jumlah (2) Rp. 571,709.00
Jumlah (1) + (2) Rp. 817,339.00 Rp. 817,330.00

A. 5.1.1.17 1 Bh Pemasangan Bak Kontrol Pasangan Bata 60x60 Tinggi 65 cm


A. 5.1.1.17.a Bahan
Batu bata 123.0000 bh x Rp. 630.00 = Rp. 77,490.00
Semen portland 114.0000 kg x Rp. 1,700.00 = Rp. 193,800.00
Pasir pasang 0.1840 m3 x Rp. 172,500.00 = Rp. 31,740.00
Pasir beton 0.1200 m3 x Rp. 172,500.00 = Rp. 20,700.00
Kerikil beton 0.0330 m3 x Rp. 230,000.00 = Rp. 7,590.00
Besi beton polos 4.8500 kg x Rp. 10,800.00 = Rp. 52,380.00
Jumlah (1) Rp. 383,700.00
A. 5.1.1.17.b Tenaga
Pekerja 3.2000 oh x Rp. 115,000.00 = Rp. 368,000.00
Tukang batu 1.1500 oh x Rp. 172,000.00 = Rp. 197,800.00
Kepala Tukang 0.0110 oh x Rp. 207,000.00 = Rp. 2,277.00
Mandor 0.0160 oh x Rp. 227,000.00 = Rp. 3,632.00
Jumlah (2) Rp. 571,709.00
Jumlah (1) + (2) Rp. 955,409.00 Rp. 955,400.00

A. 5.1.1.19 1 Bh Pemasangan Kran Air Stainless Ø 3/4" atau 1/2" (Single)


A. 5.1.1.19.a Bahan
Kran air stainless Φ 3/4" / Φ 1/2" (single) 1.0000 bh x Rp. 80,500.00 = Rp. 80,500.00
Sealtape 0.0250 bh x Rp. 5,700.00 = Rp. 142.50
Jumlah (1) Rp. 80,642.50
A. 5.1.1.19.b Tenaga
Pekerja 0.0100 oh x Rp. 115,000.00 = Rp. 1,150.00
Tukang batu 0.4000 oh x Rp. 172,000.00 = Rp. 68,800.00
Kepala Tukang 0.0400 oh x Rp. 207,000.00 = Rp. 8,280.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 79,365.00
Jumlah (1) + (2) Rp. 160,007.50 Rp. 160,000.00

A. 5.1.1.19.1 1 Bh Pemasangan Kran Air Stainless Ø 3/4" atau 1/2" (Double)


A. 5.1.1.19.1.a Bahan
Kran air stainless Φ 3/4" / Φ 1/2" (double) 1.0000 bh x Rp. 166,700.00 = Rp. 166,700.00
Sealtape 0.0250 bh x Rp. 5,700.00 = Rp. 142.50
Jumlah (1) Rp. 166,842.50
A. 5.1.1.19.1.b Tenaga
Pekerja 0.0100 oh x Rp. 115,000.00 = Rp. 1,150.00
Tukang batu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 21,555.00
Jumlah (1) + (2) Rp. 188,397.50 Rp. 188,390.00

A. 5.1.1.25 1 M Pemasangan Pipa PVC Tipe AW Ø 1/2"


1

A. 5.1.1.25.a Bahan
Pipa PVC tipe AW Ø 1/2" 1.2000 m' x Rp. 7,300.00 = Rp. 8,760.00
Perlengkapan 35% x Rp. 7,300.00 = Rp. 2,555.00
Jumlah (1) Rp. 11,315.00
A. 5.1.1.25.b Tenaga
Pekerja 0.0360 oh x Rp. 115,000.00 = Rp. 4,140.00
Tukang batu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 16,156.00
Jumlah (1) + (2) Rp. 27,471.00 Rp. 27,470.00

A. 5.1.1.26 1 M1 Pemasangan Pipa PVC Tipe AW Ø 3/4"


A. 5.1.1.26.a Bahan
Pipa PVC tipe AW Ø 3/4" 1.2000 m' x Rp. 10,000.00 = Rp. 12,000.00
Perlengkapan 35% x Rp. 10,000.00 = Rp. 3,500.00
Jumlah (1) Rp. 15,500.00

Analisis Harga Satuan Pekerjaan (AHSP)


56 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 5.1.1.26.b Tenaga
Pekerja 0.0360 oh x Rp. 115,000.00 = Rp. 4,140.00
Tukang batu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 16,156.00
Jumlah (1) + (2) Rp. 31,656.00 Rp. 31,650.00

A. 5.1.1.27 1 M Pemasangan Pipa PVC Tipe AW Ø 1"


1

A. 5.1.1.27.a Bahan
Pipa PVC tipe AW Ø 1" 1.2000 m' x Rp. 13,600.00 = Rp. 16,320.00
Perlengkapan 35% x Rp. 13,600.00 = Rp. 4,760.00
Jumlah (1) Rp. 21,080.00
A. 5.1.1.27.b Tenaga
Pekerja 0.0360 oh x Rp. 115,000.00 = Rp. 4,140.00
Tukang batu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 16,156.00
Jumlah (1) + (2) Rp. 37,236.00 Rp. 37,230.00

A. 5.1.1.28 1 M1 Pemasangan Pipa PVC Tipe AW Ø 1 1/2"


A. 5.1.1.28.a Bahan
Pipa PVC tipe AW Ø 1 1/2" 1.2000 m' x Rp. 23,600.00 = Rp. 28,320.00
Perlengkapan 35% x Rp. 23,600.00 = Rp. 8,260.00
Jumlah (1) Rp. 36,580.00
A. 5.1.1.28.b Tenaga
Pekerja 0.0540 oh x Rp. 115,000.00 = Rp. 6,210.00
Tukang batu 0.0900 oh x Rp. 172,000.00 = Rp. 15,480.00
Kepala Tukang 0.0090 oh x Rp. 207,000.00 = Rp. 1,863.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 24,234.00
Jumlah (1) + (2) Rp. 60,814.00 Rp. 60,810.00

A. 5.1.1.29 1 M1 Pemasangan Pipa PVC Tipe AW Ø 2"


A. 5.1.1.29.a Bahan
Pipa PVC tipe AW Ø 2" 1.2000 m' x Rp. 32,600.00 = Rp. 39,120.00
Perlengkapan 35% x Rp. 32,600.00 = Rp. 11,410.00
Jumlah (1) Rp. 50,530.00
A. 5.1.1.29.b Tenaga
Pekerja 0.0540 oh x Rp. 115,000.00 = Rp. 6,210.00
Tukang batu 0.0900 oh x Rp. 172,000.00 = Rp. 15,480.00
Kepala Tukang 0.0090 oh x Rp. 207,000.00 = Rp. 1,863.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 24,234.00
Jumlah (1) + (2) Rp. 74,764.00 Rp. 74,760.00

A. 5.1.1.30 1 M1 Pemasangan Pipa PVC Tipe AW Ø 2 1/2"


A. 5.1.1.30.a Bahan
Pipa PVC tipe AW Ø 2 1/2" 1.2000 m' x Rp. 45,700.00 = Rp. 54,840.00
Perlengkapan 35% x Rp. 45,700.00 = Rp. 15,995.00
Jumlah (1) Rp. 70,835.00
A. 5.1.1.30.b Tenaga
Pekerja 0.0810 oh x Rp. 115,000.00 = Rp. 9,315.00
Tukang batu 0.1350 oh x Rp. 172,000.00 = Rp. 23,220.00
Kepala Tukang 0.0135 oh x Rp. 207,000.00 = Rp. 2,794.50
Mandor 0.0040 oh x Rp. 227,000.00 = Rp. 908.00
Jumlah (2) Rp. 36,237.50
Jumlah (1) + (2) Rp. 107,072.50 Rp. 107,070.00

A. 5.1.1.31 1 M Pemasangan Pipa PVC Tipe AW Ø 3"


1

A. 5.1.1.31.a Bahan
Pipa PVC tipe AW Ø 3" 1.2000 m' x Rp. 66,900.00 = Rp. 80,280.00
Perlengkapan 35% x Rp. 66,900.00 = Rp. 23,415.00
Jumlah (1) Rp. 103,695.00
A. 5.1.1.31.b Tenaga
Pekerja 0.0810 oh x Rp. 115,000.00 = Rp. 9,315.00
Tukang batu 0.1350 oh x Rp. 172,000.00 = Rp. 23,220.00
Kepala Tukang 0.0135 oh x Rp. 207,000.00 = Rp. 2,794.50
Mandor 0.0040 oh x Rp. 227,000.00 = Rp. 908.00
Jumlah (2) Rp. 36,237.50
Jumlah (1) + (2) Rp. 139,932.50 Rp. 139,930.00

A. 5.1.1.32 1 M1 Pemasangan Pipa PVC Tipe AW Ø 4"


A. 5.1.1.32.a Bahan
Pipa PVC tipe AW Ø 4" 1.2000 m' x Rp. 103,200.00 = Rp. 123,840.00
Perlengkapan 35% x Rp. 103,200.00 = Rp. 36,120.00
Jumlah (1) Rp. 159,960.00
A. 5.1.1.32.b Tenaga
Pekerja 0.0810 oh x Rp. 115,000.00 = Rp. 9,315.00
Tukang batu 0.1350 oh x Rp. 172,000.00 = Rp. 23,220.00
Kepala Tukang 0.0135 oh x Rp. 207,000.00 = Rp. 2,794.50
Mandor 0.0040 oh x Rp. 227,000.00 = Rp. 908.00
Jumlah (2) Rp. 36,237.50
Jumlah (1) + (2) Rp. 196,197.50 Rp. 196,190.00

Analisis Harga Satuan Pekerjaan (AHSP)


57 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 5.1.1.37 1 M1 Pemasangan Pipa PVC Tipe AW Ø 6"
A. 5.1.1.37.a Bahan
Pipa PVC tipe AW Ø 6" 1.2000 m' x Rp. 138,000.00 = Rp. 165,600.00
Perlengkapan 35% x Rp. 138,000.00 = Rp. 48,300.00
Jumlah (1) Rp. 213,900.00
A. 5.1.1.37.b Tenaga
Pekerja 0.0810 oh x Rp. 115,000.00 = Rp. 9,315.00
Tukang batu 0.1350 oh x Rp. 172,000.00 = Rp. 23,220.00
Kepala Tukang 0.0135 oh x Rp. 207,000.00 = Rp. 2,794.50
Mandor 0.0040 oh x Rp. 227,000.00 = Rp. 908.00
Jumlah (2) Rp. 36,237.50
Jumlah (1) + (2) Rp. 250,137.50 Rp. 250,130.00

A. 5.1.1.38 1 M1 Pemasangan Pipa PVC Tipe AW Ø 8"


A. 5.1.1.38.a Bahan
Pipa PVC tipe AW Ø 8" 1.2000 m' x Rp. 384,100.00 = Rp. 460,920.00
Perlengkapan 35% x Rp. 384,100.00 = Rp. 134,435.00
Jumlah (1) Rp. 595,355.00
A. 5.1.1.38.b Tenaga
Pekerja 0.0810 oh x Rp. 115,000.00 = Rp. 9,315.00
Tukang batu 0.1350 oh x Rp. 172,000.00 = Rp. 23,220.00
Kepala Tukang 0.0135 oh x Rp. 207,000.00 = Rp. 2,794.50
Mandor 0.0041 oh x Rp. 227,000.00 = Rp. 930.70
Jumlah (2) Rp. 36,260.20
Jumlah (1) + (2) Rp. 631,615.20 Rp. 631,610.00

A. 5.1.1.39 1 M1 Pemasangan Pipa PVC Tipe AW Ø 10"


A. 5.1.1.39.a Bahan
Pipa PVC tipe AW Ø 10" 1.2000 m' x Rp. 594,500.00 = Rp. 713,400.00
Perlengkapan 35% x Rp. 594,500.00 = Rp. 208,075.00
Jumlah (1) Rp. 921,475.00
5.1.1.39.b Tenaga
Pekerja 0.0810 oh x Rp. 115,000.00 = Rp. 9,315.00
Tukang batu 0.1350 oh x Rp. 172,000.00 = Rp. 23,220.00
Kepala Tukang 0.0135 oh x Rp. 207,000.00 = Rp. 2,794.50
Mandor 0.0041 oh x Rp. 227,000.00 = Rp. 930.70
Jumlah (2) Rp. 36,260.20
Jumlah (1) + (2) Rp. 957,735.20 Rp. 957,730.00

