System Rehabilitation for NRW Reduction in South Part of Colombo City

Summary of Man Power Detail for Site Works


Date : 26-Apr-2021

Man Power Machineries


Sub Contractor
Day / Location /
No. Name of the road Type of Work / Fitter / Fusion Remarks
Night DMA Labour Excavator JCB Asphalt Cutter Compactor Generator
Direct Team Skill labour Machine

Day 1 Andarawatta Road (1 Gang) FM Trial Trench Sub 1 4 - - 1 - 1 -

Day 2 Averihena Road (1 Gang) 32A Leak FInding 32A-D23-32A-28 Direct - 4 - 1 - - - -

Day 3 Malalasekera Mawatha 31A House Connection Direct 2 5 2 - - - - 1

Day 4 Thalakotuwa Garden (1 Gang) 33D Pipe Laying Direct - 2 - - - - - -

Day 5 Colombo Plan byy road 38B Pipe Laying Sub 1 3 1 1 - 1 1 1

Day 6 Rohini Road (1 Sunpower Group) 37A Pipe Laying 37A- D33- 37A- D33A Direct 1 6 1 - 1 1 1 1

Day 7 Dharmarama 3rd Lane 37A Pressure Testing 37A- D49 -37A- D49B Direct - 2 - - - - - -

Day 8 Pamankada Road FM Cold mix rectification Direct - 3 - - - - 1 -

Day 9 Kirulapone Bridge Crossing FM Piling Work Direct - 3 - - - - - -

Day 10 Buchanan Street 35C Pipe Laying Sub 1 14 1 - - 1 1 1

Day 11 Chithra Lane 36A Compaction Test Direct - 1 - - - - - -

Total Man Power 6 47 5 2 2 3 5 4

Sub Contractor 3 21

Direct Team 3 26