PM-F502-02

(1-4-2002 - Rev.0)
Page 1 of 2

CHECKLIST FOR PILING WORKS

Project :

Location :

OK! Not OK! Not Remarks


S/N Items Required
(Tick & (Cross &
Date Date
Checked) Checked)
1 Underground Cable/
Services Detection
2 Required Diversion of
Buried Services
3 Setting Out for Pile
Positions
4 Temporary Drainage

5 Excavation /Filled to
Required Platform Level
6 Proper Piling Records
(eg. setting records)
7 Conduct of Required Pile
Test
8 Eccentricities of Piles

9 Piles Trimmed to Required


Cut-off Level
10 Pile Eccentricities Plan

Name Signature Date

Checked By :

Verified By :