A. 5.1.1.40 1 M Pemasangan Riol Ukr. Ø 15 cm


1

A. 5.1.1.40.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. Ø 15 cm panjang 1 m 1.0000 bh x Rp. 28,700.00 = Rp. 28,700.00
Jumlah (1) Rp. 29,824.50
A. 5.1.1.40.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 109,269.50 Rp. 109,260.00

A. 5.1.1.41 1 M1 Pemasangan Riol Ukr. Ø 20 cm


A. 5.1.1.41.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. Ø 20 cm panjang 1 m 1.0000 bh x Rp. 31,000.00 = Rp. 31,000.00
Jumlah (1) Rp. 32,124.50
A. 5.1.1.41.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 111,569.50 Rp. 111,560.00

A. 5.1.1.42 1 M Pemasangan Riol Ukr. Ø 30 cm


1

A. 5.1.1.42.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. Ø 30 cm panjang 1 m 1.0000 bh x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 47,124.50
A. 5.1.1.42.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 126,569.50 Rp. 126,560.00

A. 5.1.1.43 1 M1 Pemasangan Riol Ukr. Ø 40 cm


A. 5.1.1.43.a Bahan
Semen portland @ 40 kg 0.0180 zak x Rp. 68,000.00 = Rp. 1,224.00
Pasir pasang 0.0018 m3 x Rp. 172,500.00 = Rp. 310.50
Riol ukr. Ø 40 cm panjang 1 m 1.0000 bh x Rp. 86,200.00 = Rp. 86,200.00
Jumlah (1) Rp. 87,734.50

Analisis Harga Satuan Pekerjaan (AHSP)


58 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
5.1.1.43.b Tenaga
Pekerja 0.5333 oh x Rp. 115,000.00 = Rp. 61,329.50
Tukang batu 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0266 oh x Rp. 227,000.00 = Rp. 6,038.20
Jumlah (2) Rp. 105,907.70
Jumlah (1) + (2) Rp. 193,642.20 Rp. 193,640.00

A. 5.1.1.44 1 M Pemasangan Riol Ukr. Ø 50 cm


1

A. 5.1.1.44.a Bahan
Semen portland @ 40 kg 0.0225 zak x Rp. 68,000.00 = Rp. 1,530.00
Pasir pasang 0.0022 m3 x Rp. 172,500.00 = Rp. 379.50
Riol ukr. Ø 50 cm panjang 1 m 1.0000 bh x Rp. 103,500.00 = Rp. 103,500.00
Jumlah (1) Rp. 105,409.50
A. 5.1.1.44.b Tenaga
Pekerja 0.6666 oh x Rp. 115,000.00 = Rp. 76,659.00
Tukang batu 0.2500 oh x Rp. 172,000.00 = Rp. 43,000.00
Kepala Tukang 0.0250 oh x Rp. 207,000.00 = Rp. 5,175.00
Mandor 0.0332 oh x Rp. 227,000.00 = Rp. 7,536.40
Jumlah (2) Rp. 132,370.40
Jumlah (1) + (2) Rp. 237,779.90 Rp. 237,770.00

A. 5.1.1.45 1 M1 Pemasangan Riol Ukr. Ø 60 cm


A. 5.1.1.45.a Bahan
Semen portland @ 40 kg 0.0270 zak x Rp. 68,000.00 = Rp. 1,836.00
Pasir pasang 0.0026 m3 x Rp. 172,500.00 = Rp. 448.50
Riol ukr. Ø 60 cm panjang 1 m 1.0000 bh x Rp. 126,500.00 = Rp. 126,500.00
Jumlah (1) Rp. 128,784.50
A. 5.1.1.45.b Tenaga
Pekerja 0.7999 oh x Rp. 115,000.00 = Rp. 91,988.50
Tukang batu 0.3000 oh x Rp. 172,000.00 = Rp. 51,600.00
Kepala Tukang 0.0300 oh x Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0398 oh x Rp. 227,000.00 = Rp. 9,034.60
Jumlah (2) Rp. 158,833.10
Jumlah (1) + (2) Rp. 287,617.60 Rp. 287,610.00

A. 5.1.1.46 1 M1 Pemasangan Riol Ukr. Ø 80 cm


A. 5.1.1.46.a Bahan
Semen portland @ 40 kg 0.0360 zak x Rp. 68,000.00 = Rp. 2,448.00
Pasir pasang 0.0034 m3 x Rp. 172,500.00 = Rp. 586.50
Riol ukr. Ø 80 cm panjang 1 m 1.0000 bh x Rp. 130,500.00 = Rp. 130,500.00
Jumlah (1) Rp. 133,534.50
A. 5.1.1.46.b Tenaga
Pekerja 1.0665 oh x Rp. 115,000.00 = Rp. 122,647.50
Tukang batu 0.4000 oh x Rp. 172,000.00 = Rp. 68,800.00
Kepala Tukang 0.0400 oh x Rp. 207,000.00 = Rp. 8,280.00
Mandor 0.0530 oh x Rp. 227,000.00 = Rp. 12,031.00
Jumlah (2) Rp. 211,758.50
Jumlah (1) + (2) Rp. 345,293.00 Rp. 345,290.00

A. 5.1.1.47 1 M Pemasangan Riol Ukr. Ø 100 cm


1

A. 5.1.1.47.a Bahan
Semen portland @ 40 kg 0.0450 zak x Rp. 68,000.00 = Rp. 3,060.00
Pasir pasang 0.0042 m3 x Rp. 172,500.00 = Rp. 724.50
Riol ukr. Ø 100 cm panjang 1 m 1.0000 bh x Rp. 143,700.00 = Rp. 143,700.00
Jumlah (1) Rp. 147,484.50
A. 5.1.1.47.b Tenaga
Pekerja 1.3331 oh x Rp. 115,000.00 = Rp. 153,306.50
Tukang batu 0.5000 oh x Rp. 172,000.00 = Rp. 86,000.00
Kepala Tukang 0.0500 oh x Rp. 207,000.00 = Rp. 10,350.00
Mandor 0.0662 oh x Rp. 227,000.00 = Rp. 15,027.40
Jumlah (2) Rp. 264,683.90
Jumlah (1) + (2) Rp. 412,168.40 Rp. 412,160.00

A. 5.1.1.48 1 M1 Pemasangan Riol Ukr. 1/2 Ø 15 cm


A. 5.1.1.48.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. 1/2 Ø 15 cm panjang 1 m 1.0000 bh x Rp. 17,200.00 = Rp. 17,200.00
Jumlah (1) Rp. 18,324.50
A. 5.1.1.48.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 97,769.50 Rp. 97,760.00

A. 5.1.1.49 1 M Pemasangan Riol Ukr. 1/2 Ø 20 cm


1

A. 5.1.1.49.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Riol ukr. 1/2 Ø 20 cm panjang 1 m 1.0000 bh x Rp. 19,500.00 = Rp. 19,500.00
Jumlah (1) Rp. 20,624.50
A. 5.1.1.49.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 100,069.50 Rp. 100,060.00

Analisis Harga Satuan Pekerjaan (AHSP)


59 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 5.1.1.51 1 M1 Pemasangan Bodem Ø 30 cm
A. 5.1.1.51.a Bahan
Semen portland @ 40 kg 0.0140 zak x Rp. 68,000.00 = Rp. 952.00
Pasir pasang 0.0010 m3 x Rp. 172,500.00 = Rp. 172.50
Bodem Ø 30 cm 1.0000 bh x Rp. 28,700.00 = Rp. 28,700.00
Jumlah (1) Rp. 29,824.50
A. 5.1.1.51.b Tenaga
Pekerja 0.4000 oh x Rp. 115,000.00 = Rp. 46,000.00
Tukang batu 0.1500 oh x Rp. 172,000.00 = Rp. 25,800.00
Kepala Tukang 0.0150 oh x Rp. 207,000.00 = Rp. 3,105.00
Mandor 0.0200 oh x Rp. 227,000.00 = Rp. 4,540.00
Jumlah (2) Rp. 79,445.00
Jumlah (1) + (2) Rp. 109,269.50 Rp. 109,260.00

PEKERJAAN BESI DAN ALUMINIUM


A. 4.2.1.1 1 Kg Pemasangan Besi Profil
A. 4.2.1.1.a Bahan
Besi profil 1.1500 kg x Rp. 15,800.00 = Rp. 18,170.00
Jumlah (1) Rp. 18,170.00
A. 4.2.1.1.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang las 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 19,143.00
Jumlah (1) + (2) Rp. 37,313.00 Rp. 37,310.00

A. 4.2.1.2 1 Kg Pemasangan rangka kuda - kuda baja IWF


A. 4.2.1.2.a Bahan
Besi baja IWF 1.1500 kg x Rp. 14,700.00 = Rp. 16,905.00
Jumlah (1) Rp. 16,905.00
A. 4.2.1.2.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang las 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 19,143.00
Jumlah (1) + (2) Rp. 36,048.00 Rp. 36,040.00

A. 4.2.1.3 100 Kg Pekerjaan Perakitan


A. 4.2.1.3.a Bahan
Solar 1.0000 ltr x Rp. 11,200.00 = Rp. 11,200.00
Minyak pelumas 0.1000 ltr x Rp. 51,700.00 = Rp. 5,170.00
Jumlah (1) Rp. 16,370.00
A. 4.2.1.3.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang besi 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0010 oh x Rp. 207,000.00 = Rp. 207.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 30,042.00
A. 4.2.1.3.c Alat
Sewa alat 0.8000 jam x Rp. 60,000.00 = Rp. 48,000.00
Jumlah (3) Rp. 48,000.00
Jumlah (1) + (2) + (3) Rp. 94,412.00 Rp. 94,410.00

A. 4.2.1.4 1 M2 Pembuatan Pintu Besi Plat Baja tbl. 2 mm Rangkap, Rangka Baja Siku
A. 4.2.1.4.a Bahan
Besi siku L 30.30.3 15.0000 kg x Rp. 9,400.00 = Rp. 141,000.00
Besi plat baja 32.8000 kg x Rp. 12,600.00 = Rp. 413,280.00
Kawat las 0.0500 kg x Rp. 25,500.00 = Rp. 1,275.00
Jumlah (1) Rp. 555,555.00
A. 4.2.1.4.b Tenaga
Pekerja 1.0500 oh x Rp. 115,000.00 = Rp. 120,750.00
Tukang las 1.0500 oh x Rp. 172,000.00 = Rp. 180,600.00
Kepala Tukang 0.1050 oh x Rp. 207,000.00 = Rp. 21,735.00
Mandor 0.0520 oh x Rp. 227,000.00 = Rp. 11,804.00
Jumlah (2) Rp. 334,889.00
Jumlah (1) + (2) + (3) Rp. 890,444.00 Rp. 890,440.00

A. 4.2.1.5 10 Cm Pengelasan dengan Las Listrik


A. 4.2.1.5.a Bahan
Kawat las listrik 0.4000 kg x Rp. 25,500.00 = Rp. 10,200.00
Solar 0.3000 ltr x Rp. 11,200.00 = Rp. 3,360.00
Minyak pelumas 0.0400 ltr x Rp. 51,700.00 = Rp. 2,068.00
Jumlah (1) Rp. 15,628.00
A. 4.2.1.5.b Tenaga
Pekerja 0.0400 oh x Rp. 115,000.00 = Rp. 4,600.00
Tukang besi konstruksi 0.0200 oh x Rp. 172,000.00 = Rp. 3,440.00
Kepala Tukang 0.0020 oh x Rp. 207,000.00 = Rp. 414.00
Mandor 0.0020 oh x Rp. 227,000.00 = Rp. 454.00
Jumlah (2) Rp. 8,908.00
A. 4.2.1.5.c Alat
Sewa alat 0.1700 jam x Rp. 60,000.00 = Rp. 10,200.00
Jumlah (3) Rp. 10,200.00
Jumlah (1) + (2) + (3) Rp. 34,736.00 Rp. 34,730.00

