Night 5 Kirula Road (1 Gang) 31C. Valve Protection Tube - - - - - - - - Not Started
Night 6 Abayarama Lane (1 Gang) 31C. Valve Protection Tube - - - - - - - - Not Started
Night 7 Kirula Road (1 Gang) 31C. Valve Surface box Placing - - - - - - - - Not Started
Night 8 Fife Road (1 Gang) 36A Hot Mix 36A-D35-36A-D111 Sub - 3 - - - 1 1 1
Night 9 Chithra Lane (1 Gang) 36A Hot Mix 36A-D80-36A-D83 Sub - - - - - - - - Same team in item 8
Night 10 Adamaly Place (1 SMA Group) 35C Pipe Laying 35C - D35 - 35C - D35B Sub 1 8 - - - 1 1 1
Night 11 Bucanan Place (1 SMA Group) 35C Pipe Laying 35C - D28 - 35C - D28B Sub 1 9 - - - 1 1 1
Night 12 Beltena Lane (1 SMA Group) 35C Pipe Laying 35C - D25 - 35C - D25A Sub 1 8 - - - 1 1 1
Night 13 Ransivi Lane (1 SMA Group) 35C Pipe Laying 35C - D27 - 35C - D42 Sub - 4 - - - - - -
Sub Contractor 3 36
Direct Team 3 12