System Rehabilitation for NRW Reduction in South Part of Colombo City

Summary of Man Power Detail for Site Works


Date : 27-Apr-2021

Man Power Machineries


Sub Contractor
Day / Location /
No. Name of the road Type of Work / Fitter / Fusion Remarks
Night DMA Labour Excavator JCB Asphalt Cutter Compactor Generator
Direct Team Skill labour Machine

Night 1 Hampden Lane (1 Gang) FM Pipe Laying - - - - - - - - Cancelled


Night 2 Boswell Road (1 Gang) 38A Washout Chamber Placing 38A Sub - 4 - - - 1 1 -

Night 3 Kirula Placc (1 Gang) 31C. Valve Replacing 31C-D13-31C-D36 Direct 1 4 - - - 1 - 1

Night 4 Thimbirigasyaya Avenue (1 Gang) 31A Leak Finding Direct 2 8 - 1 - 2 1 2

Night 5 Kirula Road (1 Gang) 31C. Valve Protection Tube - - - - - - - - Not Started
Night 6 Abayarama Lane (1 Gang) 31C. Valve Protection Tube - - - - - - - - Not Started
Night 7 Kirula Road (1 Gang) 31C. Valve Surface box Placing - - - - - - - - Not Started
Night 8 Fife Road (1 Gang) 36A Hot Mix 36A-D35-36A-D111 Sub - 3 - - - 1 1 1

Night 9 Chithra Lane (1 Gang) 36A Hot Mix 36A-D80-36A-D83 Sub - - - - - - - - Same team in item 8
Night 10 Adamaly Place (1 SMA Group) 35C Pipe Laying 35C - D35 - 35C - D35B Sub 1 8 - - - 1 1 1

Night 11 Bucanan Place (1 SMA Group) 35C Pipe Laying 35C - D28 - 35C - D28B Sub 1 9 - - - 1 1 1

Night 12 Beltena Lane (1 SMA Group) 35C Pipe Laying 35C - D25 - 35C - D25A Sub 1 8 - - - 1 1 1

Night 13 Ransivi Lane (1 SMA Group) 35C Pipe Laying 35C - D27 - 35C - D42 Sub - 4 - - - - - -

Total Man Power 6 48 0 1 0 8 6 7

Sub Contractor 3 36

Direct Team 3 12