Analisis Harga Satuan Pekerjaan (AHSP)


60 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.2.1.7 1 M2 Pemasangan Pintu Rolling Door Besi
A. 4.2.1.7.a Bahan
Pintu gulung besi 1.0000 m2 x Rp. 1,725,000.00 = Rp. 1,725,000.00
Jumlah (1) Rp. 1,725,000.00
A. 4.2.1.7.b Tenaga
Pekerja 1.2000 oh x Rp. 115,000.00 = Rp. 138,000.00
Tukang las biasa 1.2000 oh x Rp. 172,000.00 = Rp. 206,400.00
Kepala Tukang 0.1200 oh x Rp. 207,000.00 = Rp. 24,840.00
Mandor 0.0060 oh x Rp. 227,000.00 = Rp. 1,362.00
Jumlah (2) Rp. 370,602.00
Jumlah (1) + (2) Rp. 2,095,602.00 Rp. 2,095,600.00

A. 4.2.1.8 1 M2 Pemasangan Pintu Lipat (Folding Door) Bahan Plastik/PVC


A. 4.2.1.8.a Bahan
Pintu lipat bahan plastik/PVC 1.0000 m2 x Rp. 625,200.00 = Rp. 625,200.00
Jumlah (1) Rp. 625,200.00
A. 4.2.1.8.b Tenaga
Pekerja 0.4400 oh x Rp. 115,000.00 = Rp. 50,600.00
Tukang 0.4400 oh x Rp. 172,000.00 = Rp. 75,680.00
Kepala Tukang 0.0440 oh x Rp. 207,000.00 = Rp. 9,108.00
Mandor 0.0220 oh x Rp. 227,000.00 = Rp. 4,994.00
Jumlah (2) Rp. 140,382.00
Jumlah (1) + (2) Rp. 765,582.00 Rp. 765,580.00

A. 4.2.1.9 1 M2 Pemasangan Sunscreen Aluminium


A. 4.2.1.9.a Bahan
Sunscreen aluminium 1.0000 m2 x Rp. 586,500.00 = Rp. 586,500.00
Jumlah (1) Rp. 586,500.00
A. 4.2.1.9.b Tenaga
Pekerja 0.0800 oh x Rp. 115,000.00 = Rp. 9,200.00
Tukang 0.8000 oh x Rp. 172,000.00 = Rp. 137,600.00
Kepala Tukang 0.0800 oh x Rp. 207,000.00 = Rp. 16,560.00
Mandor 0.0040 oh x Rp. 227,000.00 = Rp. 908.00
Jumlah (2) Rp. 164,268.00
Jumlah (1) + (2) Rp. 750,768.00 Rp. 750,760.00

A. 4.2.1.10 1 M2 Pemasangan Rolling Door Alluminium


A. 4.2.1.10.a Bahan
Rolling door alluminium 1.0000 m2 x Rp. 1,150,000.00 = Rp. 1,150,000.00
Jumlah (1) Rp. 1,150,000.00
A. 4.2.1.10.b Tenaga
Pekerja 1.0000 oh x Rp. 115,000.00 = Rp. 115,000.00
Tukang 1.0000 oh x Rp. 172,000.00 = Rp. 172,000.00
Kepala Tukang 0.1000 oh x Rp. 207,000.00 = Rp. 20,700.00
Mandor 0.0500 oh x Rp. 227,000.00 = Rp. 11,350.00
Jumlah (2) Rp. 319,050.00
Jumlah (1) + (2) Rp. 1,469,050.00 Rp. 1,469,050.00

A. 4.2.1.11 1 M Pemasangan Kusen Pintu Aluminium


1

A. 4.2.1.11.a Bahan
Profil aluminium 1.1000 m x Rp. 46,000.00 = Rp. 50,600.00
Skrup fixer 2.0000 Bh x Rp. 19,500.00 = Rp. 39,000.00
Sealant 0.0600 tube x Rp. 14,900.00 = Rp. 894.00
Jumlah (1) Rp. 90,494.00
A. 4.2.1.11.b Tenaga
Pekerja 0.0430 oh x Rp. 115,000.00 = Rp. 4,945.00
Tukang 0.0430 oh x Rp. 172,000.00 = Rp. 7,396.00
Kepala Tukang 0.0043 oh x Rp. 207,000.00 = Rp. 890.10
Mandor 0.0021 oh x Rp. 227,000.00 = Rp. 476.70
Jumlah (2) Rp. 13,707.80
Jumlah (1) + (2) Rp. 104,201.80 Rp. 104,200.00

A. 4.2.1.14 1 M2 Pemasangan Venetions Blinds


A. 4.2.1.14.a Bahan
Venetions blinds 1.0000 m2 x Rp. 753,200.00 = Rp. 753,200.00
Jumlah (1) Rp. 753,200.00
A. 4.2.1.14.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 111,781.00
Jumlah (1) + (2) Rp. 864,981.00 Rp. 864,980.00

A. 4.2.1.14.1 1 M2 Pemasangan Vertical Blinds


A. 4.2.1.14.1.a Bahan
Vertical blinds 1.0000 m2 x Rp. 402,500.00 = Rp. 402,500.00
Jumlah (1) Rp. 402,500.00
A. 4.2.1.14.1.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 111,781.00
Jumlah (1) + (2) Rp. 514,281.00 Rp. 514,280.00

Analisis Harga Satuan Pekerjaan (AHSP)


61 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
A. 4.2.1.15 1 M2 Pemasangan Terali Besi Strip (2x3) mm
A. 4.2.1.15.a Bahan
Besi strip 6.1770 kg x Rp. 9,700.00 = Rp. 59,916.90
Pengelasan 27.0800 cm x Rp. 3,100.00 = Rp. 83,948.00
Jumlah (1) Rp. 143,864.90
A. 4.2.1.15.b Tenaga
Pekerja 1.6700 oh x Rp. 115,000.00 = Rp. 192,050.00
Tukang las 1.6700 oh x Rp. 172,000.00 = Rp. 287,240.00
Kepala Tukang 0.1670 oh x Rp. 207,000.00 = Rp. 34,569.00
Mandor 0.0830 oh x Rp. 227,000.00 = Rp. 18,841.00
Jumlah (2) Rp. 532,700.00
Jumlah (1) + (2) Rp. 676,564.90 Rp. 676,560.00

A. 4.2.1.16 1 M2 Pemasangan Kawat Nyamuk


A. 4.2.1.16.a Bahan
Kawat nyamuk 1.1000 m2 x Rp. 32,200.00 = Rp. 35,420.00
Pengelasan 11.1100 cm x Rp. 3,100.00 = Rp. 34,441.00
Baja strip 1.7160 kg x Rp. 9,700.00 = Rp. 16,645.20
Jumlah (1) Rp. 86,506.20
A. 4.2.1.16.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 118,411.20 Rp. 118,410.00

A. 4.2.1.17 1 M2 Pemasangan Jendela Nako dan Tralis


A. 4.2.1.17.a Bahan
Jendela nako (rangka + kaca 5 mm) 1.1000 m2 x Rp. 207,000.00 = Rp. 227,700.00
Paku skrup 10.0000 bh x Rp. 19,500.00 = Rp. 195,000.00
Besi strip 7.0000 m x Rp. 9,700.00 = Rp. 67,900.00
Jumlah (1) Rp. 490,600.00
A. 4.2.1.17.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 61,767.00
Jumlah (1) + (2) Rp. 552,367.00 Rp. 552,360.00

A. 4.2.1.18 1 M1 Pemasangan Talang Datar / Jurai Seng BJLS 28 lebar 90 cm


A. 4.2.1.18.a Bahan
Seng plat 1.0500 m1 x Rp. 59,800.00 = Rp. 62,790.00
Paku 0.0150 kg x Rp. 23,000.00 = Rp. 345.00
Papan kayu sembarang 0.0190 m3 x Rp. 6,325,000.00 = Rp. 120,175.00
Jumlah (1) Rp. 183,310.00
A. 4.2.1.18.b Tenaga
Pekerja 0.2000 oh x Rp. 115,000.00 = Rp. 23,000.00
Tukang 0.2000 oh x Rp. 172,000.00 = Rp. 34,400.00
Kepala Tukang 0.0200 oh x Rp. 207,000.00 = Rp. 4,140.00
Mandor 0.0010 oh x Rp. 227,000.00 = Rp. 227.00
Jumlah (2) Rp. 61,767.00
Jumlah (1) + (2) Rp. 245,077.00 Rp. 245,070.00

A. 4.2.1.19 1 M1 Pemasangan Talang 1/2 Lingkaran D - 15 cm, Seng Plat BJLS 30 lebar 45 cm
A. 4.2.1.19.a Bahan
Seng plat 1.0500 m x Rp. 59,800.00 = Rp. 62,790.00
Paku 0.0100 kg x Rp. 40,200.00 = Rp. 402.00
Besi Strip 0.5000 kg x Rp. 9,700.00 = Rp. 4,850.00
Jumlah (1) Rp. 68,042.00
A. 4.2.1.19.b Tenaga
Pekerja 0.1500 oh x Rp. 115,000.00 = Rp. 17,250.00
Tukang 0.3000 oh x Rp. 172,000.00 = Rp. 51,600.00
Kepala Tukang 0.0300 oh x Rp. 207,000.00 = Rp. 6,210.00
Mandor 0.0080 oh x Rp. 227,000.00 = Rp. 1,816.00
Jumlah (2) Rp. 76,876.00
Jumlah (1) + (2) Rp. 144,918.00 Rp. 144,910.00

A. 4.2.1.20 1 M Pemasangan Rangka Besi Hollow 1x40.40.2mm, Modul 60x120 cm, untuk Partisi
2

A. 4.2.1.20.a Bahan
Rangka metal hollow 40.40.2 mm 3.5000 m1 x Rp. 46,000.00 = Rp. 161,000.00
Assesoris (perkuatan, las dll) 100% Ls x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 207,000.00
A. 4.2.1.20.b Tenaga
Pekerja 0.2500 oh x Rp. 115,000.00 = Rp. 28,750.00
Tukang 0.2500 oh x Rp. 172,000.00 = Rp. 43,000.00
Kepala Tukang 0.0250 oh x Rp. 207,000.00 = Rp. 5,175.00
Mandor 0.0130 oh x Rp. 227,000.00 = Rp. 2,951.00
Jumlah (2) Rp. 79,876.00
Jumlah (1) + (2) Rp. 286,876.00 Rp. 286,870.00

A. 4.2.1.21 1 M2 Pemasangan Rangka Besi Hollow 1x40.40.2mm, Modul 60x60 cm, untuk Plafond
A. 4.2.1.21.a Bahan
Rangka metal hollow 40.40.2 mm 4.0000 m1 x Rp. 46,000.00 = Rp. 184,000.00
Assesoris (perkuatan, las dll) 100% Ls x Rp. 46,000.00 = Rp. 46,000.00
Jumlah (1) Rp. 230,000.00
A. 4.2.1.21.b Tenaga
Pekerja 0.3500 oh x Rp. 115,000.00 = Rp. 40,250.00
Tukang 0.3500 oh x Rp. 172,000.00 = Rp. 60,200.00
Kepala Tukang 0.0350 oh x Rp. 207,000.00 = Rp. 7,245.00
Mandor 0.0180 oh x Rp. 227,000.00 = Rp. 4,086.00
Jumlah (2) Rp. 111,781.00
Jumlah (1) + (2) Rp. 341,781.00 Rp. 341,780.00

Analisis Harga Satuan Pekerjaan (AHSP)


62 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN LANGIT - LANGIT
A. 4.5.1.1 1 M2 Pemasangan Langit - langit Asbes Semen, tbl. 4mm, 5mm, dan 6mm
A. 4.5.1.1.a Bahan
Asbes 1.1000 m2 x Rp. 23,000.00 = Rp. 25,300.00
Paku biasa 0.0100 kg x Rp. 23,000.00 = Rp. 230.00
Jumlah (1) Rp. 25,530.00
A. 4.5.1.1.b Tenaga
Pekerja 0.0300 oh x Rp. 115,000.00 = Rp. 3,450.00
Tukang kayu 0.0700 oh x Rp. 172,000.00 = Rp. 12,040.00
Kepala Tukang 0.0070 oh x Rp. 207,000.00 = Rp. 1,449.00
Mandor 0.0040 oh x Rp. 227,000.00 = Rp. 908.00
Jumlah (2) Rp. 17,847.00
Jumlah (1) + (2) Rp. 43,377.00 Rp. 43,370.00

A. 4.5.1.5 1 M2 Pemasangan Langit - langit Triplek Ukr. 120x240 cm, Tbl. 4mm
A. 4.5.1.5.a Bahan
Triplek tebal 4mm 0.3750 lbr x Rp. 92,000.00 = Rp. 34,500.00
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Jumlah (1) Rp. 35,190.00
A. 4.5.1.5.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 67,095.00 Rp. 67,090.00

A. 4.5.1.5.1 1 M Pemasangan Langit - langit Triplek Ukr. 120x240 cm, Tbl. 6 mm


2

A. 4.5.1.5.1.a Bahan
Triplek tebal 6 mm 0.3750 lbr x Rp. 103,500.00 = Rp. 38,812.50
Paku biasa 0.0300 kg x Rp. 23,000.00 = Rp. 690.00
Jumlah (1) Rp. 39,502.50
A. 4.5.1.5.1.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.1000 oh x Rp. 172,000.00 = Rp. 17,200.00
Kepala Tukang 0.0100 oh x Rp. 207,000.00 = Rp. 2,070.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 31,905.00
Jumlah (1) + (2) Rp. 71,407.50 Rp. 71,400.00

A. 4.5.1.6 1 M2 Pemasangan Langit - langit Lambriziring Kayu, Tebal 9 mm


A. 4.5.1.6.a Bahan
Papan kayu 0.0150 m3 x Rp. 6,900,000.00 = Rp. 103,500.00
Paku tripleks 0.0100 kg x Rp. 23,000.00 = Rp. 230.00
Jumlah (1) Rp. 103,730.00
A. 4.5.1.6.b Tenaga
Pekerja 0.8000 oh x Rp. 115,000.00 = Rp. 92,000.00
Tukang kayu 0.8000 oh x Rp. 172,000.00 = Rp. 137,600.00
Kepala Tukang 0.0800 oh x Rp. 207,000.00 = Rp. 16,560.00
Mandor 0.0400 oh x Rp. 227,000.00 = Rp. 9,080.00
Jumlah (2) Rp. 255,240.00
Jumlah (1) + (2) Rp. 358,970.00 Rp. 358,970.00

A. 4.5.1.7 1 M2 Pemasangan Langit - langit Gypsum board ukr. 120x240x9 mm, tbl. 9mm
A. 4.5.1.7.a Bahan
Gypsum board 0.3640 lbr x Rp. 60,900.00 = Rp. 22,167.60
Paku skrup 0.1100 kg x Rp. 69,000.00 = Rp. 7,590.00
Jumlah (1) Rp. 29,757.60
A. 4.5.1.7.b Tenaga
Pekerja 0.1000 oh x Rp. 115,000.00 = Rp. 11,500.00
Tukang kayu 0.0500 oh x Rp. 172,000.00 = Rp. 8,600.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0050 oh x Rp. 227,000.00 = Rp. 1,135.00
Jumlah (2) Rp. 22,270.00
Jumlah (1) + (2) Rp. 52,027.60 Rp. 52,020.00

4.5.1.7.1 1 M Pemasangan List Plafond Gypsum Profil 16-20 cm


1

4.5.1.7.1.a Bahan
List gypsum profil 16-20 cm 1.0500 m x Rp. 14,300.00 = Rp. 15,015.00
Tepung gypsum 0.1500 kg x Rp. 5,700.00 = Rp. 855.00
Jumlah (1) Rp. 15,870.00
4.5.1.7.1.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 19,143.00
Jumlah (1) + (2) Rp. 35,013.00 Rp. 35,010.00

4.5.1.7.2 1 M Pemasangan List Plafond Gypsum Profil 12-15 cm


1

4.5.1.7.2.a Bahan
List gypsum profil 12-15 cm 1.0500 m x Rp. 11,500.00 = Rp. 12,075.00
Tepung gypsum 0.1500 kg x Rp. 5,700.00 = Rp. 855.00
Jumlah (1) Rp. 12,930.00

Analisis Harga Satuan Pekerjaan (AHSP)


63 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
4.5.1.7.2.b Tenaga
Pekerja 0.0600 oh x Rp. 115,000.00 = Rp. 6,900.00
Tukang kayu 0.0600 oh x Rp. 172,000.00 = Rp. 10,320.00
Kepala Tukang 0.0060 oh x Rp. 207,000.00 = Rp. 1,242.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 19,143.00
Jumlah (1) + (2) Rp. 32,073.00 Rp. 32,070.00

A. 4.5.1.9 1 M Pemasangan List Langit - langit Kayu Profil


1

A. 4.5.1.9.a Bahan
List kayu profil 1.0500 m x Rp. 34,500.00 = Rp. 36,225.00
Paku 0.0100 kg x Rp. 23,000.00 = Rp. 230.00
Jumlah (1) Rp. 36,455.00
A. 4.5.1.9.b Tenaga
Pekerja 0.0500 oh x Rp. 115,000.00 = Rp. 5,750.00
Tukang kayu 0.0500 oh x Rp. 172,000.00 = Rp. 8,600.00
Kepala Tukang 0.0050 oh x Rp. 207,000.00 = Rp. 1,035.00
Mandor 0.0030 oh x Rp. 227,000.00 = Rp. 681.00
Jumlah (2) Rp. 16,066.00
Jumlah (1) + (2) Rp. 52,521.00 Rp. 52,520.00

Binjai, Maret 2019

KEPALA DINAS PEKERJAAN UMUM


DAN PENATAAN RUANG KOTA BINJAI/
PENGGUNA ANGGARAN

Ir. ELVI KRISTINA SRI ULINA, M.Sc


PEMBINA UTAMA MUDA
NIP. 19641001 199003 2 005

Analisis Harga Satuan Pekerjaan (AHSP)


64 Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN PERSIAPAN

A. 2.2.1.1 M2 Pembuatan Pagar Sementara dari Kayu Tinggi 2 Meter Rp 592,290.00


A. 2.2.1.2 M2
Pembuatan Pagar Sementara dari Seng Gelombang Tinggi 2 Meter Rp 364,420.00
A. 2.2.1.4 M1 Pengukuran dan Pemasangan Bowplank Rp 152,540.00
A. 2.2.1.5 M2
Pembuatan Kantor Sementara/Direksi Keet, dengan Lantai Plesteran Rp 1,447,240.00
A. 2.2.1.6 M2
Pembuatan Rumah Jaga (Konstruksi Kayu) Rp 2,281,450.00
A. 2.2.1.7 M2
Pembuatan Gudang Semen dan Peralatan Rp 1,118,000.00
A. 2.2.1.8 M2 Pembuatan Bedeng Pekerja Rp 1,189,400.00
A. 2.2.1.9 M2
Pembersihan Lapangan dan Peralatan Rp 22,850.00
A. 2.2.1.10 M2
Pembuatan Steger / Perancah dari Bambu Rp 545,830.00
A. 2.2.1.11 Bh Pembuatan Kotak Adukan ukr. 40cm x 50cm x 25cm Rp 375,900.00
A. 2.2.1.13 M3 Pembongkaran Beton Bertulang Rp 1,684,590.00
A. 2.2.1.14 M3
Pembongkaran Dinding Tembok Bata Rp 842,290.00
A. 2.2.1.17 M2
Pembongkaran Rangka dan Penutup Atap Rp 28,110.00
A. 2.2.1.18 M2 Pembongkaran Rangka dan Penutup Plafond Rp 27,620.00
A. 2.2.1.19 M2
Pembongkaran Lantai Rp 20,210.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN TANAH

A. 2.3.1.1 M3 Penggalian Tanah Biasa Sedalam 1 M Rp 91,920.00


A. 2.3.1.2 M3 Penggalian Tanah Biasa Sedalam 2 M Rp 113,710.00
A. 2.3.1.3 M3 Penggalian Tanah Biasa Sedalam 3 M Rp 135,950.00
A. 2.3.1.4 M3
Penggalian Tanah Keras Sedalam 1 M Rp 122,260.00
A. 2.3.1.5 M3
Penggalian Tanah Cadas Sedalam 1 M Rp 186,120.00
A. 2.3.1.6 M3 Penggalian Tanah Lumpur Sedalam 1 M Rp 148,210.00
A. 2.3.1.7 M2
Pekerjaan Stripping Tanah Tebing Setinggi 1 M Rp 6,880.00
A. 2.3.1.8 M3
Pembuangan Tanah Sejauh 30 M Rp 40,220.00
A. 2.3.1.9 M3
Pengurugan Kembali Galian Tanah Rp 68,850.00
A. 2.3.1.10 M3 Pemadatan Tanah Rp 68,850.00
A. 2.3.1.11 M3
Pengurugan Pasir Rp 243,770.00
A. 2.3.1.13 M2
Pemasangan Lapisan Ijuk Tebal 10 cm untuk bidang resapan Rp 192,850.00
A. 2.3.1.14 M3
Pengurugan Sirtu Padat Rp 275,620.00
A. 2.3.1.15 M3 Pengurugan Tanah Rp 174,770.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN PONDASI

A. 3.2.1.1 M3 Pemasangan Pondasi Batu Kali Camp. 1Pc : 3Pp Rp 1,106,110.00


A. 3.2.1.2 M3 Pemasangan Pondasi Batu Kali Camp. 1Pc : 4Pp Rp 1,045,850.00
3.2.1.2.1 M3
Pemasangan kembali Pondasi Batu Kali Camp. 1Pc : 4Pp Rp 700,850.00
A. 3.2.1.3 M3
Pemasangan Pondasi Batu Kali Camp. 1Pc : 5Pp Rp 1,004,090.00
A. 3.2.1.9 M3
Pemasangan Batu Kosong (Anstamping) Rp 593,220.00
A. 3.2.1.10 M3 Pemasangan Pondasi Siklop, 60% Beton Camp. 1Pc : 2Pb : 3Kr dan 40% Batu Kali Rp 2,635,100.00
A. 3.2.1.11 M3 Pemasangan Pondasi Sumuran, Diameter 100 cm Rp 1,077,800.00
A. 3.2.1.13 M3
Pemasangan Pondasi Batu Kali Camp. 1Pc : 4Pp (Upah) Rp 334,050.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN DINDING

A. 4.4.1.1 M2 Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 2Pp Rp 290,300.00
A. 4.4.1.2 M2 Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 3Pp Rp 274,260.00
A. 4.4.1.3 M2
Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 4Pp Rp 263,720.00
A. 4.4.1.4 M2
Pemasangan Dinding Bata Merah Tbl. 1 Bata, Camp. Spesi 1Pc : 5Pp Rp 257,880.00
A. 4.4.1.7 M2
Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 2Pp Rp 140,040.00
A. 4.4.1.8 M2 Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 3Pp Rp 132,600.00
A. 4.4.1.9 M2
Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 4Pp Rp 128,240.00
A. 4.4.1.10 M2
Pemasangan Dinding Bata Merah Tbl. 1/2 Bata, Camp. Spesi 1Pc : 5Pp Rp 125,490.00
A. 4.4.1.22 M2
Pemasangan Dinding Terawang (Rooster) 12x11x24 Camp. Spesi 1Pc : 3Pp Rp 1,287,910.00
A. 4.4.1.23 M2 Pemasangan Dinding Terawang (Rooster) 12x11x24 Camp. Spesi 1Pc : 4Pp Rp 1,287,910.00
A. 4.4.1.25 M2
Pemasangan Dinding Bata Ringan tebal 7,5 cm dengan Mortar Siap Pakai Rp 9,373,190.00
A. 4.4.1.26 M2
Pemasangan Dinding Bata Ringan tebal 10 cm dengan Mortar Siap Pakai Rp 9,370,270.00
A. 4.4.1.27 M2
Pemasangan Glass Block Rp 936,820.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN PLESTERAN

A. 4.4.2.1 M2 Pemasangan Plesteran 1Pc : 1Pp, Tbl 15 mm Rp 95,920.00


A. 4.4.2.2 M2 Pemasangan Plesteran 1Pc : 2Pp, Tbl 15 mm Rp 87,640.00
A. 4.4.2.3 M2
Pemasangan Plesteran 1Pc : 3Pp, Tbl 15 mm Rp 83,990.00
A. 4.4.2.4 M2
Pemasangan Plesteran 1Pc : 4Pp, Tbl 15 mm Rp 81,550.00
A. 4.4.2.5 M2
Pemasangan Plesteran 1Pc : 5Pp, Tbl 15 mm Rp 80,100.00
A. 4.4.2.19 M2 Pemasangan Berapen 1SP : 5PP, Tbl. 15 mm Rp 46,910.00
A. 4.4.2.23 M2
Pemasangan Plesteran Ciprat 1Pc : 2Pp Rp 65,550.00
A. 4.4.2.24 M2
Pemasangan Finishing Siar Pasangan Bata Merah Rp 38,900.00
A. 4.4.2.26 M2
Pemasangan Finishing Siar Pasangan Batu Kali Camp. 1Pc : 2 Pp Rp 79,650.00
A. 4.4.2.27 M2 Pemasangan Acian Rp 50,060.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN KAYU

A. 4.6.1.1 M3 Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. I Rp 27,149,100.00
A. 4.6.1.2 M3 Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. II Rp 16,727,150.00
4.6.1.2.1 M3
Pembuatan dan Pemasangan Kusen Pintu dan Jendela Kayu kls. III Rp 12,587,150.00
A. 4.6.1.3 M2
Pembuatan dan Pemasangan Pintu Klamp Standar, Kayu kls. II Rp 661,820.00
A. 4.6.1.4 M2
Pembuatan dan Pemasangan Pintu Klamp Sederhana, Kayu kls. III Rp 523,820.00
A. 4.6.1.5 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu kls. I Rp 1,535,300.00
4.6.1.5.1 M2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu kls. II Rp 1,144,300.00
A. 4.6.1.6 M2 Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. I Rp 1,062,070.00
4.6.1.6.1 M2 Pembuatan dan Pemasangan Pintu dan Jendela Kaca Kayu kls. II Rp 827,470.00
A. 4.6.1.7 M2
Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. I Rp 2,018,300.00
4.6.1.7.1 M3
Pembuatan dan Pemasangan Pintu dan Jendela Jalusi Kayu kls. II Rp 1,392,700.00
A. 4.6.1.8 M2 Pembuatan Daun Pintu Tripleks Rangkap, Rangka Kayu kls. II tertutup Rp 870,400.00
A. 4.6.1.8.1 M2 Pembuatan dan Pemasangan Pintu Tripleks Rangkap, Rangka Tertutup Kayu Lapis Seng Rp 1,609,570.00
A. 4.6.1.9 M2
Pembuatan Pintu Tripleks Rangkap, Rangka Expose Kayu kls. I Rp 1,197,300.00
4.6.1.9.1 M2
Pembuatan Pintu Tripleks Rangkap, Rangka Expose Kayu kls. II Rp 947,060.00
A. 4.6.1.10 M2
Pemasangan Jalusi Kusen Kayu kls. I Rp 1,749,440.00
4.6.1.10.1 M2 Pemasangan Jalusi Kusen Kayu kls. II Rp 1,162,940.00
A. 4.6.1.13 M3
Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. I Bentang 6m Rp 25,229,600.00
4.6.1.13.1 M3
Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. II Bentang 6m Rp 14,477,100.00
4.6.1.13.2 M3 Pemasangan Kontruksi Kuda-kuda Kayu Konvensional, Kayu kls. III Bentang 6m Rp 10,682,100.00
A. 4.6.1.14 M3
Pemasangan Kontruksi Kuda-kuda Ekspose, Kayu kls. I Rp 29,144,110.00
A. 4.6.1.15 M3
Pemasangan Kontruksi Gording, Kayu kls. II Rp 16,319,310.00
A. 4.6.1.16 M2 Pemasangan Rangka Atap Genteng Keramik, Kayu kls. II Rp 555,150.00
A. 4.6.1.17 M2
Pemasangan Rangka Atap Genteng Beton, Kayu kls. II Rp 772,500.00
A. 4.6.1.18 M2 Pemasangan Rangka Atap Sirap, Kayu kls. II Rp 184,490.00
A. 4.6.1.19 M2
Pemasangan Rangka Langit-langit (50×100 ) cm, Kayu kls. II Rp 256,070.00
4.6.1.19.1 M2
Pemasangan Rangka Langit-langit (50×100 ) cm, Kayu kls. III Rp 202,940.00
A. 4.6.1.20 M2 Pemasangan Rangka Kayu Langit-langit (60×60 ) cm, Kayu kls. II Rp 257,530.00
4.6.1.20.1 M2
Pemasangan Rangka Kayu Langit-langit (60×60 ) cm, Kayu kls. III Rp 201,300.00
A. 4.6.1.21 M1 Pemasangan Lisplank ukr. (3x20) cm, Kayu kls. I Rp 270,820.00
4.6.1.21.1 M1
Pemasangan Lisplank ukr. (3x20) cm, Kayu kls. II Rp 165,250.00
A. 4.6.1.22 M1
Pemasangan Lisplank ukr. (3x30) cm, Kayu kls. I Rp 273,700.00
4.6.1.22.1 M1 Pemasangan Lisplank ukr. (3x30) cm, Kayu kls. II Rp 166,170.00
A. 4.6.1.23 M2
Pemasangan Rangka Dinding Pemisah (60x120) cm, Kayu kls. II Rp 399,030.00
4.6.1.23.1 M2 Pemasangan Rangka Dinding Pemisah (60x120) cm, Kayu kls. III Rp 302,430.00
A. 4.6.1.24 M2
Pembuatan dan Pemasangan Daun Pintu Panel Kayu Lapis Seng Rp 1,842,300.00
A. 4.6.1.25 M2
Pemasangan Dinding Pemisah Tripleks Rangkap, Rangka Kayu kls. II Rp 542,210.00
A. 4.6.1.26 M2 Pemasangan Dinding Lambrisering dari Papan Kayu kls. I Rp 576,190.00
A. 4.6.1.27 M2
Pemasangan Dinding Lambrisering dari Triplek Ukr. (120 x 240) cm Rp 55,600.00
A. 4.6.1.28 M2 Pemasangan Daun Pintu Panel Double Tripleks 9 mm Lapis HPL Rangka Kayu Rp 1,292,140.00
A. 4.6.1.29 M2 Pemasangan Dinding Pemisah Kalsiboard Rangkap, Rangka Kayu Rp 419,620.00
A. 4.6.1.30 M2
Pemasangan Dinding Pemisah GRC Rangkap, Rangka Besi Rp 290,150.00
A. 4.6.1.31 M2 Pemasangan Dinding Pemisah GRC (1 Sisi), Rangka Besi Rp 250,360.00
A. 4.6.1.32 M2
Pemasangan Dinding Pemisah GRC Tanpa Rangka Rp 139,820.00
A. 4.6.1.33 M2 Pemasangan Dinding Kalsiplank (Dinding Susun Sirih) 1 Sisi Rp 773,100.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN BETON

A. 4.1.1.1 M3 Pembuatan Beton Mutu f'c, = 7,4 MPa Rp 958,900.00


A. 4.1.1.2 M3
Pembuatan Beton Mutu f'c = 9,8 MPa Rp 1,005,330.00
A. 4.1.1.3 M3
Pembuatan Beton Mutu f'c = 12,2 MPa Rp 1,041,670.00
A. 4.1.1.4 M3 Pembuatan Lantai Kerja Beton Mutu f'c = 7,4 MPa slump (3-6) cm, w/c = 0,87 Rp 866,240.00
A. 4.1.1.4.1 M2 Pembuatan Lantai Kerja Beton Camp. 1PC :3PB : 5KR Rp 169,070.00
A. 4.1.1.5 M3
Pembuatan Beton Mutu f'c = 14,5 MPa, slump (120 ±20) mm Rp 1,084,810.00
4.1.1.5.1 M3
Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 14,5 MPa Rp 1,142,840.00
A. 4.1.1.6 M3
Pembuatan Beton Mutu f'c = 16,9 MPa Rp 1,125,850.00
4.1.1.6.1 M3
Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 16,9 MPa Rp 1,165,840.00
A. 4.1.1.7 M3
Pembuatan Beton Mutu f'c = 19,3 MPa Rp 1,156,940.00
4.1.1.7.1 M3
Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 19,3 MPa Rp 1,188,840.00
A. 4.1.1.8 M3
Pembuatan Beton Mutu f'c = 21,7 MPa Rp 1,176,800.00
4.1.1.8.1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 21,7 MPa Rp 1,222,840.00
A. 4.1.1.9 M3 Pembuatan Beton Mutu f'c = 24,0 MPa Rp 1,211,030.00
4.1.1.9.1 M3 Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 24,0 MPa Rp 1,245,840.00
A. 4.1.1.10 M3
Pembuatan Beton Mutu f'c = 26,4 MPa Rp 1,221,500.00
4.1.1.10.1 M3
Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 26,4 MPa Rp 1,303,840.00
A. 4.1.1.11 M3
Pembuatan Beton Mutu f'c = 28,8 MPa Rp 1,333,050.00
4.1.1.11.1 M3
Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 28,8 MPa Rp 1,373,390.00
A. 4.1.1.12 M3
Pembuatan Beton Mutu f'c = 31,2 MPa, slump (120 ± 20) mm Rp 1,346,920.00
4.1.1.12.1 M3
Pengecoran Beton Fabrikasi/Ready Mix Concrete Mutu f'c = 31,2 MPa Rp 1,408,390.00
A. 4.1.1.17 KG Pembesian dengan Besi Polos Rp 14,010.00
A. 4.1.1.17.1 KG Pembesian dengan Besi Ulir Rp 16,530.00
A. 4.1.1.19 KG Pemasangan Jaring Kawat Baja/Wire Mesh Rp 31,380.00
A. 4.1.1.20 M2
Pemasangan Bekisting untuk Pondasi Rp 377,420.00
A. 4.1.1.21 M2
Pemasangan Bekisting untuk Sloof Rp 262,420.00
4.1.1.21.1 M2
Pemasangan kembali Bekisting untuk Sloof Rp 124,420.00
A. 4.1.1.22 M2
Pemasangan Bekisting untuk Kolom Rp 351,380.00
4.1.1.22.1 M2
Pemasangan kembali Bekisting untuk Kolom Rp 159,620.00
A. 4.1.1.23 M2
Pemasangan Bekisting untuk Balok Rp 360,870.00
4.1.1.23.1 M2
Pemasangan kembali Bekisting untuk Balok Rp 159,620.00
A. 4.1.1.24 M2 Pemasangan Bekisting untuk Plat Lantai Rp 555,790.00
A. 4.1.1.24.1 M2 Pemasangan Bekisting untuk Plat Duiker Rp 345,350.00
A. 4.1.1.25 M2 Pemasangan Bekisting untuk Dinding Rp 335,570.00
4.1.1.25.1 M2
Pemasangan kembali Bekisting untuk Dinding Rp 159,620.00
A. 4.1.1.26 M2
Pemasangan Bekisting untuk Tangga Rp 491,680.00
A. 4.1.1.27 M2
Pemasangan Jembatan untuk Pengecoran Beton Rp 209,480.00
A. 4.1.1.35 M1
Pembuatan Kolom Praktis Beton Bertulang (11x11) cm Rp 102,400.00
A. 4.1.1.36 M1
Pembuatan Ring Balok Beton Bertulang (10x15) cm Rp 130,760.00
A. 4.1.1.37 M2
Pemasangan Bekisting untuk Dinding Drainase Rp 329,530.00
4.1.1.37.1 M2
Pemasangan Bekisting untuk Dinding Drainase (Upah) Rp 146,980.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN PENUTUP ATAP

A. 4.5.2.32 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,25 mm Rp 123,240.00
A. 4.5.2.32.1 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,30 mm Rp 136,890.00
A. 4.5.2.32.2 M2 Pemasangan Genteng Metal ukr. 800x100 Atap Pelana Tebal 0,35 mm Rp 153,400.00
A. 4.5.2.32.3 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Pelana Tebal 0,40 mm Rp 167,050.00
A. 4.5.2.33 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,25 mm Rp 159,290.00
A. 4.5.2.33.1 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,30 mm Rp 180,290.00
A. 4.5.2.33.2 M2 Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,35 mm Rp 205,690.00
A. 4.5.2.33.3 M2
Pemasangan Genteng Metal ukr. 80x100 Atap Jurai Tebal 0,40 mm Rp 226,690.00
A. 4.5.2.37 M1
Pemasangan Nok/Rabung Genteng Metal Rp 96,940.00
A. 4.5.2.39 M2
Pemasangan Atap Seng Gelombang Rp 70,990.00
A. 4.5.2.40 M1 Pemasangan Nok/Rabung Seng Rp 39,550.00
A. 4.5.2.43 M2 Pemasangan Aluminium Foil / Sisalation Rp 40,980.00
A. 4.5.2.45 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,25 mm Rp 78,230.00
A. 4.5.2.45.1 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,30 mm Rp 87,070.00
A. 4.5.2.45.2 M2
Pemasangan Atap Zincalume (Spandeck) Tebal 0,35 mm Rp 101,810.00
A. 4.5.2.45.3 M2 Pemasangan Atap Zincalume (Spandeck) Tebal 0,40 mm Rp 120,920.00
A. 4.5.2.46 M1
1 M Pemasangan Nok/Rabung Zincalume (Spandeck)
1
Rp 124,100.00
A. 4.5.2.47 M2 Pemasangan Atap Genteng Keramik Rp 369,340.00
A. 4.5.2.48 M1
Pemasangan Rabung Genteng Keramik Rp 174,080.00
A. 4.5.2.49 M2
Pemasangan Atap Single Bituminius Rp 434,040.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN KUNCI DAN KACA

A. 4.6.2.1 BH Pemasangan Kunci Tanam Antik Rp 295,700.00


A. 4.6.2.2 BH Pemasangan Kunci Tanam Biasa Rp 328,630.00
A. 4.6.2.3 BH Pemasangan Kunci Tanam Kamar Mandi Rp 143,600.00
A. 4.6.2.5 BH Pemasangan Engsel Pintu Rp 76,800.00
A. 4.6.2.6 BH Pemasangan Engsel Jendela Kupu-kupu Rp 43,530.00
A. 4.6.2.9 BH Pemasangan Kait Angin Rp 61,140.00
A. 4.6.2.12 BH Pemasangan Pegangan Pintu/Door Holder Stainless Rp 447,780.00
A. 4.6.2.17 M2 Pemasangan Kaca Bening, Tbl. 5 mm Rp 201,300.00
A. 4.6.2.24 M2 Pemasangan Kaca Reben, Tbl. 5 mm Rp 53,900.00
A. 4.6.2.25 BH Pemasangan Engsel Salon Rp 78,850.00
A. 4.6.2.26 BH Pemasangan Gerendel Pintu Rp 53,770.00
A. 4.6.2.27 BH Pemasangan Gerendel Kodok / Jendela Rp 36,470.00
A. 4.6.2.28 BH Pemasangan Rambuncis Rp 79,670.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN PENUTUP LANTAI DAN DINDING

A. 4.4.3.4 M2 Pemasangan Lantai Keramik Ukr. 40x40 cm Warna/Motif Rp 204,940.00


A. 4.4.3.4.1 M2 Pemasangan Lantai Keramik Ukr. 40x40 cm Warna/Motif Bertekstur Kasar Rp 204,940.00
A. 4.4.3.4.2 M2
Pemasangan Lantai Keramik Ukr. 40x40 cm Putih Polos Rp 167,140.00
A. 4.4.3.13 M2 Pemasangan Lantai Keramik Ukr. 60x60 cm Warna/Motif (Homogeneous Tile) Rp 352,150.00
A. 4.4.3.35 M2 Pemasangan Lantai Keramik Ukr. 30x30 cm Warna/Motif Rp 268,590.00
A. 4.4.3.35.1 M2
Pemasangan Lantai Keramik Ukr. 30x30 cm Warna/Motif Bertekstur Kasar Rp 287,580.00
A. 4.4.3.35.2 M2 Pemasangan Lantai Keramik Ukr. 30x30 cm Putih Polos Rp 256,720.00
A. 4.4.3.36 M2
Pemasangan Lantai Keramik Ukr. 20x20 cm Warna/Motif Rp 267,230.00
A. 4.4.3.38 M2
Pemasangan Lantai Mosaik Ukr. 30x30 cm Rp 653,580.00
A. 4.4.3.43 M2
Pemasangan Lantai Marmer Ukr. 100x100 cm Rp 486,170.00
A. 4.4.3.44 M2 Pemasangan Lantai Karpet Rp 495,070.00
A. 4.4.3.45 M2
Pemasangan Underlayer (Pelapis Bawah Karpet) Rp 135,650.00
A. 4.4.3.46 M2
Pemasangan Lantai Parquet Kayu Rp 639,670.00
A. 4.4.3.54 M2 Pemasangan Dinding Keramik Ukr. 20x20 cm Warna/Motif Rp 351,870.00
A. 4.4.3.55 M2 Pemasangan Dinding Marmer Ukr. 100x100 cm Rp 638,370.00
A. 4.4.3.57 M2
Pemasangan Dinding Batu Alam Paras Rp 434,900.00
A. 4.4.3.58 M2 Pemasangan Dinding Batu Alam Candi Rp 434,900.00
A. 4.4.3.60 M2
Pemasangan Wallpaper, Lebar 50 cm Rp 276,880.00
A. 4.4.3.63 M1
Pemasangan Plint Kayu Tbl 2 cm, Lebar 10 cm Rp 62,430.00
A. 4.4.3.64 M2
Pemasangan Paving Blok Natural, Tbl. 6cm Rp 246,010.00
A. 4.4.3.65 M2 Pemasangan Paving Blok Natural, Tbl. 8cm Rp 651,300.00
A. 4.4.3.66 M2
Pemasangan Paving Blok Berwarna, Tbl. 6cm Rp 242,350.00
A. 4.4.3.67 M2
Pemasangan Paving Blok Berwarna, Tbl. 8cm Rp 652,960.00
A. 4.4.3.69 M2
Pemasangan Dinding Keramik Ukr. 30x60 cm Warna/Motif Rp 453,060.00
A. 4.4.3.71 M1 Pemasangan Kanstin Beton Ukr. ± 15x30x60 cm Rp 163,840.00
A. 4.4.3.72 M2
Pemasangan Lantai Keramik Ukr. 25x25 cm Warna/Motif Rp 307,820.00
A. 4.4.3.73 M2 Pemasangan Dinding Keramik Ukr. 25x45 cm Warna/Motif Rp 387,040.00
A. 4.4.3.74 M2
Pemasangan Dinding Keramik Ukr. 25x40 cm Warna/Motif Rp 369,360.00
A. 4.4.3.75 M2
Pemasangan Dinding Keramik Ukr. 20x25 cm Warna/Motif Rp 358,360.00
A. 4.4.3.76 M2 Pemasangan Dinding Batu Alam Palimanan Rp 434,900.00
A. 4.4.3.77 M2
Pemasangan Dinding Batu Alam Andesit Rp 498,150.00
A. 4.4.3.78 M2 Pemasangan Dinding Batu Alam Andesit Motif Rp 498,150.00
A. 4.4.3.79 M2
Pemasangan Dinding Batu Alam Andesit Bintik Bakar Rp 498,150.00
A. 4.4.3.80 M2
Pemasangan Paving Block Tipe Segi Enam (Merah) Rp 205,920.00
A. 4.4.3.81 M2 Pemasangan Paving Block Tipe Bata Rp 170,120.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN PENGECATAN

A. 4.7.1.1 M2 Pengikisan / Pengerokan Permukaan Cat Tembok Lama Rp 19,180.00


A. 4.7.1.2 M2 Pencucian Bidang Permukaan Tembok yang Pernah Dicat Rp 18,060.00
A. 4.7.1.3 M2
Pengerokan Karat pada Permukaan Baja / Besi Cara Manual Rp 19,190.00
A. 4.7.1.4 M2
Pengecatan Bidang Kayu Lama (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Rp 64,640.00
A. 4.7.1.5 M2
Pengecatan Bidang Kayu Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 3 Lapis Cat Minyak) Rp 76,120.00
A. 4.7.1.8 M2 Pelaburan Bidang Kayu dengan Residu Rp 43,030.00
A. 4.7.1.9 M2
Pelaburan Bidang Kayu dengan Vernis Rp 42,450.00
A. 4.7.1.10 M2
Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 3 Lapis Cat Penutup) Rp 61,710.00
A. 4.7.1.11 M2
Pengecatan Tembok Lama (1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Rp 36,140.00
A. 4.7.1.16 M2 Pengecatan Permukaan Baja / Besi dengan Menie Besi Rp 46,060.00
A. 4.7.1.17 M2
Pengecatan Permukaan Baja / Besi dengan Menie Besi dan Perancah Kayu Rp 91,690.00
A. 4.7.1.18 M2
Pengecatan Permukaan Baja Galvanis secara Manual 4 Lapis Rp 92,980.00
A. 4.7.1.19 M2
Pengecatan Permukaan Baja Galvanis secara Manual 1 Lapis Cat Mutakhir Rp 44,340.00
A. 4.7.1.20 M2 Pengecatan Permukaan Baja Galvanis secara Manual Sistem 3 Lapis Rp 218,440.00
A. 4.7.1.21 M2 Pengecatan Permukaan Baja Galvanis secara Semprot Sistem 3 Lapis Cat Mutakhir Rp 199,800.00
A. 4.7.1.23 M2 Waterproof (1 Lapis Dasar, 1 Lapis Penutup) Rp 37,750.00
A. 4.7.1.24 M2
Pendempulan dan Penggosokan Kayu Rp 25,610.00
A. 4.7.1.25 M2
Pengecatan Bidang Baja / Besi dengan Cat Minyak Rp 39,840.00
A. 4.7.1.26 M2 Pengecatan Bidang Baja / Besi dengan Cat Minyak dan Perancah Kayu Rp 52,490.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN SANITASI

A. 5.1.1.1 BH Pemasangan Klozet Duduk / duoblock + Jet Spray Rp 4,507,890.00


A. 5.1.1.2 BH Pemasangan Kloset Jongkok Porselin Rp 906,290.00
A. 5.1.1.4 BH Pemasangan Urinoir + Flusher (dewasa) Rp 9,300,970.00
A. 5.1.1.4.1 BH Pemasangan Urinoir + Flusher (anak-anak) Rp 6,310,970.00
A. 5.1.1.5 BH Pemasangan Washtafel Rp 1,430,690.00
A. 5.1.1.12 BH Pemasangan Bak Cuci Piring Stainless Steel 1 Lobang Rp 553,460.00
A. 5.1.1.12.1 BH Pemasangan Bak Cuci Piring Stainless Steel 2 Lobang Rp 838,010.00
A. 5.1.1.14 BH Pemasangan Floor Drain / Saringan Air Lantai Rp 84,750.00
A. 5.1.1.15 BH Pemasangan Bak Kontrol Pasangan Bata 30x30 Tinggi 35 cm Rp 545,440.00
A. 5.1.1.16 BH Pemasangan Bak Kontrol Pasangan Bata 45x45 Tinggi 50 cm Rp 817,330.00
A. 5.1.1.17 BH Pemasangan Bak Kontrol Pasangan Bata 60x60 Tinggi 65 cm Rp 955,400.00
A. 5.1.1.19 BH Pemasangan Kran Air Stainless Ø 3/4" atau 1/2" (Single) Rp 160,000.00
A. 5.1.1.19.1 BH Pemasangan Kran Air Stainless Ø 3/4" atau 1/2" (Double) Rp 188,390.00
A. 5.1.1.25 M1 Pemasangan Pipa PVC Tipe AW Ø 1/2" Rp 27,470.00
A. 5.1.1.26 M1
Pemasangan Pipa PVC Tipe AW Ø 3/4" Rp 31,650.00
A. 5.1.1.27 M1 Pemasangan Pipa PVC Tipe AW Ø 1" Rp 37,230.00
A. 5.1.1.28 M1
Pemasangan Pipa PVC Tipe AW Ø 1 1/2" Rp 60,810.00
A. 5.1.1.29 M1
Pemasangan Pipa PVC Tipe AW Ø 2" Rp 74,760.00
A. 5.1.1.30 M1 Pemasangan Pipa PVC Tipe AW Ø 2 1/2" Rp 107,070.00
A. 5.1.1.31 M1 Pemasangan Pipa PVC Tipe AW Ø 3" Rp 139,930.00
A. 5.1.1.32 M1 Pemasangan Pipa PVC Tipe AW Ø 4" Rp 196,190.00
A. 5.1.1.37 M1
Pemasangan Pipa PVC Tipe AW Ø 6" Rp 250,130.00
A. 5.1.1.38 M1
Pemasangan Pipa PVC Tipe AW Ø 8" Rp 631,610.00
A. 5.1.1.39 M1 Pemasangan Pipa PVC Tipe AW Ø 10" Rp 957,730.00
A. 5.1.1.40 M1
Pemasangan Riol Ukr. Ø 15 cm Rp 109,260.00
A. 5.1.1.41 M1 Pemasangan Riol Ukr. Ø 20 cm Rp 111,560.00
A. 5.1.1.42 M1
Pemasangan Riol Ukr. Ø 30 cm Rp 126,560.00
A. 5.1.1.43 M1
Pemasangan Riol Ukr. Ø 40 cm Rp 193,640.00
A. 5.1.1.44 M1 Pemasangan Riol Ukr. Ø 50 cm Rp 237,770.00
A. 5.1.1.45 M1
Pemasangan Riol Ukr. Ø 60 cm Rp 287,610.00
A. 5.1.1.46 M1 Pemasangan Riol Ukr. Ø 80 cm Rp 345,290.00
A. 5.1.1.47 M1
Pemasangan Riol Ukr. Ø 100 cm Rp 412,160.00
A. 5.1.1.48 M1
Pemasangan Riol Ukr. 1/2 Ø 15 cm Rp 97,760.00
A. 5.1.1.49 M1 Pemasangan Riol Ukr. 1/2 Ø 20 cm Rp 100,060.00
A. 5.1.1.51 M1 Pemasangan Bodem Ø 30 cm Rp 109,260.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN BESI DAN ALUMINIUM

A. 4.2.1.1 KG Pemasangan Besi Profil Rp 37,310.00


A. 4.2.1.2 KG Pemasangan Rangka Kuda - kuda Baja IWF Rp 36,040.00
A. 4.2.1.3 100 KG Pekerjaan Perakitan Rp 94,410.00
A. 4.2.1.4 M2 Pembuatan Pintu Besi Plat Baja tbl. 2 mm Rangkap, Rangka Baja Siku Rp 890,440.00
A. 4.2.1.5 10 CM Pengelasan dengan Las Listrik Rp 34,730.00
A. 4.2.1.7 M2 Pemasangan Pintu Rolling Door Besi Rp 2,095,600.00
A. 4.2.1.8 M2
Pemasangan Pintu Lipat (Folding Door) Bahan Plastik/PVC Rp 765,580.00
A. 4.2.1.9 M2 Pemasangan Sunscreen Aluminium Rp 750,760.00
A. 4.2.1.10 M2
Pemasangan Rolling Door Alluminium Rp 1,469,050.00
A. 4.2.1.11 M1
Pemasangan Kusen Pintu Aluminium Rp 104,200.00
A. 4.2.1.14 M2
Pemasangan Venetions Blinds Rp 864,980.00
A. 4.2.1.14.1 M2 Pemasangan Vertical Blinds Rp 514,280.00
A. 4.2.1.15 M2
Pemasangan Terali Besi Strip (2x3) mm Rp 676,560.00
A. 4.2.1.16 M2
Pemasangan Kawat Nyamuk Rp 118,410.00
A. 4.2.1.17 M2
Pemasangan Jendela Nako dan Tralis Rp 552,360.00
A. 4.2.1.18 M1 Pemasangan Talang Datar / Jurai Seng BJLS 28 lebar 90 cm Rp 245,070.00
A. 4.2.1.19 M1
Pemasangan Talang 1/2 Lingkaran D - 15 cm, Seng Plat BJLS 30 lebar 45 cm Rp 144,910.00
A. 4.2.1.20 M2
Pemasangan Rangka Besi Hollow 1x40.40.2mm, Modul 60x120 cm, untuk Partisi Rp 286,870.00
A. 4.2.1.21 M2 Pemasangan Rangka Besi Hollow 1x40.40.2mm, Modul 60x60 cm, untuk Plafond Rp 341,780.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
PEKERJAAN LANGIT - LANGIT

A. 4.5.1.1 M2 Pemasangan Langit - langit Asbes Semen, tbl. 4 mm, 5 mm, dan 6 mm Rp 43,370.00
A. 4.5.1.5 M2 Pemasangan Langit - langit Triplek Ukr. 120x240 cm, Tbl. 4 mm Rp 67,090.00
A. 4.5.1.5.1 M2
Pemasangan Langit - langit Triplek Ukr. 120x240 cm, Tbl. 6 mm Rp 71,400.00
A. 4.5.1.6 M2
Pemasangan Langit - langit Lambriziring Kayu, Tebal 9 mm Rp 358,970.00
A. 4.5.1.7 M2
Pemasangan Langit - langit Gypsum board ukr. 120x240x9 mm, tbl. 9 mm Rp 52,020.00
4.5.1.7.1 M1 Pemasangan List Plafond Gypsum Profil 16-20 cm Rp 35,010.00
4.5.1.7.2 M1
Pemasangan List Plafond Gypsum Profil 12-15 cm Rp 32,070.00
A. 4.5.1.9 M1
Pemasangan List Langit - langit Kayu Profil Rp 52,520.00

Analisis Harga Satuan Pekerjaan (AHSP)


Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Tahun Anggaran 2019
RENCANA ANGGARAN BIAYA
REHAB KANTOR KELURAHAN SATRIA DAN PEMAGARAN

Volume Harga Satuan Jumlah Harga


No Uraian Pekerjaan Analisa
Pekerjaan (Rp.) (Rp.)
A. BIAYA KONSTRUKSI
1. PEKERJAAN PERSIAPAN
1 Papan nama proyek ls 1.00 bh 350,000.00 350,000.00
2 Pengukuran ulang ls 1.00 unit - -
3 Pekerjaan bongkaran ls 1.00 unit - -
4 Pemasangan bouwplank ls 1.00 unit - -
5 Direksi keet/sewa gudang ls 1.00 unit - -
6 Peranca - peranca kerja ls 1.00 unit - -
Jumlah Total 1 350,000.00
2. PEKERJAAN GEDUNG KANTOR
I. Pekerjaan Tanah
1 Penggalian Tanah Biasa Sedalam 1 M A. 2.3.1.1 - M3 91,920.00 -
2 Pengurugan Sirtu Padat A. 2.3.1.14 - M3 275,620.00 -
-
II. Pekerjaan Beton/Batu
1 Penggalian Tanah Biasa Sedalam 1 M A. 2.3.1.1 - M3 91,920.00 -
2 Pemadatan Tanah A. 2.3.1.10 - M3 68,850.00 -
3 Pek. Sloof ukr. 20x20 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.17. - ### #N/A #N/A
4 Pek. Kolom ukr. 20x20 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.18. - ### #N/A #N/A
5 Pek. Balok Latei ukr. 13x20 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.19. - ### #N/A #N/A
6 Pekerjaan Ring Balok ukr. 13x20 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.19. - ### #N/A #N/A
7 ### PD 6.8. - ### #N/A #N/A
8 ### PD 6.11. - ### #N/A #N/A
9 ### PL 6.5. - ### #N/A #N/A
10 ### PL 6.6. - ### #N/A #N/A
11 Relief garis Ls - M1 #REF! #REF!
#N/A
III. Pekerjaan Atap Dan Plafond
1 Pasang rangka kuda - kuda atap baja ringan Ls - M2 #REF! #REF!
2 ### PPA 6.1.b. - ### #N/A #N/A
3 ### PPA 6.2. - ### #N/A #N/A
4 ### PBA 6.13. - ### #N/A #N/A
5 Pasang kalsiplank + cat Ls - M1 #REF! #REF!
6 Pasang plafond gypsum + profil + cat + rangka Ls - M2 #REF! #REF!
#REF!
IV.. Pekerjaan Kayu / Pintu dan Jendela
1 ### PK 6.1. - ### #N/A #N/A
2 ### PK 6.2.a. - ### #N/A #N/A
3 ### PK 6.3. - ### #N/A #N/A
4 Pintu aluminium + ventilasi (PA1) Ls - Unit #REF! #REF!
5 Pintu aluminium KM/WC (PAT) Ls - Unit #REF! #REF!
6 Jendela aluminium + ventilasi (JA2) Ls - Unit #REF! #REF!
7 Ventilasi aluminium KM/WC (VAT) Ls - Unit #REF! #REF!
#N/A
V. Pekerjaan Kunci Dan Kaca
1 ### PKK 6.2. - ### #N/A #N/A
2 ### PKK 6.4. - ### #N/A #N/A
3 ### PKK 6.5. - ### #N/A #N/A
4 ### PKK 6.6. - ### #N/A #N/A
5 ### PKK 6.7. - ### #N/A #N/A
6 ### PKK 6.8. - ### #N/A #N/A
7 ### PKK 6.12. - ### #N/A #N/A
8 ### PKK 6.13. - ### #N/A #N/A
9 ### PKK 6.14. - ### #N/A #N/A
#N/A

Volume Harga Satuan Jumlah Harga


No Uraian Pekerjaan Analisa
Pekerjaan (Rp.) (Rp.)
VI. Pekerjaan Penutup Lantai Dan Dinding
1 ### PPL 6.3.a. - ### #N/A #N/A
2 ### PPL 6.3.b. - ### #N/A #N/A
3 ### PPL 6.15. - ### #N/A #N/A
4 ### PPL 6.20. - ### #N/A #N/A
#N/A
VII. Pekerjaan Listrik
1 Instalasi Listrik dan perpipaan Ls - Ttk 172,500.00 -
2 Saklar lampu tunggal komplit Ls - Bh #REF! #REF!
3 Saklar lampu ganda komplit Ls - Bh #REF! #REF!
4 Saklar lampu triple komplit Ls - Bh #REF! #REF!
5 Stop kontak komplit Ls - Bh 12,700.00 -
6 Pasang Fitting Lampu biasa Ls - Bh 18,400.00 -
7 Pasang Fitting Lampu downlight 4" Ls - Bh 58,900.00 -
8 Pasang Lampu SL 14 watt Ls - Bh 41,500.00 -
9 Pasang Lampu SL 23 watt Ls - Bh 52,200.00 -
10 Pasang MCB 6A komplit Ls - Unit #REF! #REF!
#REF!
VIII. Pekerjaan Sanitasi
1 ### PS 6.2. - ### #N/A #N/A
2 ### PS 6.4. - ### #N/A #N/A
3 ### PS 6.5. - ### #N/A #N/A
4 ### PS 6.7.a. - ### #N/A #N/A
5 ### PS 6.8. - ### #N/A #N/A
6 Bak PVC model sudut Ls - Bh 287,500.00 -
7 ### PS 6.9. - ### #N/A #N/A
8 ### PS 6.15. - ### #N/A #N/A
9 Pembuatan sumur bor Ls - Unit #REF! #REF!
10 Pasang mesin air automatis Ls - Unit #REF! #REF!
11 Bak kontrol ukr. 60x60 cm, t = 60 cm Ls - Unit #REF! #REF!
12 Septictank ukr. 1,5x3 m, kedalaman 1,5 m dgn plat beton bertulang Ls - Unit #REF! #REF!
#N/A
IX. Pekerjaan Cat
1 ### PC 6.6. - ### #N/A #N/A
2 ### PC 6.8. - ### #N/A #N/A
3 Pengecatan coating batu alam Ls - M2 92,000.00 -
#N/A
X. Pekerjaan Lain - Lain
1 ### PPL 6.23.a. - ### #N/A #N/A
2 Pasang jerjak jendela besi hollo + cat Ls - M2 402,000.00 -
3 Pasang pintu besi hollo komplit (inc. kasa nyamuk) + cat Ls - M2 #REF! #REF!
4 Pasang AC split 1 PK Ls - Unit 4,703,500.00 -
5 Pasang lambang PEMKO stainless & acrylic (inc. lampu) ukr. 60 cm Ls - Unit 1,725,000.00 -
6 Pasang Huruf stainless steel Ls 1.00 Unit 4,635,000.00 4,635,000.00
#N/A
Jumlah Total 2 #N/A

3. PEKERJAAN PEMAGARAN
1 ### PT 6.1. - ### #N/A #N/A
2 ### PB 6.6. - ### #N/A #N/A
3 Pek. Sloof ukr. 20x20 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.17. - ### #N/A #N/A
4 Pek. Kolom ukr. 30x30 cm
a. #N/A PB 6.6. - ### #N/A #N/A
b. #N/A PB 6.14.a. - ### #N/A #N/A
c. #N/A PB 6.18. - ### #N/A #N/A
5 ### PD 6.8. - ### #N/A #N/A
6 ### PL 6.5. - ### #N/A #N/A
7 ### PPL 6.21. - ### #N/A #N/A
8 Relief minimalis Ls - M2 #REF! #REF!
9 Pasang jerjak / teralis pagar besi hollo + cat Ls - M2 575,000.00 -
10 Pasang gerbang pagar besi hollo komplit + cat Ls - M2 1,092,000.00 -
11 ### PC 6.8. - ### #N/A #N/A
12 Pengecatan coating batu alam Ls - M2 92,000.00 -
Jumlah Total 3 #N/A

Volume Harga Satuan Jumlah Harga


No Uraian Pekerjaan Analisa
Pekerjaan (Rp.) (Rp.)
4. PEKERJAAN LANSEKAP
1 ### PB 6.5. - ### #N/A #N/A
2 ### PPL 6.3.b. -
### #N/A #N/A
3 Pasang kanopi atap genteng metal (rangka besi hollo/bulat) Ls - M2 632,000.00 -
4 Pasang tiang bendera stainless steel komplit, t=6 m Ls - Unit #REF! #REF!
5 ### PPL 6.26. - ### #N/A #N/A
Jumlah Total 4 #N/A

5. PEKERJAAN AKHIR
1 Laporan dan foto dokumentasi proyek ls 1.00 unit - -
2 Asbuilt drawing ls 1.00 unit - -
3 Pembersihan lokasi pekerjaan ls 1.00 unit - -
Jumlah Total 5 -

HIMPUNAN
1 PEKERJAAN PERSIAPAN 350,000.00
2 PEKERJAAN GEDUNG KANTOR #N/A
3 PEKERJAAN PEMAGARAN #N/A
4 PEKERJAAN LANSEKAP #N/A
5 PEKERJAAN AKHIR -
Biaya Konstruksi #N/A
PPn 10% #N/A
Jumlah Biaya Konstruksi #N/A
Pembulatan #N/A

#N/A

Binjai, 2017

Diperiksa Oleh : Dihitung Oleh:


KASI. PEMB. DAN PEMELIHARAAN GEDUNG-GEDUNG STAF BIDANG CIPTA KARYA
MUHAMMAD FADHLY, ST MERPEH SITEPU
NIP. 19820420 200804 1 002 NIP. 19720306 199303 1 003

Mengetahui : Disetujui Oleh :


KEPALA DINAS PEKERJAAN UMUM KABID CIPTA KARYA
DAN PENATAAN RUANG KOTA BINJAI/
PENGGUNA ANGGARAN

Ir. ELVI KRISTINA SRI ULINA, M.Sc RIDHO INDAH PURNAMA, ST


PEMBINA UTAMA MUDA NIP. 19800925 200604 2 003
NIP. 19641001 199003 2 005
4,635,000.00
### 1,560,000.00
#N/A
#N/A
#N/A
#N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A . #N/A #N/A


milyar juta
#N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A #N/A

#N/A #N/A #N/A #N/A #N/A #N/A


#N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A #N/A
#N/A #N/A #N/A
#N/A #N/A #N/A
#N/A #N/A #N/A
#N/A #N/A #N/A #N/A

#N/A . #N/A #N/A #N/A


ribu
A #N/A
#N/A #N/A #N/A
#N/A #N/A #N/A

#N/A #N/A #N/A


#N/A #N/A #N/A
#N/A #N/A #N/A
#N/A #N/A #N/A
#N/A #N/A #N/A
#N/A
#N/A
#N/A
RENCANA ANGGARAN BIAYA
Rehabilitasi Saluran Drainase Jl. T. Amir Hamzah Gg. Kelinci Kel. Nangka

Volume Harga Satuan Jumlah Harga


No Uraian Pekerjaan Analisa
Pekerjaan (Rp.) (Rp.)
A. BIAYA KONSTRUKSI
I. Pekerjaan Persiapan
1 Papan nama proyek ls 1.00 bh 350,000.00 350,000.00
2 Tempat penyimpanan material/alat ls 1.00 unit 500,000.00 500,000.00
3 Pemasangan patok profil di lapangan ls 1.00 unit 1,250,000.00 1,250,000.00
2,100,000.00

II. Pekerjaan Parit


1 Pembersihan lokasi ls 1.00 unit 1,000,000.00 1,000,000.00
2 Penggalian Tanah Keras Sedalam 1 M A. 2.3.1.4 62.56 M3 122,260.00 7,648,585.60
3 Pembuangan Tanah Sejauh 30 M A. 2.3.1.8 62.56 M3 40,220.00 2,516,163.20
4 Pembongkaran Beton Bertulang A. 2.2.1.13 1.45 M3 1,684,590.00 2,442,655.50
5 Beton camp. 1:2,6:3,4 untuk dinding
a. Pembuatan Beton Mutu f'c = 12,2 MPa A. 4.1.1.3 62.21 M3 1,041,670.00 64,802,290.70
b. Pemasangan Bekisting untuk Dinding Drainase A. 4.1.1.37 85.50 M2 329,530.00 28,174,815.00
c. #N/A A. 4.1.1.37.1 85.50 #N/A #N/A #N/A
6 Beton bertulang camp. 1:2,3:3,2 untuk plat masuk
a. Pembuatan Beton Mutu f'c = 14,5 MPa, slump (120 ±20) mm A. 4.1.1.5 5.41 M3 1,084,810.00 5,868,822.10
b. Pembesian dengan Besi Polos A. 4.1.1.17 363.35 KG 14,010.00 5,090,533.50
c. Pemasangan Bekisting untuk Plat Duiker A. 4.1.1.24.1 29.48 M2 345,350.00 10,180,918.00
7 Pemasangan Acian A. 4.4.2.27 495.86 M2 50,060.00 24,822,751.60
8 Pemasangan Riol Ukr. 1/2 Ø 20 cm A. 5.1.1.49 380.00 M1 100,060.00 38,022,800.00
#N/A

III. Pekerjaan Lain-lain / Penyelesaian


1 Pengaman utilitas umum ls 1.00 unit 500,000.00 500,000.00
2 Chek peil proyek & asbuilt drawing ls 1.00 unit 1,300,000.00 1,300,000.00
3 Photo Dokumentasi Proyek ls 1.00 unit 800,000.00 800,000.00
4 Laporan ls 1.00 unit 1,200,000.00 1,200,000.00
3,800,000.00

HIMPUNAN
I PEKERJAAN PERSIAPAN 2,100,000.00
II PEKERJAAN PARIT #N/A
III PEKERJAAN LAIN-LAIN / PENYELESAIAN 3,800,000.00
Biaya Konstruksi #N/A
PPn 10% #N/A
Jumlah Biaya Konstruksi #N/A
Pembulatan #N/A

Terbilang : Rupiah

Binjai, 2019

Diperiksa Oleh : Dihitung Oleh:


KASI AIR BERSIH, DRAINASE dan SANITASI STAF BIDANG CIPTA KARYA

ZULHAM JUNIANDRI LUBIS, ST


NIP. 19800607 201001 1 010

Diketahui Oleh: Disetujui Oleh :


KEPALA DINAS PEKERJAAN UMUM DAN KABID CIPTA KARYA
PENATAAN RUANG KOTA BINJAI

Ir. ELVI KRISTINA SRI ULINA, M.Sc RIDHO INDAH PURNAMA, ST


PEMBINA UTAMA MUDA NIP. 19800925 200604 2 003
NIP. 19641001 199003 2 005
NOTA DINAS

Kepada : Ibu Kepala Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai
Dari : Kabid Cipta Karya
Tanggal : Maret 2019
Nomor :
Sifat : Penting
Lampiran : 1 (satu) eks
Perihal : Mohon Penandatanganan Surat Pengantar dan Analisis Harga Satuan Pekerjaan (AHSP)

1. Guna pelaksanaan Pembinaan Teknis Bangunan Gedung Negara dan Drainase Perkotaan, perlu dibuat
suatu acuan dalam hal penyusunan Analisis Harga Satuan Pekerjaan (AHSP) serta Harga Satuan Upah dan
Bahan yang dalam hal ini berpedoman pada Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat
Republik Indonesia No: 28/PRT/M/2016 dan No: 11/PRT/M/2013 tentang Pedoman Analisis Harga Satuan
Pekerjaan Bidang Pekerjaan Umum dan Perumahan Rakyat, serta Standar Pekerjaan lainnya yang disusun
oleh Bidang Cipta Karya Dinas Pekerjaan Umum dan Penataan Ruang Kota Binjai.

2. Karena penyusunsn Analisis Harga Satuan Pekerjaan (AHSP) serta Harga Satuan Upah dan Bahan telah
selesai dibuat sesuai dengan ketentuan dan peraturan yang berlaku, mohon tanda tangan Ibu

3. Demikian disampaikan, atas perhatian Ibu kami ucapkan terima kasih.

KABID CIPTA KARYA

RIDHO INDAH PURNAMA, ST


NIP.19800925 200604 2 003
PEMERINTAH KOTA BINJAI
DINAS PEKERJAAN UMUM DAN
PENATAAN RUANG
JL, M.T. HARYONO NO. 8 TELP. (061) 8821118 FAX. (061) 8821118
BINJAI 20744

KATA PENGANTAR

Dalam rangka pelaksanaan pembinaan Teknis Bangunan Gedung Negara dan Drainase Perkotaan
perlu dibuat acuan untuk keseragaman Harga Satuan Upah dan Bahan serta Analisis Harga Satuan
Pekerjaan (AHSP) di lingkungan Pemerintah Kota Binjai

Adapun penyusunan Harga Satuan Upah dan Bahan serta Analisis Harga Harga Satuan Pekerjaan (AHSP) yang
dibuat berpedoman kepada Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia Nomor :
28/PRT/M/2016 dan Nomor : 11/PRT/M/2013 tentang Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan
Umum dan Perumahan Rakyat serta Standar Pekerjaan lainnya. Harga Satuan Upah dan Bahan yang dipakai adalah
Harga Hasil Survey untuk tahun 2019.

Harga Upah Kerja dan Bahan yang tertuang dalam analisa ini hanya berlaku untuk pekerjaan di Kota Binjai.
Sedangkan untuk Kota / Kabupaten yang lain disesuaikan dengan Harga Upah Pekerja dan Bahan yang ditetapkan oleh
Pemerintah setempat.

Binjai, Maret 2019

KEPALA DINAS PEKERJAAN UMUM


DAN PENATAAN RUANG KOTA
BINJAI

Ir. ELVI KRISTINA SRIULINA, M.Sc